S.I. No. 16/2015 - European Communities (Internal Market in Natural Gas and Electricity) (Amendment) Regulations 2015

Type Statutory Instrument
Publication 2015-01-23
Last updated 2024-05-01
State In force superseded text
Text As published
articles 29

This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.

2 amending acts · 2024-05-01, GAS (AMENDMENT) AND MISCELLANEOUS PROVISIONS ACT 2024

Reform history JSON API

CONTENTS

Regulation

PART 1 Preliminary and general

1.

1.

Citation and commencement

2.

2.

Interpretation

PART 2 Unbundling of gas transmission systems and gas transmission system operators

3.

3.

Scope of Part 2

4.

4.

Prohibition of certain transfers and sharing services

5.

5.

Interpretation — Part 2

PART 3 Certification and designation of gas transmission system operators

6.

6.

Requirement to apply for certification

7.

7.

Certification and designation of gas transmission system operators

8.

8.

Decision in respect of certification

9.

9.

Designation of gas transmission system operators

10.

10.

Certification in relation to third countries

PART 4 Gas transmission system operator to prepare national ten-year network development plan

11.

11.

National ten-year network development plan

PART 5 Unbundling of electricity transmission systems and electricity transmission system operators

12.

12.

Scope of Part 5

13.

13.

Prohibition of certain transfers and sharing services

14.

14.

Interpretation

PART 6 Certification and designation of electricity transmission system operators

15.

15.

Requirement to apply for certification

16.

16.

Certification and designation of electricity transmission system operators

17.

17.

Decision in respect of certification

18.

18.

Designation of electricity transmission system operators

19.

19.

Certification in relation to third countries

PART 7 Powers of Commission and enforcement

20.

20.

Definitions — Part 7

21.

21.

Commission — powers and obligations

22.

22.

Commission — complaints

23.

23.

Commission — powers of enforcement

24.

24.

Commission — application to court for compliance order

PART 8 Consequential amendments to natural gas and electricity legislation

25.

25.

Amendment of Gas Act 1976

26.

26.

Amendment of Electricity Regulation Act 1999

27.

27.

Amendment of Gas (Interim) (Regulation) Act 2002

28.

28.

Amendment of European Communities (Internal Market in Electricity) Regulations 2000

PART 9 Revocations

29.

29.

Revocations

S.I. No. 16 of 2015

EUROPEAN COMMUNITIES (INTERNAL MARKET IN NATURAL GAS AND ELECTRICITY) (AMENDMENT) REGULATIONS 2015

Notice of the making of this Statutory Instrument was published in

“Iris Oifigiúil” of 23rd January, 2015.

I, ALEX WHITE, Minister for Communications, Energy and Natural Resources, in exercise of the powers conferred on me by section 3 of the European Communities Act 1972 (No. 27 of 1972) and for the purpose of giving further effect to Directive 2009/72/EC of the European Parliament and of the Council of 13 July 20091 and Directive 2009/73/EC of the European Parliament and of the Council of 13 July 20092 , hereby make the following regulations:

PART 1 Preliminary and general

Citation and commencement

1.

(1) These Regulations may be cited as the European Communities (Internal Market in Natural Gas and Electricity) (Amendment) Regulations 2015.

Interpretation

2.

(1) In these Regulations—

“Act of 1976” means Gas Act 1976 (No. 30 of 1976);

“Act of 1999” means Electricity Regulation Act 1999 (No. 23 of 1999);

“Agency” means the Agency for the Cooperation of Energy Regulators established by Regulation (EC) No 713/2009 of the European Parliament and of the Council of 13 July 20093 ;

“authorised officer” means an authorised officer appointed under section 11 (as amended by section 44 of the Water Services (No. 2) Act 2013 (No. 50 of 2013)) of the Act of 1999;

“assets” means any legal or equitable estate or interest (whether present or future and whether vested or contingent) in real or personal property of any description (including money), and includes securities, choses in action and documents;

“Commission” means the Commission for Energy Regulation;

“control” means any rights, contracts or any other means which, either separately or in combination and having regard to the considerations of fact or law involved, confer the possibility of exercising decisive influence on an undertaking, in particular by—

“court” means the High Court;

