S.I. No. 453/2000 - Roads Regulations, 2000
This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.
1 amending act · 2008-03-07, S.I. No. 49/2008 - Roads (Schemes) (forms) Regulations 2008
The Minister for the Environment and Local Government in exercise of the powers conferred on him by sections 7 , 47 , 48 and 51 of the Roads Act, 1993 (No. 14 of 1993) hereby makes the following Regulations:
1.
(1) These Regulations may be cited as the Roads Regulations, 2000.
- (2) These Regulations and the Roads Regulations, 1994 shall be construed as one and may be collectively cited as the Roads Regulations, 1994 to 2000.
2.
(1) In these Regulations, “the Act” means the Roads Act, 1993 (No. 14 of 1993).
- (2) Except where otherwise specified any word which has a meaning assigned to it by the Act shall have the same meaning for the purposes of these Regulations.
3.
These Regulations shall come into operation on 1 January 2001.
4.
(1) The prescribed forms for the purposes of sections 47, 48 and 51 of the Act are set out in the Schedule as follows:
- (a) Form No. 1 shall be the prescribed form for the purposes of section 47 of the Act.
- (b) Form No. 2A shall be the prescribed form for the purposes of section 48 of the Act.
- (c) Form No. 2B shall be the prescribed form for the purposes of section 51 of the Act.
- (d) Form Nos. 3 and 4 shall be the prescribed forms for the purposes of section 48 of the Act.
- (e) Form No. 5 shall be the prescribed form for the purposes of section 51 of the Act.
- (2) The area of a prescribed notice required to be published in a newspaper for the purposes of section 48(a) and subsection(3)(a) of section 51 of the Act shall exceed 800 square centimetres.
Part 9 and Schedule D of the Roads Regulations, 1994 (S.I. 119 of 1994) are hereby revoked.
SCHEDULE:
FORM NO. 1.
PRESCRIBED FORM FOR A MOTORWAY, BUSWAY OR PROTECTED ROAD SCHEME UNDER SECTION 47 OF THE ROADS ACT, 1993 AS AMENDED BY THE ROADS (AMENDMENT) ACT, 1998 AND THE PLANNING AND DEVELOPMENT ACT, 2000 .
SECTION 10 OF THE LOCAL GOVERNMENT (IRELAND) ACT, 1898, AS AMENDED BY SECTION 11 OF THE LOCAL GOVERNMENT (NO. 2) ACT, 1960 AND SECTION 213 OF THE PLANNING AND DEVELOPMENT ACT, 2000 .
In exercise of the powers conferred on it by section 47 of the Roads Act, 1993 (as amended by section 4 of the Roads (Amendment) Act, 1998 ) ______ 1 (“the road authority”) has made the following scheme in respect of the proposed provision of a motorway/busway/protected road 3 :
Subject to the provisions of the Roads Acts, 1993 and of section 10 of the Local Government (No. 2) Act, 1960 (as inserted by section 86 of the Housing Act, 1966 and amended by the Roads Act, 1993 and the Planning and Development Act, 2000 ) as applied thereby, the road authority proposes:
- (a) to acquire compulsorily the land or substratum of land described in the First Schedule,
- (b) to acquire compulsorily the rights in relation to land described in the Second Schedule,
- (c) to extinguish, over the land referred to in sub-paragraphs (a) and (b) above or, in the case of public rights of way, over land adjacent to or associated with such land,—
- (i) the public rights of way described in Part I of the Third Schedule, by order made after the acquisition of the said land or rights,
- (ii) the private rights of way described in Part II of the Third Schedule,
- (d) to prohibit, close, stop up, remove, alter, divert or restrict all or any means of direct access to or from the proposed motorway/busway/protected road 3 in respect of the land described in the Fourth Schedule,
- (e) to prohibit, close, stop up, remove, alter, divert or restrict all or any means of direct access to or from the proposed protected road, in respect of land used for a specified purpose described in the Fifth Schedule. 4
- (f) to prohibit or restrict the use of the proposed protected road or a particular part thereof by the types of traffic and/or classes of vehicles described in the Sixth Schedule 4 .
