Directive 2014/23/EU of the European Parliament and of the Council of 26 February 2014 on the award of concession contracts Text with EEA relevance

Type Directive
Publication 2014-03-28
Last updated 2026-01-01
State In force
Department Council of the European Union, European Parliament
Source EUR-Lex
articles 55
Reform history JSON API
1.

Contracting authorities and contracting entities shall offer by electronic means unrestricted and full direct access free of charge to the concession documents from the date of publication of a concession notice or, where the concession notice does not include the invitation to submit tenders, from the date on which an invitation to submit tenders was sent. The text of the concession notice or of these invitations shall specify the internet address at which the concession documents are accessible.

2.

Where, in duly justified circumstances, due to exceptional security, or technical reasons or due to the particularly sensitive nature of commercial information requiring a very high level of protection, unrestricted and full direct access free of charge by electronic means to certain concession documents cannot be offered, contracting authorities or contracting entities shall indicate in the notice or the invitation to submit a tender that the concession documents concerned will be transmitted by other means than electronic means and the time limit for the receipt of tenders shall be prolonged.

3.

Provided that it has been requested in good time, the contracting authorities and contracting entities or competent departments shall supply to all applicants or tenderers taking part in the concession award procedure additional information relating to the concession documents not later than six days before the deadline fixed for the receipt of tenders.

Article 35
Combating corruption and preventing conflicts of interest

Member States shall require contracting authorities and contracting entities to take appropriate measures to combat fraud, favouritism and corruption and to effectively prevent, identify and remedy conflicts of interest arising in the conduct of concession award procedures, so as to avoid any distortion of competition and to ensure the transparency of the award procedure and the equal treatment of all candidates and tenderers.

The concept of conflicts of interest shall at least cover any situation where staff members of the contracting authority or entity who are involved in the conduct of the concession award procedure or may influence the outcome of that procedure have, directly or indirectly, a financial, economic or other personal interest which might be perceived to compromise their impartiality and independence in the context of the concession award procedure.

With regard to conflicts of interest, the measures adopted shall not go beyond what is strictly necessary to prevent a potential conflict of interest or eliminate a conflict of interest that has been identified.

CHAPTER II Procedural guarantees

Article 36
Technical and functional requirements
1.

Technical and functional requirements shall define the characteristics required of the works or services that are the subject-matter of the concession. They shall be set out in the concession documents.

Those characteristics may also refer to the specific process of production or provision of the requested works or services provided that they are linked to the subject-matter of the contract and proportionate to its value and its objectives. The characteristics may for instance include quality levels, environmental and climate performance levels, design for all requirements (including accessibility for disabled persons) and conformity assessment, performance, safety or dimensions, terminology, symbols, testing and test methods, marking and labelling, or user instructions.

2.

Unless justified by the subject-matter of the contract, technical and functional requirements shall not refer to a specific make or source, or a particular process which characterises the products or services provided by a specific economic operator, or to trade marks, patents, types or a specific production with the effect of favouring or eliminating certain undertakings or certain products. Such a reference shall be permitted, on an exceptional basis, where a sufficiently precise and intelligible description of the subject- matter of the contract is not possible. Such reference shall be accompanied by the words ‘or equivalent’.

3.

A contracting authority or contracting entity shall not reject a tender on the grounds that the works and services tendered for do not comply with the technical and functional requirements to which it has referred, once the tenderer proves in its tender, by any appropriate means, that the solutions it has proposed satisfied in an equivalent manner the technical and functional requirements.

Article 37
Procedural guarantees
1.

Concessions shall be awarded on the basis of the award criteria set out by the contracting authority or contracting entity in accordance with Article 41, provided that all of the following conditions are fulfilled:

  • (a) the tender complies with the minimum requirements set, where applicable, by the contracting authority or contracting entity;
  • (b) the tenderer complies with the conditions for participation as referred to in Article 38(1); and
  • (c) the tenderer is not excluded from participating in the award procedure in accordance with Article 38(4) to (7), and subject to Article 38(9).

The minimum requirements referred to in point (a) shall contain conditions and characteristics (particularly technical, physical, functional and legal) that any tender should meet or possess.

2.

The contracting authority or contracting entity shall provide:

  • (a) in the concession notice, a description of the concession and of the conditions of participation;
  • (b) in the concession notice, in the invitation to submit a tender or in other concession documents, a description of the award criteria and, where applicable, the minimum requirements to be met.
3.

The contracting authority or contracting entity may limit the number of candidates or tenderers to an appropriate level, on condition that this is done in a transparent manner and on the basis of objective criteria. The number of candidates or tenderers invited shall be sufficient to ensure genuine competition.

4.

The contracting authority or contracting entity shall communicate the description of the envisaged organisation of the procedure and an indicative completion deadline to all participants. Any modification shall be communicated to all participants and, to the extent that they concern elements disclosed in the concession notice, advertised to all economic operators.

5.

The contracting authority or contracting entity shall provide for appropriate recording of the stages of the procedure using the means it judges appropriate, subject to compliance with Article 28(1).

6.

The contracting authority or contracting entity may hold negotiations with candidates and tenderers. The subject-matter of the concession, the award criteria and the minimum requirements shall not be changed during the course of the negotiations.

Article 38
Selection and qualitative assessment of candidates
1.

Contracting authorities and contracting entities shall verify the conditions for participation relating to the professional and technical ability and the financial and economic standing of the candidates or tenderers, on the basis of self-declarations, reference or references to be submitted as proof in accordance with the requirements specified in the concession notice that shall be non-discriminatory and proportionate to the subject-matter of the concession. The conditions for participation shall be related and proportionate to the need to ensure the ability of the concessionaire to perform the concession, taking into account the subject-matter of the concession and the purpose of ensuring genuine competition.

2.

With a view to meeting the conditions for participation laid down in paragraph 1, an economic operator may, where appropriate and for a particular concession, rely on the capacities of other entities, regardless of the legal nature of its links with them. Where an economic operator wants to rely on the capacities of other entities, it shall prove to the contracting authority or the contracting entity that it will have at its disposal, throughout the period of the concession, the necessary resources, for example, by producing a commitment by those entities to that effect. With regard to financial standing, the contracting authority or the contracting entity may require that the economic operator and those entities are jointly liable for the execution of the contract.

3.

Under the same conditions, a group of economic operators as referred to in Article 26 may rely on the capacities of participants in the group or of other entities.

4.

