Town and Country Planning (Scotland) Act 1972 (repealed 27.5.1997)
- (1) Where land specified in a general vesting declaration under this Act is, together with other land not so specified, charged with a charge, such proportion of the charge as may be apportioned under section 109 of the Lands Clauses Consolidation (Scotland) Act 1845, to the first mentioned land shall, subject to sub-paragraph (3) of this paragraph, be treated as having been extinguished by virtue of paragraphs 6 to 8 above on the vesting of that land in the acquiring authority under those paragraphs.
- (2) Where by virtue of the preceding sub-paragraph a portion of a charge is treated as having been extinguished, the provisions of sections 108 to 111 of the said Act of 1845 shall have effect as if the extinguishment had taken place under section 110 of that Act.
- (3) If, in the circumstances described in sub-paragraph (1) of this paragraph, the person entitled to the charge and the owner of the land subject thereto enter into an agreement to that effect, the said sections 108 to 111, shall have effect as if, at the time of the vesting of the land in the acquiring authority under paragraphs 6 to 8 above, the person entitled to the charge had released that land from the charge on the condition mentioned in section 109 of the said Act of 1845; and in that case no part of the charge shall be treated as having been extinguished as regards the remaining part of the land charged therewith.
- (4) In this paragraph “charge” means any such feu-duty, ground annual or rent or other payment or incumbrance as is mentioned in the words introductory to sections 107 to 111 of the said Act of 1845.
33
Where land specified in a general vesting declaration under this Act is, together with other land not so specified, comprised in a tenancy for a term of years unexpired, section 112 of the Lands Clauses Consolidation (Scotland) Act 1845, shall have effect in relation thereto as if for references to the time of the apportionment of rent therein mentioned there were substituted references to the time of the vesting of the tenancy in the acquiring authority.
34
Where any of the land specified in a general vesting declaration under this Act has become vested in an acquiring authority under paragraphs 6 to 8 above, any person who, in consequence thereof, is relieved from any liability (whether in respect of a feu-duty, ground annual, rent, interest on a heritable security or any other payment) and makes any payment as in satisfaction or part satisfaction of that liability shall, if he shows that when he made the payment he did not know of the facts which constituted the cause of his being so relieved, or of one or more of those facts, be entitled to recover the sum paid from the person to whom it was paid.
Miscellaneous
35
Where, after land has become vested in an acquiring authority under paragraphs 6 to 8 above, a person retains possession of any document relating to the title to the land, he shall be deemed to have given to the acquiring authority an acknowledgment in writing of the right of the acquiring authority to production of that document and to delivery of copies thereof and (except where he retains possession of the document as heritable creditor or as trustee or otherwise in a fiduciary capacity) an undertaking for safe custody thereof.
36
- (1) The time within which a question of disputed compensation, arising out of an acquisition of an interest in land in respect of which a notice to treat is deemed to have been served by virtue of paragraphs 6 to 8 above, may be referred to the Lands Tribunal shall be six years from the date at which the person claiming compensation, or a person from whom he derives title, first knew, or could reasonably be expected to have known, of the vesting of the interest by virtue of those paragraphs.
- (2) In reckoning the period of six years referred to in sub-paragraph (1) of this paragraph, no account shall be taken of any period during which the person claiming compensation or the person from whom he derives title was in minority or less age or was under legal disability.
37
At the end of the period specified in a general vesting declaration or, if a notice of objection to severance is served under this Schedule, when that notice has been disposed of in accordance with the provisions of this Schedule, that declaration, if still being proceeded with or, as the case may be, that declaration as altered under paragraph 28 above, shall be recorded in the General Register of Sasines, and on being so recorded shall have the same effect as a conveyance registered in accordance with section 80 of the Lands Clauses Consolidation (Scotland) Act 1845.
Part III — Interpretation
38
- (1) In this Schedule “short tenancy” means a tenancy for a year or from year to year or any lesser interest, and “long tenancy which is about to expire”, in relation to a general vesting declaration, means a tenancy granted for an interest greater than a short tenancy, but having at the date of the declaration a period still to run which is not more than the specified period (that is to say, such period, longer than one year, as may for the purposes of this paragraph be specified in the declaration in relation to the land in which the tenancy subsists).
- (2) In determining for the purposes of this paragraph what period a tenancy still has to run at the date of a general vesting declaration it shall be assumed—
- (a) that the tenant will exercise any option to renew the tenancy, and will not exercise any option to terminate the tenancy, then or thereafter available to him, and
- (b) that the landlord will exercise any option to terminate the tenancy then or thereafter available to him.
39
In this Schedule—
- “Acquisition Act 1947” means the Acquisition of Land (Authorisation Procedure) (Scotland) Act 1947;
- “relevant enactments”, in relation to an acquiring authority, means the enactments under which that authority may acquire or be authorised to acquire land compulsorily and which prescribe a procedure for effecting the compulsory acquisition of land by them by means of a compulsory purchase order;
- “land”, in relation to compulsory acquisition by an acquiring authority, has the same meaning as in the relevant enactments.
Survey of planning districts.
4A
- (1) The Secretary of State may by order designate areas (“structure plan areas”) in respect of which planning authorities are to prepare structure plans.
- (2) The district of every planning authority in Scotland shall be included in a structure plan area.
- (3) A structure plan area may extend to the district of more than one planning authority, and may extend to only part of the district of a planning authority.
- (4) Where a structure plan area extends to the district of more than one planning authority, the planning authorities concerned shall jointly carry out the functions conferred upon them under sections 4, 5, 6, 6A and 8 of this Act in accordance with such arrangements as they may agree for that purpose under sections 56 (discharge of functions by local authorities), 57 (appointment of committees) and 58 (expenses of joint committees) of the Local Government (Scotland) Act 1973.
- (5) An order under this section shall be made by statutory instrument subject to annulment in pursuance of a resolution of either House of Parliament.
6A
Before submitting a structure plan or proposals for alteration thereof to the Secretary of State, a planning authority shall consult every other planning authority who are likely to be affected by the plan or proposals.
General
18A
—Where, in making any determination under the planning Acts, regard is to be had to the development plan, the determination shall be made in accordance with the plan unless material considerations indicate otherwise.
Development requiring planning permission.
Simplified planning zone schemes
21A
- (1) A simplified planning zone is an area in respect of which a simplified planning zone scheme is in force.
- (2) The adoption or approval of a simplified planning zone scheme has effect to grant in relation to the zone, or any part of it specified in the scheme, planning permission for development specified in the scheme or for development of any class so specified.
- (3) Planning permission under a simplified planning zone scheme may be unconditional or subject to such conditions, limitations or exceptions as may be specified in the scheme.
- (4) Every planning authority—
- (a) shall consider, as soon as practicable after this section comes into operation, the question for which part or parts of their district a simplified planning zone scheme is desirable, and shall thereafter keep that question under review; and
- (b) shall prepare a scheme for any such part for which they decide, as a result of their original consideration or of any such review, that it is desirable to do so.
- (5) The provisions of Schedule 6A to this Act have effect with respect to the making and alteration of simplified planning zone schemes and other related matters.
21B
- (1) The conditions and limitations on planning permission which may be specified in a simplified planning zone scheme may include—
- (a) conditions or limitations in respect of all development permitted by the scheme or in respect of particular descriptions of development so permitted, and
- (b) conditions or limitations requiring the consent, agreement or approval of the planning authority in relation to particular descriptions of permitted development;
and different conditions or limitations may be specified for different cases or classes of case.
- (2) Nothing in a simplified planning zone scheme shall affect the right of any person—
- (a) to do anything not amounting to development, or
- (b) to carry out development for which planning permission is not required or for which permission has been granted otherwise than by the scheme;
and no limitation or restriction subject to which permission has been granted otherwise than under the scheme shall affect the right of any person to carry out development for which permission has been granted under the scheme.
21C
- (1) A simplified planning zone scheme shall take effect on the date of its adoption or approval and shall cease to have effect at the end of the period of ten years beginning with that date.
- (2) Upon the scheme’s ceasing to have effect planning permission under the scheme shall also cease to have effect except in a case where the development authorised by it has been begun.