(1) The permissions under Part IV of the Local Government (Planning and Development) Act, 1963 or Part III of the Planning and Development Act, 2000 for the development of land (hereinafter referred to as “planning permissions”) proposed to be revoked or modified and the extent of any such modifications are described in the Seventh Schedule.
- (2)
- (a) The planning permissions described in Part I of the Seventh Schedule stand suspended from the date of the making of the scheme until the Board approves the scheme or refuses to approve the scheme. If the scheme is approved by the Board those planning permissions will be revoked with effect from the date of such approval.
- (b) The planning permissions described in Part II of the Seventh Schedule stand modified to the extent specified in that Part of that Schedule from the date of the making of the scheme until the Board approves the scheme or refuses to approve the scheme. If the scheme is approved by the Board, with or without modifications, those planning permissions shall be modified to the extent specified in the scheme as approved.
The service areas proposed to be provided in relation to the proposed motorway/protected road 3 are described in the Eighth Schedule. (4)
5.
(1) The land or substratum of land described in the First, Second, Fourth, Fifth and Eighth Schedules and the rights of way described in the Third Schedule are individually numbered and shown on the map referred to in paragraph 1.
- (2)
- (a) The land described in Part 2 of the First Schedule and shown coloured grey on the map referred to in paragraph 1 consists of land—
- (i) necessary or incidental to the construction or maintenance of the motorway/busways/protected road, 3 4
not forming part of the motorway/busway/protected road 3 .
- (b) The land described in section II of Part I and section II of Part II of the First Schedule hereto and identified on the map referred to in paragraph 1 consists of houses which in the opinion of the road authority are unfit for human habitation and are not capable of being rendered fit for human habitation at reasonable expense.
6.
This scheme may be cited as the ______________2 .
First Schedule.
Land (or Substratum of Land) Proposed to be Compulsorily Acquired.
Part I. Land on which it is proposed to provide a motorway/busway/protected road 3 .
I.
Land or substratum of land (other than land consisting of houses unfit for human habitation and not capable of being rendered fit for human habitation at reasonable expense):
| Reference number of land on map | Area, description and situation of land | Owner or reputed owner | Lessee or reputed lessee | Occupier |
II.
Land consisting of houses unfit for human habitation and not capable of being rendered fit for-human habitation at reasonable expense:
| Reference number of land on map | Area, description and situation of land | Owner or reputed owner | Lessee or reputed lessee | Occupier |
Part II. Land not forming part of the motorway/busway/protected road 3 :
I.
Land (other than land consisting of a house or houses unfit for human habitation and not capable of being rendered fit for human habitation at reasonable expense):
| Reference number of land on map | Area, description and situation of land | Owner or reputed owner | Lessee or reputed lessee | Occupier |
II.
Land consisting of houses unfit for human habitation and not capable of being rendered fit for human habitation at reasonable expense:
| Reference number of land on map | Area, description and situation of land | Owner or reputed owner | Lessee or reputed lessee | Occupier |
Second Schedule.
Description of the Rights in Relation to Land Proposed to be Compulsorily Acquired.
Third Schedule.
Description of the Public and Private Rights of Way Proposed to be Extinguished.
Part I. Public rights of way proposed to be extinguished.
Part II. Private rights of way proposed to be extinguished.
Fourth Schedule.
Land in respect of which it is Proposed to Prohibit, Close, Stop Up, Remove, Alter, Divert or Restrict All or Any Means of Direct Access to or from the Proposed Motorway/Busway/Protected Road: 3
| Reference number of land on map | Area, description and situation of land | Owner or reputed owner | Lessee or reputed lessee | Occupier | Proposed course of action |
Fifth Schedule.
Land Used for a Specified Purpose in respect of which it is Proposed to Prohibit, Close, Stop Up, Remove, Alter, Divert or Restrict All or Any Means of Direct Access to or from the Proposed Protected Road:-
| Reference number of land on map | Area, description and situation of land | Owner or reputed owner | Lessee or reputed lessee | Occupier | Purpose of which land is used | Proposed course of action |
Sixth Schedule.
