Commission Implementing Regulation (EU) No 897/2014 of 18 August 2014 laying down specific provisions for the implementation of cross-border cooperation programmes financed under Regulation (EU) No 232/2014 of the European Parliament and the Council establishing a European Neighbourhood Instrument
All beneficiaries shall actively cooperate in the development and implementation of projects. In addition, they shall cooperate in the staffing and/or financing of projects. Each beneficiary shall be legally and financially responsible for the activities that it is implementing and for the share of the Union funds that it receives. The specific obligations as well as the financial responsibilities of the beneficiaries shall be laid down in the agreement referred to in point (c) of paragraph 3
The lead beneficiary shall:
- (a) receive the financial contribution from the Managing Authority for the implementation of project activities;
- (b) ensure that the beneficiaries receive the total amount of the grant as quickly as possible and in full in accordance with the arrangements referred to in (c). No amount shall be deducted or withheld and no specific charge with equivalent effect shall be levied that would reduce these amounts for the beneficiaries;
- (c) lay down the partnership arrangements with the beneficiaries in an agreement comprising, provisions that, inter alia, guarantee the sound financial management of the funds allocated to the project including the arrangements for recovery of funds unduly paid;
- (d) assume responsibility for ensuring implementation of the entire project;
- (e) ensure that the expenditure presented by the beneficiaries has been incurred for the purpose of implementing the project and corresponds to activities set in the contract and agreed between all beneficiaries;
- (f) verify that the expenditure presented by the beneficiaries has been examined pursuant Article 32(1).
CHAPTER 3 Eligibility of expenditure
Article 47
Forms of grants
Grants may take any of the following forms:
- (a) reimbursement of a specified proportion of the eligible costs referred to in Article 48 actually incurred;
- (b) flat-rate financing, determined by the application of a percentage to one or several defined categories of costs;
- (c) lump sums;
- (d) reimbursement on the basis of unit costs;
- (e) a combination of the forms referred to in points (a) to (d), only where each covers different categories of costs.
Grants in the form referred to in point (a) of paragraph 1 shall be calculated on the basis of the eligible costs actually incurred by the beneficiary, subject to a preliminary budget estimate as submitted with the proposal and included in the contract. Flat-rate financing as referred to in point (b) of paragraph 1 shall cover specific categories of eligible costs which are clearly identified in advance by applying a percentage. Lump sums as referred to in point (c) of paragraph 1 shall in global terms cover all or certain specific categories of eligible costs which are clearly identified in advance. Unit costs as referred to in point (d) of paragraph 1 shall cover all or certain specific categories of eligible costs which are clearly identified in advance by reference to an amount per unit.
Grants shall not have the purpose or effect of producing a profit within the framework of the project. The exceptions set out in Article 125(4) of Regulation (EU, Euratom) No 966/2012 shall apply.
Article 48
Eligibility of costs
Grants shall not exceed an overall ceiling expressed as a percentage and an absolute value which is to be established on the basis of estimated eligible costs. Grants shall not exceed the eligible costs.
Eligible costs are costs actually incurred by the beneficiary which meet all of the following criteria:
- (a) they are incurred during the implementation period of the project. In particular:
- (i) costs relating to services and works shall relate to activities performed during the implementation period. Costs relating to supplies shall relate to delivery and installation of items during the implementation period. Signature of a contract, placing of an order, or entering into any commitment for expenditure within the implementation period for future delivery of services, works or supplies after expiry of the implementation period do not meet this requirement; cash transfers between the lead beneficiary and the other beneficiaries may not be considered as costs incurred;
- (ii) costs incurred should be paid before the submission of the final project reports. They may be paid afterwards, provided they are listed in the final report together with the estimated date of payment;
- (iii) an exception is made for costs relating to final project reports, including expenditure verification, audit and final evaluation of the project, which may be incurred after the implementation period of the project;
- (iv) procedures to award contracts, as referred to in Article 52 and following, may have been initiated and contracts may be concluded by the beneficiary(ies) before the start of the implementation period of the project, provided the provisions of Article 52 and following have been respected;
- (b) they are indicated in the project's estimated overall budget;
- (c) they are necessary for the project implementation;
- (d) they are identifiable and verifiable, in particular being recorded in the accounting records of the beneficiary and determined according to the accounting standards and the usual cost accounting practices applicable to the beneficiary;
- (e) they comply with the requirements of applicable tax and social legislation;
- (f) they are reasonable, justified, and comply with the requirements of sound financial management, in particular regarding economy and efficiency;
- (g) they are supported by invoices or documents of equivalent probative value;
2a. Notwithstanding Article 19(1), expenditure shall not be eligible for the Union contribution, where it is paid after 31 December 2023.
A grant may be awarded retroactively in the following cases:
- (a) where the applicant can demonstrate the need to start the project before the contract is signed. Costs eligible for financing shall however not have been incurred prior to the date of the submission of the grant application; or
- (b) for costs related to studies and documentation for projects including an infrastructure component.
No grant may be awarded retroactively for projects already completed.
3a. By way of derogation from paragraph 3, costs of projects fostering crisis response capacities in the context of the COVID-19 pandemic shall be eligible as of 1 February 2020.
To allow the preparation of strong partnerships, costs incurred before submission of the grant application by projects to which a grant has been awarded are eligible provided that the following conditions are also met:
- (a) they are incurred after the publication of the call for proposals;
- (b) they are limited to travel and subsistence costs of staff employed by the beneficiaries, provided they meet the conditions of point (b) of paragraph 5;
- (c) they do not exceed the maximum amount fixed at programme level.