- (3) The provisions of section 41(2) to (6) of this Act (which provide for the termination of planning permission if the completion of development is unreasonably delayed) apply to planning permission under a simplified planning zone scheme where development has been begun but not completed by the time the area ceases to be a simplified planning zone.
- (4) The provisions of section 40(1) to (3) of this Act apply in determining for the purposes of this section when development shall be taken to be begun.
21D
- (1) The adoption or approval of alterations to a simplified planning zone scheme has effect as follows.
- (2) The adoption or approval of alterations providing for the inclusion of land in the simplified planning zone has effect to grant in relation to that land or such part of it as is specified in the scheme planning permission for development so specified or of any class so specified.
- (3) The adoption or approval of alterations providing for the grant of planning permission has effect to grant such permission in relation to the simplified planning zone, or such part of it as is specified in the scheme, for development so specified or development of any class so specified.
- (4) The adoption or approval of alterations providing for the withdrawal of relaxation of conditions, limitations or restrictions to which planning permission under the scheme is subject has effect to withdraw or relax the conditions, limitations or restrictions forthwith.
- (5) The adoption or approval of alterations providing for—
- (a) the exclusion of land from the simplified planning zone,
- (b) the withdrawal of planning permission, or
- (c) the imposition of new or more stringent conditions, limitations or restrictions to which planning permission under the scheme is subject,
has effect to withdraw permission, or to impose the conditions, limitations or restrictions, with effect from the end of the period of twelve months beginning with the date of the adoption or approval.
- (6) The adoption or approval of alterations to a scheme does not affect planning permission under the scheme in any case where the development authorised by it has been begun.
The provisions of section 40(1) to (3) of this Act apply in determining for the purposes of this subsection when development shall be taken to be begun.
21E
- (1) The following descriptions of land may not be included in a simplified planning zone—
- (a) land in a conservation area;
- (b) land in a National Scenic Area;
- (c) land identified in the development plan for the area as part of a green belt;
- (d) land in respect of which a notification or order is in force under section 28 or 29 of the Wildlife and Countryside Act 1981 (areas of special scientific interest).
- (2) Where land included in a simplified planning zone becomes land of such a description, subsection (1) does not have effect to exclude it from the zone.
- (3) The Secretary of State may by order provide that no simplified planning zone scheme shall have effect to grant planning permission—
- (a) in relation to an area of land specified in the order or to areas of land of a description so specified, or
- (b) for development of a description specified in the order.
- (4) An order under subsection (3) has effect to withdraw such planning permission under a simplified planning zone scheme already in force with effect from the date on which the order comes into force, except in a case where the development authorised by the permission has been begun.
The provisions of section 40(1) to (3) of this Act apply in determining for the purposes of this subsection when development shall be taken to be begun.
Determination by. . . planning authorities of applications for planning permission
26A
- (1) A planning authority may decline to determine an application for planning permission for the development of any land if—
- (a) within the period of two years ending with the date on which the application is received, the Secretary of State has refused a similar application referred to him under section 32 of this Act or has dismissed an appeal against the refusal of a similar application; and
- (b) in the opinion of the authority there has been no significant change since the refusal or, as the case may be, dismissal mentioned in paragraph (a) of this subsection in the development plan, so far as material to the application, or in any other material considerations.
- (2) For the purposes of this section an application for planning permission for the development of any land shall only be taken to be similar to a later application if the development and the land to which the applications relate are in the opinion of the planning authority the same or substantially the same.
- (3) The reference in subsection (1)(a) of this section to an appeal against the refusal of an application includes an appeal under section 34 in respect of an application.
26B
- (1) The Secretary of State may by regulations under this Act make provision about the consideration to be given, before planning permission for development of any class specified in the regulations is granted, to the likely environmental effects of the proposed development.
- (2) The regulations—
- (a) may make the same provision as, or provision similar or corresponding to, any provision made, for the purposes of any Community obligation of the United Kingdom about the assessment of the likely effects of development on the environment, under section 2(2) of the European Communities Act 1972; and
- (b) may make different provisions for different classes of development.
- (3) Where a draft of regulations made in exercise both of the power conferred by this section and the power conferred by section 2(2) of the European Communities Act 1972 is approved by resolution of each House of Parliament, no statutory instrument containing such regulations shall be subject to annulment by virtue of subsection (2) of section 273 (regulations and orders) of this Act.
27A
- (1) Where planning permission for development consisting of the winning and working of minerals or involving the depositing of refuse or waste materials is granted subject to a restoration condition, it may be granted subject also to any such aftercare condition as the planning authority think fit.
- (2) In this Act—
- “restoration condition” means a condition requiring that after the winning and working is completed or the depositing has ceased, the site shall be restored by the use of any or all of the following, namely, subsoil, topsoil and soil-making material; and
- “aftercare condition” means a condition requiring that such steps shall be taken as may be necessary to bring land to the required standard for whichever of the following uses is specified in the condition, namely—
- (a) use for agriculture;
- (b) use for forestry; or
- (c) use for amenity.
- (3) An aftercare condition may either—
- (a) specify the steps to be taken; or
- (b) require that the steps be taken in accordance with a scheme (in this section referred to as an “aftercare scheme”) approved by the planning authority.
- (4) A planning authority may approve an aftercare scheme in the form in which it is submitted to them or may modify it and approve it as modified.
- (5) The steps that may be specified in an aftercare condition or an aftercare scheme may consist of planting, cultivating, fertilising, watering, draining or otherwise treating the land.
- (6) Where a step is specified in a condition or a scheme, the period during which it is to be taken may also be specified, but no step may be required to be taken after the expiry of the aftercare period.
- (7) In subsection (6) of this section “the aftercare period” means a period of five years from compliance with the restoration condition or such other maximum period after compliance with that condition as may be prescribed; and in respect of any part of a site, the aftercare period shall commence on compliance with the restoration condition in respect of that part.
- (8) The power to prescribe maximum periods conferred by subsection (7) of this section includes power to prescribe maximum periods differing according to the use specified.
- (9) In a case where—
- (a) the use specified is a use for agriculture; and
- (b) the land was in use for agriculture at the time of the grant of the planning permission or had previously been used for that purpose and had not at the time of the grant been used for any authorised purpose since its use for agriculture ceased; and
- (c) the planning authority is aware of or can readily ascertain the physical characteristics of the land when it was last used for agriculture,
the land is brought to the required standard when its physical characteristics are restored, so far as it is practicable to do so, to what they were when it was last used for agriculture.
- (10) In any other case where the use specified is a use for agriculture the land is brought to the required standard when it is reasonably fit for that use.
- (11) Where the use specified is a use for forestry, the land is brought to the required standard when it is reasonably fit for that use.
- (12) Where the use specified is a use for amenity, the land is brought to the required standard when it is suitable for sustaining trees, shrubs or plants.
- (13) Before imposing an aftercare condition in a case where the use specified in the condition is for forestry, the planning authority shall consult the Forestry Commission as to whether it is appropriate to specify that use.
- (14) Where after consultations required by subsection (13) of this section the planning authority are satisfied that the use that they ought to specify is a use for forestry, they shall consult the Forestry Commission with regard to whether the steps to be taken should be specified in the aftercare condition or in an aftercare scheme.
- (15) The planning authority shall also consult the Forestry Commission—
- (a) as to the steps to be specified in an aftercare condition which specifies a use for forestry; and
- (b) before approving an aftercare scheme submitted in accordance with an aftercare condition which specifies such a use.
- (16) The planning authority shall also, from time to time as they consider expedient, consult the Commission as to whether the steps specified in an aftercare condition or an aftercare scheme are being taken.
- (17) On the application of any person with an interest in land in respect of which an aftercare condition has been imposed the planning authority, if they are satisfied that the condition has been complied with, shall issue a certificate to that effect.
- (18) A person who has complied with an aftercare condition but who has not himself won and worked minerals or deposited refuse or waste materials shall be entitled, subject to any condition to the contrary contained in a contract which is enforceable against him by the person who last carried out such operations, to recover from that person any expenses reasonably incurred by him in complying with the aftercare condition.
- (19) In this section “authorised” means authorised by planning permission and “forestry” means the growing of a utilisable crop of timber.
