This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.

1 amending act · 2006-02-17, S.I. No. 78/2006 - Electricity Regulation Act 1999 (Market Arrangements for Electricity) …

Reform history JSON API

ARRANGEMENT OF REGULATIONS

1. Citation.
2. Interpretation.
3. New System of Trading in Electricity.
4. Financial Instruments.
5. Market Arrangements for Electricity Rules.
6. Commission's Directions to the System and Market Operator.
7. Commission's Directions to the Board or EirGrid plc.
8. Revocation.
9. Commencement.

Electricity Regulation Act 1999 (Market Arrangements for Electricity) Regulations 2003

The Commission for Energy Regulation, in exercise of the powers conferred on it under Section 9 (1)(d) of the Electricity Regulation Act 1999 (No. 23 of 1999) (hereinafter referred to as “the 1999 Act”), acting in accordance with the policy direction issued to it by the Minister on 26 July 1999 under Section 9(1)(a) of the 1999 Act and having taken into account the matters raised in the public consultation process carried out by the Commission under Section 9(1)(b) of the 1999 Act, hereby makes the following Regulations for the purpose of establishing a new system of trading in electricity.

Citation.

1.

1.

These Regulations may be cited as the Electricity Regulation Act 1999 (Market Arrangements for Electricity) Regulations 2003.

Interpretation.

2.

2.

(1) A word or expression that is used in these Regulations and is also used in the Act has, unless the contrary intention appears, the same meaning in these Regulations as in the Act.

“Commission” means the Commission for Energy Regulation established under the Electricity Regulation Act 1999 as amended by the Gas (Interim) (Regulation) Act 2002 ;

“Counterparties” means suppliers and generators;

“Financial Transmission Right (FTR)” means a financial tradable instrument that allows the holder to hedge the difference between LMPs at different nodes or between LMPs and the uniform wholesale spot market price as set out in Regulation 3(14);

“Gate Closure” means the point in time prior to physical delivery when offers made by a generator with respect to a generating station or individual generating unit or by a supplier become final and changes to offers may no longer be accepted except in exceptional circumstances to be defined by the Commission under the Market Arrangements for Electricity Rules to be developed under Regulation 5;

“Generator” means a holder of a licence to generate electricity granted under Section 14 of the 1999 Act and the Board acting in its capacity as ESB Power Generation;

“Individual Generating Unit” means such a unit of a generating station;

“Locational Marginal Price (‘LMP’)” means the price per mega-watt hour (MWh) of electricity at a given node;

“Market Operation Date” means the date on which the new system of trading in electricity established by Regulation 3 comes into operation, which date shall be determined by the Commission following public consultation, but shall, in any event, be no later than 19 February 2006. That date shall be published by the Commission by a notice in a daily newspaper published and circulating in the State at least one month beforehand;

“Minister” means the Minister for Communications, Marine and Natural Resources;

“Node” means a location on the transmission and/or the distribution system where electricity is injected or withdrawn for which an LMP is calculated;

“Offer” means an offer by a generator with respect to a generating station or individual generating unit or by a supplier to the System and Market Operator to sell, to purchase or not to purchase a stated quantity of electricity at a stated price in one or more trading periods under the Market Arrangements for Electricity Rules to be developed under Regulation 5;

“Spot Market” means the mandatory centralised pool market in which the SMO purchases and sells electricity offered by generators and suppliers;

“Supplier” means a holder of a licence to supply electricity granted under Section 14 of the 1999 Act and the Board acting in its capacity as Public Electricity Supplier;

“System and Market Operator (‘SMO’)” means the National Grid Business Unit of the Board until such date as the Commission determines for the purposes of these Regulations that EirGrid plc is operating as Transmission System Operator and thereafter EirGrid plc;

“Trading and Settlement Code” means the code of that name designated under the Electricity Regulation Act 1999 (Trading Arrangements in Electricity) Regulations 2000 ( S.I. No. 49 of 2000 );

“Value of Lost Load (‘VoLL’)” means the price consumers are deemed to be willing to pay to prevent the failure to supply a mega-watt hour (MWh) of electricity as determined from time to time by the Commission using a methodology which shall be made publicly available.

New System of Trading in Electricity

3.

3.

(1) The system of trading in electricity and settling electricity imbalances established by the Electricity Regulation Act 1999 (Trading Arrangements in Electricity) Regulations 2000 ( S.I. No. 49 of 2000 ) shall be replaced with effect from the Market Operation Date by the new system of trading in electricity established by this Regulation.

New System of Trading in Electricity

4.

4.

(1) The Commission shall establish a system for the making available by the SMO of FTRs to generators and suppliers, and shall determine the form and content of such FTRs and the procedures for amending such instruments.

Market Arrangements for Electricity Rules.

5.

5.

(1) Detailed rules and procedures necessary to give effect to the new system of trading in electricity established by Regulation 3 shall be developed by the Commission. These detailed rules shall be known as the Market Arrangements for Electricity Rules (“The MAE Rules”) and shall take effect as and from the Market Operation Date.

Commission's Directions to the SMO.

6.

6.

(1) Subject to the approval of the Commission, the SMO shall develop, operate and maintain the spot market in accordance with the MAE Rules.

Commission's Directions to the Board or EirGrid Plc.

7.

7.

(1) The Commission may, in advance of the Market Operation Date, issue directions to ESB National Grid Business Unit or, after the date as the Commission determines for the purposes of these Regulations that EirGrid plc is operating as Transmission System Operator, to EirGrid plc in its capacity as prospective SMO with a view to ensuring that the necessary arrangements are put in place to facilitate the taking effect of the new system of trading established under Regulation 3 from the Market Operation Date and ESB National Grid Business Unit or EirGrid plc as the case may be shall comply with such directions.

Revocation.

8.

8.

(1) The Electricity Regulation Act 1999 (Trading Arrangements in Electricity) Regulations 2000 ( S.I. No. 49 of 2000 ) are revoked with effect from the Market Operation Date.

Commencement.

9.

9.

(1) These Regulations shall come into force on 21 July 2003.

Sealed with the common seal of the Commission for Energy Regulation on 16 July 2003. Sealed with the common seal of the Commission for Energy Regulation on 16 July 2003.
Tom Reeves Member of Commission
Cathy Mannion Member of Staff of Commission
The Minister for Communications, Marine and Natural Resources consents to the making of the foregoing Regulations The Minister for Communications, Marine and Natural Resources consents to the making of the foregoing Regulations
Given under the Official Seal of the Minister for Communications, Marine and Natural Resources 17 July 2003 Given under the Official Seal of the Minister for Communications, Marine and Natural Resources 17 July 2003
Dermot Ahern Minister for Communications, Marine and Natural Resources Dermot Ahern Minister for Communications, Marine and Natural Resources

EXPLANATORY NOTE.

(This note is not part of the Instrument and does not purport to be a legal interpretation.)

These regulations establish a new system of trading in electricity replacing the existing system of trading in electricity. The new system of trading will be a mandatory centralised pool. All generators and suppliers unless exempted will be required to buy and sell electricity through the pool. The regulations make further provision for supplemental rules to be developed by the Commission to give effect to the new system of trading in electricity.

This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.

This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence. Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.