Subject to paragraphs 1 and 2, the following direct costs of the beneficiary shall be eligible:
- (a) the costs of staff assigned to the project under the following cumulative conditions:
- — they relate to the costs of activities which the beneficiary would not carry out if the project was not undertaken,
- — they must not exceed those normally borne by the beneficiary unless it is demonstrated that this is essential to carry out the project,
- — they relate to actual gross salaries including social security charges and other remuneration-related costs;
- (b) travel and subsistence costs of staff and other persons taking part in the project, provided they exceed neither the costs normally paid by the beneficiary according to its rules and regulations nor the rates published by the Commission at the time of the mission if reimbursed on the basis of lump sums, unit costs or flat rate financing;
- (c) purchase or rental costs for equipment (new or used) and supplies specifically for the purpose of the project, provided they correspond to market prices;
- (d) the cost of consumables specifically purchased for the project;
- (e) costs entailed by contracts awarded by the beneficiaries for the purposes of the project;
- (f) costs deriving directly from requirements imposed by this Regulation and the project (such as information and visibility operations, evaluations, external audits, translations) including financial service costs (such as costs of bank transfers and financial guarantees).
Pursuant to Article 4 a programme may establish additional eligibility rules for the programme as a whole.
Article 49
Non-eligible costs
The following costs relating to the implementation of the project shall not be considered eligible:
- (a) debts and debt service charges (interest);
- (b) provisions for losses or liabilities;
- (c) costs declared by the beneficiary and already financed by the Union budget;
- (d) purchases of land or buildings for an amount exceeding 10 % of the eligible expenditure of the project concerned;
- (e) exchange-rate losses;
- (f) duties, taxes and charges, including VAT, except where non-recoverable under the relevant national tax legislation, unless otherwise provided in appropriate provisions negotiated with CBC partner countries;
- (g) loans to third parties;
- (h) fines, financial penalties and expenses of litigation;
- (i) contributions in kind as defined in Article 14(1).
Pursuant to Article 4 a programme may declare other categories of costs as ineligible.
Article 50
Lump sums, unit costs and flat-rate financing
The total amount of financing on the basis of lump sums, unit costs and flat rate financing may not exceed EUR 60 000 per beneficiary and per project, unless the programme establishes otherwise according to Article 4, but not exceeding EUR 100 000 .
The use of lump sums, unit-costs and flat-rate financing shall at least be supported by the following:
- (a) justification concerning the appropriateness of such forms of financing with regard to the nature of the projects as well as to the risks of irregularities and fraud and costs of control;
- (b) identification of the costs or categories of costs covered by lump sums, unit costs or flat-rate financing, which shall exclude ineligible costs as referred to in Article 49.
- (c) description of the methods for determining lump sums, unit costs or flat-rate financing, and of the conditions for reasonably ensuring that the no-profit rule and co-financing principles are complied with and that double financing is avoided. These methods shall be based on:
- (i) statistical data or similar objective means; or
- (ii) a beneficiary-by-beneficiary approach, by reference to certified or auditable historical data of the beneficiary or to its usual cost accounting practices.
Once the amounts have been assessed and approved by the Managing Authority, they will not be challenged by ex post controls.
Article 51
Indirect costs
Indirect costs may be calculated on a flat-rate of up to 7 % of eligible direct costs, excluding costs incurred in relation to the provision of infrastructure, provided that the rate is calculated on the basis of a fair, equitable and verifiable calculation method.
As indirect costs for a project shall be considered those eligible costs which may not be identified as specific costs directly linked to the implementation of the project and may not be booked to it directly according to the conditions of eligibility as defined in Article 48. They may not include ineligible costs as referred to in Article 49 or costs already declared under another cost item or heading of the budget of the project.
CHAPTER 4
Section 1 Procurement
Article 52
Applicable rules
If the implementation of a project requires procurement of goods, works or services by a beneficiary, the following rules shall apply:
- (a) where the beneficiary is a contracting authority or a contracting entity within the meaning of the Union legislation applicable to procurement procedures, it may apply national laws, regulations and administrative provisions adopted in connection with Union legislation or rules of paragraph 2;
- (b) where the beneficiary is an international organisation, it may apply its own procurement rules if they offer guarantees equivalent to internationally accepted standards;
- (c) where the beneficiary is a public authority of a CBC partner country whose co-financing is transferred to the Managing Authority, it may apply national laws, regulations and administrative provisions, provided that the financing agreement allows it and the general principles set out in point (a) of paragraph 2 are respected.
In all other cases the following obligations shall be complied with:
- (a) the contract is awarded to the tender offering best value for money, or as appropriate, to the tender offering the lowest price, while avoiding any conflict of interests;
- (b) for contracts with a value of more than EUR 60 000 , the following rules shall also apply:
- (i) an evaluation committee shall be set up to evaluate applications and/or tenders on the basis of the exclusion, selection and award criteria published by the beneficiary in advance in the tender documents. The committee must have an odd number of members with all the technical and administrative capacities necessary to give an informed opinion on the tenders/applications;
- (ii) sufficient transparency, fair competition and adequate ex-ante publicity must be ensured;
- (iii) equal treatment, proportionality and non-discrimination shall be ensured;
- (iv) tender documents must be drafted according to best international practice;
- (v) deadlines for submitting applications or tenders must be long enough to give interested parties a reasonable period to prepare their tenders;
- (vi) candidates or tenderers shall be excluded from participating in a procurement procedure if they fall within one of the situations described in Article 106(1) of Regulation (EU, Euratom) No 966/2012. Candidates or tenderers must certify that they are not in one of these situations. In addition, contracts may not be awarded to candidates or tenderers which, during the procurement procedure fall within one of the situations referred to in Article 107 of Regulation (EU, Euratom) No 966/2012;
- (vii) procurement procedures set out in Articles 53 to 56 shall be followed.