28A
- (1) This section applies to applications for planning permission for the development of land without complying with conditions subject to which a previous planning permission was granted.
- (2) Special provision may be made with respect to such applications—
- (a) by regulations under section 22 of this Act as regards the form and content of the application, and
- (b) by a development order as regards the procedure to be followed in connection with the application.
- (3) On such an application the planning authority shall consider only the question of the conditions subject to which planning permission should be granted, and—
- (a) if they decide that planning permission should be granted subject to conditions differing from those subject to which the previous permission was granted, or that it should be granted unconditionally, they shall grant planning permission accordingly, and
- (b) if they decide that planning permission should be granted subject to the same conditions as those subject to which the previous permission was granted, they shall refuse the application.
- (4) This section does not apply where the application is made after the previous planning permission has become time-expired, that is to say, the previous permission having been granted subject to a condition as to the time within which the development to which it related was to have begun, that time has expired without the development having been begun.
30A
The date of the granting or of the refusal of any such application as is mentioned in section 23(2) of this Act shall be the date on which the notice of the planning authority’s decision bears to have been signed on behalf of the authority.
31A
Notwithstanding any other provision of this Part of this Act, a planning authority may, at the request of the grantee or of a person acting with his consent, vary any planning permission granted by them, if it appears to them that the variation sought is not material.
41A
- (1) Every planning permission for development —
- (a) consisting of the winning and working of minerals; or
- (b) involving the depositing of mineral waste,
shall be subject to a condition as to the duration of the development.
- (2) Except where a condition is specified under subsection (3) of this section the condition in the case of planning permission granted or deemed to be granted after the date of the commencement of section 24 of the Town and Country Planning (Minerals) Act 1981 is that the winning and working of minerals or the depositing of mineral waste must cease not later than the expiration of the period of sixty years beginning with the date of the permission.
- (3) An authority granting planning permission after the date of the commencement of the said section 24 or directing after that date that planning permission shall be deemed to be granted may specify a longer or shorter period than sixty years, and if they do so, the condition is that the winning and working of minerals or the depositing of mineral waste must cease not later than the expiration of a period of the specified length beginning with the date of the permission.
- (4) A longer or shorter period than sixty years may be prescribed for the purposes of subsections (2) and (3) of this section.
- (5) The condition in the case of planning permission granted or the commencement of section 24 of the Town and Country Planning (Minerals) Act 1981 is that the winning and working of minerals or the depositing of mineral waste must cease not later than the expiration of the period of sixty years beginning with the date of the commencement of that section.
- (6) A condition to which planning permission for development . . . is subject by virtue of this section is not to be regarded for the purposes of this Act as a condition such as is mentioned in subsection (1)(b) of section 27 of this Act.
- (7) Where planning permission for development . . . is granted by the planning authority, any condition to which it is subject by virtue of this section is to be regarded for the purposes of section 33 of this Act as a condition imposed by a decision of the planning authority, and may accordingly be the subject of an appeal under that section.
Orders after suspension of winning and working of minerals.
49A
- (1) Where it appears to the planning authority—
- (a) that development of land—
- (i) consisting of the winning and working of minerals; or
- (ii) involving the depositing of mineral waste,
has occurred; but
- (b) the winning and working or depositing has permanently ceased,
the planning authority may by order—
- (i) prohibit the resumption of the winning and working or the depositing; and
- (ii) impose, in relation to the site, any such requirement as is specified in subsection (3) of this section.
- (2) The planning authority may assume that the winning and working or the depositing has permanently ceased only when—
- (a) no winning and working or depositing has occurred, to any substantial extent, at the site for a period of at least two years; and
- (b) it appears to the planning authority, on the evidence available to them at the time when they make the order, that resumption of the winning and working or the depositing to any substantial extent at the site is unlikely.
- (3) The requirements mentioned in subsection (1) of this section are—
- (a) a requirement to alter or remove plant or machinery which was used for the purpose of the winning and working or the depositing or for any purpose ancillary to that purpose;
- (b) a requirement to take such steps as may be specified in the order, within such period as may be so specified, for the purpose of removing or alleviating any injury to amenity which has been caused by the winning and working or depositing, other than injury due to subsidence caused by underground mining operations;
- (c) a requirement that any condition subject to which planning permission for the development was granted or which has been imposed by virtue of any provision of this Act shall be complied with; and
- (d) a restoration condition.
- (4) An order under this section may include any such aftercare condition as the planning authority think fit if—
- (a) it also includes a restoration condition;
or
- (b) a restoration condition has previously been imposed in relation to the site by virtue of any provision of this Act.
- (5) Subsections (3) to (8) and (11) to (19) of section 27A of this Act shall apply in relation to an after-care condition imposed under this section as they apply in relation to such a condition imposed under that section.
- (6) In a case where—
- (a) the use specified is a use for agriculture; and
- (b) the land was in use for agriculture immediately before development consisting of the winning and working of minerals began to be carried out in, on or under it or had previously been used for agriculture and had not been used for any authorised purpose since its use for agriculture ceased; and
- (c) the planning authority is aware of or can readily ascertain the physical characteristics of the land when it was last used for agriculture,
the land is brought to the required standard when its physical characteristics are restored, so far as it is practicable to do so, to what they were when it was last used for agriculture.
- (7) In any other case where the use specified is a use for agriculture the land is brought to the required standard when it is reasonably fit for that use.
- (8) An order under this section shall not take effect unless it is confirmed by the Secretary of State, either without modification or subject to such modifications as he considers expedient.
- (9) Where a planning authority submit an order under this section to the Secretary of State for his confirmation under this section, that authority shall serve notice of the order on any person who is an owner or occupier of any of the land to which the order relates, and on any other person who in their opinion will be affected by the order; and if within the period specified in that behalf in the notice (not being less than twenty-eight days from the service thereof) any person on whom the notice is served so requires, the Secretary of State, before confirming the order, shall afford to that person and to the planning authority an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for that purpose.
- (10) Where an order under this section has been confirmed by the Secretary of State, the planning authority shall serve a copy of the order on every person who was entitled to be served with notice under subsection (9) of this section.
- (11) On an order under this section taking effect any planning permission for the development to which the order relates shall cease to have effect but without prejudice to the power of the planning authority, on revoking the order, to make a further grant of planning permission for development consisting of the winning and working of minerals or involving the depositing of mineral waste.
49B
- (1) Where it appears to the planning authority—
- (a) that development of land—
- (i) consisting of the winning and working of minerals; or
- (ii) involving the depositing of mineral waste,
has occurred; but
- (b) the winning and working or depositing has been temporarily suspended,
the planning authority may by order (in this Act referred to as a “suspension order”) require that steps be taken for the protection of the environment.
- (2) The planning authority may assume that the winning and working or the depositing has been temporarily suspended only when—
- (a) no such winning and working or depositing has occurred, to any substantial extent, at the site for a period of at least 12 months; but
- (b) it appears to the planning authority, on the evidence available to them at the time when they make the order, that a resumption of such winning and working or depositing to a substantial extent is likely.
- (3) In this Act “steps for the protection of the environment” means steps for the purpose—
- (a) of preserving the amenities of the area in which the land in, on or under which the development was carried out is situated during the period while the winning and working or the depositing is suspended;
- (b) of protecting that area from damage during that period; or
- (c) of preventing any deterioration in the condition of the land during that period.
- (4) A suspension order shall specify a period, commencing with the date on which it is to take effect, within which any step required for the protection of the environment is to be taken, and may specify different periods for the taking of different steps.
- (5) At any time when a suspension order is in operation the planning authority may by order (in this Act referred to as a “supplementary suspension order”) direct—
- (a) that steps for the protection of the environment shall be taken in addition to or in substitution for any of the steps which the suspension order or a previous supplementary suspension order specified as required to be taken; or
- (b) that the suspension order or any supplementary suspension order shall cease to have effect.