Part I. Description of the Types of Traffic and/or Classes of Vehicles Proposed to be Prohibited from Using the Proposed Protected Road or a Particular Part thereof.
Part II. Description of the Types of Traffic and/or Classes of Vehicles Proposed to be Restricted in Their Use of the Proposed Protected Road or a Particular Part Thereof and the Nature and Extent of such Restrictions.
Seventh Schedule.
Part I. Planning Permissions which have been Suspended:
| Reference number in planning register. | Nature of permission | Date granted | Reference number of land on scheme map. |
Part II. Planning Permissions which have been Modified:
| Reference number in planning register. | Nature of permission | Date granted. | Extent of modifications. | Reference of land on scheme map. |
Eighth Schedule.
Description of Service Areas Proposed to be Provided in Relation to the Proposed Motorway/Protected Road: 5 :
The official seal of the road authority was affixed hereto this day of ___ 20 ______ in the presence of:
__________ 5
NOTES TO FORM NO. 1
All eight Schedules should always be included in a scheme. Where there are no entries in a particular schedule insert “NONE”, “NOT APPLICABLE” or a cognate word as appropriate.
FORM NO. 2A.
PRESCRIBED NOTICE TO BE PUBLISHED IN ACCORDANCE WITH SECTION 48 OF THE ACT OF THE MAKING OF A SCHEME FOR THE PROVISION OF A MOTORWAY/BUSWAY/PROTECTED ROAD, AS AMENDED BY THE PLANNING AND DEVELOPMENT ACT, 2000 .
___ 8 has made the ___ 9 under section 47 of the Roads Act, 1993 which it proposes to submit to An Bord Pleanála (“the Board”) for approval. If the Scheme is approved by the Board, ___________ 10 will then be authorised to provide a motorway/busway/protected road 11
________________ 12 ,
as illustrate below:
Approval of the scheme will authorise _______ 14 to compulsorily acquire certain land (or substratum of land) and certain rights in relation to land, to extinguish certain public and private rights of way, to prohibit or restrict direct access to the motorway/busway/protected road15 from adjoining land and to prohibit or restrict the use of the protected road or a particular part of the road by certain types of traffic and/or classes of vehicles16 . Approval of the scheme will also have the effect of revoking or modifying certain planning permissions which have already been suspended or modified by the scheme17 .
A copy of the scheme and of the map referred to in it may be inspected at ______ between the hours of ___ and __ on working days between ____ 20 and ____ 20 __ 7 .
Written objections in relation to the scheme may be made to An Board Pleanála, Floor 3, Blocks 6 & 7, Irish Life Centre, Lower Abbey Street, Dublin 1, before
____ 20 _____ 8 .
The Board may approve the scheme with or without modifications or it may refuse to approve it. However, before making its decision, the Board must arrange for the holding of an oral hearing into all matters relating to the scheme, consider any written objections to the scheme which have been made to it and not withdrawn and consider the report and any recommendations of the person holding the oral hearing. Public notice of the oral hearing will be given at a later date.
Land owners and occupiers referred to in the scheme and persons affected by the proposed revocation or modification of planning permissions specified in the scheme will receive individual written notice.
Further information may be obtained from _________ 9 .
| County Secretary/Town Clerk 21 | |
| Date |
NOTES TO FORM NO. 2A.
FORM NO. 2B.
PRESCRIBED NOTICE TO BE PUBLISHED IN ACCORDANCE WITH SECTION 51 OF THE ACT (AS AMENDED BY THE PLANNING AND DEVELOPMENT ACT, 2000 ) IN RELATION TO AN APPLICATION FOR THE APPROVAL OF A PROPOSED ROAD DEVELOPMENT AND THE PREPARATION OF AN ENVIRONMENTAL IMPACT STATEMENT.
_________ 23 has prepared an environmental impact statement in respect of __________
______________24 , as illustrated below, and has applied to An Bord Pleanála for approval of the proposed road development under section 51 of the Roads Act, 1993 (as amended by the Planning and Development Act, 2000 ).
