Channel Tunnel Act 1987
- (1) Before commencing the construction of any of Works Nos. 9A, 9B, 10A, 11 or 17 the Concessionaires shall submit to the County Council for their approval plans, sections and specifications (below in this paragraph referred to as “plans”) of the work and, unless the Concessionaires and the County Council otherwise agree, it shall not be constructed except in accordance with the plans submitted to the County Council and approved by them or, on application made to the Secretary of State by the Concessionaires after disapproval of the plans by the County Council, approved by him.
- (2) If within 28 days after the plans have been submitted the County Council have not approved or disapproved them, they shall be deemed to have approved the plans as submitted.
20
- (1) If it appears to the County Council that the construction of Work No. 17 will not be completed on or before the date on which their scheduled works will be completed and open for public use, they may by notice require the Concessionaires to complete the construction of that work by such reasonable date as they may specify in the notice.
- (2) Any difference about the reasonableness of any date specified in a notice under sub-paragraph (1) above shall be determined by the Secretary of State.
- (3) The Secretary of State shall certify the date on which the construction of Work No. 17 has been completed.
Repair of highways and agreements with highway authorities
21
- (1) Notwithstanding anything in section 46 of the Railways Clauses Consolidation Act 1845, as incorporated with this Act, the appropriate authority shall not be liable to maintain the surface of any highway under or over which the scheduled works shall be constructed or the immediate approaches thereto.
- (2) Except as provided in sub-paragraph (3) below, any new highway constructed by the Concessionaires or the Railways Board under this Act in substitution for an existing highway or part thereof shall, unless otherwise agreed between the Concessionaires or the Railways Board and the County Council, be maintained by and at the expense of the Concessionaires or the Railways Board for a period of twelve months from the date certified as the date on which it has been completed and is open for public use and, at the end of that period, shall be maintained by and at the expense of the County Council.
- (3) The new bridleway between the points G1 and G2 shown on the deposited plans to be substituted for the part of the existing bridleway in the district of Shepway (parishes of Hythe and Newington) between those points shall, when completed, be maintained by and at the expense of the Concessionaires.
- (4) Sections 116 and 117 of the Transport Act 1968 (responsibility for the maintenance of highway bridges over railways) shall apply to the Concessionaires as if they were one of the boards mentioned in those sections.
- (5) Where under this Act the appropriate authority are authorised to stop up or interfere with an existing highway or part thereof, they may enter into agreements with the persons having the charge, management or control of the highway concerning the construction, or a contribution towards the expense of the construction, of any new highway to be provided in substitution therefor or of any alteration of the existing highway and any other related matters.
- (6) The appropriate authority may, by agreement with any such persons, delegate to them the power of constructing any such new highway or any such alteration of an existing highway, including any bridge over any railway, and, where the appropriate authority are responsible for maintaining the new or altered highway (or bridge), the power to maintain it.
Temporary interference with highways
22
- (1) The appropriate authority may, for the purpose of constructing or maintaining works which they are authorised to construct under this Act, temporarily stop up, break up or interfere with, or alter or divert, the whole or any part of any highway within the limits of land to be acquired or used and may carry out and do all necessary works and things for, or in connection with, the stopping up, opening, breaking up, interference, alteration or diversion and for keeping the highway open for traffic.
- (2) The appropriate authority shall provide reasonable access for all persons, with or without vehicles, going to or returning from premises abutting on any highway affected by the exercise of the powers conferred by this paragraph.
Power to use subsoil of highways
23
Subject to the provisions of this Act the appropriate authority may enter upon, take and use for the purposes of this Act so much of the subsoil and under-surface of any highway within the limits of deviation for their scheduled works as shall be required for the purpose of the construction or maintenance of those works, without being required to acquire that subsoil and under-surface or any interest therein.
Status of certain highways constructed by the Concessionaires
24
- (1) The Secretary of State shall certify points on Works Nos. 9E and 9F to which each of those works from their commencement shall be special roads.
- (2) On the date certified by the Secretary of State as the date on which the roads forming the parts of those works from their commencement to those points have been completed and are open for public use, those roads shall become trunk roads and special roads for the exclusive use of traffic of Classes I and II of the classes of traffic specified in Schedule 4 to the Highways Act 1980 as if they had been provided by the Secretary of State in pursuance of a scheme made by him under section 16 of that Act—
- (a) prescribing the route of those roads as the route for the special roads to be provided under the scheme;
- (b) prescribing both those classes of traffic; and
- (c) specifying that date as the date on which those special roads were to become trunk roads.
- (3) The provisions of sub-paragraph (2) above shall be treated for the purposes of that Act as provisions of a scheme under that section.
- (4) On the date certified in relation to any new highway under paragraph 18(1) above the road which is the highway shall be transferred to the Kent County Council.
- (5) Where the construction of any part of the road forming Work No. 17 has been completed the Secretary of State may, if the part concerned was not a highway at the passing of this Act, certify a date on which it is to be transferred to that Council.
