DEVELOPMENT (EMERGENCY ELECTRICITY GENERATION) ACT 2022

Type Act
Publication 2022-10-29
Last updated 2024-10-17
State In force superseded text
Text As published
PDF Download
articles 12

This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.

1 amending act · 2024-10-17, PLANNING AND DEVELOPMENT ACT 2024

Act to provide for emergency measures for electricity generation development to ameliorate and protect security of supply of electricity in the State because exceptional circumstances have arisen in the market for that supply and further because of the situation in Ukraine; for disapplication of the Planning and Development Act 2000 for the purpose of such development; for such development to be exempt from the provisions of Directive No. 2011/92/EU of the European Parliament and of the Council of 13 December 2011 on the assessment of the effects of certain public and private projects on the environment amended by Directive 2014/52/EU of the European Parliament and of the Council of 16 April 2014, in accordance with Article 2(4) of that Directive; for application of arrangements for the alternative assessment of such development for the purposes of that Directive and the appropriate assessment of such development for the purposes of Council Directive 92/43/EEC of 21 May 1992 on the conservation of natural habitats and of wild fauna and flora, and for the co-ordination of such assessments; and to provide for related matters.

Reform history JSON API

An Act to provide for emergency measures for electricity generation development to ameliorate and protect security of supply of electricity in the State because exceptional circumstances have arisen in the market for that supply and further because of the situation in Ukraine; for disapplication of the Planning and Development Act 2000 for the purpose of such development; for such development to be exempt from the provisions of Directive No. 2011/92/EU of the European Parliament and of the Council of 13 December 20111 on the assessment of the effects of certain public and private projects on the environment amended by Directive 2014/52/EU of the European Parliament and of the Council of 16 April 20142, in accordance with Article 2(4) of that Directive; for application of arrangements for the alternative assessment of such development for the purposes of that Directive and the appropriate assessment of such development for the purposes of Council Directive 92/43/EEC of 21 May 19923 on the conservation of natural habitats and of wild fauna and flora, and for the co-ordination of such assessments; and to provide for related matters.

[29th October, 2022]

Be it enacted by the Oireachtas as follows:

1. Definitions

1. In this Act—

“applicant” means an applicant under section 4 for an approval under section 7;

“Board” means An Bord Pleanála;

“designated development” means development designated by section 2(1);

“Environmental Impact Assessment Directive” means Directive 2011/92/EU of the European Parliament and of the Council of 13 December 20114 on the assessment of the effects of certain public and private projects on the environment, amended by Directive 2014/52/EU of the European Parliament and of the Council of 16 April 20145;

“generating station” means a station for the generation of electricity;

“Habitats Directive” means Council Directive 92/43/EEC of 21 May 19926 on the conservation of natural habitats and of wild fauna and flora, amended by Council Directive 97/62/EC of 27 October 19977, Regulation (EC) No. 1882/2003 of the European Parliament and of the Council of 29 September 20038, Council Directive 2006/105/EC of 20 November 20069 and Council Directive 2013/17/EU of 13 May 201310;

“Minister” means Minister for the Environment, Climate and Communications;

“prescribed” means prescribed by regulations made by the Minister;

“Regulations of 2011” means the European Communities (Birds and Natural Habitats) Regulations 2011 (S.I. No. 477 of 2011).

2. Designation of development

2. (1) Development comprising of the installation of up to 450 megawatts of temporary emergency electricity generation plant, site development and works ancillary to that installation, and the operation of the plant, intended to be located at two separate sites at Shannonbridge and Tarbert generating stations or at alternative appropriate sites, which development is required urgently for the purpose of ensuring and protecting security of electricity supply by Winter of 2023 to 2024, is hereby designated for the purposes of this Act, in particular section 5.

3. Disapplication of Planning and Development Act 2000 to designated development

3. None of the provisions of the Planning and Development Act 2000 shall apply to the designated development.

4. Application to Minister

4. EirGrid, or any other person, may apply to the Minister, in accordance with the requirements of this Act and such procedures as may be prescribed, for approval under section 7 to carry out the designated development.

5. Arrangements for Environmental Impact Assessment

5. (1) Without prejudice to the generality of section 3, the designated development shall be exempt from the provisions of the Environmental Impact Assessment Directive on the basis that the designated development is an exceptional case for the purposes of Article 2(4) of that Directive and the application of those provisions would adversely affect the purpose, referred to in section 2(1), of the designated development.

6. Arrangements for Appropriate Assessment

6. (1) On receiving an application under section 4, the Minister shall arrange for an assessment of the designated development to be carried out by the Board in accordance with Part 5 of the Regulations of 2011, subject to any modifications as to process as may be prescribed for the purposes of this Act, and Part 5 of those Regulations shall apply in respect of the designated development subject to such modifications.

7. Decision of Minister

7. (1) The Minister may, having considered an application made to him or her under section 4 for an approval under this section, having taken into account the assessments carried out by the Board under sections 5(2) and 6(1) and any conditions recommended by the Board arising from those assessments, including but not limited to conditions relating to mitigation measures, and having regard to the purpose referred to in section 2(1)—

8. Requirement to comply with approval

8. The designated development shall be carried out in accordance with an approval under paragraph (a) or (c) of section 7(1).

9. Regulations for purpose of Act

9. (1) The Minister may prescribe such matters of procedure and administration as appear to the Minister to be necessary or expedient in respect of this Act.

10. Section 15 of Climate Action and Low Carbon Development Act 2015

10. Taking into account the exceptional circumstances and the urgent and compelling necessity for securing the supply of electricity in the State, the Minister and the Board, in performing their functions under this Act, shall do so in a manner consistent with the plans, strategy, framework and objectives referred to in section 15(1) of the Climate Action and Low Carbon Development Act 2015 to the extent that they consider practicable, taking particular account of the said exceptional circumstances and urgent and compelling necessity.

11. Expenses

11. The expenses incurred by the Minister in the administration of this Act shall, to such extent as may be sanctioned by the Minister for Public Expenditure and Reform, be paid out of moneys provided by the Oireachtas.

12. Short title and commencement

12. (1) This Act may be cited as the Development (Emergency Electricity Generation) Act 2022.

Footnotes

1

OJ No. L26, 28.1.2012, p.1

2

OJ No. L24, 25.4.2014, p.1

3

OJ No. L206, 22.7.1992, p.7

4

OJ No. L26, 28.1.2012, p.1

5

OJ No. L24, 25.4.2014, p.1

6

OJ No. L206, 22.7.1992, p.7

7

OJ No. L305, 8.11.1997, p. 42

8

OJ No. L284, 31.10.2003, p. 1

9

OJ No. L363, 20.12.2006, p. 368

10

OJ No. L158, 10.6.2013, p. 193

This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.

This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence. Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.