  • (7) In this section " the prescribed exemption limit", subject to subsection (8) of this section, means 3,000 square feet; any reference to development relating to a building is a reference to development consisting of or including the erection, extension or alteration of the building or a change of use of the whole or part of the building; and any reference to an application pending on a particular date is a reference to an application made before that date and not withdrawn, where no planning decision on that application has been made before that date.
  • (8) The Secretary of State may by order direct that such number of square feet (whether greater or less than 3,000 but not less than 1,000) as may be specified in the order shall be the prescribed exemption limit for the purposes of this section, either generally or in relation to any particular area to which these provisions apply in accordance with section 74(4) of this Act or in relation to any particular part of such an area.

Mixed industrial and office development

76
  • (1) Subject to subsection (2) of this section and to paragraph 3 of Schedule 12 to this Act, these provisions shall have effect without prejudice to the operation of sections 67 and 68 of this Act; and, where these provisions and those sections are applicable to the same application for planning permission, the requirements of both must be complied with.
  • (2) Compliance with section 74(1) of this Act shall not be required in respect of an application for planning permission for the development of land in any manner specified in section 67(1) of this Act if—
  • (a) no office premises will result from the development except such as are comprised within the curtilage of an industrial building and are used or designed for use for providing services or facilities ancillary to the use of other premises in the same building or curtilage; and
  • (b) there has been issued by the Secretary of State and furnished to the local planning authority with the application a copy of an industrial development certificate with conditions attached to it by virtue of section 70(3)(b) of this Act.

Restrictions or conditions attached to office development permits

77
  • (1) An office development permit in respect of any development may be issued subject to such restrictions on the making of an application for planning permission for that development (whether as to the period within which, or the persons by whom, such an application may be made, or otherwise) as the Secretary of State considers appropriate in the exercise of his discretion as mentioned in section 74(3) of this Act; and, where an office development permit in respect of any development is issued subject to any such restrictions, and an application for planning permission for that development is made which does not comply with those restrictions, these provisions shall apply in relation to that application as if no such permit had been issued.
  • (2) Without prejudice to subsection (1) of this section, an office development permit may be issued either unconditionally or subject to such conditions as the Secretary of State considers appropriate in the exercise of his discretion as mentioned in section 74(3) of this Act; and any reference in these provisions to conditions attached to an office development permit is a reference to conditions subject to which such a permit is issued.
  • (3) In so far as any of the conditions attached to an office development permit are of such a description that (apart from this section) they could not have been imposed under this Act, this Act shall apply in relation to any application for planning permission for the purposes of which that permit is required, and to any planning permission granted on such an application, as if the powers conferred by this Act included power to impose conditions of that description.
  • (4) Where conditions are attached to an office development permit, and, on an application for planning permission for the purposes of which that permit is required, planning permission is granted, the authority granting the permission shall grant it subject to those conditions, with or without other conditions.
  • (5) Planning permission to which subsection (4) of this section applies shall not be invalid by reason only that the requirements of that subsection are not complied with; but where any such planning permission is granted without complying with the requirements of that subsection the planning permission shall be deemed to have been granted subject to lie conditions attached to the office development permit, or (if any other conditions were imposed by the authority granting the permission) to have been granted subject to the conditions attached to the permit in addition to the other conditions.

Planning permission for erection of building where no office development permit required

78
  • (1) The provisions of this section shall, subject to subsection (4) of this section, have effect with respect to any planning permission for the erection of a building on land which is within a controlled area when the planning permission is granted and was also within such an area when the application for planning permission was made.
  • (2) If the case is the following, that is to say—
  • (a) either the proposed erection of the building is not development to which these provisions apply or it is such development but no office development permit is required for it; and
  • (b) the building will have a floor space of twice or more than twice, the prescribed exemption limit,

the planning permission for the erection of the building shall be granted subject to the condition specified in subsection (3) of this section (in addition to any other conditions imposed by the authority granting the permission).

  • (3) The said condition is that the use of the building, whether as originally erected or as subsequently extended or altered, shall be restricted so that (whether in consequence of a change of use or otherwise) it does not at any time contain office premises having an aggregate office floor space which exceeds the prescribed exemption limit.
  • (4) In the following two cases this section shall not apply—
  • (a) where the planning permission is in respect of a building which is wholly residential; and
  • (b) where the planning permission is subject to conditions by virtue of section 70(5) or (6) of this Act and those conditions either restrict the office floor space which the building may contain or preclude it from containing any office floor space.

Planning permission for alteration or extension of building where no office development permit required

79
  • (1) The provisions of this section shall, subject to subsection (4) of this section, have effect with respect to any planning permission for the alteration or extension of a building on land which is within a controlled area when the planning permission is granted and was also within such an area when the application for planning permission was made, but shall have effect only in the case of a building erected under a planning permission granted on or after 1st April 1969.
  • (2) If the case is the following, that is to say—
  • (a) either the erection of the building was not development to which these provisions (or Part I of the Act of 1965) applied, or it was such development but no office development permit was required for it; and
  • (b) either the proposed alteration or extension is not development to which these provisions apply or it is such development but no office development permit is required for it; and
  • (c) there will result from the proposed alteration or extension a building with an aggregate floor space of twice, or more than twice, the prescribed exemption limit,

the planning permission for the alteration or extension shall be granted subject to the condition specified in subsection (3) of this section (in addition to any other conditions imposed by the authority granting the permission).

  • (3) The said condition is that the use of the building as altered or extended, or as subsequently further altered or extended, shall be restricted so that (whether in consequence of a change of use or otherwise) it does not at any time contain office premises having an aggregate office floor space which exceeds the prescribed exemption limit.
  • (4) In the following two cases this section shall not apply—
  • (a) where the planning permission is in respect of a building which, after its alteration or extension, will be wholly residential; and
  • (b) where the planning permission is subject to conditions by virtue of section 70(5) or (6) of this Act and those conditions either restrict the office floor space which the building as extended or altered may contain or preclude it from containing any office floor space.

Planning permission for erection of two or more buildings where no office development permit required

80
  • (1) The provisions of this section shall have effect with respect to any planning permission for development involving the erection of two or more buildings on land which is within a controlled area when the planning permission is granted and was also within such an area when the application for planning permission was made, except in a case where all the buildings are exempt from this section.
  • (2) Any one of the said buildings shall be exempt from this section if—
  • (a) it is wholly residential; or
  • (b) the planning permission is subject to conditions by virtue of section 70(5) or (6) of this Act and those conditions either restrict the office floor space which the building may contain or preclude it from containing any office floor space.
  • (3) If the aggregate floor space of the buildings proposed to be erected (leaving out of account any which are exempt from this section) is twice, or more than twice, the prescribed exemption limit, and either the erection of the buildings is not development to which these provisions apply or it is such development but no office development permit is required for it, the planning permission shall be granted subject to the condition specified in subsection (4) of this section (in addition to any other conditions imposed by the authority granting the permission).
  • (4) The said condition is that the use of each one of the buildings (excluding any which are exempt from this section) shall be restricted so that (whether in consequence of "a change of use or otherwise) it does not at any time contain office premises having an aggregate floor space which exceeds the limit for that building specified in the condition, which limit shall (subject to subsection (5) of this section) be a floor space bearing such proportion to the building's total floor space as the prescribed exemption limit bears to the aggregate floor space of all the buildings (excluding any which are exempt from this section) for whose erection the planning permission is granted.
  • (5) The authority granting the planning permission may in doing so specify in the said condition, as it applies to any building, a limit differing from the one provided by subsection (4) of this section, but not so that the total of the limits for all the buildings to which the condition applies exceeds the prescribed exemption limit.
  • (6) If after the grant of the planning permission a further application for planning permission is made in respect of all or any of the buildings to which the condition specified in subsection (4) of this section applies, and the further application involves a departure from the terms of the said condition as applying to any building, the application shall be subject to section 74(1) of this Act notwithstanding anything in these provisions exempting development from the requirements of that section in particular cases.