Contracting authorities and contracting entities as referred to in point (a) of Article 7(1) shall exclude an economic operator from participation in a concession award procedure where they have established that that economic operator has been the subject of a conviction by final judgment for one of the following reasons:

  • (a) participation in a criminal organisation, as defined in Article 2 of Council Framework Decision 2008/841/JHA ([^E0009]);
  • (b) corruption, as defined in Article 3 of the Convention on the fight against corruption involving officials of the European Communities or officials of Member States of the European Union ([^E0010]) and Article 2(1) of Council Framework Decision 2003/568/JHA ([^E0011]), as well as corruption as defined in the national law of the contracting authority or entity or the economic operator;
  • (c) fraud within the meaning of Article 1 of the Convention on the protection of the European Communities’ financial interests’ ([^E0012]);
  • (d) terrorist offences or offences linked to terrorist activities, as defined in Articles 1 and 3 of Council Framework Decision 2002/475/JHA ([^E0013]) respectively, or inciting, aiding or abetting or attempting to commit an offence, as referred to in Article 4 of that Framework Decision;
  • (e) money laundering or terrorist financing, as defined in Article 1 of Directive 2005/60/EC of the European Parliament and of the Council ([^E0014]);
  • (f) child labour and other forms of trafficking in human beings as defined in Article 2 of Directive 2011/36/EU of the European Parliament and of the Council ([^E0015]).

The obligation to exclude an economic operator shall also apply where the person convicted by final judgment is a member of the administrative, management or supervisory body of that economic operator or has powers of representation, decision or control therein.

Contracting entities other than those referred to in point (a) of Article 7(1) may exclude an economic operator from participation in a concession award procedure where they are aware that that economic operator has been the subject of a conviction by a final judgment for any of the reasons listed in the first subparagraph of this paragraph.

5.

Contracting authorities and contracting entities as referred to in point (a) of Article 7(1) shall exclude the economic operator from participation in a concession award procedure where it is aware that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions and where this has been established by a judicial or administrative decision having final and binding effect in accordance with the legal provisions of the country in which it is established or with those of the Member State of the contracting authority or contracting entity.

Furthermore, contracting authorities and contacting entities as referred to in point (a) of Article 7(1) may exclude or may be required by Member States to exclude from participation in a concession award procedure an economic operator where the contracting authority or entity can demonstrate by any appropriate means that the economic operator is in breach of its obligations relating to the payment of taxes or social security contributions.

This paragraph shall no longer apply when the economic operator has fulfilled its obligations by paying or entering into a binding arrangement with a view to paying the taxes or social security contributions due, including, where applicable, any interest accrued or fines.

6.

Member States may provide for a derogation from the mandatory exclusion provided for in paragraphs 4 and 5, on an exceptional basis, for overriding reasons relating to the public interest such as public health or protection of the environment.

Member States may also provide for a derogation from the mandatory exclusion provided for in paragraph 5, where an exclusion would be clearly disproportionate, in particular where only minor amounts of taxes or social security contributions are unpaid or where the economic operator was informed of the exact amount due following its breach of its obligations relating to the payment of taxes or social security contributions at such time that it did not have the possibility to take measures as provided for in the third subparagraph of paragraph 5 before expiration of the deadline for submitting its application.

7.

Contracting authorities or contracting entities may exclude or may be required by Member State to exclude from participation in a concession award any economic operator if one of the following conditions is fulfilled:

  • (a) where it can demonstrate by any appropriate means any violation of applicable obligations referred to in Article 30(3);
  • (b) where the economic operator is bankrupt or is the subject of insolvency or winding-up proceedings, where its assets are being administered by a liquidator or by the court, where it is in an arrangement with creditors, where its business activities are suspended or it is in any analogous situation arising from a similar procedure under national laws and regulations; the contracting authority or the contracting entity may, however, decide not to exclude or be required by the Member State not to so exclude an economic operator which is in one of the above situations where it has established that the economic operator in question will be able to perform the concession, taking into account the applicable national rules and measures on the continuation of business in the case of those situations;
  • (c) where the contracting authority can demonstrate by any appropriate means that the economic operator is guilty of a grave professional misconduct, which renders its integrity questionable;
  • (d) where a conflict of interest within the meaning of the second paragraph of Article 35, cannot be effectively remedied by any other less intrusive measure;
  • (e) where the contracting authority has sufficiently plausible indications to conclude that the economic operator has entered into agreements with other economic operators aimed at distorting competition;
  • (f) where the economic operator has shown significant or persistent deficiencies in the performance of a substantive requirement under a prior concession or a prior contract with a contracting authority or with a contracting entity as defined in this Directive or in Directive 2014/25/EU which led to early termination of that prior contract, damages or other comparable sanctions;
  • (g) where the economic operator has been guilty of serious misrepresentation in supplying the information required for the verification of the absence of grounds for exclusion or the fulfilment of the selection criteria, has withheld such information or is unable to submit the required documents supporting such information;
  • (h) where the economic operator has undertaken to unduly influence the decision-making process of the contracting authority or contracting entity, to obtain confidential information that may confer upon it undue advantages in the concession award procedure or to negligently provide misleading information that may have a material influence on decisions concerning exclusion, selection or award;
  • (i) in the case of concessions in the fields of defence and security as referred to in Directive 2009/81/EC, where the economic operator has been found, on the basis of any means of evidence, including protected data sources, not to possess the reliability necessary to exclude risks to the security of the Member State.
8.

Contracting authorities and contacting entities as referred to in point (a) of Article 7(1) shall at any time during the procedure exclude an economic operator where it turns out that the economic operator in question is, in view of acts committed or omitted either before or during the procedure, in one of the situations referred to in paragraph 4 of this Article and the first subparagraph of paragraph 5 of this Article.

At any time during the procedure, contracting authorities and contacting entities may exclude or may be required by Member States to exclude an economic operator where it turns out that the economic operator in question is, in view of acts committed or omitted either before or during procedure, in one of the situations referred to in the second subparagraph of paragraph 5 and in paragraph 7.

9.

Any economic operator that is in one of the situations referred to in paragraphs 4 and 7 may provide evidence to the effect that measures taken by the economic operator are sufficient to demonstrate its reliability despite the existence of the relevant ground for exclusion. If such evidence is considered to be sufficient, the economic operator concerned shall not be excluded from the procedure.

For this purpose, the economic operator shall prove that it has paid or undertaken to pay compensation in respect of any damage caused by the criminal offence or misconduct, clarified the facts and circumstances in a comprehensive manner by actively collaborating with the investigating authorities and taken concrete technical, organisational and personnel measures that are appropriate to prevent further criminal offences or misconduct. The measures taken by the economic operators shall be evaluated taking into account the gravity and particular circumstances of the criminal offence or misconduct. Where the measures are considered to be insufficient, the economic operator concerned shall receive a statement of the reasons for that decision.