- (6) In the case of any new road constructed by the Concessionaires in pursuance of this Schedule, other than one to which sub-paragraph (2), (4) or (5) above applies, the Secretary of State may certify a date on which that road is to be transferred to that Council.
- (7) On the date certified in relation to any road or part of a road under sub-paragraph (5) or (6) above, that road or part of a road shall be transferred to that Council.
- (8) Subject to paragraph 27(4)(b) below, following a transfer under sub-paragraph (4) or (7) above the road or part of a road transferred shall be treated as if it had been constructed by that Council in exercise of their powers under section 24(2) of the Highways Act 1980.
- (9) The Secretary of State may classify any road proposed to be constructed which may be transferred to that Council under this paragraph in any manner in which, and for any purposes for which, he could under section 12(3) of that Act classify a proposed highway for which that Council are the highway authority.
- (10) On the date of its transfer to that Council any road classified under sub-paragraph (9) above shall become a highway classified in the manner and for the purposes in question as if so classified under section 12(3) of that Act.
Status of the County Council's works
25
The construction by the Kent County Council of a highway in pursuance of this Act shall be treated as the construction of a highway in pursuance of section 24(2) of the Highways Act 1980.
Regulation of traffic on new roads
26
- (1) Subject to sub-paragraph (2) below, any power under the Road Traffic Regulation Act 1984 to make an order or to give a direction with respect to any road shall be exercisable in relation to any road forming or forming part of any of the Concessionaires’ or the County Council’s scheduled works before that road is open for public use, in any case where it appears to the Secretary of State to be expedient that the order or (as the case may be) the direction should have effect immediately on the road’s becoming open for public use.
- (2) The procedure otherwise applicable under that Act in relation to the making of any such order or the giving of any such direction shall apply in any such case with such modifications as the Secretary of State may determine; and he shall publish notice of those modifications in such manner as appears to him to be appropriate for bringing them to the notice of persons likely to be affected by the provisions of any such order or (as the case may be) by any such direction.
Compensation for, and mitigation of, adverse effects of certain authorised works
27
- (1) Subject to the following provisions of this paragraph, the Secretary of State is the responsible authority for the purposes of Parts I and II of the Land Compensation Act 1973 (compensation for, and mitigation of, injurious effects of public works) as respects the Concessionaires’ scheduled works and any other works of the Concessionaires authorised by this Act (including the construction or alteration of any highway).
- (2) Where a claim under Part I of that Act relates to depreciation caused by use of the road forming Work No. 17—
- (a) if and so far as it relates to depreciation that would not have been caused but for the opening to public traffic of Kent County Council’s scheduled works, that Council shall be the responsible authority in relation to it; and
- (b) if and so far as the Secretary of State is the responsible authority in relation to it, no account shall be taken in assessing compensation of any use or expected intensification of use of that road due to that opening.
- (3) If and so far as the Kent County Council are the responsible authority in relation to a claim under that Part of that Act by virtue of sub-paragraph (2)(a) above, that Part of that Act shall have effect in relation to the claim as if—
- (a) the relevant date were the date on which all of their scheduled works were first open to public traffic;
- (b) the increase in value to be taken into account under section 6 were any increase that would not have been caused but for the opening to public traffic of those works; and
- (c) subsection (1) of section 8 did not preclude the payment of compensation unless the previous claim was in respect of depreciation that would not have been caused but for that opening and subsection (2) of that section did not preclude the payment of compensation.
- (4) Subject to the following provisions of this paragraph, the Noise Insulation Regulations 1975 shall have effect as if—
- (a) the Secretary of State were the appropriate highway authority in relation to all of the Concessionaires’ scheduled works and other works of the Concessionaires authorised by this Act which are highways, except the road forming Work No. 17;
- (b) Work No. 17 were, as from the commencement of its construction, the construction of a highway by the Kent County Council; and
- (c) the relevant noise level, in relation to the road forming that work, did not include any level of noise caused or expected to be caused by traffic using or expected to use it before the date on which all of Kent County Council’s scheduled works are first open to public traffic.
- (5) Notwithstanding anything in sub-paragraph (1) or (4) above, the Secretary of State—
- (a) is not liable to satisfy any claim under Part I of the Land Compensation Act 1973 in connection with the use of any highway for which he is not the highway authority; and
- (b) does not have any obligation or power under the Noise Insulation Regulations 1975 in connection with the use or alteration of any such highway;
if and so far as the claim, obligation or power arises in connection with the alteration of the highway otherwise than in pursuance of this Act.
- (6) Subject to the following provisions of this paragraph, in the case of any of the Concessionaires’ scheduled works and any other works of the Concessionaires authorised by this Act which involve the construction or alteration of a highway, the Secretary of State shall have the powers and duties of a highway authority under—
- (a) section 28 of that Act (power to pay expenses of persons moving temporarily during construction works); and
- (b) sections 246, 253 and 282 of the Highways Act 1980 (which relate respectively to acquisition of land, agreements with respect to use of land and execution of works for the purpose of mitigating adverse effects of highways);
as if he were constructing or altering, or proposing to construct or alter, the highway, and references in those sections to a highway authority shall be construed accordingly.
