Regulation (EU) 2021/1153 of the European Parliament and of the Council of 7 July 2021 establishing the Connecting Europe Facility and repealing Regulations (EU) No 1316/2013 and (EU) No 283/2014 (Text with EEA relevance)

Type Regulation
Publication 2021-07-07
State In force
Department Council of the European Union, European Parliament
Source EUR-Lex
Reform history JSON API

CHAPTER I

GENERAL PROVISIONS

Article 1

Subject matter

This Regulation establishes the Connecting Europe Facility (the ‘CEF’) for the period of the Multiannual Financial Framework (the “MFF”) 2021-2027.

This Regulation lays down the objectives of the CEF, its budget for the period 2021-2027, the forms of Union funding and the rules for providing such funding.

Article 2

Definitions

For the purposes of this Regulation, the following definitions apply:

(a) “action” means any activity which has been identified as financially and technically independent, has a set time-frame and is necessary for the implementation of a project;

(b) “alternative fuels” means alternative fuels for all modes of transport as defined in Article 2, point (1), of Directive 2014/94/EU;

(c) “beneficiary” means an entity with legal personality with which a grant agreement has been signed;

(d) “blending operation” means actions supported by the Union budget, including within blending facilities pursuant to Article 2, point (6), of the Financial Regulation combining non-repayable forms of support and/or financial instruments and/or budgetary guarantees from the Union budget with repayable forms of support from development or other public finance institutions, as well as from commercial finance institutions and investors;

(e) “comprehensive network” means the transport infrastructure identified in accordance with Chapter II of Regulation (EU) No 1315/2013;

(f) “core network” means the transport infrastructure identified in accordance with Chapter III of Regulation (EU) No 1315/2013;

(g) “core network corridors” means instruments to facilitate the coordinated implementation of the core network as provided for in Chapter IV of Regulation (EU) No 1315/2013 and listed in Part III of the Annex to this Regulation;

(h) “cross border link” means, in the transport sector, a project of common interest which ensures the continuity of the TEN-T between Member States or between a Member State and a third country;

(i) “missing link” means an all modes of transport missing section of the TEN-T or a transport section that is providing the connection of core or comprehensive networks with the TEN-T corridors which hampers the continuity of the TEN-T or containing one or more bottlenecks affecting the continuity of the TEN-T;

(j) “dual-use infrastructure” means a transport network infrastructure that addresses both civilian and defence needs;

(k) “cross-border project in the field of renewable energy” means a project selected or eligible to be selected under a cooperation agreement or any other kind of arrangement between two or more Member States or arrangements between one or more Member States and one or more third countries as set out in Articles 8, 9, 11 and 13 of Directive (EU) 2018/2001 in the planning or deployment of renewable energy, in accordance with the criteria set out in Part IV of the Annex to this Regulation;

(l) “energy efficiency first” means energy efficiency first as defined in Article 2, point (18), of Regulation (EU) 2018/1999;

(m) “digital connectivity infrastructure” means very high capacity networks, 5G systems, very high-quality local wireless connectivity and backbone networks, as well as operational digital platforms directly associated with transport and energy infrastructure;

(n) “5G systems” means a set of digital infrastructure elements based on globally agreed standards for mobile and wireless communications technology used for connectivity and added-value services with advanced performance characteristics such as very high data rates and capacity, low latency communications, ultra-high reliability or support for a high number of connected devices;

(o) “5G corridor” means a transport path, road, railway or inland waterway, fully covered with digital connectivity infrastructure and in particular 5G systems, enabling the uninterrupted provision of synergy digital services such as connected and automated mobility, similar smart mobility services for railways or digital connectivity on inland waterways;

(p) “operational digital platforms directly associated with transport and energy infrastructure” means physical and virtual information communication technology resources, operating via the communication infrastructure, which support the flow, storage, processing and analysis of transport or energy infrastructure data, or both;

(q) “project of common interest” means a project identified in Regulation (EU) No 1315/2013 or Regulation (EU) No 347/2013 or in Article 8 of this Regulation;

(r) “studies” means activities needed to prepare project implementation, such as preparatory, mapping, feasibility, evaluation, testing and validation studies, including in the form of software, and any other technical support measure, including prior action to define and develop a project and decide on its financing, such as reconnaissance of the sites concerned and preparation of the financial package;

(s) “socioeconomic drivers” means entities which by their mission, nature or location can directly or indirectly generate important socioeconomic benefits for citizens, business and local communities located in their surrounding territory, or in their area of influence;

(t) “third country” means a country that is not a Member State of the Union;

(u) “very high capacity networks” means very high capacity networks as defined in Article 2, point (2), of Directive (EU) 2018/1972;

(v) “works” means the purchase, supply and deployment of components, systems and services including software, the carrying-out of development and construction and installation activities relating to a project, the acceptance of installations and the launching of a project.

