S.I. No. 384 of 2008

ELECTRICITY REGULATION ACT 1999 (SECTION 14(1A)) ORDER 2008

Notice of the making of this Statutory Instrument was published in

“Iris Oifigiúil” of 30th September, 2008.

The Commission for Energy Regulation in exercise of the powers conferred on it by Section 14(1A) of the Electricity Regulation Act 1999 (as inserted by Regulation 16(b) of the European Communities (Internal Market in Electricity) Regulations 2005) ( S.I. No. 60 of 2005 ) hereby orders as follows:

Citation.

1.

1.

This Order may be cited as the Electricity Regulation Act 1999 (Section 14(1A)) Order 2008.

Commencement.

2.

2.

This Order shall come into operation on 25 September 2008.

Interpretation.

3.

3.

(1) In this Order, unless the context otherwise requires—

“Act” means the Electricity Regulation Act 1999 (No. 23 of 1999), as amended;

“generator” means a person licensed to generate electricity under Section 14(1)(a) of the Act;

“generator site” means the site owned (or occupied pursuant to a lease, licence or other agreement) by the generator which contains the connection point;

“generating unit” means any plant or apparatus for the production of electricity; and

“installed capacity” means the normal full load kW capacity of any apparatus which produces electricity, as stated on their nameplates.

Purpose.

4.

4.

(1) Pursuant to section 14(1A) of the Act, the Commission may by order provide for the licensing of a person to generate electricity by means of a class or classes of generating station.

are classes of generating station to which this Order applies.

Approval.

5.

5.

(1) (a) A person with a class of generating station referred to in Article 4(2)(a) shall apply to the Commission for approval to be duly licensed to generate electricity from such pursuant to this Order in accordance with the procedures determined and published by the Commission.

The decision shall be reasonable having regard to all the circumstances.

Amendment or Revocation of Order

6.

6.

Pursuant to section 14(1B) of the Act, the Commission may by order amend or revoke this Order.

Terms and Conditions

7.

7.

A person duly authorised to generate electricity pursuant to this Order shall be required to comply with the terms and conditions stated in the Schedule to this Order.

SCHEDULE

The terms and conditions referred to in Article 7 are as follows:

Condition 1: General and Interpretation

“licensee” a person duly authorised to generate electricity pursuant to this Order;

“Metering Code” means the metering code prepared by the Board and approved by the Commission, as from time to time revised, amended, supplemented or replaced with the approval of, or at the instance, of the Commission;

“modification” includes addition, omission, amendment and substitution, and cognate expressions shall be construed accordingly;

“representation” includes any objection or any other proposal made in writing;

“Single Electricity Market Trading and Settlement Code” means the Trading and Settlement Code provided for in Regulation 4 of the Single Market Regulations, as from time to time revised, amended, supplemented or replaced;

“Single Market Regulations” means the Electricity Regulation Act 1999 (Single Electricity Market) Regulations 2007 ( S.I. No. 406 of 2007 ); and

“system” shall, except where it appears in the context of the “transmission system” or “distribution system”, mean the electric lines owned or operated by the licensee through which electricity is conveyed from generation units to the point of connection with the transmission system or the distribution system, as the case may be, and any other electric lines which the Commission may specify as forming part of the licensees system and includes any electric plant owned or used by the licensee in connection therewith.

Condition 2: Compliance with Grid Code, Metering Code and, where applicable, Distribution Code

Condition 3: System planning

“relevant standard” means the standard laid down in the Grid Code and the Distribution Code, if applicable.

Condition 4: Security arrangements

Where requested by the Commission, the licensee shall co-operate with the Commission in strategic contingency planning in respect of fuel stocks and procedures under the Grid Code during periods when the Commission deems necessary for reasons of security of supply.

Condition 5: Connection to and use of a person’s system — requirement to offer terms

i. to accept into the licensee’s system at such entry point and in such quantities as may be specified in the application, electricity to be provided by or for that person; and

ii. to deliver electricity equal in quantity to that accepted into the licensee’s system (less only any losses incurred in the course of transporting such electricity through the licensee’s system) from such exit points on the licensee’s system and in such quantities as may be specified in the application to such person as the person making the application may specify.