- (7) The Secretary of State may with the consent of the Kent County Council by order made by statutory instrument transfer to that Council, on such terms as may be provided in the order—
- (a) any land acquired by him under section 246 of the Highways Act 1980; and
- (b) any rights and liabilities acquired by or accrued to him under that section, section 253 or 282 of the Highways Act 1980 or the Noise Insulation Regulations 1975;
by virtue of this paragraph.
- (8) For the purposes of section 26 of the Land Compensation Act 1973 (power of responsible authority to acquire land by agreement for the purpose of mitigating any adverse effects of public works) the Concessionaires’ and the Railways Board’s scheduled works and any other works of the Concessionaires or (as the case may be) of the Railways Board authorised by this Act shall be treated as public works notwithstanding that they form part of a statutory undertaking as defined by section 336(1) of the Town and Country Planning Act 1990.
SCHEDULE 3
Preliminary
1
In this Schedule—
- “authorised development” means development to which the planning permission deemed by section 9(1) of this Act to have been granted under Part III of the Act of 1971 relates;
- “spoil” means spoil from tunnelling works; and
- “surplus spoil” means spoil which is not used for the purposes of any of the works authorised by this Act.
Scheme of operation for authorised development
2
Any authorised development shall be carried out in accordance with a scheme of operation consisting of the arrangements with respect to the matters mentioned in the left-hand column of the following table which the appropriate planning authority have, at the request of the Concessionaires, for the time being approved as the arrangements which are to be adopted in carrying out the development to which the scheme relates.
Detailed plans and specifications for certain authorised development
3
To the extent that any authorised development consists of any operation or work mentioned in the left-hand column of the following table it shall be carried out in accordance with detailed plans and specifications approved, at the request of the Concessionaires, by the appropriate planning authority.
Spoil
4
- (1) No surplus spoil shall be deposited except on the landward side of the sea wall.
- (2) No more than the maximum permitted amount of spoil shall be deposited there (whether or not as surplus spoil).
- (3) The maximum permitted amount of spoil is the amount deriving from the excavation of 3.75 million cubic metres of unexcavated material.
- (4) The functions of a local planning authority of issuing enforcement notices under section 87 of the Act of 1971 or serving stop notices under section 90 of that Act shall be exercisable by the county planning authority so far as they relate to a breach of planning control consisting of failure to comply with the requirement imposed by sub-paragraph (2) above.
- (5) The county planning authority may by notice in writing require the Concessionaires to give in writing within twenty-one days after the date on which the notice is served, or such longer time as may be specified in the notice or as the authority may allow, such information as may be so specified as to—
- (a) the amount of spoil which has been deposited on the landward side of the sea wall; and
- (b) the rate at which spoil is to be deposited there in the future;
and any information as to an amount of spoil shall be given by reference to the volume of the material from which it derives in its unexcavated state.
- (6) Subsections (2) and (3) (offences) of section 284 of the Act of 1971 shall have effect in relation to notices under sub-paragraph (5) above as they have effect in relation to notices under subsection (1) of that section.
5
- (1) The methods to be employed in, and the timing of, the deposit of spoil on the landward side of the sea wall shall be in accordance with arrangements approved, at the request of the Concessionaires, by the county planning authority.
- (2) The height of the spoil deposited on the landward side of the sea wall shall not exceed the maximum specified in those arrangements.
- (3) Finishing treatment shall be applied to the surface of the spoil deposited there in accordance with those arrangements.
- (4) The county planning authority shall not refuse, or impose conditions on the grant of, any approval required for the purposes of this paragraph unless they are satisfied that it is expedient to do so on the ground that the arrangements ought to be modified to preserve the amenity of the neighbourhood or the marine environment or in the interests of nature conservation and are reasonably capable of being so modified.
6
Once the tunnel system has been brought into operation, the Concessionaires shall, in accordance with a scheme agreed with the county planning authority or, in default of agreement or on notice being given by the Secretary of State to the authority and the Concessionaires, settled by him, put so much of the area on the landward side of the sea wall as consists of land reclaimed by the deposit of spoil and is not required for or in connection with the operation of the tunnel system into such a condition as the scheme may provide.
Protection of site at Holywell Coombe
7
- (1) No part of Work No. 3 shall be constructed in any part of the protected site.
- (2) Nothing shall be done in any part of the protected site in connection with the construction of that work except necessary drainage work and landscaping of the site.
- (3) No part of that work shall be constructed, and nothing shall be done in connection with the construction of that work, anywhere else unless—
- (a) the southern boundary of the protected site is fenced; or
- (b) that boundary has been fenced but the fencing has been temporarily removed because it was necessary to remove it in order to carry out necessary drainage work or landscaping of the site.
- (4) In this paragraph “the protected site” means the area of land at Holywell Coombe in the district of Shepway (town of Folkestone) bounded on the southern side by a straight line between National Grid reference points 622058E 138078N and 622138E 138095N, on the western and eastern sides by straight lines passing due north from each of those points to the limit of deviation of Work No. 3 and on the northern side by that limit.
