← Current text · History

Commission Regulation (EC) No 498/2007 of 26 March 2007 laying down detailed rules for the implementation of Council Regulation (EC) No 1198/2006 on the European Fisheries Fund

Current text a fecha 2011-01-12

CHAPTER I

GENERAL PROVISIONS

Article 1

Subject matter

This Regulation lays down detailed rules for the implementation of Regulation (EC) No 1198/2006 (the basic Regulation) as regards the following:

(a) the structure and transmission of operational programmes;

(b) fisheries measures;

(c) the evaluation of operational programmes;

(d) information and publicity;

(e) financial engineering instruments;

(f) management, monitoring and control;

(g) irregularities;

(h) electronic exchange of data;

(i) personal data.

Article 2

Specific arrangements for certain operational programmes

For operational programmes for which the total eligible public expenditure does not exceed EUR 90 million at 2004 prices, specific arrangements are laid down in Article 28(2) and Articles 51, 52 and 53.

CHAPTER II

STRUCTURE AND TRANSMISSION OF THE OPERATIONAL PROGRAMMES

Article 3

Structure and transmission of the operational programmes

The content of the operational programme, referred to in Article 20 of the basic Regulation, shall be established in accordance with Part A of Annex I to this Regulation and the financing plan as set out in Part B of that Annex.

The ex ante evaluation, referred to in Article 48 of the basic Regulation, shall be annexed to the operational programme.

CHAPTER III

PRIORITY AXES

SECTION 1

Priority axis 1: Measures for the adaptation of the Community fishing fleet

Article 4

Public aid for permanent cessation of fishing activities

Article 5

Public aid for the temporary cessation of fishing activities

Article 6

Investments on board fishing vessels and selectivity

The 20 % reduction in engine power may be achieved by a group of vessels as provided for in Article 25(4) of the basic Regulation, subject to all the following conditions:

(a) all the vessels belonging to the same group are individually identified;

(b) all the vessels belonging to the same group operate in the same management areas;

(c) all the vessels belonging to the same group use the same main fishing gear as listed in Appendix III (section C) of Commission Regulation (EC) No 1639/2001 (12);

(d) all the vessels belonging to the same group do not exceed fifty in number.

Article 7

Small-scale coastal fishing

Article 8

Socio-economic compensation for the management of the Community fishing fleet

SECTION 2

Priority axis 2: Aquaculture, inland fishing, processing and marketing of fishery and aquaculture products

Article 9

Scope of intervention in aquaculture production

Support under Article 28(6) of the basic Regulation may cover the costs of assessments provided for in Council Directive 85/337/EEC (15).

Article 10

Measures for productive investments in aquaculture

For the purpose of Article 29(1)(a), (b) and (c) of the basic Regulation, the following definitions shall apply:

(a) ‘new species’: species for which aquaculture production in the Member State is low or non-existent and for which there are good market prospects;

(b) ‘species with good market prospects’: species for which the forecast medium-term trend shows that market demand is likely to exceed supply;

(c) ‘normal practice in the aquaculture sector’: aquaculture activities carried out in compliance with binding legislation, whether it relates to health, veterinary or environmental matters;

(d) ‘traditional aquaculture’: time-honoured practices which are linked to the social and cultural heritage of a given area.

Article 11

Aqua-environmental measures

Article 12

Animal health measures

Support provided for in Article 32 of the basic Regulation, may cover:

(a) for exotic diseases in aquaculture as listed in Article 3 of Council Decision 90/424/EEC (18), the control measures applied pursuant to Section 3 of Chapter V of Directive 2006/88/EC;

(b) for non-exotic diseases in aquaculture as listed in the Annex of Decision 90/424/EEC, eradication programmes drawn up and approved pursuant to Article 44(2) of Directive 2006/88/EC.

Article 13

Inland fishing

Article 14

Investments in processing and marketing

SECTION 3

Priority axis 3: Measures of common interest

Article 15

Collective actions

Support provided for in point (n) of the first paragraph of Article 37 of the basic Regulation may be granted for:

(a) the creation of producer organisations in order to facilitate the setting up and administrative operation of producer's organisation recognised under Council Regulation (EC) No 104/2000 (19) after 1 January 2007;

(b) the implementation of plans of producer organisations that have been specifically recognised under Article 12 of Regulation (EC) No 104/2000 in order to facilitate the implementation of their plans to improve the quality of their products; or

(c) the restructuring of producers' organisations in order to increase their efficiency in line with market requirements.

Article 16

Measures intended to protect and develop aquatic fauna and flora

Support provided for in point (a) of the first subparagraph of Article 38(2) of the basic Regulation shall concern measures for the construction and installation of artificial reefs or other facilities made up of long lasting elements.

Support may cover work preliminary to installation, including studies, components, signalling, transport and the assembly of the facilities and scientific monitoring.

Article 17

Landing sites

Where support is given for investments to restructure landing sites and to improve the conditions for fish landed by coastal fishers in existing landing sites, as provided for in the second subparagraph of Article 39(1) of the basic Regulation, Member States shall ensure compliance with the relevant sanitary rules and the enforcement of control measures in those landing sites.

Article 18

Development of new markets and promotional campaigns

Support provided for promotional measures, as provided for in Article 40(3)(a), (d), (e) and (g) of the basic Regulation, may cover in particular:

(a) the costs of advertising agencies and other service providers involved in the preparation and implementation of promotional campaigns;

(b) the purchase or hire of advertising space and the creation of slogans and labels for the duration of promotional campaigns;

(c) expenditure on publishing and external staff, required for the campaigns;

(d) the organisation of and participation in trade fairs and exhibitions.

Article 19

Pilot projects

Article 20

Modification for reassignment of fishing vessels

Support, as provided for in Article 42 of the basic Regulation, may be granted for the modification of a fishing vessel after its reassignment only if that vessel has been deleted permanently from the fishing fleet register and, where appropriate, the fishing licence associated with it has been permanently cancelled.

SECTION 4

Priority axis 4: Sustainable development of fisheries areas

Article 21

Objectives and measures

The support granted under Article 43 of the basic Regulation shall be for:

(a) implementing local development strategies as referred to in Article 45(2) of the basic Regulation and Article 24 of this Regulation with a view to achieving the objectives referred to in Article 43(2)(a), (b) and (c) of the basic Regulation and through the eligible measures provided for in Article 44(1)(a) to (g), (i) and (j) and Article 44(2) and (3) of that Regulation;

(b) implementing inter-regional and trans-national cooperation among the groups in fisheries areas as referred to in Article 44(1)(h) of the basic Regulation, mainly through networking and disseminating best practices with a view to achieving the objective referred to in Article 43(2)(d) of that Regulation.

Article 22

Geographical application of Priority axis 4

Article 23

Procedures and criteria for selecting the groups

A group, as referred to in Article 45(1) of the basic Regulation, shall be composed in such a way that it is able to draw up and implement a development strategy in the area concerned.

The relevance and effectiveness of the partnership shall be assessed on the basis its composition, as well as its transparency and clarity in the allocation of tasks and responsibilities.

The capacity of the partners to carry out the tasks assigned to them and the effectiveness and decision-making shall be guaranteed.

The partnership shall comprise, including at the decision-making level, representatives of the fisheries sector and of other relevant local socio-economic sectors.

The administrative capacity of the group shall be considered adequate where the group:

(a) either selects from the partnership, one partner as the administrative leader who will guarantee the satisfactory operation of the partnership; or

(b) comes together in a legally constituted common structure, the formal constitution of which guarantees the satisfactory operation of the partnership.

If the group is entrusted with the administration of public funds, its financial capacity shall be assessed:

(a) with regard to paragraph 2(a), in terms of the ability of the administrative leader to administer the funds;

(b) with regard to paragraph 2(b), in terms of the ability of the common structure to administer the funds.

The operational programme shall specify:

(a) the procedures and the criteria for selecting the groups, as well as the number of groups that the Member State intends to select; the selection criteria referred to in Article 45 of the basic Regulation and in this Article shall constitute a minimum and may be supplemented by specific national criteria; the procedures shall be transparent, provide adequate publicity and ensure competition where applicable, between the groups putting forward local development strategies;

(b) the management arrangements and the procedures for the mobilisation and circulation of financial flows as far as the beneficiary; it shall describe in particular how the groups are integrated into the management, monitoring and control systems.

Article 24

Local development strategy

The local development strategy proposed by the group in accordance with Article 45(2) of the basic Regulation shall:

(a) be integrated and be based on interaction between actors, sectors and operations and go beyond a mere collection of operations or a juxtaposition of sectoral measures;

(b) be consistent with the needs of the fisheries area particularly in socio-economic terms;

(c) prove its sustainability;

(d) be complementary to other interventions made in the area concerned.

Article 25

Implementing local development Strategy

SECTION 5

Common provisions for several measures

Article 26

Common provisions for priority axes 1 to 4

The following expenditure shall not be eligible for a contribution from EFF:

(a) for the purposes of the Articles 28(3) and 34(3), point (i) of the first paragraph of Article 37 and Article 44(2) of the basic Regulation, the purchase of infrastructure used for lifelong learning for an amount exceeding 10 % of total eligible expenditure of the operation concerned;

(b) the part of the cost of vehicles not directly linked to the operation concerned.

CHAPTER IV

EVALUATION OF THE OPERATIONAL PROGRAMMES

Article 27

Interim evaluations

Member States shall forward the interim evaluations referred to in Article 49 of the basic Regulation by 30 June 2011 at the latest. The Commission may decide to interrupt the payment deadline, in accordance with Article 88 of the basic Regulation, where a Member State has not complied with that obligation.

CHAPTER V

INFORMATION AND PUBLICITY

Article 28

Description of the information and publicity measures in the operational programme and in the annual and final reports on implementation

For the purpose of Article 20(1)(g)(v) of the basic Regulation, the operational programme shall include at least the following elements:

(a) the content of the information and publicity measures to be taken by the Member State or the managing authority aimed at potential beneficiaries and beneficiaries and their indicative budget;

(b) the content of the information and publicity measures to be taken by the Member State or the Managing authority for the public and their indicative budget;

(c) the administrative departments or bodies responsible for the implementation of information and publicity measures;

(d) an indication of how the information and publicity measures are to be evaluated in terms of visibility and awareness of the operational programme and of the role played by the Community.

The annual reports and final report on implementation of an operational programme, referred to in Article 67 of the basic Regulation, shall include:

(a) information and publicity measures carried out;

(b) the arrangements for the information and publicity measures referred to in point (d) of the second paragraph of Article 31 of this Regulation including, where applicable, the electronic address where such data may be found.

The annual report on implementation covering the year 2010 and the final report on implementation referred to in Article 67 of the basic Regulation shall contain a chapter assessing the results of the information and publicity measures in terms of visibility and awareness of the operational programme and of the role played by the Community, as provided for in paragraph 1(d) of this Article.

Article 29

Information measures for potential beneficiaries

The managing authority shall provide potential beneficiaries with clear and detailed information, on at least the following:

(a) the conditions of eligibility to be met in order to qualify for financing under the operational programme;

(b) a description of the procedures for examining applications for funding and of the time periods involved;

(c) the criteria for selecting the operations to be financed;

(d) the contacts at national, regional or local level who can provide information on the operational programme.

The managing authority shall involve in information and publicity measures, in accordance with national laws and practices, at least one of the following bodies that can widely disseminate the information listed in paragraph 2:

(a) national, regional and local authorities and development agencies;

(b) trade and professional associations;

(c) economic and social partners;

(d) non-governmental organisations;

(e) organisations representing business;

(f) information centres on the European Union as well as Commission representatives in the Member States;

(g) educational institutions.

Article 30

Information measures for beneficiaries

The managing authority shall inform beneficiaries that acceptance of funding is also an acceptance of their inclusion in the list of beneficiaries published in accordance with point (d) of the second paragraph of Article 31.

Article 31

Responsibilities of the managing authority relating to information and publicity measures for the public

For the purposes of Article 51(2)(c) of the basic Regulation, the managing authority shall ensure that the information and publicity measures for the public are implemented and that they aim at the widest possible media coverage using various forms and methods of communication at the appropriate territorial level.

The managing authority shall be responsible for organising at least the following information and publicity measures:

(a) a major information activity publicising the launch of the operational programme;

(b) at least one major information activity a year, presenting the achievements of the operational programme;

(c) flying the flag of the European Union during one week starting 9 may, in front of the premises of the managing authority;

(d) the publication, electronically or otherwise, of the list of beneficiaries, the names of the operations and the amount of public funding allocated to the operations.

Participants in operations supported by EFF and aimed at improving professional skills and training as well as beneficiaries receiving support for early departure from the fishing sector, including early retirement, as provided for under Article 27(1)(d) of the basic Regulation, shall not be named.

Article 32

Responsibilities of beneficiaries relating to information and publicity measures for the public

Where the total eligible cost of an operation co-financed by the EFF, exceeds EUR 500 000 and consists in the financing of infrastructure or of construction operations the beneficiary shall put up a billboard at the site of the operation during its implementation. The information referred to in Article 33 shall take up at least 25 % of the billboard.

When the operation is completed the billboard shall be replaced by the permanent explanatory plaque referred to in paragraph 3.