Provisions supplementary to ss.78 to 80

81
  • (1) Any planning permission with respect to which section 78, 79 or 80 of this Act has effect shall not be invalid by reason only that the requirements of section 78(2), 79(2) or 80(3) of this Act, as the case may be, are not complied with; but in that case the planning permission shall be deemed to have been granted subject to the condition specified in section 78(3), 79(3) or 80(4) of this Act, as the case may be, or (if any other conditions are imposed by the authority granting the permission) to have been granted subject to the condition so specified in addition to the other conditions, and references in those sections to a condition imposed thereunder shall be construed accordingly as including references to a condition deemed to be imposed.
  • (2) In sections 78, 79 and 80 of this Act—
  • " controlled area " means an area to which these provisions apply, or, as respects any time before the commencement of this Act, Part I of the Act of 1965 applied;
  • " the prescribed exemption limit " means that number of square feet which, at the time when the planning permission in question is granted, is for the purposes of section 75 of this Act the prescribed exemption limit in relation to the land to which the planning permission relates, whether— by virtue of subsection (7) of that section, or if an order under subsection (8) of that section is for the time being in force and applies to the area, or part of an area, in which that land is situated, by virtue of that order;
  • " wholly residential " in relation to a building, means for use exclusively as a dwellinghouse or comprising only units of accommodation for such use.

Provisions as to conditions imposed or implied in pursuance of these provisions

82
  • (1) This section applies to any condition subject to which planning permission is granted in accordance with these provisions or subject to which planning permission is by virtue of these provisions deemed to have been granted, whether or not it is a condition which could have been imposed apart from these provisions.
  • (2) If the planning permission is or was granted by the local planning authority, the Secretary of State shall not be required to entertain an appeal under section 36 of this Act from the decision of the local planning authority, in so far as that decision relates or related to any condition to which this section applies.
  • (3) Where planning permission is granted subject to a condition to which this section applies, and it appears to the authority granting the permission that the condition could have been imposed apart from these provisions and would have been imposed if these provisions had not been enacted, the decision granting the permission may include a certificate to that effect; and, where such a certificate is included in a decision of the local planning authority—
  • (a) the Secretary of State shall not be required to entertain an appeal from the decision in so far as it includes the certificate; but
  • (b) subject to the preceding paragraph, section 36 of this Act shall have effect in relation to the certificate as it has effect in relation to any other part of the decision.
  • (4) If any condition imposed by an authority granting planning permission is inconsistent with any condition to which this section applies, the last-mentioned condition shall prevail in so far as it is inconsistent with the condition so imposed.
  • (5) Where on an application made as mentioned in section 32(1) of this Act (as modified by section 74(2) of this Act) planning permission is granted (either unconditionally or subject to conditions) for a building to be retained, or a use of a building to be continued, without complying with a condition to which this section applies (that condition being one subject to which a previous planning permission was granted or is deemed to have been granted), nothing in sections 77 to 81 of this Act or in the preceding provisions of this section shall be construed as preventing the subsequent planning permission from operating so as to extinguish or modify that condition, as the case may be.

Development in metropolitan region: planning permission granted before passing of Act of 1965

83

Schedule 12 to this Act shall have effect as respects planning permission granted before 5th August 1965 (the date of the passing of the Act of 1965) in the cases mentioned in that Schedule.

Annual report

84

As soon as may be after the end of March in each year the Secretary of State shall prepare a report on the performance of his functions under these provisions, and shall lay the report before Parliament.

Interpretation of these provisions

85
  • (1) In these provisions—
  • " the Act of 1965 " means the Control of Office and Industrial Development Act 1965 ;
  • " building " includes any structure;
  • " building contract " means a contract (other than a lease) which is made in relation to land whereby a person undertakes to erect or extend a building on that land in the course of the carrying on by him of a business consisting wholly or mainly of the execution of building operations, or of building operations and engineering operations;
  • " erection ", in relation to a building, includes re-erection ;
  • " the metropolitan region ", subject to subsection (2) of this section, means Greater London together with the areas specified in Schedule 13 to this Act;
  • " premises " means a part of a building;
  • " these provisions " has the meaning assigned to it by section 73(7) of this Act.
  • (2) For the purposes of these provisions—
  • (a) land shall be taken to be, and at all material times to have been, in Greater London if it is in the area which constituted Greater London on 1st April 1965 ;
  • (b) land shall be taken to be, and at all material times to have been, in an area specified by name in Schedule 13 to this Act if it is in the area bearing that name on 1st April 1965 as that area was constituted on that date.
  • (3) In these provisions " office floor space" means gross floor space comprised in office premises; and for the purposes of these provisions the amount of any such space shall be ascertained by external measurement of that space, whether the office premises in question are or are to be bounded (wholly or partly) by external walls of a building or not.
  • (4) In these provisions any reference to the granting of planning permission for the carrying out of any development of land is a reference to the granting of planning permission for that development—
  • (a) either in respect of that land taken by itself or in respect of that land together with other land; and
  • (b) either on an ordinary application or on an outline application (that is to say, an application for planning permission subject to subsequent approval on any matters).
  • (5) In these provisions any reference to a building containing office premises includes a reference to a building of which every part consists or is to consist of office premises; and in these provisions any reference to the addition of office premises includes a reference to the addition of office premises together with other premises.
  • (6) In these provisions any reference to land in Greater London, within the metropolitan region, or within any other area to which these provisions apply or, as respects any time before the commencement of this Act, the Act of 1965 applied, shall be construed as a reference to land of which any part is within the area in question.
  • (7) In these provisions any reference to an application made as mentioned in section 32(1) of this Act includes a reference to an application which by virtue of section 88(7) or 95(6) of this Act is deemed to have been made for such planning permission as is mentioned in the said section 88(7) or, as the case may be, the said section 95(6).

Temporary operation of these provisions

86
  • (1) Unless Parliament otherwise determines, these provisions (other than this section) shall cease to have effect at the end of the period of seven years beginning with 5th August 1965.
  • (2) Where immediately before the end of that period any planning permission has effect subject to a condition subject to which the planning permission is by virtue of these provisions deemed to have been granted, the planning permission shall, as from the end of that period, have effect free from that condition.
  • (3) Where immediately before the end of that period any planning permission has effect subject to a condition imposed by the authority granting the permission in circumstances where that authority was required by these provisions to impose that condition, then unless the condition is the subject of a certificate under section 82(3) of this Act, the planning permission shall, as from the end of that period, have effect free from that condition.
  • (4) An enforcement notice to which paragraph 4 of Schedule 12 to this Act applies shall not operate so as to prevent or restrict the doing of anything after the end of that period.
  • (5) Subject to the preceding provisions of this section, at the end of that period section 38(2) of the Interpretation Act 1889 (effect of repeals) shall apply as if these provisions had, as from the end of that period, been repealed by another Act.

PART V — Enforcement of Control under Parts III and IV

Development requiring planning permission

Power to serve enforcement notice

87
  • (1) Where it appears to the local planning authority that there has been a breach of planning control after the end of 1963, then, subject to any directions given by the Secretary of State and to the following provisions of this section, the authority, if they consider it expedient to do so having regard to the provisions of the development plan and to any other material considerations, may serve a notice under this section (in this Act referred to as an " enforcement notice ") requiring the breach to be remedied.
  • (2) There is a breach of planning control if development has been carried out, whether before or after the commencement of this Act, without the grant of planning permission required in that behalf in accordance with Part III of the Act of 1962 or Part III of this Act, or if any conditions or limitations subject to which planning permission was granted have not been complied with.
  • (3) Where an enforcement notice relates to a breach of planning control consisting in—
  • (a) the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land ; or
  • (b) the failure to comply with any condition or limitation which relates to the carrying out of such operations and subject to which planning permission was granted for the development of that land ; or
  • (c) the making without planning permission of a change of use of any building to use as a single dwellinghouse,

it may be served only within the period of four years from the date of the breach.