Arrangements and schemes for certain authorised development
8
- (1) Where the bringing into use of any building, facility or work comprised in any authorised development will result in the emission of significant levels of noise, the building, facility or work shall not be brought into use unless measures for the suppression of that noise have been taken in accordance with arrangements approved, at the request of the Concessionaires, by the district planning authority.
- (2) The district planning authority shall not refuse any approval required for the purposes of sub-paragraph (1) above unless they are satisfied that it is expedient to do so on the ground that the arrangements ought to be modified to preserve the amenity of the neighbourhood and are reasonably capable of being so modified.
9
- (1) The land associated with any building, facility or work comprised in any authorised development shall be landscaped in accordance with a scheme approved, at the request of the Concessionaires, by the district planning authority.
- (2) No building, facility or work so comprised shall be brought into use unless—
- (a) a scheme for the landscaping of the land associated with it has been so approved; and
- (b) any landscaping operations required by the scheme to have been completed before the building, facility or work is brought into use have been completed in accordance with the scheme.
- (3) The district planning authority shall not refuse any approval required for the purposes of this paragraph unless they are satisfied that it is expedient to do so on the ground that the scheme ought to be modified to enhance the amenity of the neighbourhood or in the interests of nature conservation or of the preservation of a site of archaeological or historic interest and is reasonably capable of being so modified.
Consultation regarding County Council development
10
None of the development to which the planning permission deemed by section 9(3) of this Act to have been granted under Part III of the Act of 1971 relates shall be begun until the County Council have consulted the district planning authority with regard to the design of the development and the landscaping and noise screening to be undertaken in connection with the development.
Certificates for construction or use of certain authorised development
11
- (1) Subject to sub-paragraph (2) below, the construction of the terminal area at Cheriton, Folkestone shall cease at the end of the period of six months beginning with the day it began unless the Secretary of State has, before the end of that period, certified either—
- (a) that, in his opinion, adequate facilities for and in connection with public viewing of the construction have been provided; or
- (b) that, in his opinion, the Concessionaires have taken all reasonable steps to provide such facilities;
and it shall not be begun again unless the Secretary of State has certified as mentioned either in paragraph (a) above or in paragraph (b) above.
- (2) If it is intended to provide facilities for or in connection with public viewing of the construction of the terminal area within that area, sub-paragraph (1) above shall not apply in relation to the construction of the terminal area so far as it consists of work in connection with the provision of the facilities.
12
The inland clearance depot to be constructed at Ashford, in Kent, shall not be brought into use until the Secretary of State has—
- (a) certified either—
- (i) that, in his opinion, adequate refreshment and sleeping facilities for the use of drivers of vehicles using the depot have been provided within the limits of land to be acquired for the purposes of or in connection with the depot; or
- (ii) that, in his opinion, the Concessionaires have taken all reasonable steps to provide such facilities; and
- (b) certified, under paragraph 20(3) of Schedule 2 to this Act, completion of the construction of Work No. 17.
13
The tunnel system shall not be brought into use until the Secretary of State has certified either—
- (a) that, in his opinion, adequate facilities for and in connection with public viewing of the operation of the terminal area at Cheriton, Folkestone have been provided; or
- (b) that, in his opinion, the Concessionaires have taken all reasonable steps to provide such facilities.
14
- (1) The Secretary of State shall consult the county and district planning authorities before giving any certificate for the purposes of paragraph 11, 12(a) or 13 above.
- (2) Where the Secretary of State gives any such certificate as is mentioned in sub-paragraph (1) above he shall give a copy of the certificate to each of the authorities whom he was required by that sub-paragraph to consult before giving it.
- (3) No failure on the part of the Secretary of State to comply with his obligations under sub-paragraph (1) or (2) above shall affect the validity of any certificate given by him for the purposes of paragraph 11, 12(a) or 13 above.
Working sites: discontinuance of operations and putting into condition
15
- (1) Where any authorised development consists of or includes the carrying out on any working site within the limits of land to be acquired of operations ancillary to the construction of the tunnel system—
- (a) those operations shall be discontinued before the end of the relevant period; and
- (b) the Concessionaires shall, in accordance with a scheme agreed with the district planning authority or, in default of agreement or on notice being given by the Secretary of State to the authority and the Concessionaires, settled by him, put the site, except any part which is required either for use for or in connection with the operation of the tunnel system or for any of the Railways Board’s works, into such a condition as the scheme may provide.
- (2) The relevant period is the period of ten years beginning with the date of the passing of this Act or such longer period as the Secretary of State may specify, after consultation with the district planning authority, at any time before the end of the period of ten years or of any period previously specified by him.
