Commission Delegated Regulation (EU) 2023/1184 of 10 February 2023 supplementing Directive (EU) 2018/2001 of the European Parliament and of the Council by establishing a Union methodology setting out detailed rules for the production of renewable liquid and gaseous transport fuels of non-biological origin

Type Delegated Regulation
Publication 2023-06-20
Last updated 2024-06-10
State In force
Department European Commission, ENER
Source EUR-Lex
articles 13
Reform history JSON API

Article 1

Subject matter

This Regulation lays down detailed rules for determining when electricity used for the production of renewable fuels of non-biological origin can be considered fully renewable. These rules shall apply to the production of renewable fuels of non-biological origin via electrolysis and analogously for less common production pathways.

They shall apply regardless of whether the renewable fuel of non-biological origin is produced inside or outside the territory of the Union.

Article 2

Definitions

For the purposes of this Regulation, the following definitions apply:

Article 3

Rules for counting electricity obtained from direct connection to an installation generating renewable electricity as fully renewable

For the purpose of demonstrating compliance with the criteria set out in Article 27(3), fifth subparagraph of Directive (EU) 2018/2001 for counting electricity obtained from direct connection to an installation generating renewable electricity as fully renewable, the fuel producer shall provide evidence on the following:

If the fuel producer also uses electricity from the grid, it may count it as fully renewable if it complies with the rules set out in Article 4.

Article 4

General rules for counting electricity taken from the grid as fully renewable

1.

Fuel producers may count electricity taken from the grid as fully renewable if the installation producing the renewable fuel of non-biological origin is located in a bidding zone where the average proportion of renewable electricity exceeded 90 % in the previous calendar year and the production of renewable fuel of non-biological origin does not exceed a maximum number of hours set in relation to the proportion of renewable electricity in the bidding zone.

This maximum number of hours shall be calculated by multiplying the total number of hours in each calendar year by the share of renewable electricity reported for the bidding zone where the renewable fuel of non-biological origin is produced. The average share of renewable electricity shall be determined by dividing the gross final consumption of electricity from renewable sources in the bidding zone calculated by analogy to the rules set out in Article 7(2) of Directive (EU) 2018/2001 by the gross electricity production from all energy sources as defined in Annex B to Regulation (EC) No 1099/2008 of the European Parliament and of the Council ([^E0003]), except from water previously pumped uphill, plus imports minus exports of electricity to the bidding zone. Once the average share of renewable electricity exceeds 90 % in a calendar year, it shall be continued to be considered to be higher than 90 % for the subsequent five calendar years.

2.

Where the conditions set out under paragraph 1 are not met, fuel producers may count electricity taken from the grid as fully renewable if the installation producing the renewable fuel of non-biological origin is located in a bidding zone where the emission intensity of electricity is lower than 18 gCO2eq/MJ, provided that the following criteria are met:

3.

Electricity taken from the grid that is used to produce renewable fuel of non-biological origin may also be counted as fully renewable if the electricity used to produce renewable fuel of non-biological origin is consumed during an imbalance settlement period during which the fuel producer can demonstrate, based on evidence from the national transmission system operator, that:

4.

Where the conditions in paragraphs 1, 2 and 3 are not met, fuel producers may count electricity taken from the grid as fully renewable if it complies with the conditions on additionality, temporal correlation and geographic correlation in accordance with Articles 5, 6 and 7.

Article 5

Additionality

The additionality condition referred to in Article 4(4), first subparagraph shall be considered complied with if fuel producers produce an amount of renewable electricity in their own installations that is at least equivalent to the amount of electricity claimed as fully renewable, or have concluded directly, or via intermediaries, one or more renewables power purchase agreements with economic operators producing renewable electricity in one or more installations for an amount of renewable electricity that is at least equivalent to the amount of electricity that is claimed as fully renewable and the electricity claimed is effectively produced in this or these installations, provided that the following criteria are met:

Article 6

Temporal correlation

Until 31 December 2029 the temporal correlation condition referred to in Article 4(2) and (4), shall be considered complied with if the renewable fuel of non-biological origin is produced during the same calendar month as the renewable electricity produced under the renewables power purchase agreement or from renewable electricity from a new storage asset that is located behind the same network connection point as the electrolyser or the installation generating renewable electricity, that has been charged during the same calendar month in which the electricity under the renewables power purchase agreement has been produced.