Where the total eligible cost of the operation exceeds EUR 500 000 and consists in the purchase of a physical object or the financing of infrastructure or of construction operations, the beneficiary shall put up a permanent explanatory plaque that is visible and of significant size no later than six months from the date of completion of the operation.

The plaque shall state the type and name of the operation in addition to the information referred to in Article 33. The information referred to in that Article shall take up at least 25 % of the plaque.

An explanatory plaque shall also be installed at the locations of the groups financed under priority axis 4 of the basic Regulation.

In appropriate cases, the beneficiary shall ensure that those taking part in an operation co-financed by the EFF have been informed of that funding.

The beneficiary shall provide a clear notice to the effect that the operation being implemented has been selected under an operational programme co-financed by the EFF.

Any document, including any attendance or other certificate, concerning such an operation shall include a statement to the effect that the operational programme was co-financed by the EFF.

Article 33

Technical characteristics of information and publicity measures for the operation

All information and publicity measures aimed at beneficiaries, potential beneficiaries and the public shall include the following:

(a) the emblem of the European Union, in accordance with the graphic standards set out in Annex II and reference to the European Union;

(b) a reference to the EFF: ‘European Fisheries Fund’;

(c) a statement chosen by the managing authority, highlighting the added value of the intervention of the Community, and preferably: ‘Investing in sustainable fisheries’.

CHAPTER VI

FINANCIAL ENGINEERING INSTRUMENTS

Article 34

General provisions applicable to all financial engineering instruments

Pursuant to Article 55(8) of the basic Regulation, as part of an operational programme, the EFF may co-finance expenditure in respect of an operation comprising contributions to support financial engineering instruments for enterprises, primarily to small and medium-sized enterprises (SMEs), including micro enterprises, as defined in Commission Recommendation 2003/361/EC (21) as of 1 January 2005, such as venture capital funds, guarantee funds and loan funds including through holding funds.

The financial engineering instruments shall be in the form of actions which make repayable investments or provide guarantees for repayable investments, or both. The conditions set out in Articles 35, 36 and 37 shall apply to them.

Article 35

Conditions applicable to all financial engineering instruments

When the EFF finances operations comprising financial engineering instruments, including those organised through holding funds, a business plan shall be submitted by the co-financing partners or shareholders or by their duly authorised representative.

That business plan shall be assessed and its implementation monitored by or under the responsibility of the Member State or the managing authority. The assessment of the economic viability of the investment activities of the financial engineering instruments shall take into account all sources of income of the enterprises concerned.

The business plan provided for in paragraph 1 shall specify at least the following:

(a) the targeted market of enterprises and the criteria, terms and conditions of financing them;

(b) the operational budget of the financial engineering instrument;

(c) the ownership of the financial engineering instrument;

(d) the co-financing partners or shareholders;

(e) the by-laws of the financial engineering instrument;

(f) the provisions on professionalism, competence and independence of the management;

(g) the justification for and intended use of the contribution from EFF;

(h) the policy of the financial engineering instrument concerning exits from investments in enterprises;

(i) the winding-up provisions of the financial engineering instrument, including the reutilisation of resources returned to the financial engineering instrument from investments or left over after all guarantees have been honoured, attributable to the contribution from the operational programme.

Financial engineering instruments, including holding funds, shall be set up as independent legal entities governed by agreements between the co-financing partners or shareholders or as a separate block of finance within an existing financial institution.

Where the financial engineering instrument is established within a financial institution, it shall be set up as a separate block of finance, subject to specific implementation rules within the financial institution, stipulating, in particular, that separate accounts are kept, which distinguish the new resources invested in the financial engineering instrument, including those contributed by the operational programme, from those initially available in the institution.

The Commission shall not become a co-financing partner or shareholder in financial engineering instruments.

Management costs may not exceed, on a yearly average, for the duration of the assistance any of the following thresholds, unless a higher percentage proves necessary after a competitive tender:

(a) 2 % of the capital contributed from the operational programme to holding funds, or of the capital contributed from the operational programme or holding fund to the guarantee funds;

(b) 3 % of the capital contributed from the operational programme or the holding fund to the financial engineering instrument in all other cases, with the exception of micro credit instruments directed at micro enterprises;

(c) 4 % of the capital contributed from the operational programme or the holding fund to instruments directed at micro enterprises.

The funding agreement referred to in paragraph 5 shall include at least:

(a) the investment strategy and planning;

(b) monitoring of implementation in accordance with applicable rules;

(c) an exit policy for the contribution from the operational programme out of the financial engineering instrument;

(d) the winding-up provisions of the financial engineering instrument, including the reutilisation of resources returned to the financial engineering instrument from investments or left over after all guarantees have been honoured, that are attributable to the contribution from the operational programme.

Article 36

Specific conditions applicable to holding funds

When the EFF finances financial engineering instruments organised through holding funds, that is, funds set up to invest in several venture capital funds, guarantee funds and loan funds, the Member State or managing authority shall implement them through one or more of the following forms:

(a) the award of a public contract in accordance with applicable public procurement law;

(b) in other cases, where the agreement is not a public service contract within the meaning of public procurement law, the award of a grant, defined for this purpose as a direct financial contribution by way of a donation to: (i) the European Investment Bank or to the European Investment Fund; or (ii) a financial institution without a call for proposals, if this is pursuant to a national law compatible with the Treaty.

When the EFF finances financial engineering instruments organised through holding funds, the Member State or the managing authority, shall conclude a funding agreement with the holding fund setting out the funding arrangements and objectives.

The funding agreement shall, where appropriate, take account of the conclusions of an evaluation of gaps between the supply of such instruments to, and demand for such instruments by, SMEs.

The funding agreement, referred to in paragraph 2, shall in particular make provision for:

(a) the terms and conditions for contributions from the operational programme to the holding fund;

(b) a call for expressions of interest addressed to financial intermediaries;

(c) the appraisal, selection and accreditation of financial intermediaries;

(d) the setting up and monitoring of the investment policy, which shall comprise at least an indication of the targeted enterprises and the financial engineering products to be supported;

(e) reporting by the holding fund to the Member State or managing authority;

(f) monitoring the implementation of investments in accordance with applicable rules;

(g) audit requirements;

(h) the exit policy of the holding fund out of the venture capital funds, guarantee funds or loan funds;

(i) the winding-up provisions of the holding fund, including the reutilisation of resources returned to the financial engineering instrument from investments made or left over after all guarantees have been honoured which are attributable to the contribution from the operational programme.

Article 37

Specific conditions applicable to venture capital funds, guarantee funds and loan funds

Financial engineering instruments, other than holding funds, shall invest in enterprises, primarily in SMEs. Such investments may only be made at the establishment, in the early stages, including seed capital, or on the expansion of those enterprises, and only in activities which the managers of the financial engineering instruments judge potentially economically viable.

CHAPTER VII

MANAGEMENT, MONITORING AND CONTROL

SECTION 1

General provisions

Article 38

Intermediate bodies

Article 39

Managing authority

The verifications to be carried out by the managing authority under Article 59(b) of the basic Regulation shall cover the administrative, financial, technical and physical aspects of operations, as appropriate.

Verifications shall ensure that the expenditure declared is real, the products or services have been delivered in accordance with the approval decision, the applications for reimbursement by the beneficiary are correct and that expenditure complies with Community and national rules. They shall include procedures to avoid double-financing of expenditure with other Community or national schemes and with other programming periods.

The verifications shall include the following procedures:

(a) administrative verifications in respect of each application for reimbursement by beneficiaries;

(b) on-the-spot verifications of individual operations.

Where on-the-spot verifications under paragraph 2(b) are carried out on a sample basis for the operational programme, the managing authority shall keep records describing and justifying the sampling method and identifying the operations or transactions selected for verifications.

The managing authority shall determine the size of the sample in order to achieve reasonable assurance as to the legality and regularity of the underlying transactions having regard to the level of risk identified by the managing authority for the type of beneficiaries and operations concerned.

The managing authority shall review the sampling method each year.

Article 40

Data on operations to be communicated on request to the Commission

Article 41

Audit trail

For the purposes of Article 59(f) of the basic Regulation, an audit trail shall be considered adequate where, it complies with the following criteria:

(a) it permits the aggregate amounts certified to the Commission to be reconciled with the detailed accounting records and supporting documents held by the certifying authority, managing authority, intermediate bodies and beneficiaries as regards operations co-financed under the operational programme;

(b) it permits verification of payment of the public contribution to the beneficiary;

(c) it permits verification of the application of the selection criteria established by the monitoring committee for the operational programme;

(d) it contains, in respect of each operation, as appropriate, the technical specifications and financing plan, documents concerning the grant approval, documents relating to public procurement procedures, progress reports and reports on verifications and audits carried out.

Article 42

Audits of operations

The audits referred to in Article 61(1)(b) of the basic Regulation shall be carried out each 12-month period from 1 July 2008 on a sample of operations selected by a method established or approved by the audit authority in accordance with Article 43 of this Regulation.

The audits shall be carried out on-the-spot on the basis of documentation and records held by the beneficiary.

The audits shall verify that the following conditions are fulfilled:

(a) the operation meets the selection criteria for the operational programme, has been implemented in accordance with the approval decision and fulfils any applicable conditions concerning its functionality and use or the objectives to be attained;

(b) the expenditure declared corresponds with the accounting records and supporting documents held by the beneficiary;

(c) the expenditure declared by the beneficiary is in compliance with Community and national rules;

(d) the public contribution has been paid to the beneficiary in accordance with Article 80 of the basic Regulation.

Article 43

Sampling

Article 44

Documents presented by the audit authority

Article 45

Availability of documents

The following at least shall be considered as commonly accepted data carriers, as referred to in Article 87 of the basic Regulation:

(a) photocopies of original documents;

(b) microfiches of original documents;

(c) electronic versions of original documents;

(d) documents existing in electronic version only.

Article 46

Documents submitted by the certifying authority

By 31 March of each year, the certifying authority shall submit to the Commission a statement in accordance with the model set out in Annex X identifying for each priority axis of the operational programme:

(a) the amounts withdrawn from statements of expenditure submitted during the preceding year following cancellation of all or part of the public contribution for an operation;

(b) the amounts recovered which have been deducted from those statements of expenditure submitted during the preceding year;

(c) a statement of amounts to be recovered as at 31 December of the preceding year, classified by the year in which recovery orders were issued.

(d) a list of amounts for which it was established during the preceding year that they cannot be recovered or are not expected to be recovered, classified by the year in which the recovery orders were issued.

For the purposes of points (a), (b) and (c) of the first subparagraph, aggregated amounts related to irregularities reported to the Commission under Article 55 shall be provided for each priority axis.

For the purposes of point (d) of the first subparagraph, any amount related to an irregularity reported to the Commission under Article 55 shall be identified by the reference number of that irregularity or by any other adequate method.

The Community share shall be borne by the general budget of the European Union, where within one year from the date of the submission of the statement, the Commission does not carry out any of the following:

(a) request information for the purposes of Article 70(2) of the basic Regulation;

(b) inform in writing the Member State about its intention to open an enquiry in respect of that amount;

(c) request the Member State to continue the recovery procedure.

The time limit of one year shall not apply in cases of suspected or established fraud.

Article 47

Description of management and control systems

The description of the management and control systems for the operational programme referred to in Article 71(1) of the basic Regulation shall contain information on the points referred to in Article 57 of that Regulation, and the information set out in Articles 48 and 49 of the present Regulation.

That information shall be submitted in accordance with the model set out in Part A of Annex XII to this Regulation.

Article 48

Information concerning the managing authority, the certifying authority and intermediate bodies

As regards the managing authority, the certifying authority and each intermediate body, the Member State shall provide the Commission with the following information:

(a) a description of the tasks entrusted to them;

(b) an organisation chart of each of them, a description of the allocation of tasks between or within their departments, and the indicative number of posts allocated;

(c) the procedures for selecting and approving operations;

(d) the procedures by which beneficiaries' applications for reimbursement are received, verified and validated, and in particular the rules and procedures laid down for verification purposes in Article 39, and the procedures by which payments to beneficiaries are authorised, executed and entered in the accounts;

(e) the procedures by which statements of expenditure are drawn up, certified and submitted to the Commission;

(f) a reference to the written procedures established for the procedures referred to in points (c), (d) and (e);

(g) the eligibility rules laid down by the Member State and applicable to the operational programme;

(h) the system for keeping the detailed accounting records of operations and data on implementation referred to in Article 40(1) under the operational programme.

Article 49

Information concerning the audit authority and the bodies referred to in Article 61(3) of the basic Regulation

As regards the audit authority and the bodies, referred to in Article 61(3) of the basic Regulation, the Member State shall provide the Commission with the following information:

(a) a description of their respective tasks and their inter-relationships;

(b) the organisation chart of the audit authority and of each of the bodies involved in carrying out audits concerning the operational programme, describing how their independence is ensured, the indicative number of posts allocated and the qualifications or experience required;

(c) the procedures for monitoring the implementation of recommendations and corrective measures resulting from audit reports;

(d) the procedures, where appropriate, for the supervision by the audit authority of the work of the bodies involved in carrying out audits concerning the operational programme;

(e) the procedures for the preparation of the annual control report and the closure declaration.