16
Where any development to which any planning permission granted by virtue of section 9(4) of this Act relates consists of or includes the carrying out on any working site within the limits of land to be acquired of operations ancillary to any of the Railways Board’s works—
- (a) those operations shall be discontinued before the end of the period of ten years beginning with the date of the passing of this Act; and
- (b) the Railways Board shall, in accordance with a scheme agreed, in the case of a working site in a London borough, with the borough planning authority and, in the case of a working site anywhere else, by the district planning authority or, in default of agreement or on notice being given by the Secretary of State to the authority and the Railways Board, settled by him, put the site, except any part which is required for any of the Railways Board’s works, into such a condition as the scheme may provide.
Nature, the countryside and archaeological and historic sites
17
- (1) Where a request is made—
- (a) for an approval under paragraph 2, 3, 5 or 9 above;
- (b) for an approval of detailed plans and specifications which is required for the exercise of any planning permission granted by virtue of section 9(4) of this Act;
the planning authority shall, within five days of receiving it, commence any appropriate consultation with respect to it.
- (2) The authority shall not take any decision in relation to the request until either they have received any representations which the body or bodies consulted wish to make or the period of 21 days from the commencement of consultation has ended.
- (3) Before a planning authority agree a scheme under paragraph 6, 15 or 16 above they shall undertake any appropriate consultation with respect to it.
- (4) In this paragraph “appropriate consultation” means—
- (a) where the authority consider that nature conservation or the conservation of the natural beauty and amenity of the countryside may be affected, Natural England;
- (c) where they consider that a site of archaeological or historic interest may be affected, consultation with the Historic Buildings and Monuments Commission for England.
Approvals: supplementary
18
A planning authority shall not be required to entertain any request for an approval required for the purposes of any provision of this Schedule unless the Concessionaires have deposited with them both—
- (a) a plan showing the Concessionaires’ current proposals regarding the layout of the authorised development; and
- (b) a schedule setting out the Concessionaires’ current proposals regarding the timetable for carrying it out.
19
- (1) The Secretary of State may give directions to a planning authority requiring any request by the Concessionaires for an approval required for the purposes of any provision of this Schedule to be referred to him instead of being dealt with by them.
- (2) A direction under this paragraph may relate either to a particular request or to requests of a class specified in the direction.
- (3) A request in respect of which such a direction has effect shall be referred to the Secretary of State accordingly.
- (4) The Secretary of State may refuse or impose conditions on an approval only on the grounds open to the authority required to refer the request for it.
- (5) The determination by the Secretary of State of the request shall be final.
20
The Secretary of State may give directions to a planning authority restricting the grant, either indefinitely or during such period as may be specified in the directions, of a particular approval required for the purposes of any provision of this Schedule or of approvals so required of a class specified in the directions.
21
- (1) Where the Concessionaires are aggrieved by the decision of a planning authority on any request for an approval required for the purposes of any provision of this Schedule, they may by notice under this sub-paragraph appeal to the Secretary of State whose decision on the appeal shall be final.
- (2) Any notice under sub-paragraph (1) above shall be in writing and be served, within 28 days of notification of the decision to which it relates, on the Secretary of State and the authority whose decision is appealed against.
- (3) On an appeal under this paragraph, the Secretary of State may allow or dismiss the appeal or vary the decision of the authority whose decision is appealed against but may make a determination involving the refusal of, or imposition of conditions on, an approval only on the grounds open to that authority.
- (4) Where the authority to whom a request for approval is made fail to notify the Concessionaires of their decision on that request within—
- (a) the period of two months beginning with the date on which that request was made; or
- (b) such extended period as may from time to time be agreed upon in writing between the authority and the Concessionaires;
the provisions of this paragraph shall apply in relation to the request as if the authority had refused it and as if they had notified the Concessionaires of their decision on the last day of the two month period or, where an extended period has been agreed, on the last day of that extended period.
- (5) No appeal under section 36 of the Act of 1971 may be made against any decision in relation to which a right of appeal arises under this paragraph.
SCHEDULE 4
PART I — THE AUTHORISED WORKS
Description of works
1
The works which the Secretary of State is authorised by section 35 of this Act to construct are the following—
Limits of deviation
2
In their construction—
- (a) each of the works described in paragraph 1 above may deviate from the line or situation shown for that work on the deposited plans to the extent of the limits of deviation so shown;
- (b) so much of each of Works Nos. 31 and 32 as lies between its commencement and the point at which it passes into tunnel under Round Hill may deviate from the level shown for that part of that work on the deposited sections to the extent of 1.5 metres upwards and to any extent downwards; and
- (c) each of the works described in paragraph 1 above, other than the parts of Works Nos. 31 and 32 specified in sub-paragraph (b) above, may deviate from the level shown for that work or, in the case of Works Nos. 31 and 32, that part of that work on the deposited sections to the extent of 3 metres upwards and to any extent downwards.
Interpretation of Part I
3
In paragraph 1 above, “A20” means the trunk road from Folkestone to Dover so classified.
PART II — INTERFERENCE WITH HIGHWAYS
Stopping up of highways
4
- (1) Subject to the provisions of this paragraph, the Secretary of State may, in connection with the construction of the A20 improvement works, stop up each of the highways or parts thereof specified, by reference to the letters and numbers shown on the deposited plans, in columns (1) and (2) of the following table and any other bridleways or footpaths within the limits of deviation for the works authorised by Part IV of this Act, and thereupon all rights of way over or along the highway or part thereof so stopped up shall be extinguished.