An economic operator which has been excluded by a final judgment from participating in procurement or concession award procedures shall not be entitled to make use of the possibility provided under this paragraph during the period of exclusion resulting from that judgment in the Member States where the judgment is effective.

10.

By law, regulation or administrative provision and having regard for Union law, Member States shall specify, the implementing conditions for this Article. They shall in particular, determine the maximum period of exclusion if no measures as specified in paragraph 9 are taken by the economic operator to demonstrate its reliability. Where the period of exclusion has not been set by final judgment, that period shall not exceed five years from the date of the conviction by final judgment in the cases referred to in paragraph 4 and three years from the date of the relevant event in the cases referred to in paragraph 7.

Article 39
Time limits for receipt of applications and tenders for the concession
1.

When fixing the time limits for the receipt of applications or of tenders contracting authorities or contracting entities shall take account in particular of the complexity of the concession and the time required for drawing up tenders or applications without prejudice to the minimum time limits set out in this Article.

2.

Where applications or tenders can be made only after a visit to the site or after on-the-spot inspection of the documents supporting the concession award documents, the time limits for the receipt of applications for the concession or for the receipt of tenders, shall be fixed so that all economic operators concerned may be aware of all the information needed to produce applications or tenders and, in any event, shall be longer than the minimum time limits set out in paragraphs 3 and 4.

3.

The minimum time limit for the receipt of applications whether or not including tenders for the concession shall be 30 days from the date on which the concession notice was sent.

4.

Where the procedure takes place in successive stages the minimum time limit for the receipt of initial tenders shall be 22 days from the date on which the invitation to tender is sent.

5.

The time limit for receipt of tenders may be reduced by five days where the contracting authority or contracting entity accepts that tenders may be submitted by electronic means in conformity with Article 29.

Article 40
Provision of information to candidates and tenderers
1.

The contracting authority or contracting entity shall as soon as possible inform each candidate and tenderer of decisions taken concerning the award of a concession, including the name of the successful tenderer, the grounds for any decision to reject his application or tender and the grounds for any decision not to award a contract for which there has been publication of a concession notice or to recommence the procedure.

Moreover, on request from the party concerned, the contracting authority or contracting entity shall as quickly as possible, and in any case within 15 days from receipt of a written request inform any tenderers that have made an admissible tender of the characteristics and relative advantages of the tender selected.

2.

The contracting authority or contracting entity may decide to withhold certain information referred to in paragraph 1, regarding the contract, where the release of such information would impede law enforcement, would otherwise be contrary to the public interest, would prejudice the legitimate commercial interests of economic operators, whether public or private, or might prejudice fair competition between such operators.

Article 41
Award criteria
1.

Concessions shall be awarded on the basis of objective criteria which comply with the principles set out in Article 3 and which ensure that tenders are assessed in conditions of effective competition so as to identify an overall economic advantage for the contracting authority or the contracting entity.

2.

The award criteria shall be linked to the subject-matter of the concession, and shall not confer an unrestricted freedom of choice on the contracting authority or the contracting entity. They may include, inter alia, environmental, social or innovation-related criteria.

Those criteria shall be accompanied by requirements which allow the information provided by the tenderers to be effectively verified.

The contracting authority or the contracting entity shall verify whether tenders properly meet the award criteria.

3.

The contracting authority or the contracting entity shall list the criteria in descending order of importance.

Notwithstanding the first subparagraph, where the contracting authority or contracting entity receive a tender which proposes an innovative solution with an exceptional level of functional performance which could not have been foreseen by a diligent contracting authority or contracting entity, the contracting authority or contracting entity may, exceptionally, modify the ranking order of the award criteria to take into account that innovative solution. In that case, the contracting authority or the contracting entity shall inform all tenderers about the modification of the order of importance and shall issue a new invitation to submit tenders, in respect of the minimal time limits referred to in Article 39(4). Where the award criteria have been published at the moment of the publication of the concession notice, the contracting authority or entity shall publish a new concession notice, in respect of the minimum time limits referred to in Article 39(3).

The modification of the ranking order shall not result in discrimination.

TITLE III RULES ON PERFORMANCE OF CONCESSIONS

Article 42
Subcontracting
1.

Observance of the obligations referred to in Article 30(3) by subcontractors shall be ensured through appropriate action by the competent national authorities acting within the scope of their responsibility and remit.

2.

In the concession documents, the contracting authority or the contracting entity may ask or may be required by a Member State to ask the tenderer or the applicant to indicate in its tender any share of the concession it may intend to subcontract to third parties and any proposed subcontractors. This paragraph shall be without prejudice to the question of the main concessionaire’s liability.

3.

In the case of works concessions and in respect of services to be provided at the facility under the oversight of the contracting authority or the contracting entity, after the award of the concession and at the latest when the performance of the concession commences, the contracting authority or the contracting entity shall require the concessionaire to indicate to the contracting authority or the contracting entity the name, contact details and legal representatives of its subcontractors, involved in such works or services, insofar as known at that point in time. The contracting authority or the contracting entity shall require the concessionaire to notify it of any changes to that information during the course of the concession as well as of the required information for any new subcontractors which it subsequently involves in such works or services.

Notwithstanding the first subparagraph Member States may impose the obligation to deliver the required information directly on the concessionaire.

The first and second subparagraphs shall not apply to suppliers.

Contracting authorities and contracting entities may extend or may be required by Member States to extend the obligations provided for in the first subparagraph to for instance:

  • (a) services concessions other than those concerning services to be provided at the facilities under the oversight of the contracting authority or the contracting entity or to suppliers involved in works or services concessions;
  • (b) subcontractors of the concessionaire’s subcontractors or further down the subcontracting chain.
4.

With the aim of avoiding breaches of the obligations referred to in Article 30(3), appropriate measures may be taken, such as:

  • (a) Where the national law of a Member State provides for a mechanism of joint liability between subcontractors and the concessionaire, the Member State concerned shall ensure that the relevant rules are applied in compliance with the conditions set out in Article 30(3).
  • (b) Contracting authorities and contracting entities may verify or may be required by Member States to verify whether there are grounds for exclusion of subcontractors pursuant to Article 38(4) to (10). In such cases, the contracting authority or the contracting entity shall require the economic operator to replace a subcontractor in respect of which the verification has shown that there are compulsory grounds for exclusion. The contracting authority or the contracting entity may require or may be required by a Member State to require that the economic operator replaces a subcontractor in respect of which the verification has shown that there are non-compulsory grounds for exclusion.
5.