49C
- (1) Without prejudice to section 49D of this Act, a suspension order or supplementary suspension order (other than a supplementary suspension order revoking a suspension order or a previous supplementary suspension order and not requiring that any fresh step shall be taken for the protection of the environment) shall not take effect until it is confirmed by the Secretary of State, either without modification or subject to such modifications as he considers expedient
- (2) Subsection (9) of section 49A of this Act shall have effect in relation to a suspension order or supplementary suspension order submitted to the Secretary of State for his confirmation as it has effect in relation to an order submitted to him for his confirmation under that section.
- (3) Where a suspension order or supplementary suspension order has been confirmed by the Secretary of State, the planning authority shall serve a copy of the order on every person who was entitled to be served with notice by virtue of subsection (2) of this section.
49D
No order under section 49A or 49B of this Act shall take effect until it is registered either—
- (a) in a case where the land affected by the order is registered in that Register, in the Land Register of Scotland, or
- (b) in any other case, in the appropriate division of the General Register of Sasines.
49E
- (1) It shall be the duty of a planning authority—
- (a) to undertake in accordance with the following provisions of this section reviews of suspension orders and supplementary suspension orders which are in operation in their area; and
- (b) to determine whether they should make, in relation to any land to which a suspension order or supplementary suspension order applies—
- (i) an order under section 49A of this Act; or
- (ii) a supplementary suspension order.
- (2) The first review of a suspension order shall be undertaken not more than five years from the date on which the order takes effect.
- (3) Each subsequent review shall be undertaken not more than five years after the previous review.
- (4) If a supplementary suspension order is in operation for any part of the area for which a suspension order is in operation, they shall be reviewed together.
- (5) If a planning authority have made a supplementary suspension order which requires the taking of steps for the protection of the environment in substitution for all the steps required to be taken by a previous order under section 49B of this Act, the authority shall undertake reviews of the supplementary suspension order in accordance with subsections (6) and (7) of this section.
- (6) The first review shall be undertaken not more than five years from the date on which the order takes effect.
- (7) Each subsequent review shall be undertaken not more than five years after the previous review.
- (8) The duty to undertake reviews imposed by this section is in addition to and not in substitution for the duties imposed by section 251A of this Act.
49F
- (1) Nothing in a suspension order or a supplementary suspension order shall prevent the recommencement of development consisting of the winning and working of minerals or involving the depositing of mineral waste at the site in relation to which the order is in effect; but no person shall recommence such development without first giving the planning authority notice of his intention to do so.
- (2) A notice under subsection (1) of this section shall specify the date on which the person giving the notice intends to recommence the development.
- (3) The planning authority shall revoke the order if the winning and working of minerals or the depositing of mineral waste has recommenced to a substantial extent at the site in relation to which the order has effect.
- (4) If the authority do not revoke the order before the end of the period of two months from the date specified in the notice under subsection (1) of this section, the person who gave that notice may apply to the Secretary of State for the revocation of the order.
- (5) Notice of an application under subsection (4) of this section shall be given by the applicant to the planning authority.
- (6) If he is required to do so by the person who gave the notice or by the planning authority, the Secretary of State, before deciding whether or not to revoke the order, shall afford to that person and to the planning authority an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for the purpose.
- (7) If the Secretary of State is satisfied that the winning and working of minerals or the depositing of mineral waste has recommenced to a substantial extent at the site in relation to which the order has effect, he shall revoke the order.
- (8) If the Secretary of State revokes an order by virtue of subsection (7) of this section, he shall give notice of its revocation to the person who applied to him for the revocation and to the planning authority.
49G
49H
- (1) In this section and Schedule 10A to this Act, “old mining permission” means any planning permission for development—
- (a) consisting of the winning and working of minerals, or
- (b) involving the depositing of mineral waste,
which is deemed to have been granted by virtue of paragraph 77 of Schedule 22 to this Act (development authorised under interim development orders after 10th November 1943).
- (2) An old mining permission shall, if an application under that Schedule to determine the conditions to which the permission is to be subject is finally determined, have effect as from the final determination as if granted on the terms required to be registered.
- (3) If no such development has, at any time in the period of two years ending with 16th May 1991, been carried out to any substantial extent anywhere in, on or under the land to which an old mining permission relates, that permission shall not authorise any such development to be carried out after the coming into force of this section unless—
- (a) the permission has effect in accordance with subsection (2) above; and
- (b) the development is carried out after such an application is finally determined.
- (4) An old mining permission shall—
- (a) if no application for the registration of the permission is made under that Schedule, cease to have effect on the day following the last date on which such an application may be made, and
- (b) if such an application is refused, cease to have effect on the day following the date on which the application is finally determined.
- (5) An old mining permission shall, if—
- (a) such an application is granted; but
- (b) an application under that Schedule to determine the conditions to which the permission is to be subject is required to be served before the end of any period and is not so served,
cease to have effect on the day following the last date on which the application to determine those conditions may be served.
- (6) Subject to subsection (3) above, this section—
- (a) shall not affect any development carried out under an old mining permission before an application under that Schedule to determine the conditions to which the permission is to be subject is finally determined or, as the case may be, the date on which the permission ceases to have effect; and
- (b) shall not affect any order made or having effect as if made under section 49 or 49A to 49F of this Act (discontinuance, etc., orders).
54A
- (1) Any listed building consent granted after the commencement of this section shall be granted subject to a condition that works permitted by that consent shall be commenced within such period as the planning authority may specify in the consent.
- (2) If no time limit is specified in any grant of listed building consent under subsection (1) above, the grant shall be deemed to have been made subject to a condition that works in terms thereof shall be commenced with 5 years from the date of the grant.
- (3) Any grant of listed building consent made prior to 1st January 1980 which does not contain such a condition as is mentioned in subsection (1) above shall be deemed to have been granted subject to a condition that works in terms thereof shall be commenced within 3 years of the commencement of this section.
- (4) Any grant of listed building consent made on or after 1st January 1980 but before the commencement of this section which does not contain such a condition as is mentioned in subsection (1) above shall be deemed to have been made subject to a condition that works in terms thereof shall be commenced within 5 years of the commencement of this section.]
- (5) Nothing in this section applies to any consent to the retention of works granted under section 53(2A) of this Act.
54B
The date of the granting or of the refusal of an application for listed building consent shall be the date on which the notice of the planning authority’s decision bears to have been signed on behalf of the authority.
54C
- (1) Subject to subsection (2) below, where a local authority—
- (a) have, under or by virtue of any enactment, served a notice requiring any person to show cause why a listed building should not conform to the building regulations; or
- (b) have, under or by virtue of any enactment, served a notice or made an order requiring—
- (i) the demolition of such a building; or
- (ii) the carrying out of works affecting such a building; or
- (c) propose (whether under or by virtue of any enactment or otherwise) to carry out emergency works or demolitions affecting such a building,
they shall forthwith give written intimation of the notice, order, or proposal, as the case may be, to the planning authority:
- (2) Where the safety of the public requires that any demolition or works be carried out without such delay as would result from compliance with the provisions of subsection (1) above, the intimation (which may, in such a case, initially be oral) shall be given as long before the commencement of the demolition or works as is consistent with that requirement.
54D
- (1) Any person interested in a listed building with respect to which listed building consent has been granted subject to conditions may apply to the planning authority for the variation or discharge of the conditions.
- (2) The application shall indicate what variation or discharge of conditions is applied for and the provisions of Part I of Schedule 10 to this Act apply to such an application as they apply to an application for listed building consent.
- (3) On such an application the planning authority or, as the case may be, the Secretary of State may vary or discharge the conditions attached to the consent, and may add new conditions consequential upon the variation or discharge, as they or he think fit.
56AA
- (1) The Secretary of State may by order provide for restricting or excluding in such cases as may be specified in the order the operation in relation to ecclesiastical buildings of sections 54(1) and 56(2) of this Act (buildings excepted from provisions relating to listed buildings and building preservation notices).
- (2) An order under this section may—
- (a) make provision for buildings generally, for descriptions of building or for particular buildings;
- (b) make different provision for buildings in different areas, for buildings of different religious faiths or denominations or according to the use made of the building;
- (c) make such provision in relation to a part of a building (including, in particular, an object or structure falling to be treated as part of the building by virtue of section 52(7) of this Act) as may be made in relation to a building and make different provision for different parts of the same building;
- (d) make different provision with respect to works of different descriptions or according to the extent of the works;
- (e) make such consequential adaptations or modifications of the operation of any other provision of this Act, or of any instrument made under this Act, as appear to the Secretary of State to be appropriate.