- (2) The existing highways or part thereof specified in columns (1) and (2) of Part II of the following table shall not be stopped up under this paragraph until the new highway to be substituted therefor specified as aforesaid, or by reference to works authorised by Part IV of this Act, in column (3) of that Part of the table in relation to each such existing highway or part thereof has been completed in accordance with sub-paragraph (4) below.
Temporary interference with highways
5
- (1) The Secretary of State may, for the purpose of constructing or maintaining the A20 improvement works, temporarily stop up, open, break up or interfere with, or alter or divert, the whole or any part of any highway within the limits of deviation for the works authorised by Part IV of this Act or the limits of land to be acquired, and may carry out and do all necessary works and things for, or in connection with, the stopping up, opening, breaking up, interference, alteration or diversion and for keeping the highway open for traffic.
- (2) The Secretary of State shall provide reasonable access for all persons, with or without vehicles, going to or returning from premises abutting on any highway affected by the exercise of the powers conferred by this paragraph.
Part III — Miscellaneous
Status of new highways
6
- (1) On the date on which this Act is passed the roads mentioned in sub-paragraph (2) below shall become trunk roads and special roads for the exclusive use of traffic of Classes I and II of the classes of traffic specified in Schedule 4 to the Highways Act 1980 as if the provision by him of special roads along the route of those roads had been authorised by a scheme made by the Secretary of State under section 16 of that Act—
- (a) prescribing that route as the route for the special roads;
- (b) prescribing both those classes of traffic; and
- (c) specifying that date as the date on which those special roads were to become trunk roads.
- (2) The roads to which sub-paragraph (1) above applies are—
- (a) so much of the roads forming Works Nos. 31 and 32 as lie, in the case of Work No. 31, between its commencement and a point on the road 690 metres from that commencement and, in the case of Work No. 32, between its commencement and a point on the road 875 metres from that commencement; and
- (b) the slip roads forming or forming part of Works Nos. 34A and 34D.
- (3) On the date on which this Act is passed the roads mentioned in sub-paragraph (4) below shall become trunk roads as if they had become so by virtue of an order under section 10(2) of the Highways Act 1980 specifying that date as the date on which they were to become trunk roads.
- (4) Those roads are—
- (a) such parts of the roads forming Works Nos. 31 and 32 as do not on that date become trunk roads and special roads by virtue of sub-paragraph (1) above;
- (b) the roads forming Works Nos. 33, 34F, 44A and 44B; and
- (c) the slip roads forming or forming part of Works Nos. 34B and 34E and the trunk road parts of Works Nos. 38A, 38B, 38C and 38D.
- (5) The roads forming—
- (a) in the case of each of Works Nos. 38A and 38C, the part from its commencement to a point certified by the Secretary of State for the purposes of sub-paragraph (4)(c) above; and
- (b) in the case of each of Works Nos. 38B and 38D, the part from a point so certified to its termination;
shall be the trunk road parts of those works for those purposes.
7
- (1) On the date certified by the Secretary of State as the date on which any highway constructed in pursuance of this Schedule, other than one to which paragraph 6 above applies, is open for public use, that highway shall be transferred to the Kent County Council and, following that transfer, shall be treated for the purposes of the Highways Act 1980 as if it had been so transferred by virtue of an order made under the provision of that Act which applies in relation to its construction by virtue of paragraph 8 below.
- (2) The Secretary of State may classify any highway proposed to be constructed in pursuance of this Schedule, other than one to which paragraph 6 above applies, in any manner in which, and for any purposes for which, he could classify that highway under section 12(3) of that Act.
- (3) On the date of its transfer under sub-paragraph (1) above to the Kent County Council any highway classified under sub-paragraph (2) above shall become a highway classified in the manner and for the purposes in question as if so classified under section 12(3) of that Act.
Regulation of construction of works
8
The construction by the Secretary of State of a highway in pursuance of this Act shall be treated as the construction of a highway in pursuance of—
- (a) a scheme under section 16 of the Highways Act 1980, in the case of the roads mentioned in paragraph 6(2) above;
- (b) section 24(1) of that Act, in the case of the roads mentioned in paragraph 6(4) above;
- (c) an order under section 18 of that Act made in relation to the roads which become trunk roads and special roads by virtue of paragraph 6(1) above, in the case of the road forming Work No. 34C; and
- (d) an order under section 14 of that Act made in relation to the roads which become trunk roads by virtue of paragraph 6(3) above, in any other case.
Status of ancillary operations and works
9
- (1) The carrying out of any of the A20 improvement works which is not the construction of a highway and the stopping up of any highway in pursuance of Part II of this Schedule shall be treated as having been authorised by an order under section 14 of the Highways Act 1980 made in relation to the roads which become trunk roads by virtue of paragraph 6(3) above.