In all cases, the rules of nationality and origin set forth in Articles 8 and 9 of Regulation (EU) No 236/2014 shall apply.
Article 53
Procurement procedures for service contracts
Service contracts with a value of EUR 300 000 or more shall be awarded by means of an international restricted tender procedure following publication of a procurement notice. The procurement notice shall be published in all appropriate media beyond the programme area, stating the number of candidates which will be invited to submit tenders within a range of four to eight candidates and ensuring genuine competition.
Service contracts with a value of more than EUR 60 000 but less than EUR 300 000 shall be awarded by means of a competitive negotiated procedure without publication. The beneficiary shall consult at least three service providers of its choice and negotiate the terms of the contract with one or more of them.
Article 54
Procurement procedures for supply contracts
Supply contracts with a value of EUR 300 000 or more shall be awarded by means of an international open tender procedure following publication of a procurement notice, which shall be published in all appropriate media beyond the programme area.
Supply contracts with a value of EUR 100 000 or more but less than EUR 300 000 shall be awarded by means of an open tender procedure published in the programme area. Any eligible tenderer must be provided with the same opportunities as local firms.
Supply contracts with a value of more than EUR 60 000 but less than EUR 100 000 shall be awarded by means of a competitive negotiated procedure without publication. The beneficiary shall consult at least three suppliers of its choice and negotiate the terms of the contract with one or more of them.
Article 55
Procurement procedures for works contracts
Works contracts with a value of EUR 5 000 000 or more shall be awarded by means of an international open tender procedure, or in view of the specific characteristics of certain works by means of a restricted tender procedure, following publication of a procurement notice which shall be published in all appropriate media beyond the programme area.
Work contracts with a value of EUR 300 000 or more but less than EUR 5 000 000 shall be awarded by means of an open tender procedure published in the programme area. Any eligible tenderer must be provided with the same opportunities as local firms.
Work contracts with a value of more than EUR 60 000 but less than EUR 300 000 shall be awarded by means of a competitive negotiated procedure without publication. The beneficiary shall consult at least three contractors of its choice and shall negotiate the terms of the contract with one or more of them.
Article 56
Use of Negotiated Procedure
The beneficiary may decide to use negotiated procedure on the basis of a single tender in the cases referred to in Articles 266, 268, 270 of Delegated Regulation (EU) No 1268/2012.
Section 2 Financial support to third parties
Article 57
Financial support to third parties
If the project requires the award of financial support to third parties, it may be given on condition that:
- (a) each third party offers adequate guarantees as regards the recovery of amounts;
- (b) principles of proportionality, transparency, sound financial management, equal treatment and non-discrimination are complied with;
- (c) conflicts of interests are prevented;
- (d) financial support may not be cumulative or awarded retrospectively, it shall, in principle, involve co-financing and it may not have the purpose or the effect of producing a profit for each third party;
- (e) conditions for giving financial support are strictly defined in the contract to avoid the exercise of discretion by the beneficiary. In particular, the contract shall specify the categories of persons which are eligible for the support, the award criteria (including the criteria for determining the exact amount) and a fixed list of the different types of activity that may receive such financial support;
- (f) the maximum amount of financial support that can be paid does not exceed EUR 60 000 per third party, except where the financial support is the primary aim of the project.
Rules on nationality and origin set out in Articles 8 and 9 Regulation (EU) No 236/2014 shall apply. Where a sub-grant exceeds EUR 60 000 the rules of participation laid down in point (b)(vi) of Article 52 shall apply mutatis mutandis.
TITLE VIII PAYMENTS, PRESENTATION AND ACCEPTANCE OF ACCOUNTS, FINANCIAL CORRECTIONS AND RECOVERIES
CHAPTER 1 Payments
Article 58
Annual commitments
Under shared management, the Commission shall make the initial commitments after adoption of the programme by the Commission pursuant to Article 5.
Under indirect management, the Commission shall make the initial commitments after the adoption of the programme, after the entry into force of the agreement delegating budget execution tasks to an international organisation or to a CBC partner country referred to in Articles 81 and 82.
Subsequently the Commission shall make the corresponding commitment each financial year no later than 1 May. The amount of the annual commitments shall be determined in accordance with the financial plan taking into account the programme's progress and the availability of funds. The Commission shall inform the Managing Authority when the annual commitment is made.
Article 59
Common rules for payments
Payments to managing authorities may take the form of prefinancing or payment of the final balance.
A bank account in euro, specifically dedicated to the programme shall be opened. When payments by the Commission are channelled through another bank account than the programme's, the related amounts and any accrued interest shall be transferred to the programme bank account without delay and in full.
No amount shall be deducted or withheld and no specific charge or other charge with equivalent effect shall be levied on these amounts or on any accrued interest.
Article 60
Common rules for calculating prefinancing
Each financial year, once the Managing Authority has been notified of the annual commitment, it may request as prefinancing the transfer of up to 80 % of the Union contribution for the financial year in question. From the second financial year, requests for prefinancing shall be accompanied by the provisional budget detailing the Managing Authority's commitments and payments for the two accounting years following the latest audit opinion referred to in Article 68. After reviewing that provisional budget, assessing actual financing needs of the programme and verifying the availability of funds, the Commission shall proceed with the payment of all or part of the requested prefinancing no later than 60 days after the date on which the payment request is registered with the Commission.
In the course of the financial year, the Managing Authority may ask for the transfer of all or part of the funds already committed, as additional prefinancing. In support of its request, the Managing Authority shall submit an interim financial report showing that the expenditure actually incurred or likely to be incurred before the end of the financial year exceeds the amount of prefinancing already paid. Such subsequent transfers shall constitute additional prefinancing provided they are not supported by an audit opinion referred to in Article 68.