Member States may provide for more stringent liability rules under national law.

6.

Member States having chosen to provide for measures pursuant to paragraphs 1 and 3 shall, by law, regulation or administrative provisions and having regard to Union law, specify the implementing conditions for those measures. In so doing, Member States may limit their applicability, for instance in respect of certain types of contracts, certain categories of contracting authorities, contracting entities or economic operators or as of certain amounts.

Article 43
Modification of contracts during their term
1.

Concessions may be modified without a new concession award procedure in accordance with this Directive in any of the following cases:

  • (a) where the modifications, irrespective of their monetary value, have been provided for in the initial concession documents in clear, precise and unequivocal review clauses, which may include value revision clauses, or options. Such clauses shall state the scope and nature of possible modifications or options as well as the conditions under which they may be used. They shall not provide for modifications or options that would alter the overall nature of the concession;
  • (b) for additional works or services by the original concessionaire that have become necessary and that were not included in the initial concession where a change of concessionaire:
  • (i) cannot be made for economic or technical reasons such as requirements of interchangeability or interoperability with existing equipment, services or installations procured under the initial concession; and
  • (ii) would cause significant inconvenience or substantial duplication of costs for the contracting authority or contracting entity. However, in the case of concessions awarded by a contracting authority, for the purposes of pursuing an activity other than those referred to in Annex II, any increase in value shall not exceed 50 % of the value of the original concession. Where several successive modifications are made, that limitation shall apply to the value of each modification. Such consecutive modifications shall not be aimed at circumventing this Directive;
  • (c) where all of the following conditions are fulfilled:
  • (i) the need for modification has been brought about by circumstances which a diligent contracting authority or contracting entity could not foresee;
  • (ii) the modification does not alter the overall nature of the concession;
  • (iii) in the case of concessions awarded by contracting authority, for the purposes of pursuing an activity other than those referred to in Annex II, any increase in value is not higher than 50 % of the value of the initial concession. Where several successive modifications are made, this limitation shall apply to the value of each modification. Such consecutive modifications shall not be aimed at circumventing this Directive;
  • (d) where a new concessionaire replaces the one to which the contracting authority or the contracting entity had initially awarded the concession as a consequence of either:
  • (i) an unequivocal review clause or option in conformity with point (a);
  • (ii) universal or partial succession into the position of the initial concessionaire, following corporate restructuring, including takeover, merger, acquisition or insolvency, of another economic operator that fulfils the criteria for qualitative selection initially established provided that this does not entail other substantial modifications to the contract and is not aimed at circumventing the application of this Directive; or
  • (iii) in the event that the contracting authority or contracting entity itself assumes the main concessionaire’s obligations towards its subcontractors where this possibility is provided for under national legislation;
  • (e) where the modifications, irrespective of their value, are not substantial within the meaning of paragraph 4.

Contracting authorities or contracting entities having modified a concession in the cases set out under points (b) and (c) of this paragraph shall publish a notice to that effect in the Official Journal of the European Union. Such notice shall contain the information set out in Annex XI and shall be published in accordance with Article 33.

2.

Furthermore, and without any need to verify whether the conditions set out under points (a) to (d) of paragraph 4 are met, concessions may equally be modified without a new concession award procedure in accordance with this Directive being necessary where the value of the modification is below both of the following values:

  • (i) the threshold set out in Article 8; and
  • (ii) 10 % of the value of the initial concession.

However, the modification may not alter the overall nature of the concession. Where several successive modifications are made, the value shall be assessed on the basis of the net cumulative value of the successive modifications.

3.

For the purpose of the calculation of the value referred to in paragraph 2 and points (b) and (c) of paragraph 1, the updated value shall be the reference value when the concession includes an indexation clause. If the concession does not include an indexation clause, the updated value shall be calculated taking into account the average inflation in the Member State of the contracting authority or of the contracting entity.

4.

A modification of a concession during its term shall be considered to be substantial within the meaning of point (e) of paragraph 1, where it renders the concession materially different in character from the one initially concluded. In any event, without prejudice to paragraphs 1 and 2, a modification shall be considered to be substantial where one or more of the following conditions is met:

  • (a) the modification introduces conditions which, had they been part of the initial concession award procedure, would have allowed for the admission of applicants other than those initially selected or for the acceptance of a tender other than that originally accepted or would have attracted additional participants in the concession award procedure;
  • (b) the modification changes the economic balance of the concession in favour of the concessionaire in a manner which was not provided for in the initial concession;
  • (c) the modification extends the scope of the concession considerably;
  • (d) where a new concessionaire replaces the one to which the contracting authority or contracting entity had initially awarded the concession in other cases than those provided for under point (d) of paragraph 1.
5.

A new concession award procedure in accordance with this Directive shall be required for other modifications of the provisions of a concession during its term than those provided for under paragraphs 1 and 2.

Article 44
Termination of concessions

Member States shall ensure that contracting authorities and contracting entities have the possibility, under the conditions determined by the applicable national law, to terminate a concession during its term, where one or more of the following conditions is fulfilled:

  • (a) a modification of the concession has taken place, which would have required a new concession award procedure pursuant to Article 43;
  • (b) the concessionaire has been, at the time of concession award, in one of the situations referred to in Article 38(4) and should therefore have been excluded from the concession award procedure;
  • (c) the Court of Justice of the European Union finds, in a procedure pursuant to Article 258 TFEU, that a Member State has failed to fulfil its obligations under the Treaties by the fact that a contracting authority or contracting entity belonging to that Member State has awarded the concession in question without complying with its obligations under the Treaties and this Directive.
Article 45
Monitoring and reporting
1.

In order to ensure correct and efficient implementation, Member States shall ensure that at least the tasks set out in this Article are performed by one or more authorities or structures. They shall indicate to the Commission all authorities, or structures competent for these tasks.

2.

Member States shall ensure that the application of rules for the award of concession contracts is monitored. Where monitoring authorities or structures identify specific violations, such as fraud, corruption, conflict of interest and other serious irregularities, or systemic problems, they shall be empowered to indicate those violations or problems to national auditing authorities, courts or tribunals or other appropriate authorities or structures, such as the ombudsman, national parliaments or committees thereof.

3.

The results of the monitoring activities pursuant to paragraph 2 shall be made available to the public through appropriate means of information.

The Commission may, at the most every three years, request that Member States transmit to the Commission a monitoring report covering an overview of the most frequent causes of incorrect application of the rules for the award of concession contracts, including possible structural or recurring problems in the application of the rules, including possible cases of fraud and other illegal behaviour.