- (2) Subject to sections 21 and 22 of that Act as they apply by virtue of sub-paragraph (1) above, the stopping up of any highway in pursuance of Part II of this Schedule shall not affect any rights—
- (a) of statutory undertakers in respect of any apparatus of theirs which immediately before the date on which this Act is passed is under, in, on, over, along or across that highway; or
- (b) of any sewerage authority in respect of any sewers or sewage disposal works of theirs which immediately before that date are under, in, on, over, along or across that highway.
Application of Highways Act powers to provisions of this Schedule
10
- (1) Any provision of Part I or II of this Schedule relating to any operation or work which by virtue of any of the preceding provisions of this Part of this Schedule is to be treated as authorised by an order under section 14 or 18 of the Highways Act 1980 shall be treated for the purposes of that Act as provisions of such an order.
- (2) The provisions of paragraph 6(1) above shall be treated for those purposes as provisions of a scheme under section 16 of that Act.
Regulation of traffic on new roads
11
- (1) Subject to sub-paragraph (2) below, any power under the Road Traffic Regulation Act 1984 to make an order or to give a direction with respect to any road shall be exercisable in relation to any road forming or forming part of any of the A20 improvement works before that road is open for public use, in any case where it appears to the Secretary of State to be expedient that the order or (as the case may be) the direction should have effect immediately on the road’s becoming open for public use.
- (2) The procedure otherwise applicable under that Act in relation to the making of any such order or the giving of any such direction shall apply in any such case with such modifications as the Secretary of State may determine; and he shall publish notice of those modifications in such manner as appears to him to be appropriate for bringing them to the notice of persons likely to be affected by the provisions of any such order or (as the case may be) by any such direction.
SCHEDULE 5
Part I — Purposes for which Certain Land may be Acquired or Used Under Section 8
Part II — Purposes for which Certain Land may be Acquired or Used under Section 36
Part III — Supplementary
Provision enabling owners and lessees to require purchase of their interests
1
- (1) If the Secretary of State makes an order under section 38(1) of this Act extending the time within which a notice to treat may be served in respect of any land the following provisions of this paragraph shall have effect as from the coming into operation of that order.
- (2) If any owner or lessee of any of that land gives notice in writing to the appropriate authority that he desires his interest in any part of the land specified in the notice to be acquired by the appropriate authority, the appropriate authority shall, within the period of three months after the receipt of such notice—
- (a) enter into an agreement with him for the acquisition of his interest in the land or such part thereof as may be specified in the agreement; or
- (b) serve on him a notice to treat for the compulsory acquisition of his interest in the land specified in his notice, or in such part thereof as may be required by the appropriate authority; or
- (c) serve on him notice in writing of their intention not to proceed with the purchase of his interest in the land specified in his notice.
- (3) Where notice is given under sub-paragraph (2) above by an owner or lessee in respect of his interest in land specified in the notice, then—
- (a) if the appropriate authority—
- (i) fails to comply with the requirements of that sub-paragraph; or
- (ii) withdraws a notice to treat served in compliance with paragraph (b) of that sub-paragraph; or
- (iii) serves on him notice in compliance with paragraph (c) of that sub-paragraph;
the power of the appropriate authority to serve a notice to treat in respect of that person’s interest in the land so specified shall cease; or
- (b) if the owner’s or lessee’s interest in part only of that land is acquired in pursuance of an agreement under paragraph (a) of that sub-paragraph, or a notice to treat served by virtue of paragraph (b) of that sub-paragraph, the power of the appropriate authority to serve a notice to treat in respect of that person’s interest in the remainder of that land shall cease.
- (4) In this paragraph “lessee” means a person who holds an interest under a lease for a period of which not less than 21 years is unexpired at the date of the giving of any notice by that person under sub-paragraph (2) above.
- (5) This paragraph shall not apply to any subsoil or under-surface of land required only for the construction of a work at a level more than 9 metres below the surface of the land or, in the case of a work below a watercourse or other area of water, the surface of the adjoining ground which is at all times above water level.
Acquisition of subsoil or rights in land
2
- (1) The appropriate authority may, under section 8 or 36 of this Act—
- (a) acquire only so much as may be required for the purposes mentioned in those sections of the subsoil and under-surface of; or
- (b) create and acquire such easements or rights as may be required for those purposes in;
any land to which that section relates, not being land specified in the table in sub-paragraph (3) below, without being required to acquire any greater interest.
- (2) The provisions of Part I of the Compulsory Purchase Act 1965, as applied by section 37 of this Act, and the enactments relating to compensation for the compulsory purchase of land, shall with the necessary modifications (including the adaptations of that Part of that Act specified in paragraph 8 below) have effect in relation to the creation and acquisition of such easements or rights as if it were the purchase of land within the meaning of that Part of that Act, and any notice to treat in respect of any such easement or right shall describe its nature.