i. the carrying out of works (if any) required for the construction or modification of the entry point to connect the system of the licensee to the transmission system or to the distribution system or in connection with the construction or modification of any exit points for the delivery of electricity as specified in the application, and for the obtaining of any consents necessary for such purpose;

ii. the carrying out of works (if any) for the provision of electric plant or for the extension or reinforcement of the system of the licensee which are required to be undertaken for the provision of connection to, or the making of a modification to a connection to the licensee’s system or for provision of use of the licensee’s system to the person making the application and for the obtaining of any consents necessary for such purposes;

iii. the installation of appropriate meters or other apparatus (if any) required to enable the licensee to measure electricity being accepted into the licensee’s system at the specified entry point and leaving such system at the specified exit points;

iv. the installation of such switchgear or other apparatus (if any) as may be required for interrupting the use of the licensee’s system should there be a failure by or for a person to provide electricity at its entry point on the licensee’s system for delivery to any person specified by the person making the application from the exit points on the system of the licensee;

v. the date by which any works required so as to permit access to the system of the licensee (including for this purpose any works for its extension or reinforcement) shall be completed and so that, unless otherwise agreed by the person making the application, a failure to complete such works by such date shall be a material breach of the agreement entitling the person to rescind such agreement;

vi. the charges to be paid by the person making the application for the provision of electric plant, for connections to or modification of connections to, or the extension or reinforcement of, the system of the licensee, for the installation of meters, switchgear or other apparatus and for their maintenance, for disconnection from the system of the licensee and the removal of electric plant, electric lines and meters following disconnection, and for use of the licensee’s system of the licensee which shall, unless manifestly inappropriate, be set in conformity with paragraph 4; and

i. the appropriate proportion (taking account of the factors referred to in paragraph 5) of the costs directly or indirectly incurred by the licensee; and

ii. a reasonable rate of return on the capital represented by such costs; and

i. the Grid Code; or

ii. the Distribution Code; or

iii. the Act or any regulations made under the Act; or

iv. any other enactment relating to safety or standards applicable to the system of the licensee; or

Condition 6: Connection to and use of the system — functions of the Commission

Condition 7: Provision of information to the Commission

“information” shall include any books, documents, records, accounts, estimates, returns or reports (whether or not prepared specifically at the request of the Commission) of any description and in any format specified by the Commission.

Condition 8: Payment of levy

“Levy Order” means an Order made by the Commission under paragraph 16 of the Schedule to the Act.

Condition 9: Trading and Settlement Code

“Intermediary” has the meaning given to it in the Single Electricity Market Trading and Settlement Code.

Condition 10: Cost-Reflective Bidding in the Single Electricity Market

minus

the result of which calculation may be either a negative or a positive number.

“Bidding Code of Practice” means the document of that title published by the Commission in accordance with paragraph 5, as it may be amended from time to time;

“Commercial Offer Data” has the meaning given to it in the Single Electricity Market Trading and Settlement Code;

“Generation Licence” means a licence granted under section 14(1)(a) of the Act;

“Opportunity Cost” shall have the meaning set out in, and the value calculated in accordance with, the terms of the Bidding Code of Practice;

“Schedule Production Cost” has the meaning given to it in the Single Electricity Market Trading and Settlement Code;

“Short Run Marginal Cost” means certain costs attributable to the ownership, operation and maintenance of a generation unit, as calculated in accordance with paragraph 3 of this condition;

“Single Market Operation Business” has the meaning given to it in the licence granted pursuant to section 14(1)(j) of the Act; and

“Trading Day” has the meaning given to it in the Single Electricity Market Trading and Settlement Code.

Condition 11: Assignment of approval and transfer of Generation Business

Condition 12: Change in control

The licensee shall notify the Commission of a change in control of the licensee as soon as is practicable after such a change in control occurs.

Condition 13: Right of Commission to revoke approval

i. is unable to pay its debts (within the meaning of section 214 of the Companies Act 1963 ) or if it enters into any scheme of arrangement (other than for the purpose of reconstruction or amalgamation upon terms and within such period as may previously have been approved in writing by the Commission); or

ii. has a receiver or an examiner within the meaning of section 1 of the Companies (Amendment) Act 1990 , of the whole or any material part of its assets or undertaking appointed; or

iii. passes any resolution for winding up other than a resolution previously approved in writing by the Commission; or

iv. becomes subject to an order for winding up by a court of competent jurisdiction; or

v. is dissolved, declared bankrupt or being of unsound mind.

Sealed with the common seal of the Commission for Energy Regulation on.

GIVEN under my Offical Seal,

25 September 2008

MICHAEL G. TUTTY

Member of Commission

GIVEN under my Offical Seal,

25 September 2008

PAUL McGOWAN

Member of Staff of Commission

EXPLANATORY NOTE

(This note is not part of the Instrument and does not purport to be a legal interpretation.)

The purpose of this Order is to provide for the licensing of persons to generate electricity from generating stations located within a Generator Site with an installed capacity not exceeding 10 MW made pursuant to Order as facilitated under Section 14(1A) of the Act.

This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.

This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence. Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.