  • (4) An enforcement notice shall be served on the owner and on the occupier of the land to which it relates and on any other person having an interest in that land, being an interest which in the opinion of the authority is materially affected by the notice.
  • (5) Where planning permission has effect subject to a condition to which section 82 of this Act applies, and by reason of anything done in a particular part of a building that condition is contravened, any enforcement notice relating to the contravention shall be taken to be served on the owner and on the occupier of the land to which it relates if it is served on the owner and on the occupier of that part of the building, whether it is also served on any other person or not.
  • (6) An enforcement notice shall specify—
  • (a) the matters alleged to constitute a breach of planning control;
  • (b) the steps required by the authority to be taken in order to remedy the breach, that is to say steps for the purpose of restoring the land to its condition before the development took place or (according to the particular circumstances of the breach) of securing compliance with the conditions or limitations subject to which planning permission was granted; and
  • (c) the period for compliance with the notice, that is to say the period (beginning with the date when the notice takes effect) within which those steps are required to be taken.
  • (7) The steps which may be required by an enforcement notice to be taken include the demolition or alteration of any buildings or works, the discontinuance of any use of land, or the carrying out on land of any building or other operations.
  • (8) Subject to section 88 of this Act, an enforcement notice shall take effect at the end of such period, not being less than twenty-eight days after the service of the notice, as may be specified in the notice.
  • (9) The local planning authority may withdraw an enforcement notice (without prejudice to their power to serve another) at any time before it takes effect; and, if they do so, they shall forthwith give notice of the withdrawal to every person who was served with the notice.

Appeal against enforcement notice

88
  • (1) A person on whom an enforcement notice is served, or any other person having an interest in the land may, at any time within the period specified in the notice as the period at the end of which it is to take effect, appeal to the Secretary of State against the notice on any of the following grounds—
  • (a) that planning permission ought to be granted for the development to which the notice relates or, as the case may be, that a condition or limitation alleged in the enforcement notice not to have been complied with ought to be discharged ;
  • (b) that the matters alleged in the notice do not constitute a breach of planning control;
  • (c) in the case of a notice which, by virtue of section 87(3) of this Act, may be served only within the period of four years from the date of the breach of planning control to which the notice relates, that that period has elapsed at the date of service ;
  • (d) in the case of a notice not falling within paragraph (c) of this subsection, that the breach of planning control alleged by the notice occurred before the beginning of 1964;
  • (e) that the enforcement notice was not served as required by section 87(4) of this Act;
  • (f) that the steps required by the notice to be taken exceed what is necessary to remedy any breach of planning control;
  • (g) that the specified period for compliance with the notice falls short of what should reasonably be allowed.
  • (2) An appeal under this section shall be made by notice in writing to the Secretary of State, which shall indicate the grounds of the appeal and state the facts on which it is based; and on any such appeal the Secretary of State shall, if either the appellant or the local planning authority so desire, afford to each of them an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.
  • (3) Where an appeal is brought under this section, the enforcement notice shall be of no effect pending the final determination or the withdrawal of the appeal.
  • (4) On an appeal under this section—
  • (a) the Secretary of State may correct any informality, defect or error in the enforcement notice if he is satisfied that the informality, defect or error is not material;
  • (b) in a case where it would otherwise be a ground for determining the appeal in favour of the appellant that a person required by section 87(4) of this Act to be served with the notice was not served, the Secretary of State may disregard that fact if neither the appellant nor that person has been substantially prejudiced by the failure to serve him.
  • (5) On the determination of an appeal under this section, the Secretary of State shall give directions for giving effect to his determination, including, where appropriate, directions for quashing the enforcement notice or for varying the terms of the notice in favour of the appellant; and the Secretary of State may—
  • (a) grant planning permission for the development to which the enforcement notice relates or, as the case may be, discharge any condition or limitation subject to which planning permission for that development was granted;
  • (b) determine any purpose for which the land may, in the circumstances obtaining at the time of the determination, be lawfully used having regard to any past use thereof and to any planning permission relating to the land.
  • (6) In considering whether to grant planning permission under subsection (5) of this section, the Secretary of State shall have regard to the provisions of the development plan, so far as material to the subject-matter of the enforcement notice, and to any other material considerations; and any planning permission granted by him under that subsection may—
  • (a) include permission to retain or complete any buildings or works on the land, or to do so without complying with some condition attached to a previous planning permission;
  • (b) be granted subject to such conditions as the Secretary of State thinks fit;

and where under that subsection he discharges a condition or limitation, he may substitute another condition or limitation for it, whether more or less onerous.

  • (7) Where an appeal against an enforcement notice is brought under this section, the appellant shall be deemed to have made an application for planning permission for the development to which the notice relates and, in relation to any exercise by the Secretary of State of his powers under subsection (5) of this section, the following provisions shall have effect—
  • (a) any planning permission granted thereunder shall be treated as granted on the said application ;
  • (b) in relation to a grant of planning permission or a determination under that subsection, the Secretary of State's decision shall be final; and
  • (c) for the purposes of section 34 of this Act, the decision shall be treated as having been given by the Secretary of State in dealing with an application for planning permission made to the local planning authority.
  • (8) On an appeal under this section against an enforcement notice relating to anything done in contravention of a condition to which section 71 or 82 of this Act applies, the Secretary of State shall not be required to entertain the appeal in so far as the appellant claims that planning permission free from that condition ought to be granted.
  • (9) Schedule 9 to this Act applies to appeals under this section, including appeals under this section as applied by regulations under any other provision of this Act.

Penalties for non-compliance with enforcement notice

89
  • (1) Subject to the provisions of this section, where an enforcement notice has been served on the person who, at the time when the notice was served on him, was the owner of the land to which it relates, then, if any steps required by the notice to be taken (other than the discontinuance of a use of land) have not been taken within the period allowed for compliance with the notice, that person shall be liable on summary conviction to a fine not exceeding £400 or on conviction on indictment to a fine.
  • (2) If a person against whom proceedings are brought under subsection (1) of this section has, at some time before the end of the period allowed for compliance with the notice, ceased to be the owner of the land, he shall, upon information duly laid by him, and on giving to the prosecution not less than three clear days' notice of his intention, be entitled to have the person who then became the owner of the land (in this section referred to as "the subsequent owner") brought before the court in the proceedings.
  • (3) If, after it has been proved that any steps required by the enforcement notice have not been taken within the period allowed for compliance with the notice, the original defendant proves that the failure to take those steps were attributable, in whole or in part, to the default of the subsequent owner—
  • (a) the subsequent owner may be convicted of the offence; and
  • (b) the original defendant, if he further proves that he took all reasonable steps to secure compliance with the enforcement notice, shall be acquitted of the offence.
  • (4) If, after a person has been convicted under the preceding provisions of this section, he does not as soon as practicable do everything in his power to secure compliance with the enforcement notice, he shall be guilty of a further offence and liable—
  • (a) on summary conviction to a fine not exceeding £50 for each day following his first conviction on which any of the requirements of the enforcement notice (other than the discontinuance of the use of land) remain unfulfilled; or
  • (b) on conviction on indictment to a fine.
  • (5) Where, by virtue of an enforcement notice, a use of land is required to be discontinued, or any conditions or limitations are required to be complied with in respect of a use of land or in respect of the carrying out of operations thereon, then if any person uses the land or causes or permits it to be used, or carries out those operations or causes or permits them to be carried out, in contravention of the notice, he shall be guilty of an offence, and shall be liable on summary conviction to a fine not exceeding £400, or on conviction on indictment to a fine; and if the use is continued after the conviction he shall be guilty of a further offence and liable on summary conviction to a fine not exceeding £50 for each day on which the use is so continued, or on conviction on indictment to a fine.
  • (6) Any reference in this section to the period allowed for compliance with an enforcement notice is a reference to the period specified in the notice for compliance therewith or such extended period as the local planning authority may allow for compliance with the notice.