4.

Member States shall ensure that information and guidance on the interpretation and application of Union law for the award of concession contracts is available free of charge to assist contracting authorities and entities and economic operators in correctly applying the Union rules.

TITLE IV AMENDMENTS TO DIRECTIVES 89/665/EEC AND 92/13/EEC

Article 46
Amendments to Directive 89/665/EEC

Directive 89/665/EEC is amended as follows:

  • (1) in Article 1, paragraph 1 is replaced by the following: ‘1. This Directive applies to contracts referred to in Directive 2014/24/EU of the European Parliament and of the Council ([^E0016]) unless such contracts are excluded in accordance with Articles 7, 8, 9, 10, 11, 12, 15, 16, 17 and 37 of that Directive. This Directive also applies to concessions awarded by contracting authorities, referred to in Directive 2014/23/EU of the European Parliament and of the Council ([^E0017]) unless such concessions are excluded in accordance with Articles 10, 11, 12, 17 and 25 of that Directive. Contracts within the meaning of this Directive include public contracts, framework agreements, works and services concessions and dynamic purchasing systems. Member States shall take the measures necessary to ensure that, as regards contracts falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU, decisions taken by the contracting authorities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in Articles 2 to 2f of this Directive, on the grounds that such decisions have infringed Union law in the field of public procurement or national rules transposing that law.
  • (2) in Article 2a, paragraph 2 is amended as follows:
  • (a) the first subparagraph is replaced by the following: ‘A contract may not be concluded following the decision to award a contract falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned if fax or electronic means are used or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned or at least 10 calendar days with effect from the day following the date of the receipt of the contract award decision.’;
  • (b) in the fourth subparagraph, the first indent is replaced by the following:
  • — - ‘— a summary of the relevant reasons as set out in Article 55(2) of Directive 2014/24/EU, subject to Article 55(3) of that Directive, or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to Article 40(2) of that Directive, and’;
  • (3) Article 2b is amended as follows:
  • (a) in the first paragraph:
  • (i) point (a) is replaced by the following:
  • ‘(a) if Directive 2014/24/EU or, where relevant, Directive 2014/23/EU does not require prior publication of a contract notice in the Official Journal of the European Union;’;
  • (ii) point (c) is replaced by the following:
  • ‘(c) in the case of a contract based on a framework agreement as provided for in Article 33 of Directive 2014/24/EU and in the case of a specific contract based on a dynamic purchasing system as provided for in Article 34 of that Directive.’;
  • (b) in the second paragraph, the first and the second indent are replaced by the following:
  • — - ‘— there is an infringement of point (c) of Article 33(4) or of Article 34(6) of Directive 2014/24/EU, and
  • — - — the contract value is estimated to be equal to or to exceed the thresholds set out in Article 4 of Directive 2014/24/EU.’;
  • (4) in Article 2c, the words ‘Directive 2004/18/EC’ are replaced by the words ‘Directive 2014/24/EU or Directive 2014/23/EU’;
  • (5) Article 2d is amended as follows:
  • (a) in paragraph 1:
  • (i) point (a) is replaced by the following:
  • ‘(a) if the contracting authority has awarded a contract without prior publication of a contract notice in the Official Journal of the European Union without this being permissible in accordance with Directive 2014/24/EU or Directive 2014/23/EU’;
  • (ii) in point (b) the words ‘Directive 2004/18/EC’ are replaced by the words ‘Directive 2014/24/EU or Directive 2014/23/EU’;
  • (b) in paragraph 4, the first indent is replaced by the following:
  • — - ‘— the contracting authority considers that the award of a contract without prior publication of a contract notice in the Official Journal of the European Union is permissible in accordance with Directive 2014/24/EU or Directive 2014/23/EU’;
  • (c) in paragraph 5, the first indent is replaced by the following:
  • — - ‘— the contracting authority considers that the award of a contract is in accordance with point (c) of Article 33(4) or with Article 34(6) of Directive 2014/24/EU,’;
  • (6) in Article 2f(1), point (a) is replaced by the following:
  • ‘(a) before the expiry of at least 30 calendar days with effect from the day following the date on which:
  • — the contracting authority published a contract award notice in accordance with Articles 50 and 51 of Directive 2014/24/EU or with Articles 31 and 32 of Directive 2014/23/EU, provided that this notice includes justification of the decision of the contracting authority to award the contract without prior publication of a contract notice in the Official Journal of the European Union, or
  • — the contracting authority informed the tenderers and candidates concerned of the conclusion of the contract, provided that this information contains a summary of the relevant reasons as set out in Article 55(2) of Directive 2014/24/EU, subject to Article 55(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to Article 40(2) of that Directive. This option also applies to the cases referred to in point (c) of the first paragraph of Article 2b of this Directive’;
  • (7) in Article 3, paragraph 1 is replaced by the following: ‘1. The Commission may invoke the procedure provided for in paragraphs 2 to 5 when, prior to a contract being concluded, it considers that a serious infringement of Union law in the field of public procurement has been committed during a contract award procedure falling within the scope of Directive 2014/24/EU or Directive 2014/23/EU.’.
Article 47
Amendments to Directive 92/13/EEC

Directive 92/13/EEC is amended as follows:

  • (1) in Article 1, paragraph 1 is replaced by the following: ‘1. This Directive applies to contracts referred to in Directive 2014/25/EU of the European Parliament and of the Council ([^E0018]) unless such contracts are excluded in accordance with Articles 18 to 24, 27 to 30, 34 or 55 of that Directive. Contracts within the meaning of this Directive include supply, works and service contracts, works and services concessions, framework agreements and dynamic purchasing systems. This Directive also applies to concessions awarded by contracting entities, referred to in Directive 2014/23/EU of the European Parliament and of the Council ([^E0019]) unless such contracts are excluded in accordance with Articles 10, 12, 13, 14, 16, 17 and 25 of that Directive. Member States shall take the measures necessary to ensure that, as regards contracts falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU, decisions taken by contracting entities may be reviewed effectively and, in particular, as rapidly as possible in accordance with the conditions set out in Articles 2 to 2f of this Directive, on the grounds that such decisions have infringed Union law in the field of procurement or national rules transposing that law.
  • (2) in Article 2a, paragraph 2 is amended as follows:
  • (a) the first subparagraph is replaced by the following: ‘A contract may not be concluded following the decision to award a contract falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU before the expiry of a period of at least 10 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned if fax or electronic means are used or, if other means of communication are used, before the expiry of a period of either at least 15 calendar days with effect from the day following the date on which the contract award decision is sent to the tenderers and candidates concerned or at least 10 calendar days with effect from the day following the date of the receipt of the contract award decision.’;
  • (b) in the fourth subparagraph, the first indent is replaced by the following:
  • — - ‘— a summary of the relevant reasons as set out in Article 75(2) of Directive 2014/25/EU, subject to the provisions of Article 75(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to the provisions of Article 40(2) of that Directive, and’;
  • (3) Article 2b is amended as follows:
  • (a) in the first paragraph:
  • (i) point (a) is replaced by the following:
  • ‘(a) if Directive 2014/25/EU or, where relevant, Directive 2014/23/EU does not require prior publication of a notice in the Official Journal of the European Union;’;
  • (ii) point (c) is replaced by the following:
  • ‘(c) in the case of specific contracts based on a dynamic purchasing system as provided for in Article 52 of Directive 2014/25/EU.’;
  • (b) in the second paragraph, the first and the second indent are replaced by the following:
  • — - ‘— there is an infringement of Article 52(6) of Directive 2014/25/EU, and
  • — - — the contract value is estimated to be equal to or to exceed the thresholds set out in Article 15 of Directive 2014/25/EU.’;
  • (4) in Article 2c, the words ‘Directive 2004/17/EC’ are replaced by the words ‘Directive 2014/25/EU or Directive 2014/23/EU’;
  • (5) Article 2d is amended as follows:
  • (a) in paragraph 1,
  • (i) point (a) is replaced by the following:
  • ‘(a) if the contracting entity has awarded a contract without prior publication of a notice in the Official Journal of the European Union without this being permissible in accordance with Directive 2014/25/EU or Directive 2014/23/EU’;
  • (ii) in point (b), the words ‘Directive 2004/17/EC’ are replaced by the words ‘Directive 2014/25/EU or Directive 2014/23/EU’;
  • (b) in paragraph 4, the first indent is replaced by the following:
  • — - ‘— the contracting entity considers that the award of a contract without prior publication of a notice in the Official Journal of the European Union is permissible in accordance with Directive 2014/25/EU or Directive 2014/23/EU,’;
  • (c) in paragraph 5, the first indent is replaced by the following:
  • — - ‘— the contracting entity considers that the award of a contract is in accordance with Article 52(6) of Directive 2014/25/EU,’;
  • (6) in Article 2f(1), point (a) is replaced by the following:
  • ‘(a) before the expiry of at least 30 calendar days with effect from the day following the date on which:
  • — the contracting entity published a contract award notice in accordance with Articles 70 and 71 of Directive 2014/25/EU or with Articles 31 and 32 of Directive 2014/23/EU, provided that this notice includes the justification of the decision of the contracting entity to award the contract without prior publication of a notice in the Official Journal of the European Union, or
  • — the contracting entity informed the tenderers and candidates concerned of the conclusion of the contract, provided that this information contains a summary of the relevant reasons as set out in Article 75(2) of 2014/25/EU subject to Article 75(3) of that Directive or in the second subparagraph of Article 40(1) of Directive 2014/23/EU, subject to Article 40(2) of that Directive. This option also applies to the cases referred to in point (c) of the first paragraph of Article 2b of this Directive;’;
  • (7) in Article 8, paragraph 1 is replaced by the following: ‘1. The Commission may invoke the procedure provided for in paragraphs 2 to 5 when, prior to a contract being concluded, it considers that a serious infringement of Union law in the field of procurement has been committed during a contract award procedure falling within the scope of Directive 2014/25/EU or Directive 2014/23/EU, or in relation to Article 26(1) of Directive 2014/25/EU in the case of contracting entities to which that provision applies’.

TITLE V DELEGATED POWERS, IMPLEMENTING POWERS AND FINAL PROVISIONS

Article 48
Exercise of the delegation
1.

The power to adopt delegated acts is conferred on the Commission subject to the conditions laid down in this Article.

2.

The power to adopt delegated acts referred to in Article 7(3), Article 9(4), Article 27(2) and Article 30(4) shall be conferred on the Commission for an indeterminate period of time from 17 April 2014.

3.

The delegation of power referred to in Article 7(3), Article 9(4), Article 27(2) and Article 30(4) may be revoked at any time by the European Parliament or by the Council. A decision of to revoke shall put an end to the delegation of the power specified in that decision. It shall take effect the day following the publication of the decision in the Official Journal of the European Union or at a later date specified therein. It shall not affect the validity of any delegated acts already in force.

4.

As soon as it adopts a delegated act, the Commission shall notify it simultaneously to the European Parliament and to the Council.

5.

A delegated act adopted pursuant to Article 7(3), Article 9(4), Article 27(2) and Article 30(4) shall enter into force only where no objection has been expressed either by the European Parliament or by the Council within a period of two months of notification of the act to the European Parliament and the Council or if, before the expiry of that period, the European Parliament and the Council have both informed the Commission that they will not object. That period shall be extended by two months at the initiative of the European Parliament or of the Council.

Article 49
Urgency procedure
1.

Delegated acts adopted under this Article shall enter into force without delay and shall apply as long as no objection is expressed in accordance with paragraph 2. The notification of a delegated act to the European Parliament and to the Council shall state the reasons for the use of the urgency procedure.

2.

Either the European Parliament or the Council may object to a delegated act in accordance with the procedure referred to in Article 48(5). In such a case, the Commission shall repeal the act without delay following the notification of the decision to object by the European Parliament or by the Council.

Article 50
Committee Procedure
1.

The Commission shall be assisted by the Advisory Committee for Public Procurement established by Council Decision 71/306/EEC ([^E0020]). That committee shall be a committee within the meaning of Regulation (EU) No 182/2011.

2.

Where reference is made to this Article, Article 4 of Regulation (EU) No 182/2011 shall apply.

Article 51
Transposition
1.

Member States shall bring into force the laws, regulations and administrative provisions necessary to comply with this Directive by 18 April 2016. They shall forthwith communicate to the Commission the text thereof.

When Member States adopt those measures, they shall contain a reference to this Directive or be accompanied by such a reference on the occasion of their official publication. Member States shall determine how such reference is to be made.

2.

Member States shall communicate to the Commission the text of the main measures of national law which they adopt in the field covered by this Directive.

Article 52
Transitional provisions

References to points (a) and (b) of Article 1(3) of Directive 2004/17/EC and to Article 1(3) and (4) and Title III of Directive 2004/18/EC Directive shall be construed as references to this Directive.

