The Guarantees of Origin of Electricity Produced from High-efficiency Cogeneration Regulations (Northern Ireland) 2008
Made: 30th June 2008
Coming into operation: 22nd September 2008
The Department of Enterprise, Trade and Investment, being a Department designated [^f00001] for the purposes of section 2(2) of the European Communities Act 1972[^f00002] in relation to measures relating to regulation of the electricity sector, makes the following Regulations in exercise of the powers conferred upon it by that section:
Citation, commencement and extent
1
These Regulations may be cited as the Guarantees of Origin of Electricity Produced from High-efficiency Cogeneration Regulations (Northern Ireland) 2008 and shall come into operation on 22 September 2008.
Interpretation
2
- (1) For the purposes of these Regulations—
- “CHPGO” means a guarantee of origin of electricity produced from high-efficiency cogeneration;
- “the CHPGO holder” means the person to whom the CHPGO is issued or transferred;
- “CHPQA” means the Combined Heat and Power Quality Assurance programme referred to in the CHPQA Standard and accompanying CHPQA guidance notes, Issue 6, October 2016, prepared on behalf of the Department for Business, Energy and Industrial Strategy ;
- “cogeneration” means the simultaneous generation in one process of thermal energy and electrical or mechanical energy;
- “cogeneration unit” means a unit that is able to operate in cogeneration mode;
- “the competent authority” means the Department for the Economy;
- “economically justifiable demand” means demand that does not exceed the needs for heating or cooling and which would otherwise be satisfied at market conditions by energy generation processes other than cogeneration;
- “electricity from cogeneration” means electricity generated in a process linked to the production of useful heat and calculated in accordance with the methodology laid down in Schedule 4;
- “energy” means all forms of energy products, combustible fuels, heat, renewable energy, electricity, or any other form of energy;
- “Energy Efficiency Directive” means Directive 2012/27/EU of the European Parliament and of the Council of 25th October 2012 on energy efficiency, amending Directives 2009/125/EC and 2010/30/EU and repealing Directives 2004/8/EC and 2006/32/EC, as it applies in the European Union;
- “Great Britain” includes—the territorial sea of the United Kingdom which is adjacent to Great Britain; andany area designated under the Continental Shelf Act 1964;
- “guarantee of origin” means, except in relation to paragraphs (3) to (5) of regulation 10, a certificate issued by the competent authority certifying that the electricity in respect of which the certificate is issued is electricity produced from high-efficiency cogeneration;
- “harmonised efficiency reference values” means the values indicated in paragraph 7 of Schedule 7 and set in accordance with that paragraph and with Commission Delegated Regulation (EU) 2015/2402 of 12 October 2015 reviewing harmonised efficiency reference values for separate production of electricity and heat in application of Directive 2012/27/EU of the European Parliament and of the Council;
- “high-efficiency cogeneration” means cogeneration that meets the criteria in Schedule 3;
- “micro-cogeneration unit” means a cogeneration unit with a maximum capacity below 50 kilowatt electrical (kWe);
- “overall efficiency” means the annual sum of electricity and mechanical energy production and useful heat output divided by the fuel input used for heat produced in a cogeneration process and gross electricity and mechanical energy production;
- “power-to-heat ratio” means the ratio of electricity from cogeneration to useful heat when operating in full cogeneration mode using operational data of the specific unit;
- “small-scale cogeneration unit” means a cogeneration unit with installed capacity below 1 megawatt electrical (MWe);
- “useful heat” means heat produced in a cogeneration process to satisfy economically justifiable demand for heating or cooling.
- (2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
- (3) The Interpretation Act (Northern Ireland) 1954[^f00006] shall apply to these Regulations as it applies to an Act of the Northern Ireland Assembly.
Issue of CHPGOs and the competent authority
3
- (1) CHPGOs shall be issued by the competent authority in accordance with these Regulations.
- (2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Request to issue CHPGOs
4
- (1) A producer of electricity may request a CHPGO from the competent authority.
- (2) A request may not be made for a CHPGO under paragraph (1) where the electricity is produced outside Northern Ireland.
- (3) A request under paragraph (1) shall not be considered duly made until the competent authority is provided with all the information specified in Schedule 1 and the statement required under paragraph (4).
- (4) The person making a request under paragraph (1) shall provide with the request a statement that in respect of the electricity which is the subject of the request—
- (a) he is entitled to the issue of a CHPGO under these Regulation;
- (b) he has not made and does not intend to make a request for a CHPGO in respect of the same electricity to any person outside Northern Ireland ; and
- (c) he has not made and does not intend to make another request under paragraph (1) in respect of the same electricity.
