The Town and Country Planning (Environmental Impact Assessment) (Scotland) Regulations 2011
Made: 21st February 2011
Laid before the Scottish Parliament: 23rd February 2011
Coming into force: 1st June 2011
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 1 — INTRODUCTORY
Citation and commencement
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Prohibition on granting planning permission without an environmental impact assessment
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Consideration of environmental information when determining an application for multi stage consent
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 2 — SCREENING
General provisions relating to screening
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Requests for screening opinions of the planning authority
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Requests for screening directions of the Scottish Ministers
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 3 — PROCEDURES CONCERNING APPLICATIONS FOR PLANNING PERMISSION
Application or request to review made to a planning authority without an environmental statement
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
EIA application made to a planning authority without an environmental statement
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application or Appeal to the Scottish Ministers without an environmental statement
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
EIA application referred to the Scottish Ministers without an environmental statement
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Appeal to the Scottish Ministers without an environmental statement
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Review by the planning authority of an application without an environmental statement
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 4 — PREPARATION OF ENVIRONMENTAL STATEMENTS
Scoping opinions of the planning authority
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Scoping directions of the Scottish Ministers
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure to facilitate preparation of environmental statements
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 5 — PUBLICITY AND PROCEDURES ON SUBMISSION OF ENVIRONMENTAL STATEMENTS
Notification of environmental statement
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Publication of environmental statement
18
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Consultation where environmental statement received by planning authority
19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Copies of environmental statement for the Scottish Ministers
20
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Consultation where environmental statement received by the Scottish Ministers
21
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Copies of environmental statement for the public
22
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 6 — ADDITIONAL INFORMATION
Additional information and evidence relating to environmental statements
23
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Publication of additional information
24
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 7 — AVAILABILITY OF DIRECTIONS ETC. AND NOTIFICATION OF DECISIONS
Availability of opinions, directions etc. for inspection
25
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Duties to inform the public and the Scottish Ministers of final decisions
26
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 8 — APPLICATIONS FOR MULTI-STAGE CONSENT
Requests for screening opinions and screening directions
27
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application for multi-stage consent without environmental statement
28
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application for multi-stage consent referred or appealed to the Scottish Ministers without an environmental statement
29
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Modification of regulations relating to application for multi-stage consent
30
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application for multi-stage consent – simplified planning scheme, enterprise zone scheme and ROMP condition
31
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 9 — SPECIAL CASES
Simplified planning zone schemes or enterprise zone orders
32
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
ROMP applications
33
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Applications for permission under section 242A
34
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Marine fish farming
35
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 10 — DEVELOPMENT WITH SIGNIFICANT TRANSBOUNDARY EFFECTS
Development in Scotland likely to have significant effects in an EEA State other than the United Kingdom
36
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Projects in another EEA State likely to have significant transboundary effects
37
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 11 — MISCELLANEOUS
Electronic communications – general
38
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Electronic communications – deemed agreement
39
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Withdrawal of consent to use of electronic communications
40
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Service of notices etc.
41
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application to the Court of Session
42
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Hazardous waste and material change of use
43
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Extension of the period for an authority's decision on a planning application
44
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Directions as to whether development is EIA development
45
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Access to review procedure before a court
46
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Amendment of the Town and Country Planning (General Permitted Development) (Scotland) Order 1992
47
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Amendment of the Town and Country Planning (Development Management Procedure (Scotland) Regulations 2008
48
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocation and savings
49
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 1 — DESCRIPTIONS OF DEVELOPMENT FOR THE PURPOSES OF THE DEFINITION OF “SCHEDULE 1 DEVELOPMENT”
Interpretation
In this Schedule—
- “airport” means an airport which complies with the definition in the 1944Chicago Convention setting up the International Civil Aviation Organisation (Annex14)[^f00027];
- “express road” means a road which complies with the definition in the European Agreement on Main International Traffic Arteries of 15thNovember 1975[^f00028]; and
- “nuclear power station” and “other nuclear reactor” do not include an installation from the site of which all nuclear fuel and other radioactive contaminated materials have been permanently removed; and development for the purpose of dismantling or decommissioning a nuclear power station or other nuclear reactor is to be treated as development of the description mentioned in paragraph2(2) of this Schedule.
Descriptions of development
The carrying out of development to provide any of the following:—
1 Crude‑oil refineries (excluding undertakings manufacturing only lubricants from crude‑oil) and installations for the gasification and liquefaction of 500tonnes or more of coal or bituminous shale per day.
2 1 Thermal power stations and other combustion installations with a heat output of 300megawatts or more. 2 Nuclear power stations and other nuclear reactors (except research installations for the production and conversion of fissionable and fertile material, whose maximum power does not exceed 1kilowatt continuous thermal load).
