The Pollution Prevention and Control (Scotland) Regulations 2012

Type Scottish-Statutory-Instrument
Publication 2012-12-20
State In force
Jurisdiction Scotland
Department King's Printer for Scotland
articles Not indexed
Reform history JSON API PDF

Made: 20th December 2012

Coming into force: 7th January 2013

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART I — GENERAL

Citation, commencement and extent

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Interpretation: general

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Interpretation: enactments etc.

3

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Interpretation: best available techniques, etc.

4

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: duties relating to best available techniques

5

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: application forms

6

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: information relating to right of appeal

7

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

The Scottish Minsters and SEPA: service of notices

8

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Electronic communications

9

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART II — COMPETENT AUTHORITY

SEPA: designation as competent authority

10

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART III — GRANTING OF PERMITS

CHAPTER 1 — General

Permits: requirement for a permit

11

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: interpretation

12

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: application for a permit

13

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: authorised operations

14

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: powers to include conditions

15

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: consolidation

16

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: greenhouse gas emissions

17

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: fit and proper person

18

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: transfer and cessation

19

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

CHAPTER 2 — Schedule 1 activities

Schedule 1 activities

20

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1: general principles

21

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions : best available techniques

22

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: general provisions

23

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: off-site conditions

24

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: emission limit values and environmental quality standards

25

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: large combustion plants

26

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: titanium dioxide

27

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: mixing separately collected waste

28

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: incineration and co-incineration of waste

29

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: incineration of batteries

30

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: waste oils

31

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Schedule 1 conditions: volatile organic compounds

32

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

CHAPTER 3 — Schedule 2 activities

Schedule 2 activities

33

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Solvents: conditions

34

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Solvents installations: abatement equipment

35

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART IV — STANDARD RULES

Standard rules

36

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Standard rules: conditions

37

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Standard rules: consultation

38

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Standard rules: rules by the Scottish Ministers

39

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Standard rules: publication

40

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Standard rules: revision

41

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Standard rules: revocation

42

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Part IV: interpretation

43

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART V — REVIEW, VARIATION AND CESSATION OF PERMITS

Permits: review of conditions

44

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: proposed change in operation

45

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: variation

46

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: transfer

47

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: surrender of a Part A permit

48

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: notification of surrender of an installation or mobile plant permit

49

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Permits: revocation of permits

50

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART VI — COMPLIANCE

SEPA: duty to ensure compliance

51

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Operators: duty to report breach of permit

52

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: environmental inspection plan

53

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: environmental inspection of Part A installations

54

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: enforcement notices

55

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: suspension notices

56

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: power to prevent or remedy pollution

57

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART VII — APPEALS

Appeals to the Scottish Ministers and to the sheriff

58

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Interest for the purposes of the Industrial Emissions Directive

59

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART VIII — THE SCOTTISH MINISTERS

Scottish Ministers: directions to SEPA

60

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Scottish Ministers: guidance to SEPA

61

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Scottish Ministers: emission plans

62

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART IX — INFORMATION AND PUBLICITY

Scottish Ministers and SEPA: powers in respect of information

63

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SEPA: public register

64

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Register: exclusion of information affecting national security

65

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Register: exclusion of confidential information

66

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART X — PROVISION AS TO OFFENCES

Offences

67

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Courts: enforcement

68

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Courts: admissibility of evidence

69

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Courts: power to order cause of offence to be remedied

70

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PART XI — CROWN APPLICATION, ETC

Application to the Crown

71

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Transitional provisions

72

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Consequential amendments

73

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Revocations

74

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

SCHEDULE 1 — ACTIVITIES AND INSTALLATIONS AND MOBILE PLANT

PART 1 — ACTIVITIES

CHAPTER 1 — ENERGY INDUSTRIES

SECTION 1.1 — Combustion

Burning any fuel in a combustion appliance with a rated thermal input of 50 megawatts or more.

Interpretation of Part A

For the purposes of Part A, where two or more appliances with an aggregate rated thermal input of 50 megawatts or more are operated on the same site by the same operator those appliances are be treated as a single appliance with a rated thermal input of 50 megawatts or more.

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Interpretation of Section 1.1

For the purposes of section 1.1—

  • “rated thermal input” is the rate at which fuel can be burned at the maximum continuous rating of the appliance multiplied by the net calorific value of the fuel and expressed as megawatts thermal.

SECTION 1.2 — Gasification, liquefaction and refining activities

1.

Refining gas including natural gas or its products,

2.

Production of coke,

3.

Pyrolysis, carbonisation, distillation, gasification, liquefaction, partial oxidisation or other heat treatment of coal (other than drying of coal), lignite, oil, or other carbonaceous material or mixtures, otherwise than with a view to making charcoal,

4.

Gasification or liquefaction of fuels other than as described in paragraph (c) in installations with a total rated thermal input of 20megawatts or more,

5.

The refining of mineral oils, or the loading, unloading or other handling of, the storage of, or other physical, chemical or thermal treatment of— crude oil, or stabilised crude petroleum.

6.

Purifying or refining any of the products of an activity mentioned in paragraph (a) or its conversion into a different product.

Nothing in paragraph (c) or (f) refers to the use of any substance as a fuel or its incineration or pyrolysis as a waste or to any activity for the treatment of sewage sludge.

In paragraph (c), the heat treatment of oil does not include heat treatment of waste oil or waste emulsions containing oil in order to recover the oil from aqueous emulsions.

Interpretation of Part A

In Part A—

  • carbonaceous material” includes such materials as charcoal, coke, peat, rubber and wood, and
  • rated thermal input” has the same meaning as in Section 1.1.
1.

Blending odorant for use with natural gas or liquefied petroleum gas,

2.

The following activities:— the storage of petrol in stationary storage tanks at a terminal, or the loading or unloading of petrol into or from a road tanker, a rail tanker or an inland waterway vessel at a terminal, the unloading of petrol into stationary storage tanks at a service station if the total quantity of petrol unloaded into such tanks at the service station in any 12 month period is likely to be equal to or greater than 500m3.

3.

Motor vehicle refuelling activities at an existing service station if the petrol refuelling throughput at the station in any 12 month period is more than 3000m3,

4.

Motor vehicle refuelling activities at a new service station if the petrol refuelling throughput at the station in any 12 month period is, or is intended to be, 500m3 or more,

5.

Motor vehicle refuelling activities at a new service station if the petrol refuelling throughput at the station in any 12 month period is, or is intended to be, 100m3 or more and the service station is under permanent living quarters or working areas.

Interpretation of Part B

1

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

2

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

CHAPTER 2 — PRODUCTION AND PROCESSING OF METALS

SECTION 2.1 — Ferrous metals

1.

Roasting or sintering metal ore, including sulphide ore, or any mixture of iron ore with or without other materials,