Issue and content of CHPGOs
5
- (1) Where the competent authority—
- (a) Receives a request made in accordance with regulation 4(1); and
- (b) Is satisfied that the electricity to which the request relates was produced from high-efficiency cogeneration; and
- (c) Receives any charge payable under regulation 9;
The authority shall issue a CHPGO in respect of that electricity.
- (2) A CHPGO shall be issued to the person making the request for it under Regulation 4(1) or such other person as that person may specify in the request.
- (2A) A CHPGO—
- (a) shall be issued by reference to a standard size of 1MWh; and
- (b) shall relate to the net electricity output measured at the station boundary and exported to the grid.
- (3) A CHPGO—
- (a) shall contain the matters set out in Schedule 2 ; and
- (b) may contain such other matters as the competent authority considers appropriate.
- (4) Where a CHPGO has been issued in respect of any electricity and not revoked, a further CHPGO in respect of the same electricity shall not be issued by the competent authority.
Replacement CHPGOs
6
- (1) The CHPGO holder may request the competent authority to review the issue of the CHPGO and to issue a replacement CHPGO if—
- (a) the CHPGO holder believes that the CHPGO is inaccurate; and
- (b) the request is made in writing to the competent authority within 21 days of the issue of the CHPGO.
- (2) A request under paragraph (1) shall—
- (a) state the particulars of the CHPGO which the CHPGO holder believes are inaccurate, and
- (b) provide all necessary information in support of that request.
- (3) The competent authority shall acknowledge to the CHPGO holder the receipt of a request under paragraph (1) within seven days of receipt.
- (4) The competent authority shall (on the basis of the information provided in a request under paragraph (1))—
- (5) The 40 day period may be extended if so agreed by the CHPGO holder and the competent authority.
- (6) If the competent authority decides—
- (a) to revoke the CHPGO, it shall give notice under regulation 8(2);
- (b) not to revoke the CHPGO, it shall as soon as possible given written notice to the CHPGO holder, with reasons for that decision; and
- (c) to issue a replacement CHPGO, it shall do so as soon as possible.
Transfer of CHPGOs
7
- (1) If the CHPGO holder no longer operates the plant to which the CHPGO relates, he may request the competent authority to transfer the CHPGO to the person who does operate that plant.
- (2) If the competent authority receives—
- (a) a written request for a transfer referred to in paragraph (1);
- (b) satisfactory evidence of the matters referred to in that paragraph; and
- (c) any charge payable under regulation 9;
it shall effect the transfer of the CHPGO.
Revocation of CHPGOs
8
- (1) The competent authority shall revoke a CHPGO where—
- (a) it decides that the CHPGO is inaccurate;
- (b) it is satisfied that the information provided under regulation 4 in connection with the request for the CHPGO is incorrect in a material particular; or
- (c) it is otherwise satisfied that the CHPGO should not have been issued, or was issued to the wrong person.
- (2) Where the competent authority revokes a CHPGO, it shall as soon as possible give written notice to the CHPGO holder.
- (3) A CHPGO that is revoked—
- (a) under sub-paragraph (1)(a), shall be treated as if it had not been issued;
- (b) under sub-paragraphs (1)(b) or (c), shall cease to have effect from the date that notice is given under paragraph (2).
Charging
9
- (1) The competent authority may require the payment of a charge from—
- (a) A producer of electricity who requests a CHPGO under Regulation 4; or
- (b) A CHPGO holder who requests a transfer of a CHPGO under Regulation 8.
- (2) A charge payable under paragraph (1) shall not exceed the costs of the competent authority in complying with the request to which it relates.
- (3) The competent authority shall not be required to issue or transfer a CHPGO until the charge is paid.
Recognition of CHPGOs
10
- (1) A public authority shall recognise a CHPGO issued by the competent authority as proof of the matters referred to in Schedule 2 .
- (2) For the purposes of the regulation a public authority means any Northern Ireland Minister, government department, public body of any description or any person holding public office.
- (3) Subject to paragraph (4), a public authority must recognise, as proof of the matters referred to in Schedule 2, a CHPGO which has been issued—
- (a) in a member State in accordance with article 14(10) of the Energy Efficiency Directive; or
- (b) in Great Britain in accordance with the Guarantees of Origin of Electricity Produced from High-efficiency Cogeneration Regulations 2007 .
