The Electricity (Applications for Consent and Variation of Consent) (Fees) (Scotland) Amendment Regulations 2022

Type Scottish-Statutory-Instrument
Publication 2022-11-01
State In force
Jurisdiction Scotland
Department King's Printer for Scotland
PDF Download
articles Not indexed
Reform history JSON API

Made: 1st November 2022

Laid before the Scottish Parliament: 3rd November 2022

Coming into force: 13th December 2022

The Scottish Ministers make the following Regulations in exercise of the powers conferred by sections 36(8), 36C(2) and 60(3) of, and paragraph 1(3) of schedule 8 to, the Electricity Act 1989[^f00001] and all other powers enabling them to do so.

Citation, commencement and interpretation

1

Amendment of the 2019 Regulations

2

Subject matter of application Fee payable
1. Construction, or construction and operation, of a generating station which is not EIA development and has a capacity—
not exceeding 10 megawatts £7,800
exceeding 10 megawatts but not exceeding 50 megawatts £30,000
exceeding 50 megawatts but not exceeding 100 megawatts £84,000
exceeding 100 megawatts but not exceeding 300 megawatts £120,000
exceeding 300 megawatts but not exceeding 500 megawatts £180,000
exceeding 500 megawatts but not exceeding 750 megawatts £216,000
exceeding 750 megawatts but not exceeding 1 gigawatt £264,000
exceeding 1 gigawatt £264,000 + £15,000 for each additional 500 megawatts above 1 gigawatt
2. Extension, or extension and operation, of a generating station which is not EIA development, resulting in increase in capacity—
not exceeding 10 megawatts £7,800
exceeding 10 megawatts but not exceeding 50 megawatts £30,000
exceeding 50 megawatts but not exceeding 100 megawatts £84,000
exceeding 100 megawatts but not exceeding 300 megawatts £120,000
exceeding 300 megawatts but not exceeding 500 megawatts £180,000
exceeding 500 megawatts but not exceeding 750 megawatts £216,000
exceeding 750 megawatts but not exceeding 1 gigawatt £264,000
exceeding 1 gigawatt £264,000 + £15,000 for each additional 500 megawatts above 1 gigawatt
3. Construction, or construction and operation, of a generating station which is EIA development and has a capacity—
not exceeding 10 megawatts £8,400
exceeding 10 megawatts but not exceeding 50 megawatts £42,000
exceeding 50 megawatts but not exceeding 100 megawatts £150,000
exceeding 100 megawatts but not exceeding 300 megawatts £216,000
exceeding 300 megawatts but not exceeding 500 megawatts £336,000
exceeding 500 megawatts but not exceeding 750 megawatts £437,000
exceeding 750 megawatts but not exceeding 1 gigawatt £548,000
exceeding 1 gigawatt £548,000 + £30,000 for each additional 500 megawatts above 1 gigawatt
4. Extension, or extension and operation, of a generating station which is EIA development, resulting in an increase in capacity—
not exceeding 10 megawatts £8,400
exceeding 10 megawatts but not exceeding 50 megawatts £42,000
exceeding 50 megawatts but not exceeding 100 megawatts £150,000
exceeding 100 megawatts but not exceeding 300 megawatts £216,000
exceeding 300 megawatts but not exceeding 500 megawatts £336,000
exceeding 500 megawatts but not exceeding 750 megawatts £437,000
exceeding 750 megawatts but not exceeding 1 gigawatt £548,000
exceeding 1 gigawatt £548,000 + £30,000 for each additional 500 megawatts above 1 gigawatt
5. Any other extension of a generating station which does not result in an increase in capacity, where the capacity of the generating station does—
not exceed 10 megawatts £7,800
exceed 10 megawatts £30,000
6. Operation only or change to manner of operation of a generating station, which does not result in an increase in capacity, where the capacity of the generating station does—
not exceed 10 megawatts £7,800
exceed 10 megawatts £30,000
Subject matter of application Fee payable
1. Overhead line which is not EIA development with a total distance—
not exceeding 500 metres £430
exceeding 500 metres but not exceeding 15 kilometres £720 per kilometre, up to a maximum of £4,800
exceeding 15 kilometres £10,800 + £720 per kilometre, up to a maximum of £180,000
2. Overhead line which is EIA development with a total distance—
not exceeding 1 kilometre £1,800
exceeding 1 kilometre £1,800 per kilometre, up to a maximum of £360,000
Variation application Fee payable
1. A variation application which is not for EIA development and which, if granted, would increase the capacity of the generating station such that the increased capacity would—
not exceed 10 megawatts £5,850
exceed 10 megawatts but not exceed 50 megawatts £22,500
exceed 50 megawatts but not exceed 100 megawatts £63,000
exceed 100 megawatts but not exceed 300 megawatts £90,000
exceed 300 megawatts but not exceed 500 megawatts £135,000
exceed 500 megawatts but not exceed 750 megawatts £164,400
exceed 750 megawatts but not exceed 1 gigawatt £200,500
exceed 1 gigawatt £200,500 + £15,000 for each additional 500 megawatts above 1 gigawatt
2. A variation application which is for EIA development and which, if granted, would increase the capacity of the generating station such that the increased capacity would—
not exceed 10 megawatts £6,300
exceed 10 megawatts but not exceed 50 megawatts £31,500
exceed 50 megawatts but not exceed 100 megawatts £112,500
exceed 100 megawatts but not exceed 300 megawatts £162,000
exceed 300 megawatts but not exceed 500 megawatts £252,000
exceed 500 megawatts but not exceed 750 megawatts £310,000
exceed 750 megawatts but not exceed 1 gigawatt £367,000
exceed 1 gigawatt £367,000 + £30,000 for each additional 500 megawatts above 1 gigawatt
3. A variation application which is not for EIA development and which, if granted, would not increase the capacity of the generating station, where the generating station has a capacity—
not exceeding 10 megawatts £5,740
exceeding 10 megawatts £22,500
4. A variation application which is for EIA development and which, if granted, would not increase the capacity of the generating station, where the generating station has a capacity—
not exceeding 10 megawatts £6,300
exceeding 10 megawatts but not exceeding 50 megawatts £31,500
exceeding 50 megawatts but not exceeding 100 megawatts £112,500
exceeding 100 megawatts but not exceeding 300 megawatts £162,000
exceeding 300 megawatts but not exceeding 500 megawatts £252,000
exceeding 500 megawatts but not exceeding 750 megawatts £310,000
exceeding 750 megawatts but not exceeding 1 gigawatt £367,000
exceeding 1 gigawatt £367,000 + £30,000 for each additional 500 megawatts above 1 gigawatt