“customers”, in relation to a gas transmission system, means wholesale customers and, where the context so requires, includes final or end customers;

“determination” means determination under section 25 of the Act of 1999;

“distribution system”, in relation to natural gas, means a system for the transport of natural gas through local or regional pipelines with a view to its delivery to customers;

“Electricity Market Directive” means Directive 2009/72/EC of the European Parliament and of the Council of 13 July 20091;

“Electricity Market Regulation” means Regulation (EC) No 714/2009 of the European Parliament and of the Council of 13 July 20094 ;

“electricity transmission system operator” has the meaning assigned to “transmission system operator” in point (4) of Article 2 of the Electricity Market Directive, and includes an interconnector operator;

“Ervia” means the body formerly known as Bord Gáis Éireann;

“gas transmission system” means a system for the transport of natural gas through a high pressure pipeline, other than an upstream pipeline, with a view to delivering natural gas to customers;

“gas transmission system operator” has the meaning assigned to “transmission system operator” in point (4) of Article 2 of the Natural Gas Market Directive;

“interconnector operator” means the holder of a licence under section 14(1)(i) of the Act of 1999;

“LNG” means liquefied natural gas;

“Minister” means the Minister for Communications, Energy and Natural Resources;

“Natural Gas Market Directive” means Directive 2009/73/EC of the European Parliament and of the Council of 13 July 20092;

“Natural Gas Market Regulation” means Regulation (EC) No 715/2009 of the European Parliament and of the Council of 13 July 20095 ;

“network transfer date” means the date appointed by the Minister in accordance with section 15 of the Gas Regulation Act 2013 (No. 39 of 2013);

“operate” includes maintain and develop;

“publish” includes publish on the internet;

“system user” means a natural or legal person supplying to, or being supplied by, a transmission or distribution system;

“ten-year network development plan”, in relation to the gas transmission system operator, means the national plan prepared and submitted, or required to be prepared and submitted, in accordance with Regulation 11;

“third country” means a country which is not a member of the European Union;

“vertically integrated undertaking” means—

or

PART 2 Unbundling of gas transmission systems and gas transmission system operators

Scope of Part 2

3.

(1) This Part shall apply to all undertakings which own or operate a gas transmission system in the State.

(3)(a) Where 2 or more undertakings which own gas transmission systems have created a joint venture that acts as a gas transmission system operator in 2 or more Member States for the gas transmission systems concerned, it shall be deemed to be a gas transmission system operator for the purposes of paragraph (2).

an undertaking which is a gas transmission system operator or is a gas transmission system.

an undertaking;

shall be deemed not to be the same person or persons.

Prohibition of certain transfers and sharing services

4.

(1) The following shall not be transferred from a gas transmission system operator which was part of a vertically integrated undertaking to an undertaking performing any of the functions of production and supply of natural gas:

shall not, directly or indirectly, take control of or exercise any right over a gas transmission system operator to which Article 9(1) of the Natural Gas Market Directive applies.

Interpretation — Part 2

5.

In this Part—

PART 3 Certification and designation of gas transmission system operators

Requirement to apply for certification

6.

(1) A gas transmission system operator shall, prior to commencing any gas transmission system operations, make an application to the Commission for the certification pursuant to this Part.

Certification and designation of gas transmission system operators

7.

(1) The Commission shall establish and operate a certification procedure to assess compliance by gas transmission system operators with the requirements of Part 2.

Decision in respect of certification

8.

(1) The Commission shall adopt a preliminary decision on the certification of a gas transmission system operator not later than 4 months from the date of receipt of the following:

the Commission shall adopt its final decision on the certification taking account of the opinion of the European Commission, where provided.

“final decision” means a final decision adopted by the Commission on the certification of a gas transmission system operator under paragraph (5);

“preliminary decision” means a preliminary explicit decision of the Commission on the certification of a gas transmission system operator under paragraph (1);

“tacit decision” means a deemed decision referred to in paragraph (2).

Designation of gas transmission system operators

9.

(1) The certification of a gas transmission system operator by the Commission shall be deemed to be a designation.

and

Certification in relation to third countries

10.

(1) Where certification is requested, pursuant to Regulation 6, by a gas transmission system owner or a gas transmission system operator, which is controlled by a person or persons from a third country or third countries—

the Commission shall adopt its final decision on the certification of the gas transmission system operator taking account of the opinion of the European Commission, where provided.