A copy of the environmental impact statement may be inspected at between the hours of ___ and ___ on working days between ______ 20 and ____ 20 _____ 25 .
A copy of the statement may be purchased for a fee of £ _ 26 . A Copy of the non-technical summary of the statement may also be purchased for a fee of £ _____ 27 .
Written submissions in relation to the likely effects on the environment of the proposed road development may be made to An Bord Pleanála, Floor 3, Blocks 6 & 7, Irish Life Centre, Lower Abbey Street, Dublin 1 before ____20 __ 28 .
A motorway/busway/protected road scheme 29 will be required/has been made(8) in respect of the proposed road development and an oral hearing will be held in relation to that scheme. 30 .
A compulsory purchase order will be required/has been made 31 in respect of the proposed road development and where written objections are made to the Board, an oral hearing will be held. 32
The Board may hold an oral hearing in relation to the likely effects on the environment of the proposal. 33 .
Evidence in relation to the likely effects on the environment of the proposal may be given at the oral hearing. 34 .
A bridge order will be required/has been made 35 in respect of the proposed road development and where written objections are made to the Minister for the Environment and Local Government, a local inquiry will be held. 36
Before making its decision on the application for approval, the Board must consider the environmental impact statement, any written submissions made to it and not withdrawn and, where an oral hearing is held, the report and any recommendations of the inspector holding the oral hearing where evidence was given in relation to the likely effects on the environment of the proposal. Public notice of any oral hearing will be given at a later date.
Further information may be obtained from _________ 9 .
| County Secretary/Town Clerk 37 | |
| Date |
NOTES TO FORM NO. 2B.
FORM NO 3.
PRESCRIBED FORM OF NOTICE OF THE MAKING OF A SCHEME FOR THE PROVISION OF A MOTORWAY/BUSWAY/PROTECTED ROAD TO BE SERVED ON OWNERS AND OCCUPIERS OF LAND IN ACCORDANCE WITH SECTION 48 OF THE ACT, AS AMENDED BY THE PLANNING AND DEVELOPMENT ACT, 2000 .
To ___ 39
of ______
___________ 1 has made the ________ 40 under section 47 of the Roads Act, 1993 which it proposes to submit to An Bord Pleanála (“the Board”) for approval. If the scheme is approved by the Board, ___ 1 will then be authorised to provide a motorway/busway/protected road
41 ______________
_____ 42 .
Approval of the scheme will authorise ____ 1 to compulsorily acquire certain land or substratum of land and certain rights in relation to land, to extinguish certain public and private rights of way, to prohibit or restrict direct access to the motorway/busway/protected road 43 from adjoining land and to prohibit or restrict the use of the protected road to or a particular part of the road by certain types of traffic and/or classes of vehicles 44 . Approval of the scheme will also have the effect of revoking or modifying certain planning permissions, which have been suspended, or modified, by the scheme. 45 .
The extract from the scheme and accompanying map appeared to this notice describe the land/rights in relation to land/rights of way/means of access 46 in which you have an interest and which are affected by the scheme.
A copy of the scheme and of the map referred to in it may be inspected at _____ between the hours of ___ and ___ on working days between ___ 20 _ and ____ 20 ____ 47 .
Written objections in relation to the scheme may be made to An Bord Pleanála, Floor 3, Blocks 6 & 7, Irish Life Centre, Lower Abbey Street, Dublin 1 before ____ 20 _ 48 .
An Bord Pleanála may approve the scheme with or without modifications or it may refuse to approve it. However, before making its decision the Board must arrange for the holding of an oral hearing into all matters relating to the scheme, consider any written objections to the scheme which have been made to it and not withdrawn and consider the report and any recommendations of the person holding the oral hearing. Public notice of the oral hearing will be given a later date.
7.
Where the scheme is approved by the Board, with or without modifications, _____ 1 will be authorised to compulsorily acquire the land, substratum of land or rights to land as specified in the scheme as approved. Any land or rights in relation to land being acquired will be subject to assessment with a view to compensating the owner/occupier of that land.