- (3) This section is without prejudice to the Church of Scotland Act 1921.
Hazardous substances]
56A
- (1) Subject to subsection (2) of this section . . . , it shall be the duty of the planning authority to control hazardous substances in accordance with the provisions of this Act.
- (2) An urban development corporation shall control hazardous substances in their area if they are the planning authority in relation to all kinds of development.
56B
56C
- (1) Subject to the provisions of this Part of this Act, the presence of a hazardous substance on, over or under land requires the consent of the planning authority (in this Act referred to as “hazardous substances consent”) unless the aggregate quantity of the substance—
- (a) on, under or over the land;
- (b) on, under or over other land which is within 500 metres of it and controlled by the same person; or
- (c) in or on a structure controlled by the same person any part of which is within 500 metres of it,
is less than the controlled quantity.
- (2) The temporary presence of a hazardous substance while it is being transported from one place to another is not to be taken into account unless it is unloaded.
- (3) The Secretary of State—
- (a) shall by regulations specify—
- (i) the substances that are hazardous substances for the purposes of this Act;
- (ii) the quantity which is to be the controlled quantity of any such substance;
- (b) may by regulations provide that hazardous substances consent is not required or is only required—
- (i) in relation to land of prescribed descriptions;
- (ii) by reason of the presence of hazardous substances in prescribed circumstances;
- (c) may by regulations provide that, except in such circumstances as may be prescribed, all hazardous substances falling within a group specified in the regulations are to be treated as a single substance for the purposes of this Act.
- (4) Regulations which—
- (a) are made by virtue of sub-paragraph (i) of subsection (3)(a) above; or
- (b) are made by virtue of sub-paragraph (ii) of that paragraph and reduce the controlled quantity of a substance,
may make such transitional provision as appears to the Secretary of State to be appropriate.
- (5) The power to make such transitional provision includes, without prejudice to its generality, power to apply section 38 of the Housing and Planning Act 1986 subject to such modifications as appear to the Secretary of State to be appropriate.
- (6) Regulations under this section may make different provision for different cases or descriptions of cases.
- (7) Bodies corporate which are inter-connected for the purposes of the Fair Trading Act 1973 are to be treated as being one person for the purposes of this section and sections 56D to 56L and 97B below.
56D
- (1) Provision may be made by regulations with respect to—
- (a) the form and manner in which applications under this Act for hazardous substances consent are to be made;
- (b) the particulars which they are to contain and the evidence by which they are to be verified;
- (c) the manner in which they are to be advertised; and
- (d) the time within which they are to be dealt with.
- (2) Regulations may provide that an application for hazardous substances consent, or an appeal against the refusal of such an application or against the imposition of a condition on such a consent, shall not be entertained unless it is accompanied by a certificate in the prescribed form and corresponding to one or other of those described in section 24(1)(a) to (d) of this Act and any such regulations may—
- (a) include requirements corresponding to those mentioned in sections 23(1), 24(2) and (4) and 26(3), of this Act; and
- (b) make provision as to who is to be treated as the owner of land for the purposes of any provision of the regulations.
- (3) If any person issues a certificate which purports to comply with the requirements of regulations made by virtue of subsection (2) above and which contains a statement which he knows to be false or misleading in a material particular, or recklessly issues a certificate which purports to comply with those requirements and which contains a statement which is false or misleading in a material particular, he shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.
- (4) Regulations—
- (a) may require an applicant for hazardous substances consent or the planning authority or both to give publicity to an application for hazardous substances consent in such manner as may be prescribed;
- (b) may require the planning authority to conduct appropriate consultations before determining applications for hazardous substances consent;
- (c) may provide for the manner in which such a consultation is to be carried out and the time within which—
- (i) such a consultation;
- (ii) any stage in such a consultation,
is to be completed;
- (d) may require the planning authority to determine applications for hazardous substances consent within such time as may be prescribed;
- (e) may require the planning authority to give prescribed persons or bodies prescribed information about applications forhazardous substances consent including information as to the manner in which such applications have been dealt with.
- (5) In subsection (4) above “appropriate consultations” means consultations with the Health and Safety Executive and with such persons or bodies as may be prescribed
- (6) Regulations under this section may make different provision for different cases or descriptions of cases.
56DA
- (1) The Secretary of State may by regulations makeprovision for fees of the prescribed amount in respect of applications for, or for the continuation of, hazardous substances consent—
- (a) made to an urban development corporation under section 56A(2) above to be paid to the corporation;
- (b) referred to him under section 32 above as having effect by virtue of section 56F below to be paid to him;
- (c) deemed to have been made to him under section 85(7) below by virtue of regulations made under section 97B(10) below to be paid to him.
- (2) Regulations made under this section may provide for—
- (a) the transfer to the Secretary of State of any fee received by a planning authority in respect of an application referred to in paragraph (b) or (c) of subsection (1) above;
- (b) the remission or refunding of a prescribed fee (in whole or in part) in prescribed circumstances or in pursuance of a direction given by him;
and the regulations may make different provision for different areas or for different cases or descriptions of cases.
56E
- (1) Subject to the following provisions of this Act, where an application is made to a planning authority for hazardous substances consent, that authority, in dealing with the application, shall have regard to any material considerations, and—
- (a) may grant hazardous substances consent, either unconditionally or subject to such conditions as they think fit; or
- (b) may refuse hazardous substances consent.
- (2) Without prejudice to the generality of subsection (1) above, in dealing with an application the authority shall have regard—
- (a) to any current or contemplated use of the land to which the application relates;
- (b) to the way in which land in the vicinity is being used or is likely to be used;
- (c) to any planning permission that has been granted for development of land in the vicinity;
- (d) to the provisions of the development plan; and
- (e) to any advice which the Health and Safety Executive . . . have given following consultations in pursuance of regulations under section 56D(4) above.
- (3) If an application relates to more than one hazardous substance, the authority may make different determinations in relation to each.
- (4) It shall be the duty of a planning authority, when granting hazardous substances consent, to include in that consent—
- (a) a description of the land to which the consent relates;
- (b) a description of the hazardous substance or substances to which it relates; and
- (c) in respect of each hazardous substance to which it relates, a statement of the maximum amount permitted by the consent to be present at any one time and of all conditions relating to that substance subject to which the consent is granted.
- (5) Without prejudice to the generality of subsection (1) above, a planning authority may grant hazardous substances consent subject to conditions with respect to any of the following—
- (a) how and where any hazardous substance to which the consent relates is to be kept or used;
- (b) times between which any such substance may be present;
- (c) the permanent removal of any such substance—
- (i) on or before a date specified in the consent; or
- (ii) before the end of a period specified in it and commencing on the date on which it is granted;
- (d) the consent being conditional on the commencement or partial or complete execution of development on the land which is authorised by a specified planning permission,
but they may only grant consent subject to conditions as to how a hazardous substance is to be kept or used if the conditions are conditions to which the Health and Safety Executive have advised the authority that any consent they might grant should be subject.
56F
- (1) Subject to subsections (2) . . . below, sections 32 to 34 of this Act . . . shall have effect in relation to applications for hazardous substances consent and to decisions on such applications as though they were applications for planning permission.
- (2) In the application of sections 32 to 34 of this Act to hazardous substances consent—
- (a) section 32(4) and section 33(5) and (7) shall be omitted;
- (b) the words “and in such manner as may be prescribed” shall be substituted for the words in section 33(2) following “time”;
- (c) in section 34, the words “by the development order” shall be omitted from both places where they occur.
- (3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
56G
- (1) Where—
- (a) the authorisation of a government department is required by virtue of an enactment in respect of development to be carried out by a local authority, or by statutory undertakers not being a local authority; and
- (b) the development would involve the presence of a hazardous substance in circumstances requiring hazardous substances consent,
the department may, on granting that authorisation, also direct that hazardous substances consent for that development shall be deemed to be granted subject to such conditions (if any) as may be specified in the directions.
