The ECB shall specify in the contract notice the documents to be submitted by candidates or tenderers as proof of their financial, economic, technical and professional capacity. It may require, in particular, submission of a European Single Procurement Document as specified in Article 59 of Directive 2014/24/EU, documents held in eCertis, or certificates issued by national databases of approved suppliers. The documentation requested shall not go beyond the subject of the contract and shall take account of the legitimate interests of the suppliers as regards in particular the protection of their technical and business secrets.
If, for some exceptional reason which the ECB considers justified, a tenderer or candidate is unable to provide the documents requested, it may prove its capacity by any other means which the ECB considers appropriate and equivalent.
A supplier may, where appropriate and for a particular contract, rely on the capacities of another entity, regardless of the legal nature of the links which it has with them. It shall in that case prove to the ECB that it will have the resources necessary for performance of the contract at its disposal, and that the entity itself is eligible to participate in tender procedures in accordance with Article 30. Under the same conditions, a temporary grouping of suppliers may rely on the capacities of participants in the group.
Article 32
Award criteria
The ECB shall award the contract to the tenderer that submitted the most economically advantageous tender.
Unless otherwise provided in this Decision, the most economically advantageous tender is identified on the basis of one of the following options:
- — the price or costs only,
- — the best price-quality ratio, or
- — quality only, the relevant price or cost for the products, works and services tendered being fixed.
The price or cost element shall, to the extent relevant, take account of life-cycle costs such as costs relating to acquisition, use, maintenance and end-of-life of products, works and services. Costs relating to environmental externalities linked to products, works and services during their life cycle may also be considered. Prices and costs shall be considered only if they can be determined and verified.
The best price-quality ratio shall be assessed on the basis of criteria, including qualitative, environmental and/or social aspects linked to the subject matter of the contract, such as:
- (a) quality, including technical merit, aesthetic and functional characteristics, accessibility, design for all users, social, environmental and innovative characteristics and trading and the conditions thereof;
- (b) organisational structure, qualifications and experience of staff assigned to perform the contract, where staff quality can have a significant impact on the level of performance of the contract; or
- (c) after-sales service and technical assistance, delivery conditions such as delivery date, delivery process and delivery period, or period of completion.
All of the award criteria shall be linked to the subject matter of the contract which may include the different stages involved in the life cycle of the products, works or services tendered such as the processes of production, provision or trading thereof.
The contract notice or the invitation to tender or, in the case of a competitive dialogue, the request for a proposal, shall specify how the most economically advantageous tender shall be identified pursuant to paragraph 2.
Article 33
Abnormally low tenders
The ECB shall request in writing explanations of prices or costs proposed in tenders that appear to be abnormally low in relation to the products, works or services tendered. The request may relate in particular to:
- (a) the economics of the manufacturing process, of the provision of services or of the construction method;
- (b) the technical solutions chosen or any exceptionally favourable conditions available to the tenderer;
- (c) the originality of the deliverables proposed in the tender;
- (d) compliance with the provisions of environmental, social security and labour law in force at the place where the deliverables are to be executed, provided or supplied; and
- (e) the tenderer's possibility to obtain State aid.
Following a review of the information submitted by the tenderer, the ECB may reject abnormally low tenders, in particular in the following cases:
- — where the information provided by the tenderer does not sufficiently account for the low level of the price or costs,
- — where the tender and the additional information provided do not provide sufficient assurance of proper contract performance, or
- — where the tenderer has obtained State aid, unless the tenderer proves, within a reasonable time limit fixed by the ECB, that the aid was granted legally in accordance with the procedures and decisions specified in the Union rules on State aid.
The ECB shall reject tenders that are abnormally low due to breaches of any of the provisions referred to in paragraph 1(d).
SECTION 7 Communication of the outcome
Article 34
Notification of selection and award decisions
The ECB shall notify its decision in writing and without undue delay to all candidates or tenderers whose applications or tenders are rejected.
The notification of the award decision shall be sent at least 10 days prior to the signature of the contract by the ECB if the notification is sent by fax or electronic means, or at least 15 days prior to the signature of the contract if other means of communication are used (‘standstill period’). The ECB shall not sign the contract with the successful tenderer until this standstill period has elapsed.
The ECB shall notify all concerned candidates or concerned tenderers whose applications or tenders are rejected of the reasons for rejecting their application or tender as well as the duration of the standstill period referred to in paragraph 2. The ECB shall notify any unsuccessful tenderer that has made an admissible tender, and who makes a request in writing, of the name of the successful tenderer as well as the characteristics and relative advantages of the successful tender.
