S.I. No. 719/2022 - Development (Emergency Electricity Generation) Regulations 2022

Type Statutory Instrument
Publication 2022-12-30
State In force
Text As published
articles 11

This is the act as published. Later amendments are not folded into the text below: each one is a separate act in this repository and an entry in this law's history.

Reform history JSON API

Notice of the making of this Statutory Instrument was published in

“Iris Oifigiúil” of 30th December, 2022.

I, EAMON RYAN, Minister for the Environment, Climate and Communications, in exercise of the powers conferred on me by sections 4 , 5 (2), 6 (1) and 9 of the Development (Emergency Electricity Generation) Act 2022 (No. 35 of 2022), hereby make the following regulations:

Citation

1.

1.

These Regulations may be cited as the Development (Emergency Electricity Generation) Regulations 2022.

Definitions

2.

2.

In these Regulations –

“Act of 2022” means the Development (Emergency Electricity Generation) Act 2022 (No. 35 of 2022);

“application” means an application under section 4 of the Act of 2022 for an approval under section 7 of that Act, made in accordance with Regulation 3;

“Appropriate Assessment” has the meaning assigned to it by Regulation 2 of the Regulations of 2011;

“Appropriate Assessment screening report” means a report prepared by the applicant for the purpose of the carrying out by the Board of a screening for Appropriate Assessment in respect of the designated development;

“Environmental Report” means a report prepared in accordance with Regulation 7;

“European Site” has the meaning assigned to it by Regulation 2 of the Regulations of 2011;

“Natura Impact Statement” has the meaning assigned to it by Regulation 2 of the Regulations of 2011.

Application to Minister

3.

3.

(1) An application shall be made to the Minister by electronic means in a readable form that enables copies of the application to be made.

Notice of application

4.

4.

An applicant shall, within 2 weeks before making an application, publish a notice in one national newspaper specifying the following:

Provision of information by Minister to Board

5.

5.

Any information to be provided by the Minister to the Board for the purposes of an assessment of the designated development by the Board in accordance with section 5(2) or 6(1) of the Act of 2022 (including the assessment required to be carried out under section 6(2) of that Act as part of those assessments) shall be provided by electronic means in a readable form that enables copies of the information to be made.

Public consultation

6.

6.

(1) As soon as may be after receipt of an application by the Minister, the application shall be published on the website maintained by the Minister together with a notice stating that –

Environmental Report

7.

7.

(1) An applicant shall prepare and submit a report (in these Regulations referred to as an “Environmental Report”) for the purposes of an assessment by the Board under section 5(2) of the Act of 2022.

Assessment by Board

8.

8.

(1) An assessment carried out by the Board under section 5(2) of the Act of 2022 for the purposes of that section, and for the purpose of ensuring that the objectives of the Environmental Impact Assessment Directive are met, shall identify the likely main effects on the environment of the designated development.

and shall reach a conclusion on the likely main effects of the designated development on the environment.

Appropriate Assessment

9.

9.

(1) For the purposes of section 6(1) of the Act of 2022, Part 5 of the Regulations of 2011 is modified as follows:

Recommendation to Minister under section 6(2)

10.

10.

(1) Where the Board decides to make a recommendation under section 6(2) of the Act of 2022, the Board shall issue the recommendation, and the reasons for the recommendation, to the Minister in writing and by electronic means together with its conclusion under Regulation 8(9).

Effects of steps not being completed by Board or Minister within specified time period

11.

11.

A person shall not question the validity of any step taken by the Minister or the Board under the Act of 2022 or these Regulations by reason only that such step was not completed within the time required to take such step under these Regulations.

GIVEN under my Official Seal,

21 December, 2022.

EAMON RYAN,

Minister for the Environment, Climate and Communications.

.

Footnotes

1

OJ No. L 206, 22.7.1992, p. 7.

2

OJ No. L 20, 26.1.2010, p. 7.

This document does not substitute the official text published in the Irish Statute Book. We accept no responsibility for any inaccuracies arising from the transcription of the original into this format.

This text is published under Irish Statute Book's own terms of reuse, not a Legalize or public-domain licence. Irish Statute Book
CC-BY 4.0 (Oireachtas Open Data PSI Licence)
Contains Irish Public Sector Information licensed under the Oireachtas (Houses of the Oireachtas) Open Data PSI Licence / Creative Commons Attribution 4.0 International, sourced from https://www.irishstatutebook.ie.