Article 53
Monitoring and reporting

The Commission shall assess the economic effects on the internal market, in particular in terms of factors such as cross-border award of contracts and transaction costs, resulting from the application of the thresholds set out in Article 8, and report thereon to the European Parliament and the Council by 18 April 2019. The appropriateness of the level of thresholds shall be examined in the context of negotiations under the GPA taking into account the impact of inflation and transaction costs. The Commission shall, where possible and appropriate, consider suggesting an increase of the threshold amounts applicable under the GPA during the next round of negotiations.

In the event of any change to the threshold amounts applicable under the GPA, the report shall, where appropriate, be followed by a legislative proposal amending the thresholds set out in this Directive.

The Commission shall also assess the economic effects on the internal market of the exclusions set out in Article 12 taking into account the specific structures of the water sector, and report thereon to the European Parliament and the Council by 18 April 2019.

The Commission shall review the functioning of this Directive and shall report to the European Parliament and to the Council by 18 April 2021, and every five years thereafter, based on information that Member States shall provide in accordance with Article 45(3).

The Commission shall make the results of the review carried out in accordance with the fourth paragraph publicly available.

Article 54
Entry into force

This Directive shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.

This Directive shall not apply to the award of concessions tendered or awarded before 17 April 2014.

Article 55
Addressees

This Directive is addressed to the Member States.

ANNEX I

LIST OF THE ACTIVITIES REFERRED TO IN POINT (7) OF ARTICLE 5 [^E0021]
NACE Rev. 1 [^E0022] NACE Rev. 1 [^E0022] NACE Rev. 1 [^E0022] NACE Rev. 1 [^E0022] NACE Rev. 1 [^E0022] CPV code
SECTION F SECTION F SECTION F CONSTRUCTION CONSTRUCTION CPV code
Division Group Class Subject Notes CPV code
45 Construction This division includes: construction of new buildings and works, restoring and common repairs. 45000000
45.1 Site preparation 45100000
45.11 Demolition and wrecking of buildings; earth moving This class includes: — demolition of buildings and other structures, — clearing of building sites, — earth moving: excavation, landfill, levelling and grading of construction sites, trench digging, rock removal, blasting, etc., — site preparation for mining, — overburden removal and other development and preparation of mineral properties and sites. This class also includes: — building site drainage, — drainage of agricultural or forestry land. 45110000
45.12 Test drilling and boring This class includes: — test drilling, test boring and core sampling for construction, geophysical, geological or similar purposes. This class excludes: — drilling of production oil or gas wells, see 11.20, — water well drilling, see 45.25, — shaft sinking, see 45.25, — oil and gas field exploration, geophysical, geological and seismic surveying, see 74.20. 45120000
45.2 Building of complete constructions or parts thereof; civil engineering 45200000
45.21 General construction of buildings and civil engineering works This class includes: — construction of all types of buildings construction of civil engineering constructions, — bridges, including those for elevated highways, viaducts, tunnels and subways, — long-distance pipelines, communication and power lines, — urban pipelines, urban communication and power lines, — ancillary urban works, — assembly and erection of prefabricated constructions on the site. This class excludes: — service activities incidental to oil and gas extraction, see 11.20, — erection of complete prefabricated constructions from self-manufactured parts not of concrete, see divisions 20, 26 and 28, — construction work, other than buildings, for stadiums, swimming pools, gymnasiums, tennis courts, golf courses and other sports installations, see 45.23, — building installation, see 45.3, — building completion, see 45.4, — architectural and engineering activities, see 74.20, — project management for construction, see 74.20. 45210000 Except: – 45213316 45220000 45231000 45232000
45.22 Erection of roof covering and frames This class includes: — erection of roofs, — roof covering, — waterproofing. 45261000
45.23 Construction of highways, roads, airfields and sport facilities This class includes: — construction of highways, streets, roads, other vehicular and pedestrian ways, — construction of railways, — construction of airfield runways, — construction work, other than buildings, for stadiums, swimming pools, gymnasiums, tennis courts, golf courses and other sports installations, — painting of markings on road surfaces and car parks. This class excludes: — preliminary earth moving, see 45.11. 45212212 and DA03 45230000 except: – 45231000 – 45232000 – 45234115
45.24 Construction of water projects This class includes construction of: — waterways, harbour and river works, pleasure ports (marinas), locks, etc., — dams and dykes, — dredging, — subsurface work. 45240000
45.25 Other construction work involving special trades This class includes: — construction activities specialising in one aspect common to different kinds of structures, requiring specialised skill or equipment, — construction of foundations, including pile driving, — water well drilling and construction, shaft sinking, — erection of non-self-manufactured steel elements, — steel bending, — bricklaying and stone setting, — scaffolds and work platform erecting and dismantling, including renting of scaffolds and work platforms, — erection of chimneys and industrial ovens. This class excludes: — renting of scaffolds without erection and dismantling, see 71.32. 45250000 45262000
45.3 Building installation 45300000
45.31 Installation of electrical wiring and fittings This class includes: installation in buildings or other construction projects of: — electrical wiring and fittings, — telecommunications systems, — electrical heating systems, — residential antennas and aerials, — fire alarms, — burglar alarm systems, — lifts and escalators, — lightning conductors, etc. 45213316 45310000 Except: – 45316000
45.32 Insulation work activities This class includes: — installation in buildings or other construction projects of thermal, sound or vibration insulation. This class excludes: — waterproofing, see 45.22. 45320000
45.33 Plumbing This class includes: — installation in buildings or other construction projects of: — plumbing and sanitary equipment, — gas fittings, — heating, ventilation, refrigeration or air-conditioning equipment and ducts, — sprinkler systems. This class excludes: — installation of electrical heating systems, see 45.31. 45330000
45.34 Other building installation This class includes: — installation of illumination and signalling systems for roads, railways, airports and harbours, — installation in buildings or other construction projects of fittings and fixtures n.e.c. 45234115 45316000 45340000
45.4 Building completion 45400000
45.41 Plastering This class includes: — application in buildings or other construction projects of interior and exterior plaster or stucco, including related lathing materials. 45410000
45.42 Joinery installation This class includes: — installation of not self-manufactured doors, windows, door and window frames, fitted kitchens, staircases, shop fittings and the like, of wood or other materials, — interior completion such as ceilings, wooden wall coverings, movable partitions, etc. This class excludes: — laying of parquet and other wood floor coverings, see 45.43. 45420000
45.43 Floor and wall covering This class includes: — laying, tiling, hanging or fitting in buildings or other construction projects of: — ceramic, concrete or cut stone wall or floor tiles, — parquet and other wood floor coverings carpets and linoleum floor coverings, — including of rubber or plastic, — terrazzo, marble, granite or slate floor or wall coverings, — wallpaper. 45430000
45.44 Painting and glazing This class includes: — interior and exterior painting of buildings, — painting of civil engineering structures, — installation of glass, mirrors, etc. This class excludes: — installation of windows, see 45.42. 45440000
45.45 Other building completion This class includes: — installation of private swimming pools, — steam cleaning, sand blasting and similar activities for building exteriors, — other building completion and finishing work n.e.c. This class excludes: — interior cleaning of buildings and other structures, see 74.70. 45212212 and DA04 45450000
45.5 Renting of construction or demolition equipment with operator 45500000
45.50 Renting of construction or demolition equipment with operator This class excludes: — renting of construction or demolition machinery and equipment without operators, see 71.32. 45500000