Each financial year of the programme's implementation, the Commission shall clear previous prefinancing payments on the basis of eligible expenditure actually incurred, supported by the audit opinion referred to in Article 68 following the acceptance of accounts as described in Article 69(2). On the basis of the results of this clearance, the Commission may proceed with the necessary financial adjustments.
Article 61
Interruption of the payment deadline
The authorising officer by delegation within the meaning of Regulation (EU, Euratom) No 966/2012 may interrupt payment deadline for a payment request for a maximum period of six months in any of the following circumstances:
- (a) following information provided by a national or Union audit body, there is a clear evidence to suggest a significant deficiency in the functioning of the management and control system;
- (b) the authorising officer by delegation has to carry out additional verifications following information coming to his attention alerting him that expenditure is linked to an irregularity having serious financial consequences;
- (c) there is a failure to submit one of the documents required under Article 77;
- (d) there is a failure to submit one of the documents required under Articles 60 and 64.
The Managing Authority may agree to an extension of the interruption period for another three months.
The authorising officer by delegation shall limit the interruption to the part of the expenditure covered by the payment request affected by the elements referred to in the first subparagraph of paragraph 1, unless it is not possible to identify the part of the expenditure affected. The authorising officer by delegation shall inform the Member State hosting the Managing Authority and the Managing Authority immediately of the reasons for interruption and shall ask them to remedy the situation. The interruption shall be ended by the authorising officer by delegation as soon as the necessary measures have been taken. This interruption may be extended beyond six months if the necessary measures have not been taken.
Article 62
Suspension of payments
The Commission may suspend all or part of the payments in any of the following circumstances:
- (a) there is a serious deficiency in the effective functioning of the management and control systems of the programme which has put the Union contribution at risk and for which corrective measures have not been taken;
- (b) there is a serious breach by participating countries of their obligations under Article 31;
- (c) expenditure is linked to an irregularity which has not been corrected having serious financial consequences;
- (d) there is a serious deficiency in the quality and reliability of the evaluation and monitoring system;
- (e) there is evidence resulting from monitoring, evaluation or audit that the programme does not deliver in accordance with the time-frames indicated in Article 4 and as reported in accordance with Article 77.
The Commission may decide to suspend all or part of prefinancing payments after having given the Managing Authority the opportunity to present its observations.
The Commission shall end suspension of all or part of payments where the Managing Authority has taken the necessary measures to enable the suspension to be lifted.
Article 63
Payment to lead beneficiaries
Payments to lead beneficiaries can take one of the following forms:
- (a) prefinancing;
- (b) interim payment;
- (c) payment of the final balance.
The Managing Authority shall ensure that payments to lead beneficiaries are processed as quickly as possible according to the signed contract. No amount shall be deducted or withheld, unless supported by the signed contract and no specific charge or other charge with equivalent effect shall be levied reducing these payments.
Article 64
Payment of the final balance
The managing authority shall submit the payment request of the final balance accompanied by the documents referred to in Article 68 and Article 77(5).
The final balance shall be paid no later than three months after the date of clearance of accounts of the final accounting year or one month after the date of acceptance of the final implementation report, whichever date is later.
Payment of the final balance for the programme in the final accounting year may exceed up to 10 % of the Union contribution for each thematic objective as laid down in the Commission implementing decision approving the programme.
The Union contribution through payment of the final balance in the final accounting year shall not exceed the total Union contribution to each programme as laid down in the Commission implementing decision approving the programme.
Article 65
Exception to the de-commitment
The amount concerned by de-commitment shall be reduced by the amounts that the Managing Authority has not been able to declare to the Commission because of:
- (a) projects suspended by a legal proceeding or by an administrative appeal having suspensory effect; or
- (b) reasons of force majeure seriously affecting the implementation of all or part of the programme;
- (c) application of Articles 61 or 62;
The Managing Authority claiming force majeure under point (b) of paragraph 1 shall demonstrate the direct consequences of the force majeure on the implementation of all or part of the programme. For the purpose of points (a) and (b) of paragraph 1 the reduction may be requested once, if the suspension or force majeure has lasted no longer than one year, or a number of times that corresponds to the duration of the force majeure or the number of years between the date of the legal or administrative decision suspending the implementation of the project and the date of the final legal or administrative decision.
By 15 February, the Managing Authority shall send to the Commission information on the exceptions referred to in paragraph 1 for the amount to be declared by 31 December of preceding financial year.
Article 66
De-commitment procedure
The Commission shall timely inform the Managing Authority whenever there is a risk of de-commitment pursuant to Article 6 of Regulation (EU) No 236/2014.
On the basis of information received as of 15 February, the Commission shall inform the Managing Authority of the amount of the de-commitment resulting from that information.
The Managing Authority shall have two months to agree to the amount to be de-committed or to submit its observations.
By 30 June, the Managing Authority shall submit a revised financial plan to the Commission reflecting the impact of the reduced amount of support on the thematic objectives or technical assistance of the programme for the financial year concerned. Failing such a submission, the Commission shall revise the financial plan by reducing the Union contribution for the financial year concerned. The reduction shall affect the thematic objectives and technical assistance proportionately.
The Commission shall amend the decision adopting the programme.
Article 67
Use of the euro
Expenditure incurred in a currency other than the euro shall be converted into euro by the Managing Authority and by the beneficiary using the monthly accounting exchange rate of the Commission of one of the following:
- (a) the month during which the expenditure was incurred;
- (b) the month during which the expenditure was submitted for examination in accordance with Article 32(1);
- (c) the month during which the expenditure was reported to the lead beneficiary.
The method chosen shall be set out in the programme and shall apply throughout the programme duration. Different methods may be applied to technical assistance and to projects.
