S.I. No. 459/2022 - Electricity Regulation Act 1999 (Section 16(3A)) Order 2022

Type Statutory Instrument
Publication 2022-09-16
State In force
Text As published
articles 8

This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.

Reform history JSON API

Notice of the making of this Statutory Instrument was published in

“Iris Oifigiúil” of 16th September, 2022.

The Commission for Energy Regulation in exercise of the powers conferred on it by Section 16 (3A) of the Electricity Regulation Act 1999 (as inserted by Regulation 13(b) of the European Communities (Internal Market in Electricity) Regulations 2005 ( S.I. No. 60 of 2005 )) hereby orders as follows—

Citation.

1.

1.

This Order may be cited as the Electricity Regulation Act 1999 (Section16(3A)) Order 2022.

Commencement.

2.

2.

This Order shall come into operation on 7^th September 2022.

Revocation

3.

3.

The Electricity Regulation Act 1999 (Section 16(3A)) Order 2008 (SI 383 of 2008) is revoked.

Interpretation.

4.

4.

(1) In this Order, unless the context otherwise requires—

“Act” means the Electricity Regulation Act 1999 (No. 23 of 1999), as amended;

“generator” means a person licensed to generate electricity under Section 14(1)(a) of the Act;

“generator site” means the site owned (or occupied pursuant to a lease, licence or other agreement) by the generator which contains the connection point;

“installed capacity” means the normal full load kW capacity of any apparatus which produces electricity, as stated on their nameplates; and

“ S.I. No. 60 of 2005 ” means the European Communities (Internal Market in Electricity) Regulations 2005 (S. I. No. 60 of 2005).

Purpose.

5.

5.

(1) Pursuant to Section 16(3A) of the Act, the Commission may by order provide for the authorisation of persons in relation to the construction or reconstruction of a class or classes of generating station.

Authorisation.

6.

6.

(1) (a) A person proposing to construct or re-construct a class of generating station referred to in Article 5(2)(a) shall provide a notification of this proposal to the Commission in the manner prescribed in the terms and conditions as set out in Schedule 2 to this Order.

Amendment or Revocation of Order.

7.

7.

Pursuant to section 16(3B) of the Act, the Commission may by order amend or revoke this Order.

Terms and Conditions.

8.

8.

A person duly authorised to construct or reconstruct a generating station pursuant to this Order shall be required to comply with the terms and conditions stated in Schedule 1 to this Order.

SCHEDULE 1

The terms and conditions referred to in Article 8 are as follows:

1.

In this Schedule, “authorised person” means a person duly authorised to construct or reconstruct a generating station pursuant to this Order.

2.

This Order shall continue in force unless and until revoked by the Commission by order, in accordance with the Act.

3.

An authorised person shall not commence construction or reconstruction of the generating station in question until all necessary planning authority and statutory consents, permissions or approvals, have been acquired.

4.

An authorised person shall comply at all times with all planning authority and statutory consents, permissions or approvals.

5.

A person duly authorised to construct or reconstruct a generating station pursuant to Article 6(2) of this Order shall complete the construction/reconstruction and commissioning of the generating station no later than five (5) years from the date of authorisation, or such longer period as the Commission may thereafter direct in writing.

6.

An authorised person shall furnish to the Commission information in such manner and at such times as the Commission may require, and shall procure and furnish to it such reports as the Commission may consider necessary in the light of the conditions or as it may require for the purpose of performing the functions assigned or transferred to it by or under the Act. The power of the Commission to request information under this paragraph is without prejudice to the power of the Commission to request information under or pursuant to the Act or this Order.

In this paragraph, “information” shall include any permissions, consents, licences, (including any conditions attached to such permissions, consents or licences), surveys, investigations, documents, records (whether stored, maintained or preserved by means of any mechanical or electronic device or otherwise), accounts, estimates, or reports (whether or not prepared specifically at the request of the Commission) of any description specified by the Commission.

7.

A person duly authorised to construct or reconstruct a generating station pursuant to Article 6(2) of this Order shall not, without the prior written consent of the Commission, assign or transfer an authorisation. Any consent of the Commission to any assignment or transfer of an authorisation under Article 6(2) shall be subject to the Commission being satisfied that the assignee will have the technical and financial capability to comply with:

8.

The Commission may at any time revoke an authorisation issued to an authorised person by giving not less than 30 days’ notice in writing if in the opinion of the Commission, one or more of the following circumstances exist:

SCHEDULE 2

A valid notification under Article 6(1) shall take the form of a signed declaration that the authorised person shall abide by the terms and conditions listed in Schedule 1 and include, among other things, details relating to the name of the generation station, the address of the generating station, owner of the generating station, the generation station type, and the installed capacity of the generating station.

Sealed with the common seal of the Commission for Regulation of Utilities on 7 September, 2022.

AOIFE MACEVILLY,

Chairperson of the Commission.

EXPLANATORY NOTE

(This note is not part of the Instrument and does not purport to be a legal interpretation.)

The purpose of this Order is to provide for the authorisation of persons to construct or reconstruct generating stations located within a Generator Site with an installed capacity not exceeding 10 MW by way of Order made pursuant to Section 16(3A) of the Act.

This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.

This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence. Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.