Power to stop further development pending proceedings on enforcement notice

90
  • (1) Where in respect of any land the local planning authority have served an enforcement notice, they may at any time before the notice takes effect serve a further notice (in this Act referred to as a " stop notice ") referring to, and having annexed to it a copy of, the enforcement notice and prohibiting any person on whom the stop notice is served from carrying out or continuing any specified operations on the land, being operations either alleged in the enforcement notice to constitute a breach of planning control or so closely associated therewith as to constitute substantially the same operations.
  • (2) The operations which may be the subject of a stop notice shall include the deposit of refuse or waste materials on land where that is a breach of planning control alleged in the enforcement notice.
  • (3) A stop notice may be served by the local planning authority on any person who appears to them to have an interest in the land or to be concerned with the carrying out or continuance of any operations thereon.
  • (4) A stop notice—
  • (a) shall specify the date (not being earlier than three nor later than fourteen days from the day on which the notice is first served on any person) when it is to take effect;
  • (b) in relation to any person served with it, shall have effect as from that date or the third day after the date of service on him, whichever is the later; and
  • (c) shall, without prejudice to subsection (7) of this section, cease to have effect when the enforcement notice takes effect or is withdrawn or quashed.
  • (5) If while a stop notice has effect in relation to him a person carries out, or causes or permits to be carried out, any operations prohibited by the notice, he shall be guilty of an offence and liable on summary conviction to a fine not exceeding £400, or on conviction on indictment to a fine; and if the offence is continued after conviction he shall be guilty of a further offence and liable on summary conviction to a fine not exceeding £50 for each day on which the offence is continued, or on conviction on indictment to a fine.
  • (6) A stop notice shall not be invalid by reason that the enforcement notice to which it relates was not served as required by section 87(4) of this Act if it is shown that the local planning authority took all such steps as were reasonably practicable to effect proper service.
  • (7) The local planning authority may at any time withdraw a stop notice (without prejudice to their power to serve another) by serving notice to that effect on persons who were served with the stop notice; and the stop notice shall cease to have effect as from the date of service of the notice under this subsection.
  • (8) Where a person (in this subsection called " the contractor ") is under contract to another person (in this subsection called " the developer ") to carry out any operations on land and—
  • (a) a stop notice takes effect (whether in relation to the developer or the contractor, or both) prohibiting the carrying out or continuance of those operations; and
  • (b) the operations are countermanded, or discontinued by the contractor accordingly,

then, unless and in so far as the contract makes, provision explicitly to the contrary of this subsection, the developer shall be under the same liability in contract as if the operations had been countermanded or discontinued on instructions given by him in breach of the contract.

This subsection applies only to contracts entered into before the end of 1969.

Execution and cost of works required by enforcement notice

91
  • (1) If, within the period specified in an enforcement notice for compliance therewith, or within such extended period as the local planning authority may allow, any steps required by the notice to be taken (other than the discontinuance of a use of land) have not been taken, the local planning authority may enter the land and take those steps, and may recover from the person who is then the owner of the land any expenses reasonably incurred by them in doing so.
  • (2) Any expenses incurred by the owner or occupier of any land for the purpose of complying with an enforcement notice served in respect of any breach of planning control (as defined in section 87(2) of this Act) and any sums paid by the owner of any land under subsection (1) of this section in respect of expenses incurred by the local planning authority in taking steps required by such a notice to be taken, shall be deemed to be incurred or paid for the use and at the request of the person by whom the breach of planning control was committed.
  • (3) Regulations made under this Act may provide that, in relation to any steps required to be taken by an enforcement notice, all or any of the enactments specified in subsection (4) of this section shall apply, subject to such adaptations and modifications as may be specified in the regulations, including, in the case of the enactment specified in paragraph (b) of that subsection, adaptations and modifications for the purpose of affording to the owner of land to which an enforcement notice relates the right, as against all other persons interested in the land, to comply with the requirements of the enforcement notice.
  • (4) The said enactments are the following provisions of the Public Health Act 1936, that is to say—
  • (a) section 276 (power of local authorities to sell materials removed in executing works under that Act subject to accounting for the proceeds of sale);
  • (b) section 289 (power to require the occupier of any premises to permit works to be executed by the owner of the premises);
  • (c) section 292 (power of local authorities to include a sum in respect of establishment charges in their expenses in executing works); and
  • (d) section 294 (limit on liability of persons holding premises as agents or trustees in respect of the expenses recoverable under that Act).
  • (5) Any regulations made in accordance with subsection (3) of this section may provide for the charging on the land of any expenses recoverable by a local authority under subsection (1) of this section.

Effect of planning permission on enforcement notice

92
  • (1) If, after the service of an enforcement notice, planning permission is granted for the retention on land of buildings or works, or for the continuance of a use of land, to which the enforcement notice relates, the enforcement notice shall cease to have effect in so far as it requires steps to be taken for the demolition or alteration of those buildings or works, or the discontinuance of that use, as the case may be.
  • (2) If the planning permission granted as mentioned in sub section (1) of this section is granted so as to permit the retention of buildings or works, or the continuance of a use of land, without complying with some condition subject to which a previous planning permission was granted, the enforcement notice shall cease to have effect in so far as it requires steps to be taken for complying with that condition.
  • (3) The preceding provisions of this section shall be without prejudice to the liability of any person for an offence in respect of a failure to comply with the enforcement notice before the relevant provision of the enforcement notice ceased to have effect.

Enforcement notice to have effect against subsequent development

93
  • (1) Compliance with an enforcement notice, whether in respect of—
  • (a) the demolition or alteration of any buildings or works; or
  • (b) the discontinuance of any use of land,

or in respect of any other requirements contained in the enforcement notice, shall not discharge the enforcement notice.

  • (2) Without prejudice to subsection (1) of this section, any provision of an enforcement notice requiring a use of land to be discontinued shall operate as a requirement that it shall be discontinued permanently, to the extent that it is in contravention of Part III of this Act; and accordingly the resumption of that use at any time after it has been discontinued in compliance with the enforcement notice shall to that extent be in contravention of the enforcement notice.
  • (3) Without prejudice to subsection (1) of this section, if any development is carried out on land by way of reinstating or restoring buildings or works which have been demolished or altered in compliance with an enforcement notice, the notice shall, notwithstanding that its terms are not apt for the purpose, be deemed to apply in relation to the buildings or works as reinstated or restored as it applied in relation to the buildings or works before they were demolished or altered; and, subject to subsection (4) of this section, the provisions of section 91(1) and (2) of this Act, shall apply accordingly.
  • (4) Where, at any time after an enforcement notice takes effect—
  • (a) any development is carried out on land by way of reinstating or restoring buildings or works which have been demolished or altered in compliance with the notice; and
  • (b) the local planning authority propose, under section 91(1) of this Act, to take any steps required by the enforcement notice for the demolition or alteration of the buildings or works in consequence of the reinstatement or restoration,

the local planning authority shall, not less than twenty-eight days before taking any such steps, serve on the owner and occupier of the land a notice of their intention to do so.

  • (5) A person who, without the grant of planning permission in that' behalf, carries out any development on land by way of reinstating or restoring buildings or works which have been demolished or altered in compliance with an enforcement notice shall be guilty of an offence, and shall be liable on summary conviction to a fine not exceeding £400; and no person shall be liable under any of the provisions of section 89(1) to (4) of this Act for failure to take any steps required to be taken by an enforcement notice by way of demolition or alteration of what has been so reinstated or restored.

Certification of established use

94
  • (1) For the purposes of this Part of this Act, a use of land is established if—
  • (a) it was begun before the beginning of 1964 without planning permission in that behalf and has continued since the end of 1963 ; or
  • (b) it was begun before the beginning of 1964 under a planning permission in that behalf granted subject to conditions or limitations, which either have never been complied with or have not been complied with since the end of 1963 ; or
  • (c) it was begun after the end of 1963 as the result of a change of use not requiring planning permission and there has been, since the end of 1963, no change of use requiring planning permission.
  • (2) Where a person having an interest in land claims that a particular use of it has become established, he may apply to the local planning authority for a certificate (in this Act referred to as an " established use certificate ") to that effect:

Provided that no such application may be made in respect of the use of land as a single dwellinghouse, or of any use not subsisting at the time of the application.