Article 50

Assessment of the management and control systems

SECTION 2

Derogations with regard to the control of operational programmes referred to in Article 2

Article 51

General derogations

For the operational programmes referred to in Article 2 of this Regulation, where the opinion on the compliance of the system referred to in Article 71(2) of the basic Regulation is without reservations, or where reservations have been withdrawn following corrective measures, the Commission may conclude:

(a) that it may rely principally on the opinion referred to in Article 61(1)(e)(ii) of the basic Regulation with regard to the effective functioning of the systems;

(b) that it will carry out its own on-the-spot audits only if there is evidence to suggest shortcomings in the system affecting expenditure certified to the Commission in a year for which an opinion under Article 61(1)(e)(ii) of the basic Regulation has been provided which contains no reservation in respect of such shortcomings.

Where the Commission reaches the conclusion referred to in paragraph 2 of this Article, it shall inform the Member State concerned accordingly.

Where there is evidence to suggest shortcomings, it may require the Member State concerned to carry out audits in accordance with Article 72(3) of the basic Regulation or it may carry out its own audits under Article 72(2) of that Regulation

Article 52

Establishment of bodies and procedures under national law

For the operational programmes referred to in Article 2, a Member State may in addition to the general derogations provided for in Article 51, exercise the option of establishing, in accordance with national rules, the bodies and procedures for carrying out:

(a) the functions of the managing authority in relation to the verification of the co-financed products and services and expenditure declared under Article 59(b) of the basic Regulation;

(b) the functions of the certifying authority under Article 60 of the basic Regulation;

(c) the functions of the audit authority under Article 61 of the basic Regulation.

Article 53

Specific provisions for bodies and procedures established under national law

Article 44 (2) to (5) shall apply *mutatis mutandis* to the preparation of the documents issued by the national bodies referred to in Article 52(1).

The annual control report and the annual opinion shall be drawn up following, as appropriate, the models set out in Annex VI.

The obligations laid down in Article 46(2), shall be carried out by the national bodies referred to in Article 52(1).

The statement of expenditure shall be drawn up following the models set out in Annexes IX and XI.

CHAPTER VIII

IRREGULARITIES

Article 54

Definitions

For the purposes of this Chapter the following definitions shall apply:

(a) ‘economic operator’: any natural or legal person or other entity taking part in the implementation of assistance from the EFF, with the exception of a Member States exercising its prerogatives as a public authority;

(b) ‘primary administrative or judicial finding’: a first written assessment by a competent authority, either administrative or judicial, concluding on the basis of specific facts that an irregularity has been committed, without prejudice to the possibility that this conclusion may subsequently have to be revised or withdrawn as a result of developments in the course of the administrative or judicial procedure;

(c) ‘suspected fraud’: an irregularity giving rise to the initiation of administrative or judicial proceedings at national level in order to establish the presence of intentional behaviour, in particular fraud, as defined in Article 1(1)(a) of the Convention drawn up on the basis of Article K.3 of the Treaty of the European Union, on the protection of the European Communities' financial interests (23);

(d) ‘bankruptcy’: insolvency proceedings as defined in Article 2 (a) of Council Regulation (EC) No 1346/2000 (24).

Article 55

Initial reporting — derogations

Without prejudice to the obligations under Article 70 of basic Regulation, within two months following the end of each quarter, Member States shall report to the Commission any irregularities which have been the subject of a primary administrative or judicial finding.

In that report, Member States shall in all cases give details concerning the following:

(a) the EFF, the objective, the operational programme, the priority axis and the operation concerned and the Common Identification Code (CCI) number;

(b) the provision which has been infringed;

(c) the date and source of the first information which led to a suspicion that an irregularity has been committed;

(d) the practices employed in committing the irregularity;

(e) where appropriate, whether the practice gives rise to a suspicion of fraud;

(f) the manner in which the irregularity was discovered;

(g) where appropriate, the Member States and third countries involved;

(h) the period during which, or the moment at which, the irregularity was committed;

(i) the national authorities or bodies which drew up the official report on the irregularity and the authorities responsible for the administrative or judicial follow-up;

(j) the date on which the primary administrative or judicial finding on the irregularity was established;

(k) the identity of the natural and legal persons involved or of any other participating entities, except where such information is irrelevant for the purposes of combating irregularities, given the nature of the irregularity concerned;

(l) the total eligible expenditure and the public contribution approved for the operation together with the corresponding amount of the Community contribution;

(m) the expenditure and the public contribution certified to the Commission which are affected by the irregularity and the corresponding amount of the Community contribution at risk;

(n) in case of suspected fraud and where no payment of the public contribution has been made to the persons or other entities identified under point (k), the amounts which would have been unduly paid had the irregularity not been identified;

(o) the code of region or area where the operation has been located or carried out, by specifying the NUTS level or otherwise;

(p) the nature of the irregular expenditure.

By way of derogation from the paragraph 1, the following cases need not be reported:

(a) cases where the irregularity consists solely in the failure to execute an operation, in whole or in part, included in the co-financed operational programme owing to the bankruptcy of the beneficiary;

(b) cases brought to the attention of the managing or certifying authority by the beneficiary voluntarily and before detection by either of them, whether before or after the inclusion of the expenditure concerned in a certified statement submitted to the Commission;

(c) cases which are detected and corrected by the managing or certifying authority before the inclusion of the expenditure concerned in a statement of expenditure submitted to the Commission.

However, irregularities preceding a bankruptcy and cases of suspected fraud must be reported.

Article 56

Urgent cases

Each Member State shall immediately report to the Commission and, where necessary, to the other Member States concerned, any irregularities discovered or supposed to have occurred, where it is feared that:

(a) they may very quickly have repercussions outside its territory; or

(b) they show that a new malpractice has been employed.

Article 57

Follow-up reporting

With regard to irregularities for which penalties have been imposed, Member States shall also indicate the following:

(a) whether the penalties are of administrative or criminal nature;

(b) whether the penalties result from breach of Community or national law;

(c) a reference to the provisions in which the penalties are laid down;

(d) whether fraud was established.

Article 58

Electronic transmission

The information referred to in Articles 55 and 56 and Article 57(1) shall be submitted, whenever it is possible to do so, by electronic means, using the module provided by the Commission for this purpose via a secure connection

Article 59

Reimbursement of judicial costs

Where the competent authorities of a Member State decide, at the express request of the Commission, to initiate or continue judicial proceedings with a view to recovering amounts unduly paid, the Commission may undertake to reimburse the Member State all or part of the judicial costs and costs arising directly from the proceedings, on presentation of documentary evidence, even where the proceedings are unsuccessful.

Article 60

Co-operation with Member States

The Commission shall every year inform that Committee and the committee referred to in Article 101 of the basic Regulation of the order of magnitude of the irregularities affecting the Fund which have been discovered and of the various categories of irregularities, broken down by type and number.

Article 61

Use of information

The Commission may use any information of a general or operational nature communicated by Member States under this Regulation to perform risk analyses, and may, on the basis of the information obtained, produce reports and develop early-warning systems serving to identify risks more effectively.

Article 63

Irregularities under the reporting threshold

Where the irregularities relate to amounts of less than EUR 10 000 chargeable to the general budget of the European Communities, Member States shall not submit to the Commission the information provided for in Articles 55 and 57 unless the latter expressly requests it.

Where the amounts relate to expenditure registered in the accounts of the certifying authority during more than one month, the exchange rate in the month during which expenditure was last registered may be used. Where the expenditure has not been registered in the accounts of the certifying authority, the most recent accounting exchange rate published electronically by the Commission shall be used.

CHAPTER IX

ELECTRONIC EXCHANGE OF DATA

Article 64

Computer system for data exchange

For the purpose of Articles 65 and 75 of the basic Regulation, a computer system for exchange of data shall be established as a tool for the exchange of all data relating to the operational programme.

The exchange of data between each Member State and the Commission shall be carried out using that computer system, established by the Commission, which permits the secure exchange of data between the Commission and each Member State.

The Member States shall be involved in the further development of the computer system for data exchange.

Article 65

The content of computer system for data exchange

The computer system for data exchange shall contain information of common interest to the Commission and the Member States, and at least the following data necessary for financial transactions:

(a) the financing plan for operational programmes in accordance with the model set out in Part B of Annex I;

(b) statements of expenditure and applications for payment in accordance with the model set out in Annex IX;

(c) the annual statement on withdrawn and recovered amounts and pending recoveries in accordance with the model set out in Annex X;

(d) annual forecasts of likely applications for payment in accordance with the model set out in Annex XIII;

(e) the financial section of the annual and final reports on implementation in accordance with the model set out in point 3.3 of Annex XIV.

In addition to paragraph 1, the computer system for data exchange shall contain at least the following documents and data of common interest enabling monitoring to be carried out:

(a) the national strategic plan referred to in Article 15 of the basic Regulation;

(b) the operational programme, including any revisions of it in accordance with the model set out in Part A of Annex I;

(c) the Commission decision concerning the contribution of the EFF;

(d) the annual and final reports on implementation in accordance with the model set out in Annex XIV;

(e) the audit strategy in accordance with the model set out in Annex V;

(f) the description of management and control system in accordance with the model set out in Part A of Annex XII;

(g) the reports and opinions of audits in accordance with the models set out in Annexes VI, VII, VIII and Part B of Annex XII and correspondence between the Commission and each Member State;

(h) the statements of expenditure concerning partial closure in accordance with the model set out in Annex XI;

(i) the annual statement on withdrawn and recovered amounts and pending recoveries in accordance with the model set out in Annex X.

Article 66

Functioning of the computer system for data exchange

Article 67

Transmission of data through the computer system for data exchange

CHAPTER X

PERSONAL DATA

Article 68

Protection of personal data

The information referred to in Article 40(1), of this Regulation together with information collected by the Commission in the course of its audits, shall be used by the Commission for the sole purpose of fulfilling its responsibilities provided for in Article 72 of the basic Regulation.

The European Court of Auditors and the European Anti-Fraud Office shall have access to that information.

CHAPTER XI

FINAL PROVISIONS

Article 69

Repeal

Regulations (EC) No 2722/2000, (EC) No 908/2000 and (EC) No 366/2001 are repealed. References to the repealed Regulations shall be construed as references to this Regulation.

The provisions of the Regulations repealed shall continue to apply to assistance approved under Regulation (EC) No 2792/1999.

Article 70

Entry into force

This Regulation shall enter into force on the 20th day following its publication in the Official Journal of the European Union.

This Regulation shall be binding in its entirety and directly applicable in all Member States.

ANNEX I

PART A

Content of an operational programme

Information referred to in points 3 and 4 shall be provided in a summary form where it is included in the national strategic plan.

1. TITLE OF THE OPERATIONAL PROGRAMME, MEMBER STATE

2. GEOGRAPHICAL ELIGIBILITY

Identify:

(1) ‘convergence objective’ regions (if relevant);

(2) ‘Non-convergence objective’ regions (if relevant).

3. ANALYSIS

(a) General description of the fishing sector in the Member State including: (1) an analysis of national and/or local circumstances; (2) an analysis of convergence regions and non-convergence regions; (3) main lessons learned from the previous programming period or from similar experience in other Regions or Member State as well as the findings of the ex ante evaluation when available; (4) context indicators and where relevant, national or regional statistics collected by Eurostat as well as in other sources of statistical data. Where relevant, the indicators listed in the National Strategic Plan for the description of the fisheries sector shall be used.

(b) Driving forces and development tendencies, including the sectoral and regional dimension of the socio-economic development of the fisheries sector. The description of the strengths and weaknesses, opportunities and threats in the form of a SWOT (strengths, weaknesses, opportunities and threats) analysis aiming to identify the strategic choices made by the Member State for the operational programme and the priority axes.

(c) Description of: (1) the environmental situation including, where relevant, the results of the Strategic Environmental Assessment; (2) the situation in terms of equality between men and women with regard to labour market opportunities, including constraints on specific groups, where appropriate;

(d) Main outcomes of the analysis.

4. STRATEGY AT OPERATIONAL PROGRAMME LEVEL

Strategy chosen to meet strengths and weaknesses including:

(1) overall objective(s) of the operational programme using impact indicators (26);

(2) specific objectives which the operational programme's priorities aim to achieve, using result indicators (27);

(3) calendar and intermediary objectives.

5. SUMMARY OF THE EX ANTE EVALUATION

Include a summary of the ex ante evaluation that will identify and appraise the elements referred to in Article 48 of Regulation (EC) No 1198/2006.

The ex ante evaluation shall address also the requirements of the environmental assessment provided for by Directive 2001/42/EC of the European Parliament and of the Council (28) (the ‘Strategic Environmental Assessment Directive’).

The complete ex ante evaluation shall be presented as an annex to the operational programme.

6. PROGRAMME'S PRIORITY AXES

(a) Coherence and justification of the priority axes chosen, having regard to: (1) The relevant part of the national strategic plan; (2) guiding principles of the operational programme (Article 19 of Regulation (EC) No 1198/2006); (3) outcomes of the ex ante evaluation referred to in Article 48 of Regulation (EC) No 1198/2006.

(b) Description of each priority axis including: (1) main objectives of the priority axis; (2) baseline and quantified targets using the indicators referred to in Point 4.2; (3) justification of the average rate of co-financing (if relevant), target groups/sectors/areas and/or beneficiaries for the overall operational programme and for each priority axis; (4) a description of the main measures proposed for each priority axis resulting of the strategy proposed; (5) information on demarcation with similar activities financed by the European Agricultural Fund for Rural Development, the Structural Funds and by the Cohesion Fund, as well as measures taken to ensure complementarity with these funds and other existing financial instruments, where appropriate.