3 1 Installations for the reprocessing of irradiated nuclear fuel. 2 Installations designed— a for the production or enrichment of nuclear fuel; b for the processing of irradiated nuclear fuel or high‑level radioactive waste; c for the final disposal of irradiated nuclear fuel; d solely for the final disposal of radioactive waste; e solely for the storage (planned for more than tenyears) of irradiated nuclear fuels or radioactive waste in a different site than the production site.
4 1 Integrated works for the initial smelting of cast‑iron and steel. 2 Installations for the production of non‑ferrous crude metals from ore, concentrates or secondary raw materials by metallurgical, chemical or electrolytic processes.
5 Installations for the extraction of asbestos and for the processing and transformation of asbestos and products containing asbestos— a for asbestos‑cement products, with an annual production of more than 20,000tonnes of finished products; b for friction material, with an annual production of more than 50tonnes of finished products; and c for other uses of asbestos, utilisation of more than 200tonnes per year.
6 Integrated chemical installations, that is to say, installations for the manufacture on an industrial scale of substances using chemical conversion processes, in which several units are juxtaposed and are functionally linked to one another and which are— a for the production of basic organic chemicals; b for the production of basic inorganic chemicals; c for the production of phosphorous–, nitrogen– or potassium‑based fertilisers (simple or compound fertilisers); d for the production of basic plant health products and of biocides; e for the production of basic pharmaceutical products using a chemical or biological process; f for the production of explosives.
7 1 Construction of lines for long‑distance railway traffic and of airports with a basic runway length of 2,100metres or more. 2 Construction of motorways and express roads. 3 Construction of a new road of four or more lanes, or realignment and/or widening of an existing road of twolanes or less so as to provide four or more lanes, where such new road, or realigned and/or widened section of road, would be 10kilometres or more in a continuous length.
8 1 Inland waterways and ports for inland‑waterway traffic which permit the passage of vessels of over 1,350tonnes. 2 Trading ports, piers for loading and unloading connected to land and outside ports (excluding ferry piers) which can take vessels of over 1,350tonnes.
9 Waste disposal installations for the incineration, chemical treatment (as defined in AnnexI to Directive 2008/98/EC of the European Parliament and of the Council on waste and repealing certain Directives[^f00029] under headingD9), or landfill of hazardous waste (that is to say, waste which is considered to be hazardous in accordance with Articles3(2) and 7 of that Directive).
10 Waste disposal installations for the incineration or chemical treatment (as defined in AnnexI to Directive 2008/98/EC under headingD9) of non‑hazardous waste with a capacity exceeding 100tonnes per day.
11 Groundwater abstraction or artificial groundwater recharge schemes where the annual volume of water abstracted or recharged is equivalent to or exceeds 10million cubic metres.
12 1 Works for the transfer of water resources, other than piped drinking water, between river basins where the transfer aims at preventing possible shortages of water and where the amount of water transferred exceeds 100million cubic metres per year. 2 In all other cases, works for the transfer of water resources, other than piped drinking water, between river basins where the multi‑annual average flow of the basin of abstraction exceeds 2,000million cubic metres per year and where the amount of water transferred exceeds 5% of this flow.
13 Waste water treatment plants with a capacity exceeding 150,000 population equivalent as defined in Article2(6) of Council Directive 91/271/EEC concerning urban waste-water treatment[^f00030].
14 Extraction of petroleum and natural gas for commercial purposes where the amount extracted exceeds 500tonnes perday in the case of petroleum and 500,000cubic metres per day in the case of gas.
15 Dams and other installations designed for the holding back or permanent storage of water, where a new or additional amount of water held back or stored exceeds 10million cubic metres.
16 Pipelines with a diameter of more than 800millimetres and a length of more than 40kilometres for the transport of— a gas, oil or chemicals; b carbon dioxide streams for the purposes of geological storage, including associated booster stations.
17 Installations for the intensive rearing of poultry or pigs with more than— a 85,000places for broilers or 60,000places for hens; b 3,000places for production pigs (over 30kg); or c 900places for sows.
18 Industrial plants for— a the production of pulp from timber or similar fibrous materials; b the production of paper and board with a production capacity exceeding 200tonnes per day.
19 Quarries and open‑cast mining where the surface of the site exceeds 25hectares, or peat extraction where the surface of the site exceeds 150hectares.
20 Installations for storage of petroleum, petrochemical or chemical products with a capacity of 200,000tonnes or more.
21 Storage sites pursuant to the CCS Directive.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.