- (2) The department shall consult the Health and Safety Commission before issuing any such directions.
- (3) The provisions of this Act (except Part XII) shall apply in relation to any hazardous substances consent deemed to be granted by virtue of directions under this section as if it had been granted by the Secretary of State on an application referred to him under section 32 of this Act, as applied by section 56F of this Act.
- (4) The reference in subsection (1) above to the authorisation of a government department is to be construed in accordance with section 37(3) of this Act,
- (5) A government department or the Secretary of State shall, as respects any hazardous substances consent deemed to be granted by virtue of directions under this section, send to the planning authority concerned any such information as appears to be required by them for the purposes of a register under section 56N.
56H
- (1) This section applies to an application for hazardous substances consent without a condition subject to which a previous hazardous substances consent was granted or is deemed to have been granted.
- (2) On such an application the planning authority shall consider only the question of the conditions subject to which hazardous substances consent should be granted, and—
- (a) if they determine that hazardous substances consent should be granted subject to conditions differing from those subject to which the previous consent was granted, or that it should be granted unconditionally, they shall grant hazardous substances consent accordingly; and
- (b) if they determine that hazardous substances consent should be granted subject to the same conditions as those subject to which the previous consent was granted, they shall refuse the application.
- (3) Where—
- (a) hazardous substances consent has been granted or is deemed to have been granted for the presence on, over or under land of more than one hazardous substance; and
- (b) an application under this section does not relate to all the substances,
the planning authority shall only have regard to any condition relating to a substance to which the application does not relate to the extent that it has implications for a substance to which the application does relate.
- (4) Where—
- (a) more than one hazardous substances consent has been granted or is deemed to have been granted in respect of the same land; and
- (b) an application under this section does not relate to all the consents,
the planning authority shall only have regard to any consent to which the application does not relate to the extent that it has implications for a consent to which the application does relate.
- (5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
56J
- (1) If it appears to the planning authority that—
- (a) there has been a material change of use of land to which a hazardous substances consent relates; or
- (b) planning permission has been granted for development the carrying out of which would involve a material change of use of such land and the development to which the permission relates has been commenced,
they may by order—
- (i) if the consent relates only to one substance, revoke it;
- (ii) if it relates to more than one, revoke it or revoke it so far as it relates to a specified substance.
- (2) The planning authority may by order—
- (a) revoke a hazardous substances consent which relates to only one substance if it appears to them that that substance has not for at least 5 years been present on, under or over the land to which the consent relates in a quantity equal to or exceeding the controlled quantity; and
- (b) revoke a hazardous substances consent which relates to a number of substances if it appears to them that none of those substances has for at least 5 years been so present.
- (3) The planning authority may by order revoke a hazardous substances consent or modify it to such extent as they consider expedient if it appears to them, having regard to any material consideration, that it is expedient to revoke or modify it.
- (4) An order under this section shall specify the grounds on which it is being made.
- (5) An order under this section, . . . , shall not take effect unless it is confirmed by the Secretary of State, and the Secretary of State may confirm any such order submitted to him either without modification or subject to such modification as he considers expedient.
- (6) Where a planning authority submit an order under this section to the Secretary of State for his confirmation under this section, the authority shall serve notice of the order on—
- (a) any person who is an owner, occupier or lessee of the whole or any part of the land to which the order relates; and
- (b) any other person who in their opinion will be affected by the order;
and if within the period specified in that behalf in the notice (not being less than 28 days from the service thereof) any person on whom the notice is served so requires, the Secretary of State, before confirming the order, shall afford to that person and to the planning authority an opportunity of appearing before, and being heard by, a person appointed by the Secretary of State for that purpose.
- (7) Where an order under this section has been confirmed by the Secretary of State, the planning authority shall serve a copy of the order on every person who was entitled to be served with notice under subsection (6) of this section.
- (8) Section 159 of this Act shall have effect where a hazardous substances consent is revoked or modified by an order made in the exercise of the power conferred by subsection (3) of this section as it has effect where an order is made under section 49 of this Act.
56K
- (1) Without prejudice to the provisions of this Part of this Act, any hazardous substances consent shall (except in so far as it otherwise provides) enure for the benefit of the land to which it relates and of all persons for the time being interested in the land.
- (2) A hazardous substances consent is revoked if there is a change in the person in control of part of the land to which it relates unless an application for the continuation of the consent has previously been made to the planning authority.
- (3) Regulations may make provision in relation to applications under subsection (2) above corresponding to any provision that may be made by regulations under section 56D of this Act in relation to applications for hazardous substances consent.
- (4) When such application is made, the authority, having regard to any material consideration—
- (a) may modify the consent in any way they consider appropriate; or
- (b) may revoke it.
- (5) Without prejudice to the generality of subsection (4) above, in dealing with an application the authority shall have regard—
- (a) to the matters to which a planning authority are required to have regard by section 56E(2)(a) to (d) above; and
- (b) to any advice which the Health and Safety Executive . . . have given following consultations in pursuance of regulations under subsection (3) above.
- (6) If an application relates to more than one consent, the authority may make different determinations in relation to each.
- (7) If a consent relates to more than one hazardous substance, the authority may make different determinations in relation to each.
- (8) It shall be the duty of a planning authority, when continuing hazardous substances consent, to attach to the consent one of the following—
- (a) a statement that is unchanged in relation to the matters included in it by virtue of section 56E(4) above;
- (b) a statement of any change in respect of those matters.
- (9) The modifications which a planning authority may make by virtue of subsection (4)(a) above include, without prejudice to the generality of that paragraph, the making of the consent subject to conditions with respect to any of the matters mentioned in section 56E(5) above.
- (10) Subject to subsection (11) below, sections 32 to 34 of this Act . . . shall have effect in relation to applications under subsection (2) above and to decisions on such applications as though they were applications for planning permission.
- (11) In the application of sections 32 to 34 of this Act by virtue of subsection (10) above—
- (a) section 32(4) and section 33(5) and (7) shall be omitted;
- (b) the words “and in such manner as may be prescribed” shall be substituted for the words in section 33(2) following “time”;
- (c) in section 34—
- (i) the words “by the development order” shall be omitted from the first place where they occur; and
- (ii) the words “the application shall be deemed to have been granted” shall be substituted for the words following paragraph (b).
- (12) Where the authority modify or revoke the consent, they shall pay to the person in control of the whole of the land before the change compensation in respect of any loss or damage sustained by him and directly attributable to the modification or revocation.
56L
- (1) Subject to this Part of this Act, if there is a contravention of hazardous substances control, the appropriate person shall be guilty of an offence.
- (2) There is a contravention of hazardous substances control—
- (a) if a quantity of a hazardous substance equal to or exceeding the controlled quantity is or has been present on, under or over land and either—
- (i) there is no hazardous substances consent for the presence of the substance; or
- (ii) there is hazardous substances consent for its presence but the quantity present exceeds the maximum quantity permitted by the consent;
- (b) if there is or has been a failure to comply with a condition subject to which a hazardous substances consent was granted.
- (3) In subsection (1) above
- “the appropriate person” means—
- (a) in relation to a contravention falling within paragraph (a) of subsection (2) above—
- (i) any person knowingly causing the substance to be present on, over or under the land;
- (ii) any person allowing it to be so present; and
- (b) in relation to a contravention falling within paragraph (a) or (b) of that subsection, the occupier of the land.
- (4) A person guilty of an offence under this section shall be liable—
- (a) on summary conviction, to a fine not exceeding £20,0; or
- (b) on conviction on indictment, to a fine,
- (4A) In determining the amount of any fine to be imposed on a person convicted of an offence under this section, the court shall in particular have regard to any financial benefit which has accrued or appears likely to accrue to him in consequence of the offence.
- (5) In any proceedings for an offence under this section it shall be a defence for the accused to prove—
- (a) that he took all reasonable precautions and exercised all due diligence to avoid commission of the offence; or
- (b) that commission of the offence could be avoided only by the taking of action amounting to a breach of a statutory duty.