  • (3) An established use certificate may be granted (either by the local planning authority or, under section 95 of this Act, by the Secretary of State)—
  • (a) either for the whole of the land specified in the application, or for a part of it;
  • (b) in the case of an application specifying two or more uses, either for all those uses or for some one or more of them.
  • (4) On an application to them under this section, the local planning authority shall, if and so far as they are satisfied that the applicant's claim is made out, grant to him an established use certificate accordingly; and if and so far as they are not so satisfied, they shall refuse the application.
  • (5) Where an application is made to a local planning authority for an established use certificate, then unless within such period as may be prescribed by a development order, or within such extended period as may at any time be agreed upon in writing between the applicant and the local planning authority, the authority give notice to the applicant of their decision on the application, then, for the purposes of section 95(2) of this Act, the application shall be deemed to be refused.
  • (6) Schedule 14 to this Act shall have effect with respect to established use certificates and applications therefor and to appeals under section 95 of this Act.
  • (7) An established use certificate shall, as respects any matters stated therein, be conclusive for the purposes of an appeal to the Secretary of State against an enforcement notice served in respect of any land to which the certificate relates, but only where the notice is served after the date of the application on which the certificate was granted.
  • (8) If any person, for the purpose of procuring a particular decision on an application (whether by himself or another) for an established use certificate or on an appeal arising out of such an. application—
  • (a) knowingly or recklessly makes a statement which is false in a material particular; or
  • (b) with intent to deceive, produces, furnishes, sends or otherwise makes use of any document which is false in a material particular; or
  • (c) with intent to deceive, withholds any material information,

he shall be guilty of an offence and liable on summary conviction to a fine not exceeding £400 or, on conviction on indictment, to imprisonment for a term not exceeding two years or a fine, or both.

Grant of certificate by Secretary of State on referred application or appeal against refusal

95
  • (1) The Secretary of State may give directions requiring applications for established use certificates to be referred to him instead of being dealt with by local planning authorities; and, on any such application being referred to him in accordance with such directions, section 94(4) of this Act shall apply in relation to the Secretary of State as it applies in relation to the local planning authority in the case of an application determined by them.
  • (2) Where an application is made to a local planning authority for an established use certificate and is refused, or is refused in part, the applicant may by notice under this subsection appeal to the Secretary of State; and on any such appeal the Secretary of State shall—
  • (a) if and so far as he is satisfied that the authority's refusal is not well-founded, grant to the appellant an established use certificate accordingly or, as the case may be, modify the certificate granted by the authority on the application; and
  • (b) if and so far as he is satisfied that the authority's refusal is well-founded, dismiss the appeal.
  • (3) On an application referred to him under subsection (1) of this section or on an appeal to him under subsection (2) of this section, the Secretary of State may, in respect of any use of land for which an established use certificate is not granted (either by him or by the local planning authority), grant planning permission for that use or, as the case may be, for the continuance of that use without complying with some condition subject to which a previous planning permission was granted.
  • (4) Before determining an application or appeal under this section the Secretary of State shall, if either the applicant or appellant (as the case may be) or the local planning authority so desire, afford to each of them an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.
  • (5) The decision of the Secretary of State on an application referred to him, or on an appeal, under this section shall be final.
  • (6) In the case of any use of land for which the Secretary of State Has power to grant planning permission under this section, the applicant or appellant shall be deemed to have made an application for such planning permission; and any planning permission so granted shall be treated as granted on the said application.
  • (7) Schedule 9 to this Act applies to appeals under this section.

Listed buildings

Power to serve listed building enforcement notice

96
  • (1) Where it appears to the local planning authority that any works have been, or are being, executed to a listed building in .their area and are such as to involve a contravention of section 55(1) or (4) of this Act, then, subject to any directions given by the Secretary of State, they may, if they consider it expedient to do so having regard to the effect of the works on the character of the building as one of special architectural or historic interest, serve a notice—
  • (a) specifying the alleged contravention ; and
  • (b) requiring such steps as may be specified in the notice for restoring that building to its former state or, as the case may be, for bringing it to the state it would have been in if the terms and conditions of any fisted building consent for the works had been complied with, to be taken within such period as may be so specified.
  • (2) A notice under this section is in this Act referred to as a " listed building enforcement notice
  • (3) A listed building enforcement notice shall be served on the owner and on the occupier of the building to which it relates and on any other person having an interest in the building, being an interest which in the opinion of the authority is materially affected by the notice.
  • (4) Subject to section 97 of this Act, a listed building enforcement notice shall take effect at the end of such period, not being less than twenty-eight days after the service of the notice, as may be specified in the notice.
  • (5) The local planning authority may withdraw a listed building enforcement notice (without prejudice to their power to serve another) at any time before it takes effect; and if they do so, they shall forthwith give notice of the withdrawal to every person who was served with the notice.

Appeal against listed building enforcement notice

97
  • (1) A person on whom a listed building enforcement notice is served, or any other person having an interest in the building to which it relates, may, at any time within the period specified in the notice as the period at the end of which it is to take effect, appeal to the Secretary of State against the notice on any of the following grounds—
  • (a) that the building is not of special architectural or historic interest;
  • (b) that the matters alleged to constitute a contravention of section 55 of this Act do not involve such a contravention ;
  • (c) that the works were urgently necessary in the interests of safety or health, or for the preservation of the building;
  • (d) that listed building consent ought to be granted for the works, or that any relevant condition of such consent which has been granted ought to be discharged, or different conditions substituted ;
  • (e) that the notice was not served as required by section 96(3) of this Act;
  • (f) that the requirements of the notice exceed what is necessary for restoring the building to its condition before the works were carried out;
  • (g) that the period specified in the notice as the period within which any steps required thereby are to be taken falls short of what should reasonably be allowed;
  • (h) that the steps required by the notice to be taken would not serve the purpose of restoring the character of the building to its former state.
  • (2) An appeal under this section shall be made by notice in writing to the Secretary of State, which shall indicate the grounds of appeal and state the facts on which it is based; and on any such appeal the Secretary of State shall, if either the appellant or the local planning authority so desire, afford to each of them an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.
  • (3) Where an appeal is brought under this section the notice shall be of no effect pending the final determination or withdrawal of the appeal.
  • (4) On an appeal under this section,—
  • (a) the Secretary of State may correct any informality, defect or error in the notice if he is satisfied that the informality, defect or error is not material;
  • (b) in a case where it would otherwise be a ground for determining the appeal in favour of the appellant that a person required by section 96(3) of this Act to be served with the notice was not served, the Secretary of State may disregard that fact if he is satisfied that the person has not been substantially prejudiced by the failure to serve him.
  • (5) On the determination of an appeal under this section the Secretary of State shall give directions for giving effect to his determination, including, where appropriate, directions for quashing the listed building enforcement notice or for varying the terms of the notice in favour of the appellant, and the Secretary of State may—
  • (a) grant listed building consent for the works to which the notice relates or, as the case may be, discharge any condition subject to which such consent was granted and substitute any other condition, whether more or less onerous;
  • (b) in so far as any works already executed constitute development for which planning permission is required, grant such permission in respect of the works;
  • (c) if he thinks fit, exercise his power under section 54 of this Act to amend any list compiled or approved thereunder by removing from it the building to which the appeal relates or his power under subsection (10) of that section to direct that that subsection shall no longer apply to the building.
  • (6) Any planning permission granted by the Secretary of State under subsection (5) of this section shall be treated as granted on an; application for the like permission under Part III of this Act, and any listed building consent granted by him thereunder shall be treated as granted on an application for the like consent under Part I of Schedule 11 to this Act; and—
  • (a) in relation to the grant thereunder either of planning permission or of listed building consent., the Secretary of State's decision shall be final;
  • (b) for the purposes of section 34 of this Act a decision of the Secretary of State to grant planning permission shall be treated as having been given by him in dealing with an application for planning permission made to the local planning authority.
  • (7) Schedule 9 to this Act applies to appeals under this section.