(c) Specific information required for the priority axes and measures (if relevant). — Priority axis 1: Measures for the adaptation of the Community fishing fleetPublic aid for permanent cessation of fishing activities Description of priority given to the financing of recovery plans Description of the methods for the calculation of premiums for the permanent cessation of fishing activities — Public aid for temporary cessation of fishing activities Description of the methods for the calculation of premiums for temporary cessation of fishing activities — Investment on board fishing vessels and selectivity Description of the conditions applied where Member States choose the option to allow that the reduction of engine power is achieved by a group of vessels and a description of the mechanism put in place for the supervision of compliance with these conditions. Description of the objective criteria used for the establishment of the maximum amount for the total eligible expenditure to be supported per fishing vessel over the entire programming period for investment on board vessels and selectivity under Article 25 of Regulation (EC) No 1198/2006 and in accordance with Article 6(2) of this Regulation. — Small scale coastal fishing Description of the methods for the calculation of socio economic compensations provided for under Article 26(3) of Regulation (EC) No 1198/2006 in favour of small scale coastal fishing. Description of the methods for the calculation of premiums for fishers and owners of fishing vessels provided for under Article 26(4) of Regulation (EC) No 1198/2006 in favour of small scale coastal fishing. — Socio-economic compensation for the management of the Community fishing fleet Description of the methods for the calculation of socio-economic compensations provided for under Article 27 of Regulation (EC) No 1198/2006. — Priority axis 2: aquaculture, inland fishing, processing and marketing of fishery and aquaculture products:Measures for productive investments in aquaculture Description of how priority to micro and small enterprises is ensured. — Inland fishing Description of the mechanisms put in place to ensure that the investments supported under Article 33 of Regulation (EC) No 1198/2006 shall not jeopardise the equilibrium between the fleet size and the corresponding fish resources available. Description of the measures to be taken in order to ensure that the vessels receiving assistance under Article 33 of Regulation (EC) No 1198/2006 shall continue to operate exclusively in inland waters. Description of the objective criteria used for the establishment of the maximum amount for the total eligible expenditure to be supported per vessel operating in inland vessel over the entire programming period for investment on board vessels and selectivity under Article 33 of Regulation (EC) No 1198/2006 and in accordance with Article 6(2) of this Regulation. Description of the methods for the calculation of premiums for the reassignment of vessels operating in inland fishing to activities outside fishing and the measures to be taken in order to ensure that the vessels receiving assistance from EFF shall not return to operate in inland fishing. Description of the methods for the calculation of premiums for temporary cessation of fishing activities under Article 33(4) of Regulation (EC) No 1198/2006. — Investments in processing and marketing Description of how priority to micro and small enterprises is ensured. — Priority axis 4: sustainable development of fisheries areas Procedures and criteria for selecting the fisheries areas. Justification for the selection of fisheries areas whose size falls outside the limits set out in Article 43(3) of Regulation (EC) No 1198/2006 Procedures, criteria and timetable for selecting the groups, including indicative number of groups and planned percentage of fisheries areas to be covered by the local development strategies Description of the management arrangements and financial circuits as far as the beneficiary, including description of the procedure for the selection of the operations and the role and tasks of the groups with regard the management, monitoring and control systems Justification for the running costs whose cost exceeds the ceiling fixed under Article 44(5) of Regulation (EC) No 1198/2006. Identification of the measures eligible for support by more than one Community support instrument and justification of the option chosen — Priority axis 5: Technical assistance Justification of actions relating to the preparation, monitoring, evaluation, publicity, control and audit as well as networking whose cost exceed the ceiling fixed under Article 46(2) of Regulation (EC) No 1198/2006.

7. FINANCIAL PROVISIONS

To be drawn up in accordance with this Annex, Part B: Financing plans for the operational programme.

8. IMPLEMENTING PROVISIONS

(a) Designation by the Member State of the entities provided for in Article 58 of Regulation (EC) No 1198/2006 or where the Member State exercises the option provided for in Article 52 of this Regulation the designation of the bodies and procedures in accordance with the rules laid down in Article 53 of this Regulation.

(b) The body responsible for receiving payments made by the Commission and the body or bodies responsible for making payments to the beneficiaries.

(c) Description of procedures for mobilisation and circulation of financial flows in order to ensure their transparency.

(d) Description of the monitoring and evaluation system as well as the composition of the Monitoring Committee.

(e) The arrangements (to be) agreed between the Commission and the Member State for the computerised exchange of data needed to fulfil the management, monitoring and evaluation requirements.

(f) The designation of the partners referred to in Article 8 of Regulation (EC) No 1198/2006 and the results of their cooperation. List of the consulted partners and supply of a summary of the results of the consultations. For the purposes of Article 8(2) of Regulation (EC) No 1198/2006, Member States shall, taking into account the need to promote equality between men and women and sustainable development through integration of environmental protection and enhancement, consider the involvement of relevant stakeholders, including non governmental organisations.

(g) The elements aiming at ensuring the information and publicity of the operational programme in accordance with the rules laid down in Article 28 of this Regulation.

PART B

Financing plan for the operational programme

Table I: Financing plan of the operational programme giving the annual commitment of the EFF in the operational programme separately, where appropriate, for the regions eligible under the convergence objective and the non-convergence objective

Commitments shall be made on an annual basis according to the following plan:

Operational programme reference (CCI number):

Year by source for the programme, in EUR:

Year EFF
2007
2008
2009
2010
2011
2012
2013
Total EFF
Year EFF
--- ---
2007
2008
2009
2010
2011
2012
2013
Total EFF

Table II: Financing plan of the operational programme giving, separately for the whole programming period, and for each priority axis, and separately, where appropriate, for regions eligible under the convergence objective and the non-convergence objective, the amount of the total financial allocation of the EFF in the operational programme, the national public contribution and the rate of reimbursement by priority axis

Operational programme reference (CCI number):

Priority axes in EUR

Table II: Financial table for operational programme by priority axis

Priority Total public a = (b + c) EFF contribution (b) National contribution (c) EFF co-financing rate (1) (d) = (b) / (a) × 100
Priority axis 1
Priority axis 2
Priority axis 3
Priority axis 4
Priority axis 5 (2)
Total
(1) The EFF co-financing rate may be rounded-off in the table. The precise rate used to reimburse payments is the percentage (d). (2) In the case of operational programmes covering a mix of regions eligible under the convergence objective and the non-convergence objective, the total public contribution for priority axis 5 may be allocated to the predominant type of regions which have the highest total amount of public contribution in the operational programme.
Priority Total public a = (b + c) EFF contribution (b) National contribution (c) EFF co-financing rate (1) (d) = (b) / (a) × 100
--- --- --- --- ---
Priority axis 1
Priority axis 2
Priority axis 3
Priority axis 4
Priority axis 5 (2)
Total
(1) The EFF co-financing rate may be rounded-off in the table. The precise rate used to reimburse payments is the percentage (d). (2) In the case of operational programmes covering a mix of regions eligible under the convergence objective and the non-convergence objective, the total public contribution for priority axis 5 may be allocated to the predominant type of regions which have the highest total amount of public contribution in the operational programme.

ANNEX II

Symbolic description

Against a background of blue sky, 12 golden stars form a circle representing the union of the peoples of Europe. The number of stars is fixed, 12 being the symbol of perfection and unity.

Heraldic description

On an azure field a circle of twelve golden mullets, their points not touching.

Geometric description

The emblem has the form of a blue rectangular flag of which the fly is one and a half times the length of the hoist. Twelve gold stars situated at equal intervals form an invisible circle whose centre is the point of intersection of the diagonals of the rectangle. The radius of the circle is equal to one third of the height of the hoist. Each of the stars has five points which are situated on the circumference of an invisible circle whose radius is equal to 18th of the height of the hoist. All the stars are upright, i.e. with one point vertical and two points in a straight line at right angles to the mast. The circle is arranged so that the stars appear in the position of the hours on the face of a clock. Their number is invariable.

Regulation colours

The emblem is in the following colours: PANTONE REFLEX BLUE for the surface of the rectangle; PANTONE YELLOW for the stars. Four-colour process If the four-colour process is used, recreate the two standard colours by using the four colours of the four-colour process. PANTONE YELLOW is obtained by using 100 % ‘Process Yellow’. PANTONE REFLEX BLUE is obtained by mixing 100 % ‘Process Cyan’ and 80 % ‘Process Magenta’. Internet In the web-palette PANTONE REFLEX BLUE corresponds to colour RGB:0/0/153 (hexadecimal: 000099) and PANTONE YELLOW to colour RGB:255/204/0 (hexadecimal: FFCC00).

Monochrome reproduction process

Using black, outline the rectangle in black and print the stars in black on white.
Using blue (Reflex Blue), use 100 % with the stars reproduced in negative white.

Reproduction on a coloured background

If there is no alternative to a coloured background, put a white border around the rectangle, the width of the border being 1/25th of the height of the rectangle.

ANNEX III

The data on operations that the Commission may request at any time under Article 40 of this Regulation comprises the following information, without prejudice to other information required for financial management, monitoring, control or evaluation and specified in Regulation (EC) No 1198/2006.

At the written request of the Commission, the Member State shall provide the Commission with the appropriate information within 15 working days of receipt of the request or other agreed period for the purpose of carrying out documentary and on-the-spot checks. The Commission may require the information at the level of the operations, measures, priority axes or of the operational programme.

Member State

Details of the operation

— Convergence objective

— Non-convergence objective

(delete as appropriate)

Short description of the operation using data listed here after, where appropriate

C.C.I. (common identification code) for programme:

Commission Decision approving the Operational programme … No … of ../../200..

Information on individual operations

Financial data expressed in EUR

Wording of columns: see hereafter.

(1) (2) (3) (16) (17) (18)

Name, status and signature of representative of competent authority:

Date: ../../20..

Wording of table columns

(Information to be provided for each operation)

Columns 1 to 5: administrative details of operation

(1) Operation identification number (number allocated by the managing authority when an administrative decision granting public aid is taken — 20 characters maximum).

(2) (To be completed only where the operation comes under Priority axis 1: Community Fleet Register number (CFR) (do not give registration number); an operation shall concern only one vessel.

(3) The place where the operation is carried out (commune).

(4) NUTS III code for the place where the operation is carried out.

(5) Beneficiary (business name).

(6) Gender (male, female).

Columns 7 to 10: expenditure forecasts under the operation in accordance with the administrative decision granting public aid taken by managing authority

(7) Total cost taken into account in the decision granting public aid (EUR).

(8) Total public cost taken into account in the decision granting public aid (EUR).

(9) EFF aid granted to the operation (EUR).

(10) Date of the administrative decision granting public aid (dd/mm/yyyy).

Columns 11 to 15: physical data concerning the operation (classification and physical implementation)

(11) Measure (2 digits) in accordance with nomenclature (individual operation may concern one measure only)

(12) Action (1 digit) in accordance with nomenclature (individual operation may consist of more than one action; in that case, give one action per line and use several lines).

(13) Implementation data (1 or 2 digits) in accordance with nomenclature (an action forming part of an operation may feature more than one implementation data; in that case, give one implementation data only per line and use several lines).

(14) Physical quantity achieved (one quantity for each implementation data).

(15) State of implementation of operation (1 digit): code 0 (operation covered by a decision granting aid but for which no expenditure has yet been declared to the managing authority)/code 1 (operation under way)/code 2 (operation interrupted following partial implementation)/code 3 (operation abandoned following partial implementation)/code 4 (operation completed).

Columns 16 to 18: information concerning financial implementation of operation — statement of eligible expenditure and corresponding public aid

(16) Eligible expenditure certified and actually paid by beneficiaries (EUR) whose accuracy has been checked in accordance with Article 39(2) of this Regulation.

(17) National contribution (EUR): aids paid to beneficiaries by the Member State, including subsidies and other public aids, at national, regional or local level, within the limits set by Annex II to Regulation (EC) No 1198/2006.

(18) EFF aid paid to beneficiaries (EUR).