In the event of any difference of interpretation between the CPV and the NACE, the CPV nomenclature will apply.

Council Regulation (EEC) No 3037/90 of 9 October 1990 on the statistical classification of economic activities in the European Community (OJ L 293, 24.10.1990, p. 1).

ANNEX II

ACTIVITIES EXERCISED BY CONTRACTING ENTITIES AS REFERRED TO IN ARTICLE 7

The provisions of this Directive governing concessions awarded by contracting entities shall apply to the following activities:

    1. As far as gas and heat are concerned:
  • (a) the provision or operation of fixed networks intended to provide a service to the public in connection with the production, transport or distribution of gas or heat;
  • (b) the supply of gas or heat to such fixed networks. The supply by a contracting entity referred to in points (b) and (c) of Article 7(1) of gas or heat to fixed networks which provide a service to the public shall not be considered to be a relevant activity within the meaning of the first subparagraph of this paragraph where all of the following conditions are met:
  • (i) the production of gas or heat by that contracting entity is the unavoidable consequence of carrying out an activity other than those referred to in this paragraph or in paragraphs 2 and 3 of this Annex;
  • (ii) the supply to the public network is aimed only at the economic exploitation of such production and amounts to not more than 20 % of that contracting entity’s turnover on the basis of the average for the preceding three years, including the current year. For the purposes of this Directive, ‘supply’ includes the generation/production, wholesale and retail sale of gas. However, production of gas in the form of extraction falls within the scope of paragraph 4 of this Annex.
    1. As far as electricity is concerned:
  • (a) the provision or operation of fixed networks intended to provide a service to the public in connection with the production, transport or distribution of electricity;
  • (b) the supply of electricity to such fixed networks. For the purposes of this Directive, supply of electricity includes generation/production, wholesale and retail sale of electricity. The supply by a contracting entity referred to in points (b) and (c) of Article 7(1) of electricity to networks which provide a service to the public shall not be considered to be a relevant activity within the meaning of the first subparagraph of this paragraph where all of the following conditions are met:
  • (a) the production of electricity by that contracting entity takes place because its consumption is necessary for carrying out an activity other than those referred to in this paragraph or in paragraphs 1 and 3 of this Annex;
  • (b) supply to the public network depends only on that contracting entity’s own consumption and has not exceeded 30 % of that contracting entity’s total production of energy, on the basis of the average for the preceding three years, including the current year.
    1. Activities relating to the provision or operation of networks providing a service to the public in the field of transport by railway, automated systems, tramway, trolley bus, bus or cable. As regards transport services, a network shall be considered to exist where the service is provided under operating conditions laid down by a competent authority of a Member State, such as conditions on the routes to be served, the capacity to be made available or the frequency of the service.
    1. Activities relating to the exploitation of a geographical area for the purpose of the provision of airports and maritime or inland ports or other terminal facilities to carriers by air, sea or inland waterway.
    1. Activities relating to the provision of:
  • (a) postal services;
  • (b) other services than postal services, on condition that such services are provided by an entity which also provides postal services within the meaning of point (ii) of the second subparagraph of this paragraph and provided that the conditions set out in Article 34(1) of Directive 2014/25/EU are not satisfied in respect of the services falling within point (ii) of the second subparagraph. For the purpose of this Directive and without prejudice to Directive 97/67/EC:
  • (i) ‘postal item’ means an item addressed in the final form in which it is to be carried, irrespective of weight. In addition to items of correspondence, such items also include for instance books, catalogues, newspapers, periodicals and postal packages containing merchandise with or without commercial value, irrespective of weight;
  • (ii) ‘postal services’: means services consisting of the clearance, sorting, routing and delivery of postal items. This shall include both services falling within as well as services falling outside the scope of the universal service set up in conformity with Directive 97/67/EC;
  • (iii) ‘other services than postal services’: means services provided in the following areas:
  • — mail service management services (services both preceding and subsequent to despatch, including ‘mailroom management services’),
  • — services concerning postal items not included in point (a), such as direct mail bearing no address.
    1. Activities relating to the exploitation of a geographical area for the purpose of:
  • (a) extracting oil or gas;
  • (b) exploring for, or extracting, coal or other solid fuels.

ANNEX III

LIST OF LEGAL ACTS OF THE UNION REFERRED TO IN POINT (B) OF ARTICLE 7(2)

Rights which have been granted by means of a procedure in which adequate publicity has been ensured and where the granting of those rights was based on objective criteria shall not constitute ‘special or exclusive rights’ within the meaning of this Directive. The following lists procedures, ensuring adequate prior transparency, for granting authorisations on the basis of other legislative acts of the Union which do not constitute ‘special or exclusive rights’ within the meaning of this Directive:

  • (a) Granting authorisation to operate natural gas installations in accordance with the procedures laid down in Article 4 of Directive 2009/73/EC;
  • (b) Authorisation or an invitation to tender for the construction of new electricity production installations in accordance with Directive 2009/72/EC;
  • (c) The granting in accordance with the procedures laid down in Article 9 of Directive 97/67/EC of authorisations in relation to a postal service which is not or shall not be reserved;
  • (d) A procedure for granting an authorisation to carry on an activity involving the exploitation of hydrocarbons in accordance with Directive 94/22/EC;
  • (e) Public service contracts within the meaning of Regulation (EC) No 1370/2007 for the provision of public passenger transport services by bus, tramway, rail or metro, which have been awarded on the basis of a competitive tendering procedure in accordance with its Article 5(3), provided that its length is in conformity with Article 4(3) or (4) of that Regulation.

ANNEX IV

SERVICES REFERRED TO IN ARTICLE 19

Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.

This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence. EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.