(11)(a) The Commission’s final decision and the European Commission’s opinion, where provided, shall be published simultaneously in the Official Journal of the European Union.

“preliminary decision” means a preliminary decision adopted by the Commission on the certification of a gas transmission system operator in accordance with paragraph (4);

“final decision” means a final decision adopted by the Commission on the certification of a gas transmission system operator in accordance with paragraph (9);

“opinion” means the opinion of the European Commission requested in accordance with paragraph (8);

“third country” means a country which is not at the relevant time a Member State.

PART 4 Gas transmission system operator to prepare national ten-year network development plan

National ten-year network development plan

11.

(1) In order to allow the Commission to assess the medium-term investment plans of gas transmission system operators as regards consistency with the European Union ten-year network development plan, gas transmission system operators shall, on an annual basis, prepare and submit to the Commission a ten-year network development plan with respect to investment in its gas transmission network system.

(4)(a) The Commission shall consult all actual or potential system users regarding a plan in an open and transparent manner.

“European Union ten-year network development plan” means the plan referred to in Article 8(3)(b) of the Natural Gas Market Regulation;

“plan” means the national ten-year network development plan prepared and submitted to the Commission pursuant to paragraph (1).

PART 5 Unbundling of electricity transmission systems and electricity transmission system operators

Scope of Part 5

12.

(1) This Part shall not apply to an undertaking while it is certified under Article 9(9) of the Electricity Market Directive.

(3)(a) Where 2 or more undertakings which own electricity transmission systems have created a joint venture that acts as an electricity transmission system operator in 2 or more Member States for the electricity transmission systems concerned, it shall be deemed to be an electricity transmission system operator for the purposes of paragraph (2).

an undertaking which is an electricity transmission system operator or electricity transmission system.

an undertaking;

shall be deemed not to be the same person or persons.

Prohibition of certain transfers and sharing services

13.

(1) The following shall not be transferred from an electricity transmission system operator which was part of a vertically integrated undertaking to an undertaking performing any of the functions of generation and supply of electricity:

shall not, directly or indirectly, take control of or exercise any right over an electricity transmission system operator to which Article 9(1) of the Electricity Market Directive applies.

Interpretation

14.

In this Part—

PART 6 Certification and designation of electricity transmission system operators

Requirement to apply for certification

15.

(1) Prior to an undertaking being designated and approved as a transmission system operator under these Regulations, it shall be certified according to the procedures under this Part.

Certification and designation of electricity transmission system operators

16.

(1)(a) The Commission shall establish and operate a certification procedure to assess compliance by electricity transmission system operators with the requirements of Article 9 of the Electricity Market Directive.

Decision in respect of certification

17.

(1) The Commission shall adopt a preliminary decision on the certification of an electricity transmission system operator not later than 4 months from the date of receipt of—

(5)(a) Not later than 2 months—

the Commission shall adopt its final decision on the certification taking account of the opinion of the European Commission, where provided.

“final decision” means a final decision adopted by the Commission on the certification of an electricity transmission system operator under paragraph (5);

“preliminary decision” means a preliminary explicit decision of the Commission on the certification of an electricity transmission system operator under paragraph (1);

“tacit decision” means a deemed decision referred to in paragraph (2).

Designation of electricity transmission system operators

18.

(1) The certification of an electricity transmission system operator by the Commission shall be deemed to be a designation.

Certification in relation to third countries

19.

(1) Where certification is requested, pursuant to Regulation 15, by an electricity transmission system owner or an electricity transmission system operator, which is controlled by a person or persons from a third country or third countries—

the Commission shall adopt its final decision on the certification of the electricity transmission system operator taking account of the opinion of the European Commission, where provided.

(11)(a) The Commission’s final decision and the European Commission’s opinion, where provided, shall be published simultaneously in the Official Journal of the European Union.

“preliminary decision” means a preliminary decision adopted by the Commission on the certification of an electricity transmission system operator in accordance with paragraph (4);

“final decision” means a final decision adopted by the Commission on the certification of an electricity transmission system operator in accordance with paragraph (9);

“opinion” means the opinion of the European Commission requested in accordance with paragraph (8);

“third country” means a country which is not at the relevant time a Member State.