NOMENCLATURE OF PRIORITY AXES, MEASURES, ACTIONS AND IMPLEMENTATION DATA

Priority axis 1: Measures for the adaptation of the Community fishing fleet

— Action 1: Scrapping — Data 1: GT — Data 2: kW

— Action 2: Reassignment for activities outside fishing — Data 1: GT — Data 2: kW

— Action 3: Reassignment for the creation of artificial reefs — Data 1: GT — Data 2: kW

— Action 1: Temporary cessation of activities — Data 1: Number of fishers/day — Data 2: Vessels concerned if appropriate

— Action 1: Improvement of safety on board — Data 1: Vessel concerned

— Action 2: Improvement of working conditions — Data 1: Vessel concerned

— Action 3: Improvement of hygiene — Data 1: Vessel concerned

— Action 4: Improvement of product quality — Data 1: Vessel concerned

— Action 5: Improvement of energy efficiency — Data 1: Vessel concerned

— Action 6: Improvement of selectivity — Data 1: Vessel concerned

— Action 7: Replacement of engine — Data 1: Power of engine (after modernisation) (kW) — Data 2: Decrease of power related to engines replaced (-kW) — Data 3: Vessel concerned

— Action 8: Replacement of gear — Data 1: Number of fishing gear replaced — Data 2: Vessel concerned

— Action 9: Others investments on board fishing vessels and selectivity — Data 1: Vessel concerned

— Action 1: Small-scale coastal fishing — Data 1: Number of fishers/owners of fishing vessels that have received premiums in order to improve management and control of access conditions to certain fishing areas. — Data 2: Number of fishers/owners of fishing vessels that have received premiums in order to promote the organisation of the production, processing and marketing chain of fisheries products. — Data 3: Number of fishers/owners of fishing vessels that have received premiums in order to encourage voluntary steps to reduce fishing effort for the conservation of resources. — Data 4: Number of fishers/owners of fishing vessels that have received premiums in order to encourage the use of technological innovations that do not increase fishing effort. — Data 5: Total number of fishers/owners of fishing vessels that have received premiums in order to improve safety training. — Data 6: Number of female fishers/owners of fishing vessels that have received premiums in order to improve safety training. — Data 7: Total number of fishers/owners of fishing vessels that have received premiums in order to improve professional skills. — Data 8: Number of female fishers/owners of fishing vessels that have received premiums in order to improve professional skills.

— Action 1: Socio-economic compensations — Data 1: Total number of fishers concerned by the diversification of activities, if appropriate. — Data 2: Number of female fishers concerned by the diversification of activities, if appropriate. — Data 3: Total number of fishers concerned by early departure from the fishing sector. — Data 4: Number of female fishers concerned by early departure from the fishing sector. — Data 5: Total number of individual premiums to fishers younger than 40 years — Data 6: Number of individual premiums to female fishers younger than 40 years — Data 7: Total number of fishers concerned by the upgrading professional skills. — Data 8: Number of female fishers concerned by the upgrading professional skills — Data 9: Total number of fishers benefiting of schemes for retraining outside fishing sector. — Data 10: Number of female fishers benefiting of schemes for retraining outside fishing sector. — Data 11: Number of training days received. — Data 12: Total number of fishers benefiting from the non-renewable compensations, if appropriate. — Data 13: Number of female fishers benefiting from the non-renewable compensations, if appropriate.

Priority axis 2: Aquaculture, inland fishing, processing and marketing of fishing and aquaculture products

— Action 1: Increase in production capacity due to construction of new farms — Data 1: Tonnes/year of mussels — Data 2: Tonnes/year of clams — Data 3: Tonnes/year of oysters — Data 4: Tonnes/year of bass — Data 5: Tonnes/year of sea bream — Data 6: Tonnes/year of turbot — Data 7: Tonnes/year of salmon — Data 8: Tonnes/year of seawater farmed trout — Data 9: Tonnes/year of eel — Data 10: Tonnes/year of carp — Data 11: Tonnes/year of freshwater farmed trout — Data 12: Tonnes/year of tuna — Data 13: Tonnes/year of other species — Data 14: Size of enterprise (Micro, Small, Medium, Large)

— Action 2: Variation in production due to the extension or modernisation of existing farms — Data 1: Tonnes/year of mussels — Data 2: Tonnes/year of clams — Data 3: Tonnes/year of oysters — Data 4: Tonnes/year of bass — Data 5: Tonnes/year of sea bream — Data 6: Tonnes/year of turbot — Data 7: Tonnes/year of salmon — Data 8: Tonnes/year of seawater farmed trout — Data 9: Tonnes/year of eel — Data 10: Tonnes/year of carp — Data 11: Tonnes/year of freshwater farmed trout — Data 12: Tonnes/year of tuna — Data 13: Tonnes/year of other species — Data 14: Size of enterprise (Micro, Small, Medium, Large)

— Action 3: Increase in number of hatchery-produced fry — Data 1: Number/year of mussels — Data 2: Number/year of clams — Data 3: Number/year of oysters — Data 4: Number/year of bass — Data 5: Number/year of sea bream — Data 6: Number/year of turbot — Data 7: Number/year of salmon — Data 8: Number/year of seawater farmed trout — Data 9: Number/year of eel — Data 10: Number/year of carp — Data 11: Number/year of freshwater farmed trout — Data 12: Number/year of tuna — Data 13: Number/year of other species — Data 14: Size of enterprise (Micro, Small, Medium, Large)

— Action 4: Aqua-environmental measures — Data 1: Unit that has implemented aqua-environmental measures as provided for in Article 30(2)(a) of Regulation (EC) No 1198/2006. — Data 2: Unit that has adhered to the Community eco-management and audit scheme (EMAS). — Data 3: Unit that has put in place organic production.

— Action 5: Public health measures — Data 1: Mollusc farmer that has benefited from compensation.

— Action 6: Animal health measures — Data 1: Farmer that has benefited from compensation.

— Action 1: Inland fishing vessels — Data 1: Tonnage of vessel modernised (GT). — Data 2: Power of vessel modernised (kW). — Data 3: Tonnage of vessel re-assigned (GT). — Data 4: Power of vessel re-assigned (kW). — Data 5: Vessel concerned.

— Action 2: Investments for the construction of inland fishing facilities — Data 1: Unit that has benefited.

— Action 3: Investments for extension, equipment and modernisation of inland fishing facilities — Data 1: Unit that has benefited.

— Action 1: Increase in processing capacity (construction of new units and/or extension of existing units) — Data 1: Tonnes/year of fresh or chilled products. — Data 2: Tonnes/year of preserved or semi-preserved products. — Data 3: Tonnes/year of frozen or deep-frozen products. — Data 4: Tonnes/year of other processed products (prepared meals, smoked, salted, dried products). — Data 5: size of enterprise (Micro, Small, Medium, Large).

— Action 2: Construction, extension, equipment and modernisation of processing units — Data 1: Unit that has benefited from improved hygiene/working conditions. — Data 2: Unit that has benefited from improved environmental conditions. — Data 3: Unit that has put in place improved production systems (quality, technological innovations). — Data 4: Size of enterprise (Micro, Small, Medium, Large).

— Action 3: Construction of new marketing establishment — Data 1: m2 of effective surface area. — Data 2: Size of enterprise (Micro, Small, Medium, Large).

— Action 4: Modernisation of existing marketing establishments — Data 1: Unit that has benefited from improved hygiene/working conditions. — Data 2: Unit that has benefited from improved environmental conditions. — Data 3: Unit that has put in place improved systems (quality, technological innovations). — Data 4: Unit that has put in place the treatment, processing and marketing of fisheries and aquaculture products wastes. — Data 5: Unit benefiting from this action broken down by size of enterprise (Micro, Small, Medium, Large).

Priority axis 3: Measures of common interest

— Data 1: Producers' organisations created.

— Data 2: Producers' organisations restructured.

— Data 3: Operation that upgrades professional skills, or develops new training methods and tools.

— Data 4: Operation that promotes partnership between scientists and operators in the fisheries sector.

— Data 5: Operation on networking and exchange of experience and best practice among organisations promoting equal opportunities between men and women and other stakeholders.

— Data 6: Other operation(s).

— Data 1: Marine area (km2) protected by the installation of static or movable facilities.

— Data 2: Operation concerning rehabilitation of inland waters.

— Data 3: Operation concerning Nature 2000 areas.

— Data 4: Operation concerning spawning grounds and migration routes rehabilitated.

— Action 1: Investments in existing fishing ports — Data 1: m3 of cold storage created. — Data 2: m3 of storage other than cold stores. — Data 3: Operation of handling installations. — Data 4: Operation of ice machines. — Data 5: Operation to supply installations (electricity, water, fuel) — Data 6: Operation regarding other facilities. — Data 7: m2 of quays restructured. — Data 8: Linear metres of quays restructured. — Data 9: m2 of surface usable for first sale.

— Action 2: Investments in restructuring and improvement of landing sites — Data 1: Landing site that has benefited.

— Action 3: Safety related investments for the construction or modernisation of small fishing shelters — Data 1: Fishing shelter that has benefited.

— Action 4: Safety related investments for the modernisation of small fishing shelters — Data 1: Fishing shelter that has benefited.

— Data 1: Campaign for fisheries and aquaculture products.

— Data 2: Campaign to improve the image of fisheries.

— Data 3: Operation to promote products obtained using methods with low impact on the environment.

— Data 4: Operation to promote products recognised under the terms of Council Regulation (EEC) No 2081/92 (29).

— Data 5: Operation to implement a quality policy for fisheries and aquaculture products.

— Data 6: Operation to promote quality certification.

— Data 7: Operation to promote the supply of the market of surplus or underexploited species.

— Data 8: Operation to implement market surveys.

— Data 1: Test on innovative technology.

— Data 2: Test on management plans and fishing effort allocation plans.

— Data 3: Operation to develop and test methods to improve gear selectivity/reduce by-catches and discards.

— Data 4: Operation to test alternative types of fishing management techniques.

— Data 1: Vessel modified for historical heritage.

— Data 2: Vessel modified for fisheries research (FR).

— Data 3: Vessel modified for training activities (TA).

— Data 4: Vessel modified for control (C).

Priority axis 4: Sustainable development of fisheries areas

— Data 1: Operation for strengthening the competitiveness of the fisheries areas.

— Data 2: Operation for restructuring and redirecting economic activities.

— Data 3: Operation for diversifying activities.

— Data 4: Operation for adding value to fisheries products.

— Data 5: Operation for supporting small fisheries communities and tourism related infrastructure.

— Data 6: Operation for protecting the environment in fisheries areas.

— Data 7: Operation for re-establishing the production potential in fisheries areas.

— Data 8: Operation for promoting inter-regional and trans-national cooperation.

— Data 9: Operation for acquiring skills and facilitating the preparation and implementation of the local development strategy.

— Data 10: Operation for the contribution to the running cost of the groups.

— Data 11: Operation on communication actions by the groups.

— Data 12: Other operation(s).

Priority axis 5: Technical assistance

— Action 1: Management and implementation of programmes — Data 1: Operation for technical assistance for the implementation of the operational programme. — Data 2: Operation for improving administrative capacity. — Data 3: Operation on communications actions. — Data 4: Operation for facilitating networking. — Data 5: Operations for evaluation.

— Action 2: Studies (excluding evaluation) — Data 1: studies.

— Action 3: Publicity and information — Data 1: Operation for publicity. — Data 2: Operation for information to stakeholders.

— Action 4: Other technical assistance measures — Data 1: Operation of other kind of technical assistance.

ANNEX IV

1.

A random statistical sampling method allows conclusions to be drawn from the results of audits of the sample on the overall expenditure from which the sample was taken, and hence provides evidence to obtain assurance on the functioning of the management and control systems

2.

The assurance provided on the functioning of the systems is determined by the degree of confidence resulting from the conclusions of the system audits and from the audits of operations in the sample selected by a random statistical sampling method. In order to obtain a high level of assurance, that is, a reduced audit risk, the audit authority shall combine the results of system audits and audits of operations. The audit authority first evaluates the reliability of the systems (high, average or low), taking into account the results of the system audits, so as to determine the technical parameters of the sampling, in particular the confidence level and the expected error rate. Member States may also use the results of the report on the compliance assessment under Article 71(2) of Regulation (EC) No 1198/2006. The combined level of assurance obtained from the system audits and the audits of operations must be high. The confidence level used for sampling operations must not be less than 60 % with a maximum materiality level of 2 %. For a system evaluated as having low reliability, the confidence level used for sampling operations must not be below 90 %. The audit authority shall describe in the annual control report the way assurance has been obtained.

3.

The reliability of management and control systems shall be determined using criteria established by the audit authority for systems audits, including a quantified assessment of all key elements of the systems and encompassing the main authorities and intermediate bodies participating in the management and control of the operational programme. A record of the assessments carried out shall be kept in the audit file.

ANNEX V

1. INTRODUCTION

— Identification of the audit authority responsible for drawing up the audit strategy and of any other bodies which have contributed. Explanation of the procedure followed for drawing up the audit strategy.

— Specification of the overall objectives of the audit strategy.

— Explanation of the functions and responsibility of the audit authority and other bodies carrying out audits under its responsibility.

— Indication of the independence of the audit authority from the managing authority and certifying authority.

— Confirmation by the audit authority that the bodies that carry out the audits pursuant to Article 61(3) of Regulation (EC) No 1198/2006 have the requisite functional independence.

2. LEGAL BASIS AND SCOPE

— Indication of any national regulatory framework that affects the audit authority, and its functions.

— Indication of the period covered by the strategy.

3. METHODOLOGY

— Indicate the audit methodology to be followed taking account of internationally accepted audit standards (including but not limited to, INTOSAI, IFAC and IIA), audit manuals and any other specific documents.

4. AUDIT APPROACH AND PRIORITIES

— Materiality thresholds for planning purposes and for reporting deficiencies.

— Indication of the types of audits to be carried out (system audits, audits of operations).

— For system audits: (a) Specification of the body or bodies responsible for the audit work; (b) Specification of the bodies to be audited; (c) Indication of any horizontal issues to be covered by the system audits, such as public procurement, state aid, environmental requirements, equal opportunities and IT systems.