Penalties for non-compliance with listed building enforcement notice

98
  • (1) Subject to the provisions of this section, where a listed building enforcement notice has been served on the person who, at the time when the notice was served on him, was the owner of the building to which it relates, then, if any steps required by the notice to be taken have not been taken within the period allowed for compliance with the notice, that person shall be guilty of an offence and liable on summary conviction to a fine not exceeding £400, or on conviction on indictment to a fine.
  • (2) If a person against whom proceedings have been brought under subsection (1) of this section has, at some time before the end of the period allowed for compliance with the notice, ceased to be the owner of the building, he shall, upon information duly laid by him, and on giving to the prosecution not less than three clear days' notice of his intention, be entitled to have the person who then became the owner of the building (in this section referred to as " the subsequent owner ") brought before the court in the proceedings.
  • (3) If, after it has been proved that any steps required by the notice have not been taken within the period allowed for compliance with the notice, the original defendant proves that the failure to take those steps was attributable, in whole or in part, to the default of the subsequent owner—
  • (a) the subsequent owner may be convicted of the offence; and
  • (b) the original defendant, if he further proves that he took all reasonable steps to secure compliance with the notice, shall be acquitted of the offence.
  • (4) If, after a person has been convicted under the preceding provisions of this section, he does not as soon as practicable do everything in his power to secure compliance with the notice, he shall be guilty of a further offence and be liable—
  • (a) on summary conviction to a fine not exceeding £50 for each day following his first conviction on which any of the requirements of the notice remain unfulfilled ; or
  • (b) on conviction on indictment to a fine.
  • (5) Any reference in this section to the period allowed for compliance with a listed building enforcement notice is a reference to the period specified in the notice as that within which the steps specified in the notice are required thereby to be taken, or such extended period as the local planning authority may allow for taking them.

Execution and cost of works required by listed building enforcement notice

99
  • (1) If, within the period specified in a listed building enforcement notice as that within which the steps specified in the notice are required thereby to be taken, or within such extended period as the local planning authority may allow, any steps required by the notice to be taken have not been taken, the authority may enter the land and take those steps, and may recover from the person who is then the owner of the land any expenses reasonably incurred by them in doing so.
  • (2) Any expenses incurred by the owner or occupier of a building for the purpose of complying with a listed building enforcement notice, and any sums paid by the owner of a building under subsection (1) of this section in respect of expenses incurred by the local planning authority in taking steps required by such a notice to be taken, shall be deemed to be incurred or paid for the use and at the request of the person who carried out the works to which the notice relates.
  • (3) The provisions of section 91(3) and (4) of this Act shall apply in relation to a listed building enforcement notice as they apply in relation to an enforcement notice; and any regulations made by virtue of this subsection may provide for the charging on the land on which the building stands of any expenses recoverable by a local planning authority under subsection (1) of this section.

Enforcement by, or by direction of, the Secretary of State

100
  • (1) If it appears to the Secretary of State, after consultation with the local planning authority (and, in Greater London, also with the Greater London Council), to be expedient that a listed building enforcement notice should be served in respect of any land, he may give directions to the local planning authority requiring them to serve such a notice, or may himself serve such a notice; and any notice so served by the Secretary of State shall have the like effect as a notice served by the local planning authority.
  • (2) In relation to a listed building enforcement notice served by the Secretary of State, the provisions of section 99 of this Act shall apply as if for any reference therein to the local planning authority there were substituted a reference to the Secretary of State.

Works for preservation of unoccupied listed building in cases of urgency

101

If it appears to a local authority that any works are urgently necessary for the preservation of any unoccupied building situated in their area which—

  • (a) is included in a list compiled or approved under section 54 of this Act; and
  • (b) is not an excepted building as defined in section 58(2) of this Act,

they may, after giving to the owner of the building not less than seven days' notice in writing of the proposed execution of the works, take such steps as they consider appropriate for executing the works.

Trees

Penalties for non-compliance with tree preservation order

102
  • (1) If any person, in contravention of a tree preservation order, cuts down or wilfully destroys a tree, or tops or lops a tree in such a manner as to be likely to destroy it, he shall be guilty of an offence and liable on summary conviction to a fine not exceeding £250 or twice the sum which appears to the court to be the value of the tree, whichever is the greater.
  • (2) If any person contravenes the provisions of a tree preservation order otherwise than as mentioned in subsection (1) of this section, he shall be guilty of an offence and liable on summary conviction to a fine not exceeding £50.
  • (3) If, in the case of a continuing offence under this section, the contravention is continued after the conviction, the offender shall be guilty of a further offence and liable on summary conviction to an additional fine not exceeding £2 for each day on which the contravention is so continued.

Enforcement of duties as to replacement of trees

103
  • (1) If it appears to the local planning authority that the provisions of section 62 of this Act, or any conditions of a consent given under a tree preservation order which require the replacement of trees, are not complied with in the case of any tree or trees, that authority may, at any time within four years from the date of the alleged failure to comply with the said provisions or conditions, serve on the owner of the land a notice requiring him, within such period as may be specified in the notice, to plant a tree or trees of such size and species as may be so specified.
  • (2) Subject to the following provisions of this section, a notice under this section shall take effect at the end of such period, not being less than twenty-eight days after the service of the notice, as may be specified in the notice.
  • (3) A person on whom a notice under this section is served may, at any time within the period specified in the notice as the period at the end of which it is to take effect, appeal to the Secretary of State against the notice on any of the following grounds—
  • (a) that the provisions of the said section 62 or the conditions aforesaid are not applicable or have been complied with;
  • (b) that the requirements of the notice are unreasonable in respect of the period or the size or species of trees specified therein ;
  • (c) that the planting of a tree or trees in accordance with the notice is not required in the interests of amenity or would be contrary to the practice of good forestry;
  • (d) that the place on which the tree is or trees are required to be planted is unsuitable for that purpose;

and the provisions of section 88(2), (3) and (4)(a) of this Act, and of so much of section 88(5) of this Act as enables the Secretary of State to give directions, shall apply in relation to any such appeal as they apply in relation to an appeal against an enforcement notice.

  • (4) Schedule 9 to this Act applies to appeals under subsection (3) of this section.
  • (5) In section 91 of this Act, and in regulations in force under that section, references to an enforcement notice and an enforcement notice served in respect of any breach of planning control shall include references to a notice under this section; and in relation to such a notice the reference in subsection (2) of that section to the person by whom the breach of planning control was committed shall be construed as a reference to any person, other than the owner, responsible for the cutting down, destruction or removal of the original tree or trees.

Waste land

Penalty for non-compliance with notice as to waste land

104
  • (1) The provisions of this section shall have effect where a notice has been served under section 65 of this Act, and the period within which the steps required by the notice are to be taken has expired.
  • (2) If at any time after the end of that period any of those steps have not been taken, and any person does anything which has the effect of continuing or aggravating the injury caused by the condition of the land to which the notice relates, he shall be guilty of an offence and liable on summary conviction to a fine not exceeding £50.

Appeal to magistrates' court against notice as to waste land

105
  • (1) A person on whom a notice under section 65 of this Act is served, or any other person having an interest in the land to which the notice relates, may, at any time within the period specified in the notice as the period at the end of which it is to take effect, appeal against the notice on any of the following grounds—
  • (a) that the condition of the land to which the notice relates does not seriously injure the amenity of any part of the area of the local planning authority who served the notice, or of any adjoining area ;
  • (b) that the condition of the land to which the notice relates is attributable to, and such as results in the ordinary course of events from, the carrying on of operations or a use of land which is not in contravention of Part III of this Act;
  • (c) that the land to which the notice relates does not constitute a garden, vacant site or other open land in the area of the local planning authority who served the notice;
  • (d) that the requirements of the notice exceed what is necessary for preventing the condition of the land from seriously injuring the amenity of any part of the area of the local planning authority who served the notice, or of any adjoining area ;
  • (e) that the period specified in the notice as the period within which any steps required by the notice are to be taken falls short of what should reasonably be allowed.
  • (2) Any appeal under this section shall be made to a magistrates' court acting for the petty sessions area in which the land in question is situated.
  • (3) Where an appeal is brought under this section, the notice to which it relates shall be of no effect pending the final determination or withdrawal of the appeal.
  • (4) On an appeal under this section the magistrates' court may correct any informality, defect or error in the notice if satisfied that the informality, defect or error is not material.
  • (5) On the determination of an appeal under this section the magistrates' court shall give directions for giving effect to their determination, including, where appropriate, directions for quashing the notice or for varying the terms of the notice in favour of the appellant.

Further appeal to the Crown Court

106

Where an appeal has been brought under section 105 of this Act, an appeal against the decision of the magistrates' court thereon may be brought to the Crown Court by the appellant or by the local planning authority.