The ECB may decide to withhold certain information where its release would affect other suppliers' legitimate commercial interests, would hinder the application of the law, might prejudice fair competition between suppliers or would otherwise be contrary to the public interest.
The ECB shall publish a contract award notice in line with the requirements of Directive 2014/24/EU in the Official Journal. The notice shall be sent to the Official Journal within 30 days following signature of the contract.
CHAPTER III PROCUREMENT PROCEDURE FOR CONTRACTS BELOW THE THRESHOLDS AND SERVICE CONTRACTS REFERRED TO IN ARTICLE 6(2)
Article 35
Conduct of the procedure
Contracts the estimated value of which is below the thresholds specified in Article 4(3) and service contracts referred to in Article 6(2) shall be awarded in accordance with the following procedure.
-
- If the value of the contract net of VAT exceeds or is equal to EUR 50 000 for products and services or EUR 500 000 for works, the ECB shall invite at least five suitable suppliers, if available, to submit a tender.
-
- If the value of contract net of VAT is below these thresholds but equal to or above EUR 20 000 , the ECB shall invite at least three suitable suppliers, if available, to submit a tender.
-
- The ECB shall select the suppliers invited to participate in the tender procedure either from among the tenderers admitted to a dynamic purchasing system or, where no such system is in place, from a list of suitable suppliers drawn up following a call for expression of interest. Where no such list is established, the ECB shall select the suppliers to be invited at its own discretion, on the basis of a proper market analysis, taking account of any possible cross-border interest, confirming the suppliers' suitability and their interest in participating in the procedure. The market analysis may include a publication of the contract opportunity in an electronic procurement system. Alternatively, the ECB may publish a contract notice on its website or using other appropriate media. In that case, the suppliers invited to participate in the tender procedure shall be selected on the basis of the responses received. Other suppliers that meet the same criteria may also be invited to participate in the tender procedure.
-
- If the value of a service contract referred to in Article 6(2) net of VAT exceeds or is equal to EUR 750 000 , the ECB shall publish a contract notice in the Official Journal. The suppliers invited to participate in the tender procedure shall be selected on the basis of the responses received. Other suppliers that meet the same criteria may also be invited to participate in the tender procedure.
-
- The ECB shall provide the suppliers invited to participate in the tender procedure with a request for a proposal specifying the ECB's requirements, the submission process and the criteria for the award of the contract. When fixing the time limit for the submission of tenders, the ECB shall take account of the complexity of the contract and the time required to prepare a tender.
-
- The tenders received shall be evaluated against the formal requirements and the selection and award criteria set out in the request for a proposal. Following the evaluation of the written tenders, the ECB may enter into negotiations with the tenderers if that possibility was mentioned in the request for a proposal. The negotiations may be carried out as consecutive negotiations in the order of the tenderers' ranking or as parallel negotiations with several tenderers whose tenders best meet the award criteria.
-
- The ECB shall award the contract to the tenderer whose tender best meets the award criteria set out in the request for a proposal.
-
- The procurement procedure shall be carried out in accordance with the general principles set out in Article 3. Article 9(6) and (7), Article 13(5) and (6) and Articles 18, 19, 20, 26, 27, 28, 30 and 33 shall apply accordingly.
Article 36
Notification of award decision and list of contractors
Following the award decision, the ECB shall inform the tenderers in writing and without undue delay of the results of the tender procedure.
Tenderers may, within 15 days of receipt of the notification, request the ECB to provide the reasons for rejecting their tender.
Notwithstanding paragraph 1 and the first subparagraph of this paragraph, Article 34(1) to (4) shall apply when the ECB awards through the procedure specified in Article 35(4) a service contract referred to in Article 6(2) with a value net of VAT that exceeds or is equal to EUR 750 000 , provided that there is a clear cross-border interest.
The ECB shall publish annually a list of contracts with a value in excess of EUR 50 000 that were awarded in accordance with Article 35 or subject to an exception in accordance with Article 6(1). The list shall specify the names of the contractors to whom contracts were awarded, the subject matter and the value of the contracts. For contracts covered by Article 6(2) whose value exceeds EUR 750 000 , the ECB shall publish a contract award notice in the Official Journal.
Article 37
Direct award
The ECB may award contracts on the basis of a single offer if the estimated value of the contract is less than EUR 20 000 , net of VAT.