Article 3

Objectives

The specific objectives of the CEF are:

(a) in the transport sector: (i) to contribute to the development of projects of common interest relating to efficient, interconnected and multimodal networks and infrastructure for smart, interoperable, sustainable, inclusive, accessible, safe and secure mobility in accordance with the objectives of Regulation (EU) No 1315/2013; and (ii) to adapt parts of the TEN-T for the dual use of the transport infrastructure with a view to improving both civilian and military mobility;

(b) in the energy sector: (i) to contribute to the development of projects of common interest relating to further integration of an efficient and competitive internal energy market, interoperability of networks across borders and sectors, facilitating decarbonisation of the economy, promoting energy efficiency and ensuring security of supply; and (ii) to facilitate cross-border cooperation in the area of energy, including renewable energy;

(c) in the digital sector: to contribute to the development of projects of common interest relating to the deployment of and access to safe and secure very high capacity networks, including 5G systems, to the setting up and deployment of digital capacities such as cloud, AI, AI factories and AI Gigafactories, to the increased resilience and capacity of digital backbone networks on Union territories by linking them to neighbouring territories, as well as to the digitalisation of transport and energy networks.

Article 4

Budget

In line with the Union objective of mainstreaming climate actions into Union sectoral policies and Union funds, the CEF shall contribute, through its actions, 60 % of its overall financial envelope to climate objectives.

The distribution of the amount referred to in paragraph 1 shall be as follows:

(a) EUR 25 807 000 000 for the specific objectives referred to in Article 3(2), point (a), of which: (i) EUR 12 830 000 000 from the MFF 2021-2027, Heading 1(2), European Strategic Investment; (ii) EUR 11 286 000 000 transferred from the Cohesion Fund to be spent in line with this Regulation exclusively in Member States eligible for funding from the Cohesion Fund; (iii) EUR 1 691 000 000 from the MFF 2021-2027, Heading 5(13), for the specific objective referred to in Article 3(2), point (a)(ii);

(b) EUR 5 838 000 000 for the specific objectives referred to in Article 3(2), point (b), of which 15 %, subject to market uptake, for cross-border projects in the field of renewable energy, and if the 15 % threshold is reached, the Commission shall increase that threshold up to 20 %, subject to market uptake;

(c) EUR 2 065 000 000 for the specific objectives referred to in Article 3(2), point (c).

The Commission shall do its utmost to enable Member States eligible for funding from the Cohesion Fund to attain, by the end of the period 2021-2027, the highest possible absorption of the amount transferred to the CEF, including through the organisation of additional calls.

In addition, particular attention and support shall be given to those Member States whose GNI per capita, measured in PPS for the period 2015-2017, is less than 60 % of the average GNI per capita of the EU-27.

Article 5

Third countries associated to the CEF

The CEF shall be open to the participation of the following third countries:

(a) members of the European Free Trade Association which are members of the EEA, in accordance with the conditions laid down in the EEA Agreement;

(b) acceding countries, candidate countries and potential candidates, in accordance with the general principles and general terms and conditions for the participation of those countries in Union programmes established in the respective framework agreements and Association Council decisions or in similar agreements and in accordance with the specific conditions laid down in agreements between the Union and those countries;

(c) European Neighbourhood Policy countries, in accordance with the general principles and general terms and conditions for the participation of those countries in Union programmes established in the respective framework agreements and Association Council decisions or in similar agreements and in accordance with the specific conditions laid down in agreements between the Union and those countries;

(d) other third countries, in accordance with the conditions laid down in a specific agreement covering the participation of the third country to any Union programme, provided that the agreement: (i) ensures a fair balance as regards the contributions and benefits of the third country participating in the Union programmes; (ii) lays down the conditions of participation in the programmes, including the calculation of financial contributions to individual programmes, and their administrative costs; (iii) does not confer on the third country any decision-making power in respect of the Union programme; (iv) guarantees the rights of the Union to ensure sound financial management and to protect its financial interests; (v) provides for reciprocity in accessing similar programmes in the third country participating in the Union programmes.

The contributions referred to in the first subparagraph, point (d)(ii), of this Article shall constitute assigned revenues in accordance with Article 21(5) of the Financial Regulation.

Article 6

Implementation and forms of Union funding

Article 7

Cross-border projects in the field of renewable energy

Cross-border projects in the field of renewable energy are eligible for Union funding for works if they meet the following additional criteria:

(a) the project specific cost-benefit analysis pursuant to Part IV, point 3, of the Annex is compulsory for all supported projects and takes into account any revenues resulting from support schemes, has been performed in a transparent, comprehensive and complete manner and provides evidence concerning the existence of significant cost savings or benefits, or both, in terms of system integration, environmental sustainability, security of supply or innovation; and

(b) the applicant demonstrates that the project would not materialise in the absence of the grant or that the project cannot be commercially viable in the absence of the grant.