CHAPTER 2 Presentation and acceptance of accounts
Article 68
Presentation of accounts
The accounts of the programme shall be drawn up by the Managing Authority. These accounts shall be independent and separate and shall include only transactions relating to the programme. They shall be kept in such a way as to enable analytical monitoring of the programme by priority and technical assistance.
In its annual report, the Managing Authority shall, by 15 February, provide the Commission with the following financial information:
- (a) the accounts for the preceding accounting year;
- (b) a management declaration signed by the representative of the Managing Authority confirming that:
- (i) the information is properly presented, complete and accurate;
- (ii) the expenditure was used for its intended purpose;
- (iii) the control systems put in place give the necessary guarantees concerning the legality of the underlying transactions.
- (c) an annual summary of the controls carried out by the Managing Authority, including an analysis of the nature and extent of errors and weaknesses identified in systems, as well as corrective action taken or planned;
- (d) an audit opinion on the annual accounts;
- (e) an annual audit report drawn up by the Audit Authority providing a summary of audits carried out, including an analysis of the nature and extent of errors and weaknesses identified, both at system level and for projects, as well as the corrective actions taken or planned;
- (f) an estimate of costs incurred from 1 July to 31 December of the preceding year;
- (g) the list of projects closed during the accounting year.
The accounts referred to in point (a) of paragraph 2 shall be submitted for each programme and shall include at the level of each priority and technical assistance:
- (a) the expenditure incurred and paid and the revenue earned and received by the Managing Authority;
- (b) the amounts waived and recovered during the accounting year, the amounts to be recovered by the end of the accounting year and the unrecoverable amounts.
The audit opinion referred to in point (d) of paragraph 2 shall establish whether the accounts give a true and fair view, the related transactions are legal and regular and the control systems properly put in place function. The opinion shall also state whether the audit work puts in doubt the assertions made in the management declaration referred to in point (b) of paragraph 2.
Article 69
Acceptance of accounts
The Commission shall examine the accounts and inform the Managing Authority by 31 May of the year following the end of the accounting year whether it accepts that the accounts are complete, accurate and true.
On the basis of eligible expenditure incurred, as certified by the audit opinion referred to in point (d) of Article 68(2), the Commission shall clear the prefinancing.
Acceptance of the accounts shall be without prejudice to any subsequent financial corrections in accordance with Article 72.
Article 70
Period for record-keeping
The Managing Authority and the beneficiaries shall keep all documents related to the programme or a project for five years from the date of payment of the balance for the programme. In particular they shall keep reports, supporting documents, as well as accounts, accounting documents and any other document relating to the financing of the programme (including all documents relating to the contract award) and projects.
Notwithstanding paragraph 1, records pertaining to audits, appeals, litigation or pursuit of claims arising from the programme or project performance shall be retained until such audits, appeals, litigation or claims have been completed.
CHAPTER 3 Financial corrections and Recoveries
Section 1 Financial Corrections
Article 71
Financial corrections by the Managing Authority
The Managing Authority shall in the first instance be responsible for preventing and investigating irregularities and for making the financial corrections required and pursuing recoveries. In the case of a systemic irregularity, the Managing Authority shall extend its investigation to cover all operations potentially affected.
The Managing Authority shall make the financial corrections required in connection with individual or systemic irregularities detected in projects, technical assistance or in the programme. Financial corrections shall consist of cancelling all or part of the Union contribution to a project or to technical assistance. The Managing Authority shall take into account the nature and gravity of the irregularities and the financial loss and shall apply a proportionate financial correction. Financial corrections shall be recorded in the annual accounts by the Managing Authority for the accounting year in which the cancellation is decided.
The Union contribution cancelled in accordance with paragraph 1 may be reused within the concerned programme, subject to paragraph 3.
The contribution cancelled in accordance with paragraph 1 may not be reused for the project that was the subject of a financial correction or, where a financial correction is made for a systemic irregularity and for any project affected by the systemic irregularity.
Article 72
Financial corrections by the Commission
The Commission shall make financial corrections by cancelling all or part of the Union contribution to a programme and effecting recovery from the Managing Authority in order to exclude from Union financing expenditure which is in breach of applicable law or related to deficiencies in the programme management and control systems which have been detected by the Commission or the European Court of Auditors.
A breach of applicable law shall lead to a financial correction only in relation to expenditure which has been declared to the Commission and where one of the following conditions is met:
- (a) the breach has affected the selection of a project or a technical assistance contract or in cases where, due to the nature of the breach, it is not possible to establish that impact but there is a substantiated risk that the breach has had such an effect;
- (b) the breach has affected the amount of expenditure declared by the programme or in cases where, due to the nature of the breach, it is not possible to quantify its financial impact but there is a substantiated risk that the breach has had such an effect.
In particular the Commission shall make financial corrections where, after carrying out the necessary examination, it draws any of the following conclusions:
- (a) there is a serious deficiency in the programme management and control systems of the programme which has put at risk the Union contribution already paid;
- (b) the Managing Authority has not complied with its obligations under Article 71 prior to the opening of the financial correction procedure under this paragraph;
- (c) the expenditure declared in the annual or final report is irregular and has not been corrected by the Managing Authority prior to the opening of the financial correction procedure under this paragraph.
The Commission shall base its financial corrections on individual cases of irregularity identified and shall take account of whether an irregularity is systemic. When it is not possible to quantify precisely the amount of irregular expenditure, the Commission shall apply a flat rate or extrapolated financial correction.
The Commission shall, when deciding the amount of a financial correction under paragraph 3, respect the principle of proportionality taking into account the nature and gravity of the irregularity and the extent and financial implications of the deficiencies in management and control systems found in the programme.