Execution and cost of works required by notice as to waste land

107
  • (1) If, within the period specified in a notice under section 65 of this Act in accordance with subsection (1) of that section, or within such extended period as the local planning authority may allow, any steps required by the notice to be taken have not been taken, the local planning authority may enter the land and take those steps, and may recover from the person who is then the owner of the land any expenses reasonably incurred by them in doing so.
  • (2) Any expenses incurred by the owner or occupier of any land for the purpose of complying with a notice under section 65 of this Act, and any sums paid by the owner of any land under subsection (1) of this section in respect of expenses incurred by the local planning authority in taking steps required by such a notice to be taken, shall be deemed to be incurred or paid for the use and at the request of the person who caused or permitted the land to come to be in the condition in which it was when the notice was served.
  • (3) The provisions of section 91(3) and (4) of this Act shall apply in relation to a notice under section 65 of this Act as they apply in relation to an enforcement notice; and regulations made by virtue of this subsection may provide for the charging on the land of any expenses recoverable by a local authority under subsection (1) of this section.

Other controls

Enforcement of orders under s.51

108
  • (1) Where, by virtue of an order under section 51 of this Act, the use of land for any purpose is required to be discontinued, or any conditions are imposed on the continuance thereof, then if any person, without the grant of planning permission in that behalf, uses the land for that purpose or, as the case may be, uses the land for that purpose in contravention of those conditions, or causes or permits the land to be so used, he shall be guilty of an offence, and shall be liable on summary conviction to a fine not exceeding £400 or on conviction on indictment to a fine; and if the use is continued after the conviction, he shall be guilty of a further offence and liable—
  • (a) on summary conviction to a fine not exceeding £50 for each day on which the use is so continued; or
  • (b) on conviction on indictment to a fine.
  • (2) If, within the period specified in that behalf in an order under section 51 of this Act, any steps required by that order to be taken for the alteration or removal of any buildings or works have not been taken, the local planning authority may, and shall if so required by directions of the Secretary of State, enter the land and take those steps; and section 276 of the Public Health Act 1936 shall apply in relation to any works executed by a local planning authority under this subsection as it applies in relation to works executed by a local authority under that Act.

Enforcement of control as to advertisements

109
  • (1) The matters for which provision may be made by regulations under section 63 of this Act shall include provision for enabling the local planning authority to require the removal of any advertisement which is being displayed in contravention of the regulations, or the discontinuance of the use for the display of advertisements of any site which is being so used in contravention of the regulations, and for that purpose for applying any of the provisions of this Part of this Act with respect to enforcement notices or the provisions of section 177 of this Act, subject to such adaptations and modifications as may be specified in the regulations.
  • (2) Without prejudice to any provisions included in regulations made under section 63 of this Act by virtue of subsection (1) of this section, if any person displays an advertisement in contravention of the provisions of the regulations he shall be guilty of an offence and liable on summary conviction to a fine of such amount as may be prescribed by the regulations, not exceeding £100 and, in the case of a continuing offence, £5 for each day during which the offence continues after conviction.
  • (3) For the purposes of subsection (2) of this section, and without prejudice to the generality thereof, a person shall be deemed to display an advertisement if—
  • (a) the advertisement is displayed on land of which he is the owner or occupier; or
  • (b) the advertisement gives publicity to his goods, trade, business or other concerns:

Provided that a person shall not be guilty of an offence under that subsection by reason only that an advertisement is displayed on land of which he is the owner or occupier, or that his goods, trade, business or other concerns are given publicity by the advertisement, if he proves that it was displayed without his knowledge or consent.

Supplementary provisions

Supplementary provisions as to appeals to Secretary of State under Part V

110
  • (1) Subsection (5) of section 290 of the Local Government Act 1933 (which authorises a government department holding an inquiry under that section to make orders with respect to the costs of the parties) shall apply in relation to any proceedings before the Secretary of State on an appeal under this Part of this Act as if those proceedings were an inquiry held by the Secretary of State under the said section 290.
  • (2) Where under this Part of this Act any person has appealed to the Secretary of State or (in accordance with section 105 of this Act) to a magistrates' court against a notice, neither that person nor any other shall be entitled, in any other proceedings instituted after the making of the appeal, to claim that the notice was not duly served on the person who appealed.

Recovery of expenses of local planning authorities under Part V

111

Where by virtue of any of the preceding provisions of this Part of this Act any expenses are recoverable by a local planning authority, those expenses shall be recoverable as a simple contract debt in any court of competent jurisdiction.

Acquisition and appropriation of land

Compulsory acquisition of land in connection with development and for other planning purposes

112
  • (1) The Secretary of State may authorise a local authority to whom this section applies to acquire compulsorily any land within their area if he is satisfied—
  • (a) that the land is required in order to secure the treatment as a whole, by development, redevelopment or improvement, or partly by one and partly by another method, of the land or of any area in which the land is situated; or
  • (b) that it is expedient in the public interest that the land should be held together with land so required; or
  • (c) that the land is required for development or redevelopment, or both, as a whole for the purpose of providing for the relocation of population or industry or the replacement of open space in the course of the redevelopment or improvement, or both, of another area as a whole ; or
  • (d) that it is expedient to acquire the land immediately for a purpose which it is necessary to achieve in the interests of the proper planning of an area in which the land is situated.
  • (2) Where under subsection (1) of this section the Secretary of State has power to authorise a local authority to whom this section applies to acquire any land compulsorily he may, after the requisite consultation, authorise the land to be so acquired by another authority, being a local authority within the meaning of this Act.
  • (3) Before giving an authorisation under subsection (2) of this section, the Secretary of State shall—
  • (a) where the land is in a county borough, consult with the council of the borough;
  • (b) where the land is in a county district, consult with the councils of the county and the county district;
  • (c) where the land is in a London borough, consult with the council of the borough and with the Greater London Council.
  • (4) The Acquisition of Land (Authorisation Procedure) Act 1946 shall apply to the compulsory acquisition of land under this section and accordingly shall have effect as if this section had been in force immediately before the commencement of that Act.
  • (5) The local authorities to whom this section applies are the councils of counties, county boroughs, and county districts, the Greater London Council and the councils of London boroughs.

Compulsory acquisition of land by Secretary of State for the Environment

113
  • (1) The Secretary of State for the Environment may acquire compulsorily any land necessary for the public service.
  • (2) The power of acquiring land compulsorily under this section shall include power to acquire an easement or other right over land by the grant of a new right:

Provided that this subsection shall not apply to an easement or other right over any land which would for the purposes of the Acquisition of Land (Authorisation Procedure) Act 1946 form part of a common, open space or fuel or field garden allotment.

  • (3) The said Act of 1946 shall apply to any compulsory acquisition by the Secretary of State for the Environment under this section as it applies to a compulsory acquisition by another Minister in a case falling within section 1(1) of that Act.

Compulsory acquisition of listed building in need of repair

114
  • (1) Where it appears to the Secretary of State, in the case of a building to which this section applies, that reasonable steps are not being taken for properly preserving it, the Secretary of State may authorise the council of the county, county borough or county district in which the building is situated or, in the case of a building situated in Greater London, the Greater London Council or the London borough council, to acquire compulsorily under this section the building and any land comprising or contiguous or adjacent to it which appears to the Secretary of State to be required for preserving the building or its amenities, or for affording access to it, or for its proper control or management.
  • (2) Where it appears to the Secretary of State, in the case of a building to which this section applies, that reasonable steps are not being taken for properly preserving it, he may be authorised under this section to acquire compulsorily the building and any land comprising or contiguous or adjacent to it which appears to him to be required for the purpose mentioned in subsection (1) of this section.
  • (3) This section applies to any listed building, not being an excepted building as defined in section 58(2) of this Act.
  • (4) The Secretary of State shall not make or confirm a compulsory purchase order for the acquisition of any building by virtue of this section unless he is satisfied that it is expedient to make provision for the preservation of the building and to authorise its compulsory acquisition for that purpose.
  • (5) The Acquisition of Land (Authorisation Procedure) Act 1946 shall apply to the compulsory acquisition of land under this section and accordingly shall have effect—
  • (a) as if this section had been in force immediately before the commencement of that Act; and
  • (b) as if references therein to the enactments specified in section 1(1)(b) of that Act included references to the provisions of this section.
  • (6) Any person having an interest in a building which it is proposed to acquire compulsorily under this section may, within twenty-eight days after the service of the notice required by paragraph 3(1)(b) of Schedule 1 to the said Act of 1946, apply to a magistrates' court acting for the petty sessions area within which the building is situated for an order staying further proceedings on the compulsory purchase order; and, if the court is satisfied that reasonable steps have been taken for properly preserving the building, the court shall make an order accordingly.
  • (7) Any person aggrieved by the decision of a magistrates' court on an application under subsection (6) of this section may appeal against the decision to the Crown Court.