The amount of the grant for works shall:

(a) be proportionate to the cost savings or benefits referred to in Part IV, point 2(b), of the Annex, or both;

(b) not exceed the amount required to ensure that the project materialises or becomes commercially viable; and

(c) comply with Article 15(3).

Article 8

Projects of common interest in the area of digital connectivity infrastructure

Projects of common interest in the area of digital connectivity infrastructure shall meet the following criteria:

(a) the project contributes to the specific objective provided for in Article 3(2), point (c); and

(b) the project deploys the best available and best suited technology for that specific project, which proposes the best balance in terms of data flow capacity, transmission security, network resilience, cyber security and cost efficiency.

Without prejudice to the award criteria laid down in Article 14, priority for funding shall be determined taking into account the following criteria:

(a) actions contributing to deployment of and access to very high capacity networks, including 5G systems and other state-of-the-art connectivity, in accordance with Union strategic connectivity targets in areas where socioeconomic drivers are located shall be prioritised, taking into account the connectivity needs of those areas and the additional area coverage generated, including for households, in accordance with Part V, point 1, of the Annex; stand-alone deployments to socioeconomic drivers shall be eligible for funding, provided that those deployments are economically proportionate and physically practicable;

(b) actions contributing to the provision of very high-quality local wireless connectivity in local communities shall be prioritised in accordance with Part V, point 2, of the Annex;

(c) actions contributing to the deployment of 5G corridors along major transport paths, including on the TEN-T, such as those listed in Part V, point 3, of the Annex, shall be prioritised to ensure coverage along those major transport paths, enabling the uninterrupted provision of synergy digital services, taking into account its socioeconomic relevance relative to any currently installed technological solutions in a forward looking approach;

(d) projects of common interest which aim to deploy or significantly upgrade cross-border backbone networks linking the Union to third countries and to reinforce links between electronic communications networks within the Union territory, including submarine cables, shall be prioritised according to the extent to which they significantly contribute to the increased performance, resilience and very high capacity of those electronic communications networks;

(e) projects of common interest deploying operational digital platforms shall prioritise actions based on state-of-the-art technologies, taking into account aspects such as interoperability, cybersecurity, data privacy and re-use;

(f) projects of common interest contributing to the setting up and deployment or significant upgrade of digital capacities, including cloud, AI, AI factories and AI Gigafactories shall be prioritised according to the extent they significantly contribute to improve the performance, resilience and security of transport, energy and digital infrastructure that are critical for the proper functioning of the internal market.

CHAPTER II

ELIGIBILITY

Article 9

Eligible actions

In the transport sector, only the following actions shall be eligible to receive Union financial support under this Regulation:

(a) actions relating to efficient, interconnected, interoperable and multimodal networks for the development of railway, road, inland waterway and maritime infrastructure: (i) actions implementing the core network in accordance with Chapter III of Regulation (EU) No 1315/2013, including actions relating to cross-border links and missing links, such as those listed in Part III of the Annex to this Regulation, as well as urban nodes, multimodal logistics platforms, maritime ports, inland ports, rail-road terminals and connections to airports of the core network as defined in Annex II to Regulation (EU) No 1315/2013; actions implementing the core network may include related elements located on the comprehensive network when necessary to optimise the investment and according to modalities specified in the work programmes referred to in Article 20 of this Regulation; (ii) actions relating to cross-border links of the comprehensive network in accordance with Chapter II of Regulation (EU) No 1315/2013, such as those listed in Part III, point 2, of the Annex to this Regulation, actions referred to in Part III, point 3, of the Annex to this Regulation, actions relating to studies for the development of the comprehensive network and actions relating to maritime and inland ports of the comprehensive network in accordance with Chapter II of Regulation (EU) No 1315/2013; (iii) actions to re-establish missing regional cross-border rail connections on the TEN-T that have been abandoned or dismantled; (iv) actions implementing sections of the comprehensive network located in outermost regions in accordance with Chapter II of Regulation (EU) No 1315/2013, including actions relating to the relevant urban nodes, maritime ports, inland ports, rail-road terminals, connections to airports and multimodal logistics platforms, of the comprehensive network as defined in Annex II to Regulation (EU) No 1315/2013; (v) actions supporting projects of common interest in order to connect the trans-European network with infrastructure networks of neighbouring countries as defined in Article 8(1) of Regulation (EU) No 1315/2013;