8.
Where the closing, stopping up, removing, altering, diverting or restricting of an existing means of direct access results in the owner of any land being deprived of the only means of access from that land to any public road, or to that land from a public road, ____ 1 cannot close, stop up etc. such access until an alternative means of access to or from a public road has been provided. Where a person is deprived of reasonable access (temporarily during construction or permanently) to or from his/her property or from one part of his/her property to another, the Board may direct that suitable alternative access be provided.
9.
Whenever a scheme is approved by the Board, with or without modifications and direct access from any land to a public road, or to that land from a public road, is prohibited closed, stopped up, removed, altered, diverted or restricted, any person who has suffered damage in consequence thereof by the depreciation of any interest in the land to which he is entitled or by being disturbed in his enjoyment of that land, will be entitled to obtain compensation from ___ 1 in respect of that damage. However in assessing compensation regard will be had to any new means of access provided by __ 1 and where appropriate to any existing means of access (whether restricted or otherwise) which remains.
10.
If the scheme is approved by the Board, or approved with modifications, a claim for compensation in relation to any direct access affected by the scheme must be made to _______ 1 not later than six months after the date of such approval.
11.
12.
Further information may be obtained from ____________ 53 .
| County Secretary/Town Clerk 54 | |
| Date |
NOTES TO FORM NO. 3.
The service of this notice on persons affected by the scheme shall be made in the manner set out in section 79 of the Roads Act, 1993 .
FORM NO. 4.
PRESCRIBED FORM OF NOTICE OF SUSPENSION OR MODIFICATIONS OF A PLANNING PERMISSION IN ACCORDANCE WITH SECTION 48 OF THE ACT, AS AMENDED BY THE PLANNING AND DEVELOPMENT ACT, 2000 .
SUSPENSION/MODIFICATION OF PLANNING PERMISSIONS.
To ___ 56
of ______
The planning permissions affected by this notice are as follows:
Reference No. of permission in planning register: __________
Dated: ___ 57 Nature of the permission: ____ 58
______________ 62 .
The Board may approve the scheme with or without modifications or it may refuse to approve it. However, before making its decision, it must arrange for the holding of an oral hearing into all matters relating to the scheme, consider any written objections to the scheme which have been made to it and not withdrawn and consider the report and any recommendations of the person holding the oral hearing. Public notice of the oral hearing will be given at a later date.
You are hereby notified under section 48 of the Roads Act 1993 , that—
- (a) 63 the above-mentioned planning permission has been suspended from ______ 64 the date of the making of the scheme until the Board approves the scheme or refuses to approve it. If the scheme is approved by the Board, the planning permission will be revoked.
- (b) 65 the above-mentioned planning permission has been modified to the extent shown below from ______ 66 the date of the making of the scheme until the Board approves the scheme or refuses to approve it:
If the scheme as made by the road authority is approved, or approved with modifications, the planning permission will be modified to the extent specified in the scheme as approved.
Where the Board refuses to approve the scheme, or approves it with modifications the effect of which is that the above mentioned planning permission will not be revoked or modified or will be modified in a form other than that specified in the scheme as made by ________, 1 , the duration of the planning permission will be extended by a period equivalent to the period beginning on the date this scheme was made and ending on the date on which the Board makes its decision.
A claim for compensation may be made to _______ 1 in relation to a planning permission which is revoked or modified under a scheme approved by the Board as if the revocation or modification has been made by notice under section 30 of the Local Government (Planning and Development) Act, 1963 / Section 44 of the Planning and Development Act, 2000 67 .
Any claim for compensation must be made not later than six months after the date on which the scheme to which it relates was approved by the Board, and must be made in the manner prescribed by regulations under the Planning and Development Act, 2000 . Further information in relation to compensation for planning permissions which have been revoked or modified under a scheme approved by the Board may be obtained from- 68 .
A copy of the scheme and of the map referred to in it may be inspected at ______ between the hours of __ and ___ on working days between __ 20 _ and __ 20 _ 10 .