From 1 January 2030, the temporal correlation condition shall be considered complied with if the renewable fuel of non-biological origin is produced during the same one-hour period as the renewable electricity produced under the renewables power purchase agreement or from renewable electricity from a new storage asset that is located behind the same network connection point as the electrolyser or the installation generating renewable electricity, that has been charged during the same one-hour period in which the electricity under the renewables power purchase agreement has been produced. Following a notification to the Commission, Member States may apply the rules set out in this paragraph from 1 July 2027 for renewable fuel of non-biological origin produced in their territory.

The temporal correlation condition shall always be considered complied with if the renewable fuel of non-biological origin is produced during a one-hour period where the clearing price of electricity resulting from single day-ahead market coupling in the bidding zone, as referred to in Article 39(2), point (a) of Commission Regulation (EU) 2015/1222 ([^E0004]), is lower or equal to EUR 20 per MWh or lower than 0,36 times the price of an allowance to emit 1 tonne of carbon dioxide equivalent during the relevant period for the purpose of meeting the requirements of Directive 2003/87/EC of the European Parliament and of the Council ([^E0005]).

Article 7

Geographical correlation

1.

The geographical correlation condition referred to in Article 4(2) and (4) shall be considered complied with if at least one of the following criteria relating to the location of the electrolyser is fulfilled:

2.

Without prejudice to Articles 14 and 15 of Regulation (EU) 2019/943, Member States may introduce additional criteria concerning the location of electrolysers and the installation producing renewable electricity to the criteria set out in paragraph 1, in order to ensure compatibility of capacity additions with the national planning of the hydrogen and electricity grid. Any additional criteria shall have no negative impact on the functioning of the internal electricity market.

Article 8

Common rules

Fuel producers shall provide reliable information demonstrating that all requirements set out in Articles 3 to 7 are complied with, including for each hour as relevant:

Article 9

Certification of compliance

Regardless of whether the renewable fuel of non-biological origin is produced inside or outside the territory of the Union, fuel producers may make use of national schemes or international voluntary schemes recognised by the Commission pursuant to Article 30(4) of Directive (EU) 2018/2001 to demonstrate compliance with the criteria set out in Articles 3 to 7 of this Regulation, in line with Article 8, as relevant.

Where a fuel producer provides evidence or data obtained in accordance with a scheme that has been the subject of a decision in accordance with Article 30(4) of Directive (EU) 2018/2001, to the extent that such decision covers the demonstrating of compliance of the scheme with Article 27(3), fifth and sixth subparagraphs of that Directive, a Member State shall not require the suppliers of renewable fuels of non-biological origin to provide further evidence of compliance with the criteria set out in this Regulation.

Article 10

Reporting

By 1 July 2028, the Commission shall submit a report to the European Parliament and the Council assessing the impact of the requirements set out in this Regulation, including the impact of temporal correlation, on production costs, greenhouse gas emission savings and the energy system.

Article 11

Transitional phase

Article 5 , points (a) and (b) shall not apply until 1 January 2038 to installations producing renewable fuel of non-biological origin that come into operation before 1 January 2028. This exemption shall not apply to capacity added after 1 January 2028 for the production of renewable fuel of non-biological origin.

Article 12

Entry into force

This Regulation shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.

This Regulation shall be binding in its entirety and directly applicable in all Member States.

[^E0001]: Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (OJ L 158, 14.6.2019, p. 54).

[^E0002]: Directive (EU) 2019/944 of the European Parliament and of the Council of 5 June 2019 on common rules for the internal market for electricity and amending Directive 2012/27/EU (OJ L 158, 14.6.2019, p. 125).

[^E0004]: Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a guideline on capacity allocation and congestion management (OJ L 197, 25.7.2015, p. 24, ELI: http://data.europa.eu/eli/reg/2015/1222/oj).

[^E0005]: Directive 2003/87/EC of the European Parliament and of the Council of 13 October 2003 establishing a scheme for greenhouse gas emission allowance trading within the Community and amending Council Directive 96/61/EC (OJ L 275, 25.10.2003, p. 32, ELI: http://data.europa.eu/eli/dir/2003/87/oj).

Reading this document does not replace reading the official text published in the Official Journal of the European Union. We assume no responsibility for any inaccuracies arising from the conversion of the original to this format.

This text is published under EUR-Lex's own terms of reuse, not a Legalize or public-domain licence. EUR-Lex
Creative Commons Attribution 4.0 International (CC BY 4.0)
© European Union, https://eur-lex.europa.eu — Source: EUR-Lex (Publications Office of the European Union). Reused under the Creative Commons Attribution 4.0 International (CC BY 4.0) licence. Only EU legislation published in the printed Official Journal of the European Union is deemed authentic; consolidated texts are reproduced here for documentation purposes and have been reformatted to Markdown.