— For audits of operations: (a) specification of the responsible body or bodies responsible for the audit work; (b) specification of the criteria for determining the assurance level gained from system audits and reference to the documentation used for applying the sampling methodology set out in Article 43; (c) specification of the procedure for determining steps to be taken where material errors are detected.

— Indication and justification of the priorities and audit objectives established for the whole programming period.

— Explanation of the linkage of the risk assessment results to the audit work planned.

— An indicative audit schedule of audit assignments for the forthcoming year provided in a table format.

5. RISK ASSESSMENT

— Indication of the procedures followed, including the extent to which the results of previous audits of the bodies and systems have been taken into account (such as audits from the 2000 to 2006 period, audit work for the compliance assessment).

— Indication of the managing authority, certifying authority and intermediate bodies covered.

— Indication of the risk factors taken into account, including any horizontal issues identified as risk areas.

— Indication of the results through identification and prioritisation of the key bodies, processes, controls and priority axes to audit.

6. RELIANCE ON THE WORK OF OTHERS

— Indication of the extent to which certain components are audited by other auditors and the extent of potential reliance on such work.

— Explanation of how the audit authority will ensure the quality of the work carried out by the other bodies, taking account of internationally accepted auditing standards.

7. RESOURCES

— Indication of planned resources to be allocated, at least for the forthcoming year.

8. REPORTING

— Indication of internal procedures for reporting, such as provisional and final audit reports, and of the right of the body audited to be heard and to provide an explanation before a final position is taken.

ANNEX VI

PART A

Model annual control report under Article 61(1)(e)(i) of Regulation (EC) No 1198/2006 and Article 44(2) of the present Regulation

1. INTRODUCTION

— Indication of the responsible audit authority and other bodies that have been involved in preparing the report.

— Indication of the 12-month (reference) period from which the random sample was drawn.

— Identification of the operational programme covered by the report (CCI number) and of its managing and certifying authority.

— Description of the steps taken to prepare the report.

2. CHANGES IN MANAGEMENT AND CONTROL SYSTEMS

— Indication of any significant changes in the management and control systems notified to the audit authority as compared with the description provided under Article 71(1) of Regulation (EC) No 1198/2006 and of the dates from which the changes apply.

3. CHANGES TO AUDIT STRATEGY

— Indication of any changes that have been made to the audit strategy or are proposed, and of the reasons behind them.

4. SYSTEMS AUDITS

— Indication of the bodies that have carried out systems audits, including the audit authority itself.

— Summary list of the audits carried out (bodies audited).

— Description of the basis for selection of the audits in the context of the audit strategy.

— Description of the principal findings and conclusions drawn from the audit work for the management and control systems, and their functioning, including the sufficiency of management checks, certification procedures and the audit trail, adequate separation of functions and compliance with Community requirements and policies.

— Indication of whether any problems identified were considered to be of a systemic character, and the measures taken, including a quantification of the irregular expenditure and any related financial corrections.

5. AUDITS OF SAMPLE OF OPERATIONS

— Indication of the bodies that have carried out the sample audits, including the audit authority.

— Description of the basis for the selection of the sample(s).

— Indication of the materiality level and, in the case of statistical sampling, the confidence level applied and the interval, if applicable.

— Summary table (see point 9) indicating the eligible expenditure declared to the Commission during the calendar (reference) year (ending in the audit period), the amount of expenditure audited, and the percentage of expenditure audited in relation to total eligible expenditure declared to the Commission (both for the last calendar year and cumulatively). Information relating to the random sample must be distinguished from that related to other samples.

— Description of the principal results of the audits, indicating in particular the amount of irregular expenditure and the error rate resulting from the random sample audited.

— Indication of the conclusions drawn from the results of the audits with regard to the effectiveness of the management and control system.

— Information on the follow-up of irregularities including revision of previously reported error rates.

— Indication of whether any problems identified were considered to be systemic in nature, and the measures taken, including a quantification of the irregular expenditure and any related financial corrections.

6. COORDINATION BETWEEN AUDIT BODIES AND SUPERVISION WORK OF THE AUDIT AUTHORITY

— Description of the procedure for supervision applied by the audit authority to other bodies carrying out the audits pursuant to Article 61(3) of Regulation (EC) No 1198/2006 (if applicable).

7. FOLLOW-UP OF PREVIOUS YEARS’ AUDIT ACTIVITY

— Information on the follow-up of outstanding audit recommendations and on the follow up of systems audits and audits of operations from earlier years.

8. OTHER INFORMATION (IF APPLICABLE)

9. TABLE FOR DECLARED EXPENDITURE AND SAMPLE AUDITS

Reference (CCI no) Expenditure declared in reference year Expenditure in reference year audited for the random sample Amount and percentage (error rate) of irregular expenditure in random sample Other expenditure audited (1) Amount of irregular expenditure in other expenditure sample Total expenditure declared cumulatively Total expenditure audited cumulatively as a percentage of total expenditure declared cumulatively
(2) (3) Amount %
(1) Expenditure for complementary sample and expenditure for random sample not in the reference year. (2) Amount of expenditure audited. (3) Percentage of expenditure audited in relation to eligible expenditure declared to the Commission in the reference year.
Reference (CCI no) Expenditure declared in reference year Expenditure in reference year audited for the random sample Amount and percentage (error rate) of irregular expenditure in random sample Other expenditure audited (1) Amount of irregular expenditure in other expenditure sample Total expenditure declared cumulatively Total expenditure audited cumulatively as a percentage of total expenditure declared cumulatively
--- --- --- --- --- --- --- --- --- ---
(2) (3) Amount %
(1) Expenditure for complementary sample and expenditure for random sample not in the reference year. (2) Amount of expenditure audited. (3) Percentage of expenditure audited in relation to eligible expenditure declared to the Commission in the reference year.

PART B

Model annual opinion under Article 61(1)(e)(ii) of Regulation (EC) No 1198/2006 and Article 44(2) of the present Regulation

To the European Commission, Directorate-General […]

1. INTRODUCTION

I, the undersigned, representing the (name of body designated by Member State), have examined the functioning of the management and control systems in the operational programme (name of operational programme, CCI code number, period), in order to issue an opinion on whether the systems functioned effectively so as to provide reasonable assurance that the statements of expenditure presented to the Commission are correct and as a consequence reasonable assurance that the underlying transactions are legal and regular.

2. SCOPE OF THE EXAMINATION

The examination was carried out in accordance with the audit strategy in respect of this programme during the period 1 July to 30 June (year) and reported in the attached annual control report under Article 61(1)(e)(i) of Regulation (EC) No 1198/2006.

Either

There were no limitations on the scope of the examination

Or

The scope of the examination was limited by the following factors:

(a)

(b)

(c) etc.

(Indicate any limitation on the scope of the examination, for example any systemic problems, weaknesses in the management and control system, lack of supporting documentation, cases under legal proceedings, etc and estimate the amounts of the expenditure and the Community contribution affected. If the audit authority does not consider that the limitations have an impact on the final expenditure declared, this must be stated.)

3. OPINION

Either

(Unqualified opinion)

Based on the examination referred to above, it is my opinion that for the abovementioned period the management and control system established for the programme … (name of operational programme, CCI code number, period) complied with the applicable requirements of Articles 57 to 61 of Regulation (EC) No 1198/2006 and Chapter VII of Commission Regulation (EC) No 498/2007 (30) and functioned effectively so as to provide reasonable assurance that the statements of expenditure presented to the Commission are correct and as a consequence reasonable assurance that the underlying transactions are legal and regular.

Or

(Qualified opinion)

Based on the examination referred to above, it is my opinion that for the abovementioned period the management and control systems established for the programme … (name of operational programme, CCI code number, period) complied with the applicable requirements of Articles 57 to 61 of Regulation (EC) No 1198/2006 and Chapter VII of Commission Regulation (EC) No 498/2007 and functioned effectively so as to provide reasonable assurance that the statements of expenditure presented to the Commission are correct and as a consequence reasonable assurance that the underlying transactions are legal and regular, except in the following respects (31).

My reasons for considering that this (these) aspect(s) of the systems did not comply with the requirements and/or did not operate in such a way as to give a reasonable assurance that the statements of expenditure presented to the Commission are correct as follows … (32).

I estimate the impact of the qualification(s) to be … of the total expenditure declared. The Community contribution affected is thus ….

Or

(Adverse opinion)

Based on the examination referred to above, it is my opinion that for the abovementioned period the management and control system established for the programme … (name of operational programme, CCI code number, period) did not comply with the requirements of Articles 57 to 61 of Regulation (EC) No 1198/2006 and Chapter VII of Commission Regulation (EC) No 498/2007 and did not function effectively so as to provide reasonable assurance that the statements of expenditure presented to the Commission are correct and, as a consequence, does not provide reasonable assurance that the underlying transactions are legal and regular.

This adverse opinion is based on … (33)

Date: Signature:

ANNEX VII

PART A

Model final control report

1. INTRODUCTION

— Indication of the responsible audit authority and other bodies that have been involved in preparing the report.

— Indication of the last reference period from which the random sample was drawn.

— Identification of the operational programme covered by the report and its managing and certifying authorities.

— Description of the steps taken to prepare the report.

2. CHANGES IN MANAGEMENT AND CONTROL SYSTEMS AND AUDIT STRATEGY (34)

— Indication of any significant changes in the management and control systems notified to the audit authority as compared with the description provided under Article 71(1) of Regulation (EC) No 1198/2006, and of the dates from which the changes apply.

— Indication of any changes that have been made to the audit strategy and reasons for such changes.

3. SUMMARY OF AUDITS CARRIED OUT UNDER ARTICLE 61(1)(a) AND (b) OF REGULATION (EC) No 1198/2006 AND ARTICLE 43 OF THE PRESENT REGULATION

— Indication of the bodies that have carried out systems audits, including the audit authority itself.

— Summary list of audits carried out: bodies audited and year of audit.

— Description of the basis for selection of audits in the context of the audit strategy (35).

— Description of the principal findings and the conclusions drawn from the audit work for the management and control systems and their functioning, including the sufficiency of management checks, certification procedures and the audit trail, adequate separation of functions and compliance with Community requirements and policies (35) .

— Indication of whether any problems identified were considered to be of a systemic character, and the measures taken, including a quantification of the irregular expenditure and any related financial corrections (35) .

— Indication of the bodies that carried out the sample audits, including the audit authority itself.

— Description of the basis for selection of the sample(s).

— Indication of the materiality level and, in the case of statistical sampling, the confidence level applied and the interval, if applicable.

— Description of the principal results of the audits, indicating in particular the amount of irregular expenditure and the error rate resulting from the random sample audited (35) .

— Indication of the conclusions drawn from the results of the audits with regard to the effectiveness of the management and control system.

— Information on the follow-up of irregularities, including revision of previously reported error rates.

— Indication of whether any problems identified were considered to be systemic in nature, and the measures taken, including a quantification of the irregular expenditure and any related financial corrections (35) .

4. FOLLOW-UP OF AUDIT ACTIVITY

— Information on the follow-up of the results of systems audits and audits of operations.

5. ADDITIONAL WORK UNDERTAKEN BY AUDIT AUTHORITY IN PREPARING ITS CLOSURE DECLARATION

— Summary of audits of closure procedure of managing and certifying authorities and intermediate bodies.

— Summary of the results of the examination of the debtors’ ledger kept under Article 60(f) of Regulation (EC) No 1198/2006.

— Summary of the results of re performance of controls on the accuracy of the amounts declared in relation to supporting documents.

— Summary of the results of examination of reports of other national or Community audit bodies (specify by category which reports have been received and examined).

— Summary of the results of the examination of information relating to follow-up of audit findings and dealing with irregularities.

— Summary of the results of the examination of additional work carried out by managing and certifying authorities to enable an unqualified opinion to be provided.

— Other.

6. LIMITATIONS ON THE SCOPE OF THE EXAMINATION BY THE AUDIT AUTHORITY

— Details of any factors that have limited the scope of the examination by the audit authority must be reported (36).

— Estimated amounts of expenditure and the Community contribution that are affected must be stated.

7. REPORTED IRREGULARITIES

— Confirmation that the procedure for reporting and following up irregularities, including the treatment of systemic problems, has been carried out in accordance with regulatory requirements.

— Confirmation of the accuracy of the information given in final report on implementation on the irregularities reported under Article 70(1)(b) of Regulation (EC) No 1198/2006.

— A list of cases of irregularity regarded as systemic and the amounts of expenditure affected.

8. OTHER INFORMATION (IF APPLICABLE)

9. TABLE FOR DECLARED EXPENDITURE AND SAMPLE AUDITS

Reference (CCI No) Expenditure declared in reference year Expenditure in reference year audited for the random sample Amount and percentage (error rate) of irregular expenditure in random sample Other expenditure audited (1) Amount of irregular expenditure in other expenditure sample Total expenditure declared cumulatively Total expenditure audited cumulatively as a percentage of total expenditure declared cumulatively
(2) (3) Amount. %
(1) Expenditure for complementary sample and expenditure for random sample not in the reference year. (2) Amount of expenditure audited. (3) Percentage of expenditure audited in relation to eligible expenditure declared to the Commission in the reference year.
Reference (CCI No) Expenditure declared in reference year Expenditure in reference year audited for the random sample Amount and percentage (error rate) of irregular expenditure in random sample Other expenditure audited (1) Amount of irregular expenditure in other expenditure sample Total expenditure declared cumulatively Total expenditure audited cumulatively as a percentage of total expenditure declared cumulatively
--- --- --- --- --- --- --- --- --- ---
(2) (3) Amount %
(1) Expenditure for complementary sample and expenditure for random sample not in the reference year. (2) Amount of expenditure audited. (3) Percentage of expenditure audited in relation to eligible expenditure declared to the Commission in the reference year.