- (6) In any proceedings for an offence consisting of a contravention falling within subsection (2)(a) above, it shall be a defence for the accused to prove that at the time of the alleged commission of the offence he did not know, and had no reason to believe—
- (a) if the case falls within paragraph (a)(i)
- (i) that the substance was present; or
- (ii) that it was present in a quantity equal to or exceeding the controlled quantity;
- (b) if the case falls within paragraph (a)(ii), that the substance was present in a quantity exceeding the maximum quantity permitted by the consent.
- (7) In any proceedings for an offence consisting of a contravention falling within subsection (2)(b) above, it shall be a defence for the accused to prove that he did not know, and had no reason to believe, that he was failing to comply with a condition subject to which hazardous substances consent had been granted.
56M
- (1) If it appears to the Secretary of State—
- (a) either—
- (i) that the community or part of it is being or is likely to be deprived of an essential service or commodity; or
- (ii) that there is or is likely to be a shortage of such a service or commodity affecting the community or part of it; and
- (b) that the presence of a hazardous substance on, over or under land specified in the direction in circumstances such that hazardous substances consent would be required, is necessary for the effective provision of that service or commodity,
he may direct that, subject to such conditions or exceptions as he thinks fit, the presence of the substance on, over or under the land is not to constitute a contravention of hazardous substances control so long as the direction remains in force.
- (2) A direction under this section—
- (a) may be withdrawn at any time;
- (b) shall in any case cease to have effect at the end of the period of three months beginning with the day on which it was given, but without prejudice to the Secretary of State’s power to give a further direction.
- (3) . . . The Secretary of State shall send a copy of any such direction to the planning authority in relation to the land.
- (4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
56N
- (1) Every planning authority shall keep, in such manner as may be prescribed, a register containing such information as may be so prescribed with respect—
- (a) to applications for hazardous substances consent made to that authority;
- (aa) to applications under section 56K(2) above made to that authority;
- (b) to hazardous substances consent deemed to be granted under section 38 of the Housing and Planning Act 1986 with respect to land in relation to which that authority is . . . the planning authority;
- (c) to revocations or modifications of hazardous substances consent granted with respect to such land; and
- (d) to directions under section 56M above sent to the authority by the Secretary of State, , and every such register shall also contain such information as may be prescribed as to the manner in which applications for hazardous substances consent have been dealt with.
- (2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
- (3) Every register kept under this section shall be available for inspection by the public at all reasonable hours.
56O
- (1) Nothing in—
- (a) any hazardous substances consent granted or deemed to be granted under—
- (i) the preceding provisions of this Act; or
- (ii) section 38 of the Housing and Planning Act 1986; or
- (b) any hazardous substances contravention notice issued under section 97B of this Act,
shall require or allow anything to be done in contravention of any of the relevant statutory provisions or any prohibition notice or improvement notice served under or by virtue of any of those provisions; and to the extent that such a consent or notice purports to require or allow any such thing to be done, it shall be void.
- (2) Where it appears to a planning authority who have granted or are deemed to have granted a hazardous substances consent or who have issued a hazardous substances contravention notice that the consent or notice or part of it is rendered void by subsection (1) above, the authority shall, as soon as is reasonably practicable, consult the Health and Safety Executive with regard to the matter.
- (3) If the Health and Safety Executive advise the authority that the consent or notice is rendered wholly void, the authority shall revoke it.
- (4) If they advise that part of the consent or notice is rendered void, the authority shall so modify it as to render it wholly operative.
- (5) In this section— . . .
59A
- (1) Subject to the provisions of this section, any person who, in relation to a tree to which this section applies, does any act which might by virtue of section 58(1)(a) above be prohibited by a tree preservation order shall be guilty of an offence.
- (2) Subject to the provisions of this section, this section applies to any tree in a conservation area but in respect of which no tree preservation order is for the time being in force.
- (3) It shall be a defence for a person charged with an offence under subsection (1) above to prove—
- (a) that he served notice of his intention to do the act in question, with sufficient particulars to identify the tree, on the planning authority in whose district the tree is or was situated; and
- (b) that he did the act in question—
- (i) with the consent of the said planning authority, or
- (ii) after the expiry of the period of six weeks from the date of the notice but before the expiry of the period of two years from that date.
- (4) The Secretary of State may by regulations direct that this section shall not apply in such cases as may be specified in the regulations.
- (5) Without prejudice to the generality of subsection (4) above, the regulations may be framed so as to exempt from the application of this section cases defined by reference to all or any of the following matters, namely—
- (a) acts of such descriptions or done in such circumstances or subject to such conditions as may be specified in the regulations;
- (b) trees in such conservation areas as may be so specified;
- (c) trees of a size or species so specified; or
- (d) trees belonging to persons or bodies of a description so specified;
and the regulations may, in relation to any matter by reference to which an exemption is conferred by them, make different provision for different circumstances.
- (6) Regulations under subsection (4) above may in particular, but without prejudice to the generality of that subsection, exempt from the application of this section cases exempted from the application of section 58 above by subsection (6) of that section.
- (7) It shall be the duty of every planning authority to compile and keep available for public inspection free of charge at all reasonable hours and at a convenient place a list, containing such particulars as the Secretary of State may determine of notices under this section affecting trees in their district.
- (8) If any tree to which this section applies is removed, uprooted or destroyed in contravention of this section or is removed, uprooted or destroyed or dies at a time when its uprooting or felling is authorised only by virtue of the provisions of such regulations under subsection (4) above as are mentioned in subsection (6) above, it shall be the duty of the owner of the land, unless on his application the planning authority dispense with this requirement, to plant another tree of an appropriate size and species at the same place as soon as he reasonably can.
- (9) The duty imposed by subsection (8) above on the owner of any land shall attach to the person who is from time to time the owner of he land and may be enforced as provided by section 99 of this Act and not otherwise.
63A
- (1) A person on whom a notice under section 63 of this Act is served, or any other person having an interest in the land to which the notice relates, may at any time before the date specified in the notice as the date on which it is to take effect appeal to the Secretary of State against the notice, on any of the following grounds—
- (a) that neither the amenity of any part of the planning authority’s district nor that of any adjoining district has been adversely affected;
- (b) that the steps required by the notice to be taken exceed what is necessary to remedy any such adverse effect;
- (c) that the specified period for compliance with the notice falls short of what should reasonably be allowed;
- (d) that the condition of the land is attributable to, and such as results in the ordinary course of events from, a continuing lawful use of the land or from continuing lawful operations carried out thereon; or
- (e) that the notice was served other than in accordance with section 63 of this Act.
- (2) An appeal under this section shall be made by notice in writing to the Secretary of State.
- (3) The provisions of subsections (2A) to (2D) of section 85 of this Act shall apply to appeals under this section as they apply to appeals under that section.
- (4) On an appeal under this section the Secretary of State—
- (a) may correct any informality, defect or technical error in the notice if he is satisfied that it is not material; and
- (b) may disregard the failure of the planning authority to serve the notice upon a person upon whom it should have been served, if it appears to him that neither that person nor the appellant has been substantially prejudiced by that failure.
- (5) Where an appeal is brought under this section, the notice under section 63 of this Act shall be of no effect pending the final determination, or the withdrawal, of the appeal.
- (6) In determining an appeal under this section the Secretary of State shall give such directions as seem to him appropriate; and these may include directions for quashing the notice or for varying its terms in favour of the appellant.
- (7) Subject to section 279 of this Act, Schedule 7 to this Act applies to appeals under this section.
Introductory
83A
- (1) For the purposes of this Act—
- (a) carrying out development without the required planning permission; or
- (b) failing to comply with any condition or limitation subject to which planning permission has been granted,
constitutes a breach of planning control.
- (2) For the purposes of this Act—
- (a) the issue of an enforcement notice (defined in section 84 of this Act); or
- (b) the service of a breach of condition notice (defined in section 87AA of this Act),
constitutes taking enforcement action.
- (3) In this Part of this Act “planning permission” includes planning permission under Part III of the Town and Country Planning (Scotland) Act 1947.
83B
- (1) Where there has been a breach of planning control consisting in the carrying out without planning permission of building, engineering, mining or other operations in, on, over or under land, no enforcement action may be taken after the end of the period of four years beginning with the date on which the operations were substantially completed.