PART 7 Powers of Commission and enforcement

Definitions — Part 7

20.

In this Part—

“gas transmission system operator” means a transmission system operator designated pursuant to Part 3;

“electricity transmission system operator” means a transmission system operator designated pursuant to Part 6.

Commission — powers and obligations

21.

(1) Subject to paragraph (3), the Commission shall monitor the operations of the following:

the Commission shall, by notice in writing to the party concerned, require it to take such measures to rectify the situation as the Commission specifies in the notice within such time period, if any, specified in the notice.

Commission — complaints

22.

(1) Any party having a complaint against—

in relation to that operator’s obligations under these Regulations, may refer the complaint to the Commission in accordance with section 9(1D) of the Act of 1999.

Commission — powers of enforcement

23.

(1) The Commission shall, with respect to—

have the following powers in enforcing these Regulations:

so as to ensure compliance with that operator’s obligations under these Regulations.

that judge may issue a warrant under the judge’s hand authorising an authorised officer accompanied, if the judge considers it appropriate to so provide, by such number of members of the Garda Síochána as may be specified in the warrant, at any time within 4 weeks from the date of issue of the warrant, to enter, if need be by force, the place and exercise any of the powers referred to in these Regulations.

Commission — application to court for compliance order

24.

(1) Where the Commission is of the opinion that a person to whom this Part applies has contravened, is contravening or is about to contravene, or has failed, is failing or is about to fail to comply with—

the Commission may apply to the court for a compliance order against the person.

(3)(a) An application may not be heard unless the court is satisfied that the person concerned has been served with a copy of the application.

(4)(a) The court may, as it thinks fit, on the hearing of the application make an order compelling compliance with the provision, condition, determination, requirement or direction, or refuse the application.

(7)(a) An application for an order under paragraph (1) may include an application for an order to pay to the Commission such amount not exceeding—

(i)10 per cent of the annual turnover of a gas transmission system operator, or

(ii)10 per cent of the annual turnover of either the electricity transmission system owner or the electricity system operator, as appropriate,

by way of financial penalty, as the Commission may propose as appropriate in the light of the non-compliance.

PART 8 Consequential amendments to natural gas and electricity legislation

Amendment of Gas Act 1976

25.

(1) Section 2 of the Act of 1976 is amended—

“ ‘industrial customer’ means large industrial and commercial customers with a peak hourly demand greater than 50 Megawatt and a connection pressure of 16 barg or above;”, and

“ ‘Natural Gas Market Directive’ means Directive 2009/73/EC of the European Parliament and of the Council of 13 July 20096 ;

‘Natural Gas Market Regulations’ means European Communities (Internal Market in Natural Gas and Electricity) Regulations 2015 ( S.I. No. 16 of 2015 );”.

“Take-or-Pay Gas Commitments

(21)(a) The Commission may, on a case by case basis, grant a temporary derogation from Article 32 of the Natural Gas Market Directive, where the holder of a licence considers that allowing an application for third party access would cause serious economic and financial difficulties because of take-or-pay commitments of the licence holder under one or more gas purchase contracts.

  • (b) Applications for a derogation, referred to in paragraph (a), may be made to the Commission by the holder of a licence either before or after the holder of the licence has refused third party access to the gas network system, but must be made promptly and without delay where the licence holder has refused access.

  • (c) Applications, referred to in paragraph (b), shall be accompanied by all relevant information on the nature and extent of the difficulties and on the efforts undertaken by the licence holder to resolve the difficulties.

  • (d) When making a decision to grant or refuse to grant a derogation under this subsection, the Commission shall take into account in particular the following criteria:

    • (i) the objective of achieving a competitive gas market;

    • (ii) the need to fulfill public-service obligations within the meaning of Article 3 of the Natural Gas Market Directive and to ensure security of supply;

    • (iii) the position of the natural gas undertaking concerned in the gas market and the actual level of competition in that market;

    • (iv) the seriousness of the economic and financial difficulties encountered by natural gas undertakings and transmission undertakings or eligible customers;

    • (v) the dates of signature and terms of the contract or contracts in question, including the extent to which they allow for market changes;

    • (vi) the efforts made to find a solution to the difficulties;

    • (vii) the extent to which, when accepting the take-or-pay commitments in question, the licensee could reasonably have foreseen, having regard to the provisions of the Natural Gas Market Directive, that serious difficulties were likely to arise;

    • (viii) the level of connection of the gas network system with other network systems and the degree of interoperability of those systems;

    • (ix) the effects the grant of the derogation would have on the functioning of the internal market in natural gas.