Where the Commission bases its position on reports of auditors other than those of its own services, it shall draw its own conclusions regarding the financial consequences after having heard the Managing Authority and the auditors.
The closure of the programme shall not prejudice the Commission's right to undertake, at a later stage, financial corrections vis-à-vis the Managing Authority.
The criteria for establishing the level of financial correction to be applied and the criteria for applying flat rates or extrapolated financial correction are those adopted in accordance with Regulation (EU) No 1303/2013 ([^E0005]), in particular Article 144, as well as those contained in the Commission Decision of 19 December 2013 ([^E0006]).
Article 73
Procedure
Before taking a decision on a financial correction, the Commission shall inform the Managing Authority of the provisional conclusions of its examination and request the Managing Authority to submit its comments within two months.
Where the Commission proposes a financial correction on the basis of extrapolation or a flat rate, the Managing Authority shall be given the opportunity to demonstrate through an examination of the documentation concerned that the actual extent of irregularity is less than the Commission's assessment. In agreement with the Commission, the Managing Authority may limit the scope of that examination to an appropriate proportion or sample of the documentation concerned. Except in duly justified cases, the time allowed for that examination shall not exceed a further period of two months after the two-month period referred to in paragraph 1.
The Commission shall take account of any evidence supplied by the Managing Authority within the time limits set out in paragraphs 1 and 2.
Where the Managing Authority does not accept the provisional conclusions of the Commission, the Managing Authority shall be invited to a hearing by the Commission, to ensure that all relevant information and observations are available for the conclusions of the Commission on the application of the financial correction.
In case of an agreement and without prejudice to paragraph 6, the Managing Authority may reuse the cancelled contribution for the concerned programme in accordance with Article 71(2).
In order to apply financial corrections, the Commission shall take a decision within six months of the date of the hearing or of the date of receipt of additional information where the Managing Authority agrees to submit such additional information following the hearing. The Commission shall take account of all information and observations submitted during the course of the procedure. If no hearing takes place, the six-month period shall begin to run two months after the date of the invitation letter to the hearing sent by the Commission.
Where the Commission or the European Court of Auditors detect irregularities demonstrating a serious deficiency in the effective functioning of the management and control systems, the resulting financial correction shall reduce the Union contribution.
The first subparagraph shall not apply in the case of a serious deficiency in the effective functioning of management and control systems which, prior to the date of detection by the Commission or the European Court of Auditors:
- (a) had been identified in the management declaration, annual control report or the audit opinion submitted to the Commission in accordance with Article 68, or in other audit reports of the Audit Authority submitted to the Commission and appropriate measures taken; or
- (b) had been the subject of appropriate remedial measures by the Managing Authority.
The assessment of serious deficiencies in the effective functioning of management and control systems shall be based on the applicable law when the relevant management declarations, annual control reports and audit opinions were submitted.
When deciding on a financial correction the Commission shall:
- (a) respect the principle of proportionality by taking account of the nature and gravity of the serious deficiency in the effective functioning of a management and control system and its financial implications for the budget of the Union;
- (b) for the purpose of applying a flat rate or extrapolated correction, exclude irregular expenditure previously detected by the Managing Authority which has been the subject of an adjustment in the accounts and expenditure subject to an ongoing assessment of its legality and regularity;
- (c) take into account flat rate or extrapolated corrections applied to the expenditure by the Managing Authority for other serious deficiencies detected by the Managing Authority when determining the residual risk for the budget of the Union.
Section 2 Recoveries
Article 74
Financial responsibilities and Recoveries
The Managing Authority shall be responsible for pursuing the recovery of amounts unduly paid.
Where the recovery relates to a breach of legal obligations on the part of the Managing Authority stemming from this Regulation and Regulation (EU, Euratom) No 966/2012 the Managing Authority shall be responsible for reimbursing the amounts concerned to the Commission.
Where the recovery relates to systemic deficiencies in the programme management and control systems, the Managing Authority shall be responsible for reimbursing the amounts concerned to the Commission in accordance with the apportionment of liabilities among the participating countries as laid down in the programme.
Where the recovery relates to a claim against a beneficiary established in a Member State and the Managing Authority is unable to recover the debt, the Member State in which the beneficiary is established shall pay the due amount to the Managing Authority and claim it back from the beneficiary.
Where the recovery relates to a claim against a beneficiary established in a CBC partner country and the Managing Authority is unable to recover the debt, the level of responsibility of the CBC partner country in which the beneficiary is established shall be such as it is laid down in the relevant financing agreements referred to in Articles 8 and 9.
Article 75
Repayment to the Managing Authority
The Managing Authority shall recover the amounts unduly paid together with any interest on late payments from the lead beneficiary. The concerned beneficiaries shall repay the lead beneficiary the amounts unduly paid in accordance with the partnership agreement signed between them. If the lead beneficiary does not succeed in securing repayment from the concerned beneficiary, the Managing Authority shall formally notify the latter to repay to the lead beneficiary. If the concerned beneficiary does not repay, the Managing Authority shall request the participating country in which the concerned beneficiary is established to reimburse the amounts unduly paid in accordance with Article 74(2) to (5).
The Managing Authority shall exercise due diligence to ensure reimbursement of the recovery orders with support from the participating countries. The Managing Authority shall in particular ensure that the claim is certain, of a fixed amount and due. Where the Managing Authority is planning to waive recovery of an established debt, it shall ensure that the waiver is in order and complies with the principles of sound financial management and proportionality. The waiver decision must be submitted to the Joint Monitoring Committee for prior approval.
The Managing Authority shall keep the Commission informed of all steps taken to recover the due amounts. The Commission may at any time take over the task of recovering the amounts directly either from the beneficiary or from the concerned participating country.