CHAPTER IV FINAL PROVISIONS
Article 38
Cancellation of tender procedures
The ECB may cancel a tender procedure at any time before the contract is signed without the candidates or tenderers being entitled to any compensation.
The ECB's decision to cancel shall comply with the general principles set out in Article 3(1).
The ECB shall substantiate the decision and bring it to the attention of the candidates or tenderers.
Article 39
Appeal procedure
In public tender procedures under Chapter II, candidates and tenderers may challenge in writing the ECB’s decision to reject their application or tender within 10 days of receipt of the notification in accordance with Article 34(1) or the first sentence of Article 34(3). The appeal shall include all supporting information and reasoned objections with the exception of any objections which are precluded in accordance with Article 28(2).
The appeal shall be addressed by the ECB's Procurement Review Body (PRB). If the PRB considers that the decision to reject the appellant's application or tender infringes this Decision or general principles of procurement law it shall either order that the tender procedure or parts of it are repeated or take a final decision. Otherwise the appeal shall be rejected. The PRB shall notify the appellant in writing of its decision within 1 month following the receipt of the appeal. The decision shall state the reasons on which it is based.
The appeal shall have suspensive effect in relation to the award of the contract.
If the appeal is rejected, an additional standstill period of at least 10 days prior to the signature of the contract by the ECB if the notification is sent by fax or electronic means, or at least 15 days prior to the signature of the contract if other means of communication are used, shall apply. The PRB shall notify the appellant about the duration of the standstill period.
Article 40
Jurisdiction
The Court of Justice of the European Union shall have exclusive jurisdiction in any dispute between the ECB and a supplier relating to this Decision or a specific procurement procedure. If an appeal procedure is available under Article 39, the appellant shall await the ECB's decision on the appeal before bringing the matter to the Court of Justice. The time limits set out in the Treaty on the Functioning of the European Union shall begin to run from receipt of the appeal decision by the supplier.
Article 41
Entry into force
This Decision shall enter into force on 15 April 2016 and shall repeal and replace Decision ECB/2007/5.
Tender procedures that were started before the entry into force of this Decision shall be completed in accordance with Decision ECB/2007/5. For the purpose of this provision a tender procedure is deemed to be started on the day on which the contract notice was sent to the Official Journal or, in cases where no such notice is required, on the day when the ECB invited one or more suppliers to submit a tender or a proposal.
References to the repealed Decision shall be construed as references to this Decision and be read in accordance with the correlation table set out in Annex II.
ANNEX I
SERVICES SUBJECT TO ARTICLE 6(2)
| CPV Code | Description |
|---|---|
| 75200000-8; 75231200-6; 75231240-8; 79611000-0; 79622000-0 [Supply services of domestic help personnel]; 79624000-4 [Supply services of nursing personnel] and 79625000-1 [Supply services of medical personnel] from 85000000-9 to 85323000-9; 98133100-5, 98133000-4; 98200000-5; 98500000-8 [Private households with employed persons] and 98513000-2 to 98514000-9 [Manpower services for households, Agency staff services for households, Clerical staff services for households, Temporary staff for households, Home-help services and Domestic services] | Health, social and related services |
| 85321000-5 and 85322000-2, 75000000-6 [Administration, defence and social security services], 75121000-0, 75122000-7, 75124000-1; from 79995000-5 to 79995200-7; from 80000000-4 Education and training services to 80660000-8; from 92000000-1 to 92700000-8 79950000-8 [Exhibition, fair and congress organisation services], 79951000-5 [Seminar organisation services], 79952000-2 [Event services], 79952100-3 [Cultural event organisation services], 79953000-9 [Festival organisation services], 79954000-6 [Party organisation services], 79955000-3 [Fashion shows organisation services], 79956000-0 [Fair and exhibition organisation services] | Administrative social, educational, healthcare and cultural services |
| 75300000-9 | Compulsory social security services |
| 75310000-2, 75311000-9, 75312000-6, 75313000-3, 75313100-4, 75314000-0, 75320000-5, 75330000-8, 75340000-1 | Benefit services |