Repairs notice as preliminary to compulsory acquisition under s.114

115
  • (1) Neither a council nor the Secretary of State shall start the compulsory purchase of a building under section 114 of this Act unless at least two months previously they have served on the owner of the building, and not withdrawn, a notice under this section (in this section referred to as a "repairs notice ")—
  • (a) specifying the works which they consider reasonably necessary for the proper preservation of the building; and
  • (b) explaining the effect of sections 114 to 117 of this Act.
  • (2) Where a council or the Secretary of State have served a repairs notice, the demolition of the building thereafter shall not prevent them from being authorised under section 114 of this Act to acquire compulsorily the site of the building, if the Secretary of State is satisfied that he would have confirmed or, as the case may be, would have made a compulsory purchase order in respect of the building had it not been demolished.
  • (3) A council or the Secretary of State may at any time withdraw a repairs notice served by them; and if they do so, they shall forthwith give notice of the withdrawal to the person who was served with the notice.
  • (4) For the purposes of this section a compulsory acquisition is started when the council or the Secretary of State, as the case may be, serve the notice required by paragraph 3(1)(b) of Schedule 1 to the Acquisition of Land (Authorisation Procedure) Act 1946.

Compensation on compulsory acquisition of listed building

116

Subject to section 117 of this Act, for the purpose of assessing compensation in respect of any compulsory acquisition of land including a building which, immediately before the date of the compulsorily purchase order, was listed, it shall be assumed that fisted building consent would be granted for any works for the alteration or extension of the building, or for its demolition, other than works in respect of which such consent has been applied for before the date of the order and refused by the Secretary of State, or granted by him subject to conditions, the circumstances having been such that compensation thereupon became payable under section 171 of this Act.

Minimum compensation in case of listed building deliberately left derelict

117
  • (1) A council proposing to acquire a building compulsorily under section 114 of this Act, if they are satisfied that the building has been deliberately allowed to fall into disrepair for the purpose of justifying its demolition and the development or re-development of the site or any adjoining site, may include in the compulsory purchase order as submitted to the Secretary of State for confirmation, an application for a direction for minimum compensation ; and the Secretary of State, if he is so satisfied, may include such a direction in the order as confirmed by him
  • (2) Subject to the provisions of this section, where the Secretary of State acquires a building compulsorily under section 114 of this Act, he may, if he is satisfied as mentioned in subsection (1) of this section, include a direction for minimum compensation in the compulsory purchase order.
  • (3) The notice required to be served in accordance with paragraph 3(1)(b) of Schedule 1 to the Acquisition of Land (Authorisation Procedure) Act 1946 (notices stating effect of compulsory purchase order or, as the case may be, draft order) shall, without prejudice to so much of that paragraph as requires the notice to state the effect of the order, include a statement that the authority have made application for a direction for minimum compensation or, as the case may be, that the Secretary of State has included such a direction in the draft order prepared by him in accordance with paragraph 7 of that Schedule and shall in either case explain the meaning of the expression " direction for minimum compensation ".
  • (4) A direction for minimum compensation, in relation to a building compulsorily acquired, is a direction that for the purpose of assessing compensation it is to be assumed, notwithstanding anything to the contrary in the Land Compensation Act 1961 or this Act, that planning permission would not be granted for any development or re-development of the site of the building and that listed building consent would not be granted for any works for the demolition, alteration or extension of the building other than development or works necessary for restoring it to, and maintaining it in, a proper state of repair; and if a compulsory purchase order is confirmed or made with the inclusion of such a direction, the compensation in respect of the compulsory acquisition shall be assessed in accordance with the direction.
  • (5) Where the local authority include in a compulsory purchase order made by them an application for a direction for minimum compensation, or the Secretary of State includes such a direction in a draft compulsory purchase order prepared by him, any person having an interest in the building may, within twenty-eight days after the service of the notice required by paragraph 3(1)(b) of Schedule 1 to the said Act of 1946, apply to a magistrates' court acting for the petty sessions area in which the building is situated for an order that the local authority's application for a direction for minimum compensation be refused or, as the case may be, that such a direction be not included in the compulsory purchase order as made by the Secretary of State; and if the court is satisfied that the building has not been deliberately allowed to fall into disrepair for the purpose mentioned in subsection (1) of this section, the court shall make the order applied for.
  • (6) A person aggrieved by the decision of a magistrates' court on an application under subsection (5) of this section may appeal against the decision to the Crown Court.
  • (7) The rights conferred by subsections (5) and (6) of this section shall not prejudice those conferred by section 114(6) and (7) of this Act.

Extinguishment of rights over land compulsorily acquired

118
  • (1) Subject to the provisions of this section, upon the completion by the acquiring authority of a compulsory acquisition of land under this Part of this Act, all private rights of way and rights of laying down, erecting, continuing or maintaining any apparatus on, under or over the land shall be extinguished, and any such apparatus shall vest in the acquiring authority.
  • (2) Subsection (1) of this section shall not apply to any right vested in, or apparatus belonging to, statutory undertakers for the purpose of the carrying on of their undertaking.
  • (3) In respect of any right or apparatus not falling within subsection (2) of this section, subsection (1) of this section shall have effect subject—
  • (a) to any direction given by the acquiring authority before the completion of the acquisition that subsection (1) of this section shall not apply to any right or apparatus specified in the direction ; and
  • (b) to any agreement which may be made (whether before or after the completion of the acquisition) between the acquiring authority and the person in or to whom the right or apparatus in question is vested or belongs.
  • (4) Any person who suffers loss by the extinguishment of a right or the vesting of any apparatus under this section shall be entitled to compensation from the acquiring authority.
  • (5) Any compensation payable under this section shall be determined in accordance with the Land Compensation Act 1961.

Acquisition of land by agreement

119
  • (1) The council of any county, county borough, London borough or county district may acquire by agreement—
  • (a) any land which they require for any purpose for which a local authority may be authorised to acquire land under section 112 of this Act;
  • (b) any building appearing to them to be of special architectural or historic interest; and
  • (c) any land comprising or contiguous or adjacent to such a building which appears to the Secretary of State to be required for preserving the building or its amenities, or for affording access to it, or for its proper control or management.
  • (2) The powers conferred by subsection (1) of this section shall not be exerciseable by a council except with the consent of the Secretary of State, unless the land which is to be acquired either—
  • (a) is immediately required by the council for the purpose for which it is to be acquired ; or
  • (b) if it is not so required, is land within the area of the council.
  • (3) The provisions of Part I of the Compulsory Purchase Act 1965 (so far as applicable), other than sections 4 to 8, section 10 and section 31, shall apply in relation to the acquisition of land under this section.
  • (4) The powers conferred by this section on the councils of London boroughs shall be exerciseable also by the Greater London Council—
  • (a) in a London borough, with the consent of the council of the borough; or
  • (b) in the Inner Temple or the Middle Temple with the consent of the Sub-Treasurer or, as the case may be, Under-Treasurer thereof; or
  • (c) in any of the areas aforesaid if the appropriate consent aforesaid is withheld, with the consent of the Secretary of State; or
  • (d) in relation to land in any of the areas aforesaid, without any such consent as aforesaid, if the land is used for the purposes of an industrial or commercial undertaking and is to be acquired incidentally to the removal of that undertaking from Greater London.

Acquisition of land for purposes of exchange

120

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.