Written objections in relation to the scheme may be made to An Bord Pleanála, Floor 3, Blocks 6 & 7, Irish Life Centre, Lower Abbey Street, Dublin 1 before _______ 20 __ 11 .
Further information in relation to the scheme may be obtained from __________ 12 .
| County Secretary/Town Clerk 72 | |
| Date |
NOTES TO FORM NO. 4.
The service of this notice on persons affected by the proposed revocation or modification of a planning permission shall be made in the manner set out in section 79 of the Roads Act, 1993 .
FORM NO. 5.
PRESCRIBED FORM OF NOTICE TO PRESCRIBED BODIES/PERSONS IN ACCORDANCE WITH SECTION 51 OF THE ACT, AS AMENDED BY THE PLANNING AND DEVELOPMENT ACT, 2000 .
To ___ 74
of ______
being a prescribed body for the purposes of section 51 of the Roads Act, 1993 .
________ 75 has prepared an environmental impact statement under section 50 of the Roads Act, 1993 in respect of ________
____________ 76 and has applied to An Bord Pleanála (“the Board”) for approval of the proposed road development under section 51 of that Act, as amended.
A copy of the Environmental Impact Statement is enclosed.
Written submissions in relation to the likely effects on the environment of the proposed road development may be made to An Bord Pleanála, Floor 3, Blocks 6 & 7, Irish Life Centre, Lower Abbey Street, Dublin 1 before _____ 20 ___ 77 .
A compulsory purchase order will be required/has been made 80 in respect of the proposed road development and where written objections are made to the Board, an oral hearing will be held. 81
The Board may hold an oral hearing in relation to the likely effects on the environment of the proposal.82
Evidence in relation to the likely effects on the environment of the proposal may be given at the oral hearing.83
A bridge order will be required/has been made 84 in respect of the proposed road development and where written objections are made to the Minister for the Environment and Local Government, a local inquiry will be held. 85
Before making its decision on the application for approval, the Board must consider the environmental impact statement, any written submissions made to it and not withdrawn and, where an oral hearing is held, the report and any recommendations of the inspector holding the oral hearing where evidence was given in relation to the likely effects on the environment of the proposal. Public notice of any oral hearing will be given at a later date.
Further information may be obtained from _____________ 86 .
| County Secretary/Town Clerk 87 | |
| Date |
NOTES TO FORM NO. 5.
The service of this notice on persons affected by the scheme shall be made in the manner set out in section 79 of the Roads Act, 1993 .
| GIVEN under the Official Seal of the Minister for the Environment and Local Government, this 20th day of December, 2000. | |
| NOEL DEMPSEY, T.D., | |
| Minister for the Environment and Local Government. |
EXPLANATORY NOTE.
(This note is not part of the Instrument and does not purport to be a legal interpretation of it.)
These Regulations prescribe the forms to be used by local authorities in connection with the preparation and submission to An Bord Pleanála of schemes for the provision of motorways, busways and protected roads, and to notify the public and persons affected by such schemes and the forms to be used in relation to the environmental impact assessment of roads projects and revoke Part 9 and Schedule D of the Roads Regulations, 1993 in their entirely. The forms are prescribed to take account of the transfer of the Minister for the Environment and Local Government's functions under sections 49 , 50 and 51 of the Roads Act, 1993 , to An Bord Pleanála in accordance with section 215 of the Planning and Development Act, 2000 .
Footnotes
Insert the name of the road authority.
Insert the title of the scheme such as “Barrytown Motorway Scheme, 1994”.
Delete as appropriate.
Delete if not applicable.
Insert the title of the scheme.
The name and description of the persons in whose presence the seal is affixed should be inserted e.g. “Andrew Keane, Nominated Member”, “Margaret Burke, County Manager” etc.
Insert the title of the scheme such “Barrytown Motorway Scheme, 1993”. The name and logo of the road authority should appear above the title and where the road authority is acting for another road authority, under an agreement under section 59 of the Local Government Act, 1955 or otherwise, the name and logo of that road authority should also appear above the title and an appropriate statement should be included in the notice.