PART B

Closure declaration

To the European Commission, Directorate-General […]

1. INTRODUCTION

I, the undersigned, … representing the (name of the body designated by Member State), have for the operational programme … (name of the operational programme, CCI code number, period) examined the results of the audit work carried out on this programme by or under the responsibility of the audit authority in accordance with the audit strategy (and have carried out the additional work I judged necessary). The results of the examination and the additional work I have performed are summarised in the attached final control report (which also contains the information required by the annual control reports for the period 1 January 2015 to 31 December 2016). I have planned and performed this work with a view to obtaining a reasonable assurance as to whether the payment application for the balance of the Community contribution to the programme is correct and valid and the underlying transactions covered by the final statement of expenditure are legal and regular.

2. SCOPE OF THE EXAMINATION

The examination was carried out in accordance with the audit strategy in respect of this programme and reported in the attached final control report under Article 61(1)(f) of Regulation (EC) No 1198/2006.

Either

There were no limitations on the scope of the examination.

Or

The scope of the examination was limited by the following factors:

(a)

(b)

(c) etc.

(Indicate any limitation on the scope of the examination, for example any systemic problems, weaknesses in the management and control system, lack of supporting documentation, cases under legal proceedings, etc., and estimate the amounts of expenditure and the Community contribution affected. If the audit authority does not consider that the limitations have an impact on the final expenditure declared, this must be stated.)

3. IRREGULARITIES AND ERROR RATES

Either

The cases of irregularity and error rates found in the audit work is not such as to preclude an unqualified opinion given the satisfactory way they have been dealt with by the managing authority and the trend in the level of their occurrence over time.

Or

The cases of irregularity and error rates found in the audit work and the way they have been dealt with by the managing authority are such as to preclude an unqualified opinion. A list of these cases is provided in the final control report, together with an indication of their possible systemic character and the scale of the problem. The amounts of total declared expenditure and public contribution that could be affected are … respectively. As a consequence, the corresponding Community contribution that could be affected is ….

4. OPINION

Either

(Unqualified opinion)

If there were no limitations on the scope of the examination and the cases of irregularity and error rates and the way they have been dealt with by the managing authority do not preclude an unqualified opinion:

Based on the examination referred to above, it is my opinion that the final statement of expenditure presents fairly, in all material respects, the expenditure paid under the operational programme, that the application for payment of the balance of the Community contribution to this programme is valid and that the underlying transactions covered by the final statement of expenditure are legal and regular.

Or

(Qualified opinion)

If there were limitations on the scope of the examination and/or cases of irregularity and error rates and the way they have been dealt with by the managing authority call for a qualified opinion but do not justify an unfavourable opinion for all the expenditure concerned:

Based on the examination referred to above, it is my opinion that the final statement of expenditure presents fairly, in all material respects, the expenditure paid under the operational programme, that the application for payment of the balance of the Community contribution to this programme is valid and that the underlying transactions covered by the final statement of expenditure are legal and regular, except with regard to the matters referred to at point 2 above and/or to the observations at point 3 regarding the error rates and cases of irregularity and the way they have been dealt with by the managing authority, the impact of which is quantified above. I estimate the impact of these qualifications to be … of the total expenditure declared. The Community contribution affected is thus ….

Or

(Adverse opinion)

If there were major limitations on the scope of the examination error rates and cases of irregularity and the way they have been dealt with by the managing authority are such that no conclusion can be reached on the reliability of the final statement of expenditure without considerable further work:

Based on the examination referred to above, and in particular in view of the matters referred to at point 2 and/or the error rates and cases of irregularity and the fact that they have not been dealt with satisfactorily by the managing authority as reported at point 3, it is my opinion that that the final statement of expenditure does not present fairly, in all material respects, the expenditure paid under the operational programme, that, as a consequence, the application for payment of the balance of the Community contribution to this programme is not valid and that the underlying transactions covered by the final statement of expenditure are not legal and regular.

Date: Signature:

ANNEX VIII

To the European Commission, Directorate-General […]

The managing authority for the programme … (name of the operational programme, CCI code number, period) has submitted a statement of expenditure relating to operations [completed as at … (date up to which operations were completed)/completed between … and … (dates between which operations were completed/and is applying for partial closure of the programme under Article 85(2)(b) of Regulation (EC) No 1198/2006 for these operations.

I, the undersigned, representing the (name of the body designated by the Member State), have examined the results of the audit work carried out on this programme as set out in the annual control reports and annual opinions issued under Article 61(1)(e)(i) and (ii) of Regulation (EC) No 1198/2006 for the year/years …

I have planned and performed this work with a view to obtaining a reasonable assurance as to whether the statement of expenditure concerned is correct and valid and the underlying transactions covered by the statement of expenditure are legal and regular.

Opinion

Based on the examination referred to above, it is my opinion that the statement of expenditure on completed operations submitted by the managing authority for the programme … (name of operational programme, CCI code number, period) for the purpose of partial closure of the programme in respect of operations (completed as at …/completed between … and …) presents fairly, in all material respects, the expenditure paid and that the underlying transactions are legal and regular.

Date: Signature:

ANNEX IX

PART A

Certificate and statement of expenditure and application for interim payment

PART B

Certificate and statement of expenditure and application for final payment

ANNEX X

ANNUAL STATEMENT ON WITHDRAWN AND RECOVERED AMOUNTS AND PENDING RECOVERIES AND IRRECOVERABLE AMOUNTS UNDER ARTICLE 46(2)

1.

Withdrawals for the year 20… deducted from statements of expenditure for regions eligible:

Withdrawals (1)
Under the convergence objective
a b c d e f g
Priority axis Total amount in EUR of expenditure paid by beneficiaries withdrawn (2) Corresponding public contribution withdrawn in EUR Corresponding EFF contribution withdrawn in EUR (3) Total amount in EUR of expenditure withdrawn relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (4) Amount in EUR of corresponding public contribution withdrawn relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 Amount in EUR of corresponding EFF contribution withdrawn relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (5)
1
2
3
4
5
Total
Under the non-Convergence objective
a b c d e f g
Priority axis Total amount in EUR of expenditure paid by beneficiaries withdrawn (2) Corresponding public contribution withdrawn in EUR Corresponding EFF contribution withdrawn (3) in EUR Total amount in EUR of expenditure withdrawn relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (4) Amount in EUR of corresponding public contribution withdrawn relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 Amount in EUR of corresponding EFF contribution withdrawn relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (5)
1
2
3
4
5
Total
(1) This table (withdrawals) is completed relating to expenditure already declared to the Commission and which has been withdrawn from the programme following detection of the irregularity. If table 1 is completed, tables 2, 3 and 4 of this Annex will not need to be completed. (2) This amount is the total amount of expenditure already declared to the Commission which was affected by irregularities and which has been withdrawn. (3) This amount is the EFF part of expenditure already declared to the Commission which was affected by irregularities and which has been withdrawn. (4) This amount is the part of the amount in column (b) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007. (5) This amount is part of the amount in column (d) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007.
2.

Recoveries for the year 20… deducted from statements of expenditure for regions eligible:

Recoveries (1)
Under the convergence objective
h i j k l m n
Priority axis Total amount in EUR of expenditure paid by beneficiaries (2) Public contribution recovered (3) in EUR Corresponding EFF contribution recovered (4) in EUR Total amount in EUR of expenditure recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (5) Amount in EUR of public contribution recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (6) Amount in EUR of corresponding EFF expenditure recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (7)
1
2
3
4
5
Total
Under the non-Convergence objective
h i j k l m n
Priority axis Total amount in EUR of expenditure paid by beneficiaries (2) Public contribution recovered (3) in EUR Corresponding EFF contribution recovered (4) in EUR Total amount in EUR of expenditure recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (5) Amount in EUR of public contribution recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (6) Amount in EUR of corresponding EFF expenditure recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (7)
1
2
3
4
5
Total
(1) This table (recoveries) is completed relating to expenditure which was left for the time being in the programme pending outcome of recovery proceedings and which has been deducted following recovery. If table 2 is completed, tables 1, 3 and 4 of this Annex will not need to be completed. (2) This is the total amount of expenditure already declared to the Commission which was affected by irregularities and in respect of which the corresponding public contribution has been recovered. (3) This is the amount of public contribution effectively recovered from the beneficiary. (4) This amount is the corresponding EFF part of expenditure already declared to the Commission which was affected by irregularities and which has been recovered. (5) This amount relates to the part of the amount in column (i) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007. (6) This amount is the part of the amount in column (j) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007. (7) This amount is part of the amount in column (k) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007.
3.

Pending recoveries as at 31.12.20…

Convergence
a b c d e f g h
Priority axis Year of launch of recovery proceedings Total amount in EUR of eligible expenditure paid by beneficiaries (1) Public contribution to be recovered (2) in EUR Corresponding EFF contribution to be recovered (3) in EUR Total amount in EUR of expenditure relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (4) Amount in EUR of public contribution to be recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (5) Amount in EUR of corresponding EFF expenditure to be recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (6)
1 2007
2008
2 2007
2008
3 2007
2008
Total
Non-Convergence
a b c d e f g h
Priority axis Year of launch of recovery proceedings Total amount in EUR of eligible expenditure paid by beneficiaries (1) Public contribution to be recovered (2) in EUR Corresponding EFF contribution to be recovered (3) in EUR Total amount in EUR of expenditure relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (4) Amount in EUR of public contribution to be recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (5) Amount in EUR of corresponding EFF expenditure to be recovered relating to irregularities reported under Article 55(1) of Regulation (EC) No 498/2007 (6)
1 2007
2008
2 2007
2008
3 2007
2008
Total
(1) This is the amount of expenditure paid by the beneficiary corresponding to the public contribution in column (d). (2) This is the public contribution subject to recovery proceedings at the level of the beneficiary. (3) This is the EFF contribution subject to recovery proceedings at the level of the beneficiary. (4) This amount relates to the part of the amount in column (c) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007. (5) This amount relates to the part of the amount in column (d) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007. (6) This amount relates to the part of the amount in column (e) which has been reported as irregular under the reporting procedures laid down in Article 55 of Regulation (EC) No 498/2007.
4.

Irrecoverable amounts as at 31.12.20…

Convergence
a b c d e f g h i j k l
Number of operation Priority axis Irregularity identification number if applicable (1) Year of launch of recovery proceedings Total expenditure in EUR paid by beneficiaries declared as irrecoverable (2) Public contribution declared as irrecoverable (3) in EUR Corresponding EFF contribution declared as irrecoverable (4) in EUR Date of last payment of public contribution to beneficiary Date of establishment of irrecoverability Reason for irrecoverability Recovery measures taken including date of recovery order Indicate whether the Community share should be borne by the budget of the European Union (Y/N)
X 20..
Y 20..
Z 20..
Total
Non-Convergence
a b c d e f g h i j k l
Number of operation Priority axis Irregularity identification number if applicable (1) Year of launch of recovery proceedings Total expenditure in EUR paid by beneficiaries declared as irrecoverable (2) Public contribution declared as irrecoverable (3) in EUR Corresponding EFF contribution declared as irrecoverable (4) in EUR Date of last payment of public contribution to beneficiary Date of establishment of irrecoverability Reason for irrecoverability Recovery measures taken including date of recovery order Indicate whether the Community share should be borne by the budget of the European Union (Y/N)
X 20..
Y 20..
Z 20..
Total
(1) This is the reference number attributed to the irregularity or other identification referred to in Article 40(4) of Regulation (EC) No 498/2007. (2) This amount is the amount of expenditure paid by the beneficiary corresponding to the public contribution in column (f). (3) This is the amount of public contribution paid for which it was established that recovery could not be carried out or for which recovery is not expected to take place. (4) This is the EFF contribution paid for which it was established that recovery could not be carried out or for which recovery is not expected to take place.