| 98000000-3; 98120000-0; 98132000-7; 98133110-8 and 98130000-3 | Other community, social and personal services including services furnished by trade unions, political organisations, youth associations and other membership organisation services. |
| 98131000-0 | Religious services |
| 55100000-1 to 55410000-7; 55521000-8 to 55521200-0 [55521000-8 Catering services for private households, 55521100-9 Meals-on-wheels services, 55521200-0 Meal delivery service] 55520000-1 Catering services, 55522000-5 Catering services for transport enterprises, 55523000-2 Catering services for other enterprises or other institutions, 55524000-9 School catering services 55510000-8 Canteen services, 55511000-5 Canteen and other restricted-clientele cafeteria services, 55512000-2 Canteen management services, 55523100-3 School-meal services | Hotel and restaurant services |
| 79100000-5 to 79140000-7; 75231100-5; | Legal services, to the extent not excluded pursuant to Article 2(3)(j) |
| 75100000-7 to 75120000-3; 75123000-4; 75125000-8 to 75131000-3 | Other administrative services and government services |
| 75200000-8 to 75231000-4 | Provision of services to the community |
| 75231210-9 to 75231230-5; 75240000-0 to 75252000-7; 794300000-7; 98113100-9 | Prison related services, public security and rescue services |
| 79700000-1 to 79721000-4 [Investigation and security services, Security services, Alarm-monitoring services, Guard services, Surveillance services, Tracing system services, Absconder-tracing services, Patrol services, Identification badge release services, Investigation services and Detective agency services] 79722000-1 [Graphology services], 79723000-8 [Waste analysis services] | Investigation and security services |
| 98900000-2 [Services provided by extra-territorial organisations and bodies] and 98910000-5 [Services specific to international organisations and bodies] | International services |
| 64000000-6 [Postal and telecommunications services], 64100000-7 [Post and courier services], 64110000-0 [Postal services], 64111000-7 [Postal services related to newspapers and periodicals], 64112000-4 [Postal services related to letters], 64113000-1 [Postal services related to parcels], 64114000-8 [Post office counter services], 64115000-5 [Mailbox rental], 64116000-2 [Post-restante services], 64122000-7 [Internal office mail and messenger services] | Postal services |
| 50116510-9 [Tyre-remoulding services], 71550000-8 [Blacksmith services] | Miscellaneous services |
ANNEX II
CORRELATION TABLE
| Decision ECB/2007/5 | This Decision |
|---|---|
| Article 1 | Article 1 |
| Article 2 | Article 2 |
| Article 3 | Article 3 |
| Article 4 | Article 4 |
| Article 5 | Article 5 |
| Article 6 | Article 6 |
| Article 7 | Article 7 |
| Article 8 | Article 8 |
| Article 9 | Article 9 |
| Article 10 | Article 21 |
| Article 11 | Article 10 |
| Article 12 | Article 11 |
| Article 13 | Article 12 |
| Article 14 | Article 13 |
| Article 15 | Article 18 |
| Article 16 | Article 19 |
| Article 16a | Article 22 |
| Article 17 | Article 16 |
| Article 18 | Article 23 |
| Article 19(3) | Article 15 |
| Article 19(1), (2), (4) and (5) | Article 26 |
| Article 20 | Article 27 |
| Article 21 | Article 28 |
| Article 22 | Article 24 |
| Article 23 | Article 29 |
| Article 24 | Article 30 |
| Article 25 | Article 31 |
| Article 26 | Article 32 |
| Article 27 | Article 33 |
| Article 28 | Article 34 |
| Article 29 | Article 35 |
| Article 30 | Article 36 |
| Article 31 | Article 37 |
| Article 32 | Article 38 |
| Article 33 | Article 39 |
| Article 34 | Article 40 |
| Article 35 | Article 41 |
[^E0001]: Guideline (EU) 2015/280 of the European Central Bank of 13 November 2014 on the establishment of the Eurosystem Production and Procurement System (ECB/2014/44) (OJ L 47, 20.2.2015, p. 29).
[^E0002]: Directive 2014/23/EU of the European Parliament and of the Council of 26 February 2014 on the award of concession contracts (OJ L 94, 28.3.2014, p. 1).
[^E0003]: Regulation (EEC, Euratom) No 1182/71 of the Council of 3 June 1971 determining the rules applicable to periods, dates and time limits (OJ L 124, 8.6.1971, p. 1).
[^E0004]: Regulation (EU) 2018/1725 of the European Parliament and of the Council of 23 October 2018 on the protection of natural persons with regard to the processing of personal data by the Union institutions, bodies, offices and agencies and on the free movement of such data, and repealing Regulation (EC) No 45/2001 and Decision No 1247/2002/EC (OJ L 295, 21.11.2018, p. 39).
Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.
This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence.
EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.