Insert the name of the road authority.
Insert the title of the scheme.
Insert the name of the road authority.
Delete as appropriate.
Insert a brief non-technical description of the proposed motorway/busway/protected road and the principal ancillary works.
Insert a sketch map which should cover at least 10% of the surface area of the notice and include an outline illustration of the proposed motorway/busway/protected road. It should show the terminal points of the project and key intermediate points, should identify any significant centres of population (all census towns) and important physical or other features and should include existing roads and significant proposed ancillary works (such as new access road). An approximate scale should be shown.
Insert the name of the road authority.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
The minimum period for inspection is one month.
The minimum period for making objections is two weeks from the end of the inspection period.
Insert the name, address, telephone and fax numbers and e-mail address of the road authority and, where possible, the name, telephone extension and e-mail address of an appropriate official.
Delete as appropriate.
Insert the title, for example “Environmental Impact Assessment of Proposed Barrytown Motorway”. The name and logo of the road authority should appear above the title and where the road authority is acting for another road authority, under an agreement under section 59 of the Local Government Act, 1955 or otherwise, the name and logo of that road authority should also appear above the title and an appropriate statement should be included in the notice.
Insert the name of the road authority.
Insert a brief non-technical description of the proposed road development.
The minimum period for inspection is one month.
The specified fee must not exceed the reasonable cost of making a copy.
The specified fee must not exceed the reasonable cost of making a copy.
The minimum period for making submissions is two weeks from the end of the inspection period.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Insert the title of the scheme.
Insert the name and address (if known) of the person on whom the notice is being served.
Insert the title of the scheme.
Delete as appropriate.
Insert a brief non-technical description of the proposed motorway/busway/protected road and the principal ancillary works.
Delete as appropriate.
Delete as appropriate.
Insert a brief non-technical description of the proposed motorway/busway/protected road and the principal ancillary works.
Delete as appropriate.
The minimum period for inspection is one month.
The minimum period for making written objections is two weeks from the end of the inspection period.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Insert the name, address, telephone and fax numbers and e-mail address of the road authority and, where possible, the name, telephone extension and e-mail address of an appropriate official.
Delete as appropriate.
Insert the title of the scheme.
Insert the name and address (if known) of the person(s) on whom this notice is being served.
Insert reference number and date of planning permission as recorded in register of planning permissions kept in accordance with section 8 of the Local Government (Planning and Development) Act, 1963 or section 7 of the Planning and Development Act, 2000.
Briefly outline what is authorised by the permission.
Insert the name of the road authority
Insert the title of the scheme.
Delete as appropriate.
Insert a brief non-technical description of the proposed motorway/busway/protected road and the principal ancillary works.
Delete as appropriate.
Insert the date on which the scheme was made.
Delete as appropriate.
Insert the date on which the scheme was made.
Delete as appropriate.
Insert the name, address, telephone and fax numbers of the road authority and, where possible, the name and telephone extension of an appropriate official dealing with the suspension or modification of planning permissions.
The minimum period of inspection is one month.
The minimum period for making objection is two weeks from the end of the inspection period.
Insert the name, address, telephone and fax numbers of the road authority and, where possible, the name and telephone extension of an appropriate official dealing with the scheme.
Delete as appropriate.
Insert the title, for example “Environmental Impact Assessment of Proposed Barrytown Motorway”. The name of the road authority should appear above the title and where the road authority is acting for another road authority, under an agreement under section 59 of the Local Government Act, 1955 or otherwise, the name of that road authority should also appear above the title and an appropriate statement should be included in the notice.
Insert the name and address of the body or person specified by or under section 51(3)(b) of the Road Act, 1993.
Insert the name of the road authority.
Insert a brief non-technical description of the proposed road development.
The minimum period for making of submissions is two weeks from the end of the inspection period specified in the public notice.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Delete as appropriate.
Insert the name, address, telephone, fax numbers and e-mail address of the road authority and, where possible, the name, telephone extension and e-mail address of an appropriate official.
Delete as appropriate.
This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.
This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence.
Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.