Files transferred to a participating country or to the Commission shall contain all the documents needed for recovery as well as proof of steps taken by the Managing Authority to recover the due amounts.
Contracts concluded by the Managing Authority shall contain a clause allowing the Commission or the participating country in which the beneficiary is established to recover any amounts due to the Managing Authority which the latter was not able to recover.
Article 76
Repayment to the Commission
Any repayment due to the Commission shall be effected before the due date indicated in the recovery order. The due date shall be 45 days from the date of the issuing of the debit note.
Any delay in effecting repayment shall give rise to interest on account of late payment, starting on the due date and ending on the date of actual payment. The rate of such interest shall be three and a half percentage points above the rate applied by the European Central Bank in its main refinancing operations on the first working day of the month in which the due date falls. Amounts to be repaid may be offset against amounts of any kind due to the beneficiary or participating country. This shall not affect the parties' right to agree on payment in instalments.
TITLE IX REPORTING, MONITORING AND EVALUATION
Article 77
Annual reports of the Managing Authority
By 15 February the Managing Authority shall submit an annual report approved by the Joint Monitoring Committee to the Commission. That annual report shall include one technical and one financial part covering the preceding accounting year.
The technical part shall describe:
- (a) the progress achieved in implementing the programme and its priorities;
- (b) the detailed list of signed contracts as well as the list of selected projects not yet contracted, including reserve lists;
- (c) the technical assistance activities carried out;
- (d) the measures undertaken to monitor and evaluate projects, their results and actions undertaken to remedy the problems identified;
- (e) the implemented information and communication activities.
The financial part shall be prepared in accordance with Article 68(2).
In addition, the annual report shall contain the forecast of activities to be implemented in the following accounting year. It shall include:
- (a) an updated audit strategy;
- (b) the work programme, financial plan and planned use of technical assistance;
- (c) the annual monitoring and evaluation plan in accordance with Article 78(2);
- (d) the annual information and communication plan in accordance with Article 79(4).
By 15 February 2025 the Managing Authority shall submit a final report approved by the Joint Monitoring Committee to the Commission. This final report shall contain mutatis mutandis the information requested under paragraphs 2 and 3 above for the last accounting year and for the entire duration of the programme.
The deadlines set out in paragraphs 1 and 5 may exceptionally be extended by the Commission to 1 March, upon communication by the managing authority concerned.
Article 78
Monitoring and Evaluation
Programme monitoring and evaluation shall aim at improving the quality of the design and implementation, as well as at assessing and improving its consistency, effectiveness, efficiency and impact. The findings of monitoring and evaluations shall be taken into account in the programming and implementation cycle.
An indicative monitoring and evaluation plan shall be included in the programme for its whole duration. Each programme shall subsequently draw up an annual monitoring and evaluation plan to be carried out by the Managing Authority in accordance with the Commission's guidance and evaluation methodology. The annual plan shall be submitted to the Commission not later than 15 February.
The Managing Authority shall carry out result-oriented programme and project monitoring in addition to the day-to-day monitoring.
The Commission shall have access to all monitoring and evaluation reports.
The Commission can at any moment, launch evaluation or monitoring of the programme or of a part thereof. The results of these exercises, which shall be communicated to the Joint Monitoring Committee and the Managing Authority of the programme, may lead to adjustments in the programme.
TITLE X VISIBILITY
Article 79
Visibility
The responsibility to ensure that appropriate information is communicated to the public shall lie with both the Managing Authority and the beneficiaries.
The Managing Authority and the beneficiaries shall ensure adequate visibility of the Union contribution to programmes and projects in order to strengthen public awareness of the Union action and create a consistent image of the Union support in all participating countries.
The Managing Authority shall ensure that its visibility strategy and visibility measures undertaken by the beneficiaries comply with the Commission's guidance.
The communication strategy for its whole duration and an indicative information and communication plan for the first year, including visibility measures, shall be included in the programme. Each programme shall subsequently draw up an annual information and communication plan to be carried out by the Managing Authority. That plan shall be submitted to the Commission not later than 15 February.
PART THREE
SPECIAL PROVISIONS
TITLE I INDIRECT MANAGEMENT WITH INTERNATIONAL ORGANISATIONS
Article 80
International organisations as Managing Authority
Participating countries may propose that the programme be managed by an international organisation.
Only international organisations in the sense of Article 43 of Delegated Regulation (EU) No 1268/2012 may be proposed as Managing Authority.
An international organisation shall meet the requirements set out in Article 60 of Regulation (EU) No 966/2012.
Before the Commission adopts a programme it shall obtain evidence that the requirements set out in paragraph 3 are fulfilled.
Article 81
Rules applicable to programmes managed by an international organisation
The Commission and the international organisation shall conclude an agreement detailing the arrangements applicable to the programme. In case the programme makes a contribution to a financial instrument pursuant to Article 42, conditions and reporting requirements set out in Article 140 of Regulation (EU, Euratom) No 966/2012 shall be respected.
The provisions contained in Part Two shall apply to programmes managed by an international organisation unless the agreement referred to in paragraph 1 provides otherwise.
TITLE II INDIRECT MANAGEMENT WITH A CBC PARTNER COUNTRY
Article 82
CBC partner countries as Managing Authority
Participating countries may propose that the programme is managed by a CBC partner country.
The nature of the tasks entrusted to the appointed CBC partner country shall be set out in the agreement signed by the Commission and the CBC partner country pursuant to the provisions on indirect management contained in the Regulation (EU, Euratom) No 966/2012 and Delegated Regulation (EU) No 1268/2012.
The agreement referred to in paragraph 2 shall detail the arrangements applicable to the programme. In particular, it shall lay down which provisions of Part Two apply in view of the nature of the tasks entrusted to the Managing Authority and the amounts involved.