Savings

3

The 2019 Regulations continue to apply as they did immediately before 13 December 2022 in respect of any application made before that date—

Signed

MICHAEL MATHESON — A member of the Scottish Government — 1st November 2022

Explanatory note

(This note is not part of the Regulations)

EXPLANATORY NOTE

These Regulations amend the Electricity (Applications for Consent and Variation of Consent) (Fees) (Scotland) Regulations 2019 (“the 2019 Regulations”) in order to introduce revised levels of fees in respect of applications for consents and variations to consents under the Electricity Act 1989.

Regulation 3 ensures that any application made before these Regulations come into force will be subject to the 2019 Regulations as they were immediately before that date.

A Business and Regulatory Impact Assessment has been prepared and placed in the Scottish Parliament Information Centre. Copies can be obtained from Energy Consents Unit, 5 Atlantic Quay, 150 Broomielaw, Glasgow G2 8LU.

Footnotes

[^f00001]: 1989 c. 29. The functions of the Secretary of State under section 60(3) and paragraph 1(3) of schedule 8 were transferred to the Scottish Ministers by virtue of S.I. 1999/1750, article 2 and schedule 1. The functions of the Secretary of State under section 36(8) were transferred to the Scottish Ministers by virtue of S.I. 2006/1040, article 3.

[^f00002]: S.S.I. 2019/176.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.