  • (e) The Commission may, following assessment of an application under this subsection, grant a temporary derogation if it considers that alternative solutions are not reasonably available.

  • (f) The Commission shall notify the European Commission promptly of any decision to grant a temporary derogation and shall submit to the European Commission all relevant information with respect to the proposed derogation.

  • (g) Information, referred to in paragraph (f), may be submitted to the European Commission in an aggregated form.

  • (h) Where a request is made by the European Commission to the Commission to withdraw or amend its decision to grant a temporary derogation, the Commission shall comply with such a request within 4 weeks of receiving such a request.

  • (i) Licensees that have not been granted a temporary derogation under paragraph (e) shall not refuse access to the system because of take-or-pay commitments accepted in a gas purchase contract.

  • (j) Serious difficulties shall in any case be deemed not to exist when the sales of natural gas do not fall below the level of minimum offtake guarantees contained in gas-purchase take-or-pay contracts or in so far as the relevant gas-purchase take-or-pay contract can be adapted or the natural gas undertaking is able to find alternative outlets.”.

Amendment of Electricity Regulation Act 1999

26.

(1) Section 2(1) (as amended by section 4 (1) of the ESB (Electronic Communications Networks) Act 2014 (No. 5 of 2014)) of the Act of 1999 is amended-

“ ‘electricity derivative’ means a financial instrument referred to in point 5, 6 or 7 of Section C of Annex I to Directive 2004/39/EC of the European Parliament and of the Council of 21 April 20047 , where that instrument relates to electricity;”,

“ ‘electricity supply contract’ means a contract for the supply of electricity, but does not include an electricity derivative;”,

“ ‘wholesale customer’ means a natural or legal person purchasing electricity for the purpose of resale inside or outside the system where he or she is established.”.

  • “(dc) where the Commission determines it to be necessary under paragraph (db), to—

  • (i) examine the charges and the costs underlying such charges for electricity which have been supplied by the Board,

  • (ii) examine any proposal by the Board to alter charges for the supply of electricity,

  • (iii) examine the charges and the costs underlying such charges for natural gas which have been supplied in accordance with the licence granted to Bord Gáis Energy or its assignees,

  • (iv) examine any proposal by Bord Gáis Energy or its assignees to alter charges for the supply of natural gas,

  • (v) issue directions or approvals to the Board or Bord Gáis Energy or its assignees, in relation to either or both the nature or the amount of any charge or proposed charge for the supply of electricity or natural gas as relevant, to such class or classes of final customers as the Commission may specify, and

  • (vi) publish a notice on the Commission’s website of any directions or approvals issued under subparagraph (v) stating the nature of the direction and the reasons for it,”,

  • “(dn) where applicable, to monitor technical cooperation between electricity transmission system operators and third-country electricity transmission system operators, and

  • (do) to review and approve, as appropriate, the criteria determined by the electricity transmission system operator to underpin the dispatch of generation installations and the use of interconnectors and such criteria shall—

    • (i) be objective, published, applied in a non-discriminatory matter, and be without prejudice to the supply of electricity on the basis of existing contractual obligations ensuring the proper functioning of the internal market in electricity, and

    • (ii) take into account the economic precedence of electricity from available generation installations or interconnector transfers and the technical constraints on the system,”,

  • “(faa) to ensure that any information obtained from another regulatory authority in regard to a cross-border issue under the Natural Gas Market Directive, the Natural Gas Market Regulation, the Electricity Market Directive or the Electricity Market Regulation is treated confidentially to the same extent that is required of the other regulatory authority,”, and
  • “(fe) to request the opinion of the Agency on the compliance of a decision, taken by another regulatory authority on a cross border trade issue, with guidelines referred to in the Natural Gas Market Regulation, the Natural Gas Market Directive, the Electricity Market Regulation or the Electricity Market Directive,