- (2) Where there has been a breach of planning control consisting in the change of use of any building to use as a single dwellinghouse, no enforcement action may be taken after the end of the period of four years beginning with the date of the breach.
- (3) In the case of any other breach of planning control, no enforcement action may be taken after the end of the period of ten years beginning with the date of the breach.
- (4) The preceding subsections do not prevent—
- (a) the service of a breach of condition notice in respect of any breach of planning control if an enforcement notice in respect of the breach is in effect; or
- (b) taking further enforcement action in respect of any breach of planning control if, during the period of four years ending with that action being taken, the planning authority have taken or purported to take enforcement action in respect of that breach.
Planning contravention notices
83C
- (1) Where it appears to the planning authority that there may have been a breach of planning control in respect of any land, they may serve notice to that effect (referred to in this Act as a “planning contravention notice”) on any person who—
- (a) is the owner or occupier of the land or has any other interest in it; or
- (b) is carrying out operations on the land or is using it for any purpose.
- (2) A planning contravention notice may require the person on whom it is served to give such information as to—
- (a) any operations being carried out on the land, any use of the land and any other activities being carried out on the land; and
- (b) any matter relating to the conditions or limitations subject to which any planning permission in respect of the land has been granted,
as may be specified in the notice.
- (3) Without prejudice to the generality of subsection (2) of this section, the notice may require the person on whom it is served, so far as he is able—
- (a) to state whether or not the land is being used for any purpose specified in the notice or any operations or activities specified in the notice are being or have been carried out on the land;
- (b) to state when any use, operations or activities began;
- (c) to give the name and address of any person known to him to use or have used the land for any purpose or to be carrying out, or have carried out, any operations or activities on the land;
- (d) to give any information he holds as to any planning permission for any use or operations or any reason for planning permission not being required for any use or operation;
- (e) to state the nature of his interest (if any) in the land and the name and address of any other person known to him to have an interest in the land.
- (4) A planning contravention notice may give notice of a time and place at which—
- (a) any offer which the person on whom the notice is served may wish to make to apply for planning permission, to refrain from carrying out any operations or activities or to undertake remedial works; and
- (b) any representations which he may wish to make about the notice,
will be considered by the authority, and the authority shall give him an opportunity to make in person any such offer or representations at that time and place.
- (5) A planning contravention notice must inform the person on whom it is served—
- (a) of the likely consequences of his failing to respond to the notice and, in particular, that enforcement action may be taken; and
- (b) of the effect of section 166(6) of this Act.
- (6) Any requirement of a planning contravention notice shall be complied with by giving information in writing to the planning authority.
- (7) The service of a planning contravention notice does not affect any other power exercisable in respect of any breach of planning control.
- (8) In this section references to operations or activities on land include operations or activities in, under or over the land.
83D
- (1) If at any time after the end of the period of twenty-one days beginning with the day on which a planning contravention notice has been served on any person, he has not complied with any requirement of the notice, he shall be guilty of an offence.
- (2) An offence under subsection (1) of this section may be charged by reference to any day or longer period of time and a person may be convicted of a second or subsequent offence under that subsection by reference to any period of time following the preceding conviction for such an offence.
- (3) It shall be a defence for a person charged with an offence under subsection (1) of this section to prove that he had a reasonable excuse for failing to comply with the requirement.
- (4) A person guilty of an offence under subsection (1) of this section shall be liable on summary conviction to a fine not exceeding level 3 on the standard scale.
- (5) If any person—
- (a) makes any statement purporting to comply with a requirement of a planning contravention notice which he knows to be false or misleading in a material particular; or
- (b) recklessly makes such a statement which is false or misleading in a material particular,
he shall be guilty of an offence.
- (6) A person guilty of an offence under subsection (5) of this section shall be liable on summary conviction to a fine not exceeding level 5 on the standard scale.
84AA
- (1) An enforcement notice shall state—
- (a) the matters which appear to the planning authority to constitute the breach of planning control; and
- (b) the paragraph of section 83A(1) of this Act within which, in the opinion of the authority, the breach falls.
- (2) A notice complies with subsection (1)(a) of this section if it enables any person on whom a copy of it is served to know what those matters are.
- (3) An enforcement notice shall specify the steps which the authority require to be taken, or the activities which the authority require to cease, in order to achieve, wholly or partly, any of the following purposes.
- (4) Those purposes are—
- (a) remedying the breach by making any development comply with the terms (including conditions and limitations) of any planning permission which has been granted in respect of the land by discontinuing any use of the land or by restoring the land to its condition before the breach took place; or
- (b) remedying any injury to amenity which has been caused by the breach.
- (5) An enforcement notice may, for example, require—
- (a) the alteration or removal of any buildings or works;
- (b) the carrying out of any building or other operations;
- (c) any activity on the land not to be carried on except to the extent specified in the notice; or
- (d) the contour of a deposit of refuse or waste materials on land to be modified by altering the gradient or gradients of its sides.
- (6) An enforcement notice issued in respect of a breach of planning control consisting of demolition of a building may require the construction of a building (in this section referred to as a “replacement building”) which, subject to subsection (7) of this section, is as similar as possible to the demolished building.
- (7) A replacement building—
- (a) must comply with any requirement imposed by or under any enactment applicable to the construction of buildings;
- (b) may differ from the demolished building in any respect which, if the demolished building had been altered in that respect, would not have constituted a breach of planning control;
- (c) must comply with any regulations made for the purposes of this subsection (including regulations modifying paragraphs (a) and (b) of this subsection).
- (8) An enforcement notice shall specify the date on which it is to take effect and, subject to section 85(3) of this Act, shall take effect on that date.
- (9) An enforcement notice shall specify the period at the end of which any steps are required to have been taken or any activities are required to have ceased and may specify different periods for different steps or activities; and, where different periods apply to different steps or activities, references in this Part of this Act to the period for compliance with an enforcement notice, in relation to any step or activity, are to the period at the end of which the step is required to have been taken or the activity is required to have ceased.
- (10) An enforcement notice shall specify such additional matters as may be prescribed, and regulations may require every copy of an enforcement notice served under section 84 of this Act to be accompanied by an explanatory note giving prescribed information as to the right of appeal under section 85 of this Act.
- (11) Where—
- (a) an enforcement notice in respect of any breach of planning control could have required any buildings or works to be removed or any activity to cease, but does not do so; and
- (b) all the requirements of the notice have been complied with,
then, so far as the notice did not so require, planning permission shall be treated as having been granted under section 29 of this Act in respect of development consisting of the construction of the buildings or works or, as the case may be, the carrying out of the activities.
- (12) Where—
- (a) an enforcement notice requires the construction of a replacement building; and
- (b) all the requirements of the notice with respect to that construction have been complied with,
planning permission shall be treated as having been granted under section 29 of this Act in respect of development consisting of that construction.
84AB
- (1) The planning authority may—
- (a) withdraw an enforcement notice issued by them; or
- (b) waive or relax any requirement of such a notice and, in particular, may extend any period specified in accordance with section 84AA(9) of this Act.
- (2) The powers conferred by subsection (1) may be exercised whether or not the notice has taken effect.
- (3) The planning authority shall, immediately after exercising the powers conferred by subsection (1), give notice of the exercise to every person who has been served with a copy of the enforcement notice or would, if the notice were re-issued, be served with a copy of it.
- (4) The withdrawal of an enforcement notice does not affect the power of the planning authority to issue a further enforcement notice.
84A
Breach of condition
87AA
- (1) This section applies where planning permission for carrying out any development has been granted subject to conditions.
- (2) The planning authority may, if any of the conditions is not complied with, serve a notice (in this Act referred to as a “breach of condition notice”) on—
- (a) any person who is carrying out or has carried out the development; or
- (b) any person having control of the land,
requiring him to secure compliance with such of the conditions as are specified in the notice.
- (3) References in this section to the person responsible are to the person on whom the breach of condition notice has been served.
- (4) The conditions which may be specified in a notice served by virtue of subsection (2)(b) of this section are any of the conditions regulating the use of the land.
- (5) A breach of condition notice shall specify the steps which the authority consider ought to be taken, or the activities which the authority consider ought to cease, to secure compliance with the conditions specified in the notice.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.