PART FOUR
FINAL PROVISIONS
Article 83
Transitional provisions
Commission Regulation (EC) No 951/2007 ([^E0007]) shall continue to apply for legal acts and commitments implementing the budget years preceding 2014.
Article 84
Entry into force
This Regulation shall enter into force on the third day following that of its publication in the Official Journal of the European Union.
It shall apply from 1 January 2014.
This Regulation shall be binding in its entirety and directly applicable in all Member States.
ANNEX
Designation Criteria for the Managing Authority
The designation procedure shall be based on the following components of internal control:
1. Internal control environment
- (i) An organisational structure covering the functions of managing authority and the allocation of functions between and within each body as described in Chapter 2 of Title IV of Part Two, ensuring that the principle of segregation of functions, where appropriate, is respected.
- (ii) If delegation of tasks to intermediate bodies, a framework for ensuring the definition of their respective responsibilities and obligations, verification of their capacities to carry out delegated tasks and the existence of reporting procedures.
- (iii) Reporting and monitoring procedures for preventing, detecting and correcting irregularities and for recovering amounts unduly paid.
- (iv) Plan for allocation of appropriate human resources with necessary skills, at different levels and for different functions in the organisation.
2. Risk management
Taking into account the principle of proportionality, a system for ensuring that an appropriate risk management exercise is conducted at least once per year, and in particular, in the event of major modifications of the activities.
3. Management and control activities
- (i) Project selection procedures, ensuring the principles of transparency, equal treatment, non-discrimination, objectivity and fair competition. With a view to respect these principles:
- (a) the projects shall be selected and awarded on the basis of pre-announced selection and award criteria which are defined in the evaluation grid. The selection criteria serve to assess the applicant's ability to complete the proposed action or work programme. The award criteria are used to assess the quality of the project's proposal against the set objectives and priorities;
- (b) the grants shall be subject to ex ante and ex post publicity rules;
- (c) the applicants shall be informed in writing about the evaluation results. If the grant requested is not awarded, the Managing Authority shall provide the reasons for the rejection of the application with reference to the selection and award criteria that are not met by the application;
- (d) any conflict of interest shall be avoided;
- (e) the same rules and conditions shall be applied to all applicants.
- (ii) Contract management procedures.
- (iii) Verification procedures including administrative verifications in respect of each payment request by beneficiaries and the on-the-spot verifications of projects.
- (iv) Procedures for processing and authorising payments.
- (v) Procedures for establishing a system to collect, record and store electronically data on each project and for ensuring that the IT systems are secured in line with internationally accepted standards.
- (vi) Procedures established by the managing authority to ensure that beneficiaries maintain either a separate accounting system or an adequate accounting code for all transactions relating to a project.
- (vii) Procedures for putting in place effective and proportionate anti-fraud measures.
- (viii) Procedures for drawing up the accounts and ensure that they are true, complete and accurate and that the expenditure complies with applicable rules.
- (ix) Procedures to ensure an adequate audit trail and archiving system.
- (x) Procedures to draw up the management declaration of assurance, report on the controls carried out and weaknesses identified, and the annual summary of final audits and controls.
- (xi) Where tasks are delegated to intermediate bodies, the designation criteria should include an assessment of the procedures in place to ensure that the Managing Authority verifies the capacity of the intermediate bodies to carry out tasks and to monitor that these tasks are being properly implemented.
4. Information and communication
- (i) The Managing Authority obtains or generates and uses relevant information to support the functioning of other components of the internal control.
- (ii) The Managing Authority internally disseminates information, including objectives and responsibilities for internal control, necessary to support the functioning of other components of the internal control.
- (iii) The Managing Authority communicates with external parties regarding matters affecting the functioning of other components of internal control.
5. Monitoring
Documented procedures, verifications and evaluations performed to ascertain that the components of internal control exist and function.
[^E0001]: Directive 2001/42/EC of the European Parliament and of the Council of 27 June 2001 on the assessment of the effects of certain plans and programmes on the environment (OJ L 197, 21.7.2001, p. 30).
[^E0002]: Council Regulation (EC) No 659/1999 of 22 March 1999 laying down detailed rules for the application of Article 93 of the EC Treaty (OJ L 83, 27.3.1999, p. 1).
[^E0003]: Directive 2006/43/EC of the European Parliament and of the Council of 17 May 2006 on statutory audits of annual accounts and consolidated accounts, amending Council Directives 78/660/EEC and 83/349/EEC and repealing Council Directive 84/253/EEC (OJ L 157, 9.6.2006, p. 87).
[^E0004]: Directive 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment (OJ L 26, 28.1.2012, p. 1).
[^E0005]: Regulation (EU) No 1303/2013 of the European Parliament and of the Council of 17 December 2013 laying down common provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund, the European Agricultural Fund for Rural Development and the European Maritime and Fisheries Fund and laying down general provisions on the European Regional Development Fund, the European Social Fund, the Cohesion Fund and the European Maritime and Fisheries Fund and repealing Council Regulation (EC) No 1083/2006 (OJ L 347, 20.12.2013, p. 320).
[^E0006]: Commission Decision of 19 December 2013 on the setting out and approval of the guidelines for determining financial corrections to be made by the Commission to expenditure financed by the Union under shared management for non-compliance with the rules on public procurement (C(2013)9527).
[^E0007]: Commission Regulation (EC) No 951/2007 of 9 August 2007 laying down implementing rules for cross-border cooperation programmes financed under Regulation (EC) No 1638/2006 of the European Parliament and of the Council laying down general provisions establishing a European Neighbourhood and Partnership Instrument (OJ L 210, 10.8.2007, p. 10).
Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.
This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence.
EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.