  • (ff) where it considers that a decision relevant for cross-border trade taken by another regulatory authority does not comply with the guidelines referred to in paragraph (fe), to, if it considers it necessary, inform the European Commission within 2 months of the taking of the decision by that other regulatory authority,

  • (fg) where, following a request to the Agency by another regulatory authority in regard to a decision made by the Commission on a cross-border trade issue, the European Commission has requested the Commission to withdraw its decision, to comply with any such decision within a period of 2 months and to inform the European Commission accordingly,”, and

“or

  • (ii) any dispute between Bord Gáis Éireann and the ITO in respect of their obligations under the Natural Gas Market Directive,”
  • “(2H) The holder of an electricity supply licence under subsection (1)(b) and (1)(h) shall maintain for not less than 5 years and make available on a request being made by the Commission, the Competition and Consumer Protection Commission or the European Commission all relevant data relating to all transactions in electricity supply contracts and electricity derivatives with wholesale customers and transmission system operators.

  • (2I) The data referred to in subsection (2H) shall include details on the characteristics of relevant transactions such as duration, delivery and settlement rules, the quantity, the dates and times of execution and the transaction prices and means of identifying the wholesale customer concerned, as well as specified details of all unsettled electricity supply contracts and electricity derivatives.

  • (2J) The Commission may decide to make available to market participants elements of this information provided that commercially sensitive information on individual market players or individual transactions is not released. This subsection shall not apply to information about financial instruments which fall within the scope of Directive 2004/39/EC of the European Parliament and of the Council of 21 April 20048 .

  • (2K) The obligations on undertakings under subsection (2H) with respect to transactions by them in electricity derivatives with wholesale customers and transmission system operators shall not apply until the European Commission has adopted Guidelines, referred to in Article 40 of the Electricity Market Directive, defining the methods and arrangements for record keeping as well as the form and content of the data to be kept by undertakings.

  • (2L) In the event that the authorities referred to in subsection (2H) require access to data kept by entities falling within the scope of Directive 2004/39/EC of the European Parliament and of the Council of 21 April 2004, the authorities responsible under that Directive shall provide them with the required data.”.

“(6)(a) Any dispute between the transmission system operator or the distribution system operator and any person who is, or claims to be, a person to whom the transmission system operator or the distribution system operator, as the case may be, is obliged to make an offer for connection to and use of the transmission system or distribution system, as the case may be, whether as to the terms and conditions (including proposed charges) or otherwise, shall, upon the application of such person, be determined by the Commission, and the Commission shall issue a direction regarding its determination and the transmission system operator or the distribution system operator, as the case may be shall comply with and be bound by any such direction.

  • (b) Any dispute between a transmission system operator or a distribution system operator in regard to duties under the Electricity Market Directive and a person as respects matters specified in section 9(1B) in relation to electricity shall, upon the application of such person, be determined by the Commission, and the Commission shall issue a direction regarding its determination and such direction shall be binding on all parties concerned.

(c)(i) The Commission shall issue the determination referred to in paragraphs (a) and (b) within 2 months from the date of the receipt of the complaint.

- (ii) The period referred to in subparagraph (i) may be extended by 2 months where the Commission seeks additional information in the matter, and such further extension as may be consented to by the applicant.

- (iii) Where the applicant concerns connection tariffs for major new generation facilities, the period concerned may be extended by the Commission without the consent of the applicant.

- (*d*) In the event of cross border disputes, the Commission has jurisdiction if the transmission system operator licensed under section 14(1)(*e*) is the system operator which refuses use of or access to the transmission system.”.

Amendment of Gas (Interim) (Regulation) Act 2002

27.

The Gas (Interim) (Regulation) Act 2002 (No. 10 of 2002) is amended—

“ ‘distribution system’, in relation to natural gas, means a system for the transport of natural gas through local or regional pipelines with a view to its delivery to customers;”,

“ ‘LNG facility’ has the meaning assigned to it in point 11 of Article 2 of the Natural Gas Directive;”,

and

“ ‘transmission system’, in relation to natural gas, means a system for the transport of natural gas through a high pressure pipeline, other than an upstream pipeline, with a view to delivering natural gas to customers;”,

This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.

This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence. Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.