The Planning (General Development Procedure) Order (Northern Ireland) 2015
the council shall give notice to the applicant if it considers the application has not been accompanied by such particulars, or verified by such evidence, as specified in the direction made under this Order.
- (3) A notice given under paragraph (2) shall be in writing and set out the council’s reasons for issuing the notice and shall specify the particulars or evidence as are reasonable for the council to request.
- (4) A notice given under paragraph (2) shall be deemed a refusal for an approval required under a development order under section 58(1) of the 2011 Act.
Appeal against a notice of non-compliance with direction
12B
- (1) If a council gives notice to an applicant under Article 12A(2) the applicant may by notice in writing stating the applicable grounds of appeal, appeal to the planning appeals commission.
- (2) Any notice under this Article shall be served on the planning appeals commission and the council within 14 days from the date of the council’s notice under Article 12A(2).
- (3) The appeal may be brought on any of the following grounds—
- (a) the application was accompanied by such particulars, or was verified by such evidence, as specified in the direction;
- (b) the identified particular, or such evidence verifying the particular, which the council asserts did not accompany the application has not been specified in the direction;
- (c) the council’s request specifying the particulars or evidence under the notice issued under Article 12A(2) is unreasonable; or
- (d) that the application is not one to which the direction applies.
- (4) The planning appeals commission may—
- (a) allow the appeal;
- (b) dismiss the appeal; or
- (c) vary the notice issued under Article 12A(2) to give effect to its determination on the appeal.
- (5) The planning appeals commission decision on the appeal is final.
Consultations as to applications for planning permission
Consultation before the grant of planning permission pursuant to section 54 of the 2011 Act
Duty to respond to consultation
Duty to respond to consultation: annual reports
Directions restricting the grant of planning permission
Directions requiring information
Directions requiring consideration of condition
Time periods for decisions
Permission to develop land without compliance with conditions previously attached
Written notice of decision or determination relating to a planning application
Schemes of delegation
Register of applications
Register of simplified planning zones and enterprise zones
Register of enforcement notices, etc.
Register of orders, directions and notices
Registers held using electronic storage
Use of electronic communications
Claims for compensation and purchase notices
Directions
Revocations
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.