ANNEX XI

Statement of expenditure by priority axis for a partial closure

Operational Programme reference (CCI No):

Member State:

Date of submission to the Commission:

Total certified eligible expenditure of operations completed between …/…/ and 31/12 [year] in the regions eligible under the convergence objective:

Priority axis 2007-2015
Total expenditure certified Public contribution
EFF contribution National contribution
Priority axis 1: Total
Priority axis 2: Total
Priority axis 3: Total
Priority axis 4: Total
Priority axis 5: Total
Grand total

Total certified eligible expenditure of operations completed between …/…/ and 31/12 [year] in the regions eligible under the non-convergence objective:

Priority axis 2007-2015
Total expenditure certified Public contribution
EFF contribution National contribution
Priority axis 1: Total
Priority axis 2: Total
Priority axis 3: Total
Priority axis 4: Total
Priority axis 5: Total
Grand total

ANNEX XII

PART A

Model description of management and control systems

1. GENERAL

— [Name of the] Member State:

— Title of the programme and CCI No:

— Name of main contact person, including e-mail and fax: (body responsible for coordination of descriptions)

1.3.1. Managing authority (Name, address and contact person of the managing authority)

1.3.2. Intermediate bodies (Name, address and contact person of the intermediate bodies)

1.3.3. Certifying authority (Name, address and contact person of the certifying authority)

1.3.4. The audit authority and bodies carrying out audits under the responsibility of the audit authority (Name, address and contact person of the audit authority and other audit bodies)

2. MANAGING AUTHORITY

2.1.1. The date and form of the formal designation authorising the managing authority to carry out its functions

2.1.2. Specification of the functions and tasks carried out directly by the managing authority

2.1.3. Functions formally delegated by the managing authority (functions, intermediate bodies, form of delegation)

2.2.1. Organisation chart and specifications of the functions of the units (including indicative number of posts allocated)

2.2.2. Written procedures prepared for use by staff of the managing authority/intermediate bodies (date and reference)

2.2.3. Description of procedures for selecting and approving operations and for ensuring their compliance, for their whole implementing period, with applicable Community and national rules (Article 59(a) of Regulation (EC) No 1198/2006)

2.2.4. Verification of operations (Article 59(b) of Regulation (EC) No 1198/2006)

2.2.5. Processing of applications for reimbursement

2.2.6. Description of how information will be transmitted to the certifying authority by the managing authority

2.2.7. Eligibility rules laid down by the Member State and applicable to the operational programme

2.4.1. Instructions and guidance issued on the applicable rules (date and reference)

2.4.2. Measures foreseen to ensure that applicable rules are complied with, for example management checks, controls, audits

2.5.1. Description of how the requirements under Article 41 of Regulation (EC) No 498/2007 will be implemented for the programme and/or for individual priorities

2.5.2. Instructions given on retention of supporting documents by beneficiaries (date and reference)

2.6.1. Instructions issued on reporting and correction of irregularities and recording of debt and recoveries of undue payments (date and reference)

2.6.2. Description of the procedure (including flowchart) to comply with the obligation to report irregularities in accordance with article 55 of Regulation (EC) No 498/2007

3. INTERMEDIATE BODIES

NB: This section must be completed separately for each intermediate body. Indicate the authority which has delegated the function to the intermediate bodies.

3.1.1. Specification of the main functions/tasks of the intermediate bodies.

3.2.1. Organisation chart and specifications of the functions of the units (including indicative number of posts allocated.)

3.2.2. Written procedures prepared for use by staff of the intermediate body (date and reference).

3.2.3. Description of procedures for selecting and approving operations (if not described under 2.2.3).

3.2.4. Verification of operations (Article 59(b) of Regulation (EC) No 1198/2006) (if not described under 2.2.4).

3.2.5. Description of procedures for processing of applications for reimbursement (if not described under 2.2.5).

4. CERTIFYING AUTHORITY

4.1.1. The date and form of the formal designation authorising the certifying authority to carry out its functions.

4.1.2. Specification of the functions carried out by the certifying authority.

4.1.3. Functions formally delegated by the certifying authority (functions, intermediate bodies, form of delegation).

4.2.1. Organisation chart and specification of the functions of the units (including indicative number of posts allocated).

4.2.2. Written procedures prepared for use by staff of the certifying authority (date and reference).

4.3.1. Description of the procedure by which statements of expenditure are drawn up, certified and submitted to the Commission.

4.3.2. Description of the steps performed by the certifying authority to ensure fulfilment of requirements under Article 60 of Regulation (EC) No 1198/2006).

4.3.3. Arrangements for access of the certifying authority to the detailed information on operations and verifications and audits held by the managing authority, intermediate bodies and audit authority.

4.4.1. Description of the accounting system to be set up and used as a basis for certification of expenditure to the Commission.

4.4.2. Level of detail of the accounting system:

4.5.1. Description of the system for ensuring the prompt recovery of Community assistance.

4.5.2. Arrangements made to maintain a debtors’ ledger and to deduct amounts recovered from expenditure to be declared.

5. AUDIT AUTHORITY AND AUDIT BODIES

5.2.1. Organisation charts (including the number of posts attributed).

5.2.2. Arrangements for ensuring the independence.

5.2.3. Required qualification or experience.

5.2.4. Description of procedures for monitoring the implementation of recommendations and corrective measures from audit reports.

5.2.5. Description of the procedures (where appropriate) for the supervision of the work of other bodies by the audit authority.

Description of the procedures for preparation of the annual control report, annual opinion and closure declaration.

6. INFORMATION SYSTEM (ARTICLE 59(c) OF REGULATION (EC) No 1198/2006)

— If not, indication of the date when it will be operational.

PART B

Model opinion issued under Article 71(2) of Regulation (EC) No 1198/2006 and under Article 50 of the present Regulation on the compliance of management and control system

To the European Commission, Directorate-General […]

Introduction

I, the undersigned representing (name of the audit authority or the operationally independent body designated by the Member State under Article 71(3) of Regulation (EC) No 1198/2006, as the body responsible for drawing up a report setting out the results of an assessment of the management and control systems established for the programme … (name of operational programme, CCI code number, period) and for giving an opinion on their compliance with Articles 57 to 61 of Regulation (EC) No 1198/2006 have carried out an examination in accordance with Article 50 of Regulation (EC) No 498/2007.

Scope of the examination

The examination was based on the description of the management and control systems received on dd/mm/yyyy from (name of body/bodies submitting the description). In addition, we have examined further information concerning (subjects) and interviewed staff of (bodies whose staff was interviewed).

The examination covered the managing, certifying and audit authorities, the body designated to receive the payments made by the Commission and to make the payments to beneficiaries and the following intermediate bodies (list …).

Opinion (37)

Either

(Unqualified opinion)

On the basis of the examination referred to above, it is my opinion that the management and control systems established for the programme … (name of operational programme, CCI code number, period) comply with the requirements of Articles 57 to 61 of Regulation (EC) No 1198/2006 and Chapter VII of Regulation (EC) No 498/2007.

Or

(Qualified opinion)

On the basis of the examination referred to above, it is my opinion that the management and control systems for the programme … (name of operational programme, CCI code number, period) comply with the requirements of Articles 57 to 61 of Regulation (EC) No 1198/2006 and Chapter VII of Regulation (EC) No 498/2007, except in the following respects … (38).

My reasons for considering that this/these aspect(s) of the systems do(es) not comply with the requirements and my assessment of the seriousness is as follows (39):

Or

(Adverse opinion)

On the basis of the examination referred to above, it is my opinion that the management and control systems for the programme (s) … (name of operational programme, CCI code number, period) do not comply with the requirements of Articles 57 to 61 of Council Regulation (EC) No 1198/2006 and Chapter VII of Regulation (EC) No 498/2007.

This adverse opinion is based on … (40)

Date: Signature:

ANNEXE XIII

Provisional forecasts of likely payment applications, for the current and subsequent financial year:

(in EUR)
Community co-financing (1)
(current year) (following year)
OP (CCI number) total
Convergence objective regions
Non-convergence objective regions
(1) Only provisional forecasts of likely applications for payment in respect of the Community contribution, and not total expenditure forecast, shall be stated in the table. In the provisional forecasts of likely applications for payment, the Community contribution must be stated for the year in question, and must not be cumulated from the beginning of the programming period.

ANNEX XIV

1. IDENTIFICATION

Member State:

Operational programme Programme number (CCI No):
Report on implementation Reporting year:
Date of approval of the annual report by the monitoring committee:

2. EXECUTIVE SUMMARY

3. OVERVIEW OF THE IMPLEMENTATION OF THE OPERATIONAL PROGRAMME BY PRORITY AXIS

3.1.   Information on the physical progress of the priority axes

For each quantifiable result indicator mentioned in the operational programme related to the objectives and the expected results, (for the year N, for the previous reporting years, as well as cumulatively).

Priority axis:

Indicators 2007 2008 2009 2010 2011 2012 2013 2014 2015 Total
Indicator 1: Achievement
Target (1)
Baseline
… etc … etc
Indicator n: Achievement
Target (1)
Baseline
(1) The target can be given annually or for the whole programming period.

In addition the information may be presented graphically. All indicators shall be broken down by gender where possible. If the figures (data) are not yet available, information on when they will become available and how the Managing Authority will provide it to the Commission shall be stated.

3.2.   Specific information for priority axes and measures

— Analysis of the results of in implementing the fishing effort adjustments plans using the indicators defined in the operational programme in the form of table as provided for in point 3.1.

— Fisheries areas selected, groups selected, budget allocated to them, percentage of fisheries areas covered by the local development strategies.

3.3.   Financial information (All financial data shall be expressed in Euro)

Expenditure paid by the beneficiaries included in payment claims sent to the managing authority Corresponding public contribution Corresponding EFF contribution Expenditure paid out by the body responsible for making payments to the beneficiaries EFF committed by the Managing authority Total payment requested from the Commission Specify the basis for calculating the Community contribution (Article 76(1) or 76(2) of Council Regulation (EC) No 1198/2006) Total payments received from the Commission
Priority axis 1
Priority axis 2
Priority axis 3
Priority axis 4
Priority axis 5
Grand total
Expenditure paid by the beneficiaries included in payment claims sent to the managing authority Corresponding public contribution Corresponding EFF contribution Expenditure paid out by the body responsible for making payments to the beneficiaries EFF committed by the Managing authority Total payment requested from the Commission Specify the basis for calculating the Community contribution (Article 76(1) or 76(2) of Council Regulation (EC) No1198/2006) Total payments received from the Commission
--- --- --- --- --- --- --- ---
Priority axis 1
Priority axis 2
Priority axis 3
Priority axis 4
Priority axis 5
Grand total

In addition, financial information may be provided graphically.

3.4.   Qualitative analysis

Analysis of the achievements as measured by physical and financial indicators, including qualitative analysis on the progress achieved in relation to the targets set out initially.

Demonstration on the effects of the operational programme on the promotion of equal opportunities between men and women as appropriate and description of the partnership agreements.

List of unfinished operations and the schedule for their completion (final report only).

3.5.   Monitoring arrangements

Monitoring and evaluation measures taken by the Managing Authority or the Monitoring Committee, to ensure the quality and effectiveness of implementation, in particular monitoring and evaluation measures, including mid-term and ongoing evaluation activities, data collection arrangements, difficulties encountered and steps taken to solve them.

3.6.   Significant problems encountered and measures taken to overcome them. (to be completed only if there was significant modification since the previous report)

Any significant problems encountered in implementing the operational programme and by priority axis to the extent of which any priority axis is affected, including a summary of serious problems identified under the procedure in Article 61(1)(e)(i) of Regulation (EC) No 1198/2006 where appropriate, as well as any measures taken by the managing authority or the monitoring committee to solve the problems.

3.7.   Recommendations from the Commission following annual examination of the Operational programme (to be completed only if there was significant modification since the previous report)

Where appropriate, the report must provide the description of how the Member State has implemented the recommendation from the Commission for the previous annual examination of the programme.

If any recommendation has not been implemented, the Managing Authority must provide reasons for not implementing it.

3.8.   Assistance repaid or re-used (to be completed only if there was significant modification since the previous report)

Information on the use made of assistance repaid or re-used following cancellation of assistance as referred to in Article 56 and Article 96(2) of the Regulation (EC) No 1198/2006.

3.9.   Substantial modification within the meaning of Article 56 of Regulation (EC) No 1198/2006 (to be completed only if there was significant modification since the previous report)

Cases where a substantial modification within the meaning of Article 56 of Regulation (EC) No 1198/2006 has been detected.

3.10.   Changes in the context and general conditions to the implementation of the Operational programme (to be completed only if there was significant modification since the previous report)

Description of any elements which, without stemming directly from the assistance of the operational programme, have a direct impact on the programme's implementation (such as legislative changes or unexpected socio-economic developments).

4. THE USE MADE OF TECHNICAL ASSISTANCE (TO BE COMPLETED ONLY IF THERE WAS SIGNIFICANT MODIFICATION SINCE THE PREVIOUS REPORT)

— Explanation of the use made of technical assistance.

— Percentage of the amount of the EFF's contribution allocated to the operational programme spent under technical assistance.

5. INFORMATION AND PUBLICITY (TO BE COMPLETED ONLY IF THERE WAS SIGNIFICANT MODIFICATION SINCE THE PREVIOUS REPORT)

— Measures taken to provide information and publicity on the Operational programme, including examples of best practices and highlighting significant events and the arrangements for the information and publicity measures referred to in point (d) of the second paragraph of Article 31 of Regulation (EC) No 498/2007 as well as the electronic address where such data may be found.

— Indicators in the form of tables as provided for in point 3.1.

— Evaluation of the results of the information and publicity measures in terms of visibility and awareness of the operational programme and of the role played by the Community (only in the annual implementation report covering the year 2010 and the final report on implementation).

6. INFORMATION ABOUT COMPLIANCE WITH COMMUNITY LAW

Any significant problems relating to the Compliance with the Community law which have been encountered in the implementation of the operational programme and the measures taken to deal with them.

7. COMPLEMENTARITY WITH OTHER INSTRUMENTS

Summary of the implementation of the arrangements made ensuring demarcation and complementarity between the assistance from the EFF, the Structural Funds, the Cohesion Fund, and other existing financial instruments (Article 6(4) of Regulation (EC) No 1198/2006).