- (4) A public authority is not required to recognise, to the extent referred to in paragraph (3), a CHPGO issued outside Northern Ireland if—
- (a) it has been requested to refuse or withdraw such recognition by the authority which issued or supervised the issue of the CHPGO; or
- (b) on the basis of objective, transparent and non-discriminatory criteria, it is satisfied that the CHPGO should not have been issued or that refusal of recognition is necessary for the prevention of fraud.
- (5) Where a public authority has refused to recognise a CHPGO issued in a Member State, it shall recognise that CHPGO where the Commission of the European Communities required before IP completion day such recognition under Article 14(10) of the Energy Efficiency Directive .
- (6) Nothing in this regulation shall require a public authority to satisfy itself that a CHPGO issued in a Member State or Great Britain has been properly issued.
SCHEDULE 1 — Information to be supplied with a request for a CHPGO
1
The name and address and, if a company, the registered number, of the person requesting the issue of the CHPGO.
2
Where the person signing the statement required under regulation 4(4) is not the person making the request, the name and address of the person signing the statement.
3
Whether the person requesting the issue of the CHPGO is the producer of the electricity in respect of which the CHPGO is requested and, if not, the name and address and, if a company the registered number, of the producer.
4
The beginning and end of the period covered by the request.
5
The place where the electricity in respect of which the CHPGO is requested was produced, and the name, if any, of the plant.
6
The quantity of electricity in respect of which the CHPGO is requested, together with the total quantity of electricity produced by the plant during the period covered by the request.
7
The information relating to the plant which a person would be required to provide if they requested a certificate under CHPQA in relation to that plant.
8
The primary fuel source from which the electricity was produced.
9
The heat to power ratio of the plant producing it.
10
The amount of useful heat utilised during the period covered by the request.
11
Such further information as the competent authority may, in the particular circumstances of the case, reasonably require
- (a) for the purposes of ascertaining the accuracy of the information required to be provided under paragraphs 1 to 10; or
- (b) to enable the competent authority to be satisfied that any electricity produced is from high-efficiency cogeneration.
SCHEDULE 2 — Information to be contained in a CHPGO
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed
Sealed with the Official Seal of the Department of Enterprise, Trade and Investment on 30 June 2008
Jenny Pyper — A senior officer of the — Department of Enterprise, Trade and Investment
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
These Regulations implement as respects Northern Ireland Article 5 of the Directive 2004/8/EC (OJ L 52, 21.2.2004, p.50) of the European Parliament and of the council on the promotion of cogeneration based on a useful heat demand in the internal energy market and amending Directive 92/42/EEC (OJ L 167, 22.6.1992, p.17). That article provides for the issue of guarantees of origin of electricity from high-efficiency cogeneration. The cogeneration of electricity is more commonly referred to in the United Kingdom as electricity produced from combined heat and power or CHP.
Regulation 3 provides that the Department of Enterprise, Trade and Investment, as the competent authority, is the issuer of guarantees of origin of electricity produced from high-efficiency cogeneration.
Regulation 4 provides for the procedure that a producer of electricity must follow to obtain a guarantee, Schedule 1 sets out the information that a producer must provide to the competent authority. Paragraph 7 of that Schedule refers to the Combined Heat and Power Quality Assurance (CHPQA) programme. The CHPQA Standard, Issue 2, November 2007 published by the Department for Environment, Food and Rural Affairs. It may be obtained from www.chpqa.com. Or the CHPQA administrator telephone 0870 190 6196 and E-mail: chpqainfo@chpqa.com
Regulation 5 provides for the issue and content of a guarantee. Schedule 2 specifies the information to be included in a guarantee of origin.
Regulation 6 sets out when a guarantee may be replaced.
Regulation 7 provides for the transfer of a guarantee.
Regulation 8 sets out when and how a guarantee may be revoked.
Regulation 9 provides that a charge may be made for the issue or transfer of a guarantee.
Regulation 10 provides for the recognition of guarantees, including those issued by competent authorities outside Northern Ireland.
Footnotes
[^f00001]: S.I. 1998/745
[^f00002]: 1972 c. 68 (c.46)
[^f00006]: 1954 c.33 (N.I.)
Editorial notes
[^key-b8d4bc81e9de15fd0c9c1b83e3d84955]: Reg. 1 in operation at 22.9.2008, see reg. 1
[^key-20e51e9d277ea65acb90a8a8461f33c7]: Reg. 2 in operation at 22.9.2008, see reg. 1
[^key-a38e2b8db1ef795504d9dbc96ac2f1d3]: Reg. 3 in operation at 22.9.2008, see reg. 1
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.