- (3) Notwithstanding the provisions of section 8 of this Act, the Secretary of State shall not acquire compulsorily under that section any interest in any part of any land specified in the following table, except the subsoil or under-surface or easements or rights in the subsoil and under-surface as provided by sub-paragraph (1) above—
| (1) | (2) |
|---|---|
| Area | Number of land shown on deposited plans |
| District of Shepway— | District of Shepway— |
| town of Folkestone | 59 to 88 |
| parish of Hawkinge | 1 to 17 |
| District of Dover— | District of Dover— |
| parish of Capel-le-Ferne | 1 to 98 |
| parish of Hougham Without | 1 and 3 to 51 |
| town of Dover | 1 to 6, 19, 20, 21 and 32 |
- (4) For the purposes of sub-paragraph (3) above the subsoil and under-surface of any land specified in the table in that sub-paragraph shall not include any subsoil or under-surface which is within 9 metres of the level of the surface of the ground or, in the case of a building on the land, the level of the surface of the ground adjoining the building or, in the case of a watercourse or other area of water, the level of the surface of the adjoining ground which is at all times above water level.
Acquisition of part only of certain properties
3
- (1) Where a copy of this paragraph is endorsed on, or annexed to, a notice to treat served under Part I of the Compulsory Purchase Act 1965, as applied by section 37 of this Act, the following provisions of this paragraph shall apply to the land subject to the notice instead of section 8(1) of that Act.
- (2) Where the land subject to the notice is part only of a house, building or factory, or part only of land consisting of a house together with any park or garden belonging thereto, then, if the person on whom the notice is served, within the period of two months beginning with the day on which the notice is served on him, serves on the appropriate authority a counter-notice objecting to the sale of the part and stating that he is willing and able to sell the whole (in this paragraph below referred to as “the land subject to the counter-notice”), the question whether he shall be required to sell the part shall, unless the appropriate authority agrees to take the land subject to the counter-notice, be referred to the Upper Tribunal.
- (3) If the said person does not serve such a counter-notice as aforesaid within the period of two months beginning with the day on which the notice to treat is served on him, or if on such a reference to the Upper Tribunal the tribunal determines that the part subject to the notice to treat can be taken without material detriment to the remainder of the land subject to the counter-notice or, in the case of part of any land consisting of a house together with a park or garden belonging thereto, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house, the said person shall be required to sell the part.
- (4) If, on such a reference to the Upper Tribunal, the tribunal determines that part only of the land subject to the notice to treat can be taken without material detriment to the remainder of the land subject to the counter-notice, or, as the case may be, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house, the notice to treat shall be deemed to be a notice to treat for that part.
- (5) If, on such a reference to the Upper Tribunal, the tribunal determines that the land subject to the notice to treat cannot be taken without material detriment to the remainder of the land subject to the counter-notice but that the material detriment is confined to a part of the land subject to the counter-notice, the notice to treat shall be deemed to be a notice to treat for the land to which the material detriment is confined in addition to the land already subject to the notice, whether or not the additional land is land which the appropriate authority is authorised to acquire compulsorily under section 8 or 36 of this Act.
- (6) If the appropriate authority agrees to take the land subject to the counter-notice, or if the Upper Tribunal determines that—
- (a) none of the land subject to the notice to treat can be taken without material detriment to the remainder of the land subject to the counter-notice or (as the case may be) without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house; and
- (b) the material detriment is not confined to a part of the land subject to the counter-notice;
the notice to treat shall be deemed to be a notice to treat for the land subject to the counter-notice, whether or not the whole of that land is land which the appropriate authority is authorised to acquire compulsorily under section 8 or 36 of this Act.
- (7) In any case where, by virtue of a determination by the Upper Tribunal under sub-paragraph (4), (5) or (6) above, a notice to treat is deemed to be a notice to treat for part of the land specified in the notice or for more land than is specified in the notice, the appropriate authority may, within six weeks after the tribunal makes its determination, withdraw the notice to treat and, if this is done, shall pay to the person on whom the notice to treat was served compensation for any loss or expense occasioned to him by the giving and withdrawal of the notice, to be determined in default of agreement by the tribunal.
- (8) For the purposes of sub-paragraph (7) above, the determination shall not be deemed to be made so long as—
- (a) the time for requiring the tribunal to state a case with respect to the determination has not expired;
- (b) any proceedings on points raised by a case so stated have not been concluded; or
- (c) any proceedings on appeal from any decision on points raised by a case so stated have not been concluded.
- (9) Where a person is required under this paragraph to sell part only of a house, building or factory, or of land consisting of a house together with any park or garden belonging thereto, compensation shall be payable to him for any loss sustained by him due to the severance of that part in addition to the value of his interest therein.
Minerals
4
- (1) Subject to sub-paragraph (2) below, Parts II and III of Schedule 2 to the Acquisition of Land Act 1981 (exception of minerals from compulsory purchase and regulation of the working of mines or minerals underlying an authorised undertaking) shall have effect in relation to lands within the limits of land to be acquired as if those lands were comprised in a compulsory purchase order providing for the incorporation with that order of those Parts of that Schedule.
- (2) In the application of that Schedule to lands which the Secretary of State is authorised to acquire under section 36 of this Act, the prescribed distance in relation to any seam of minerals lying under land adjoining works forming part of the A20 improvement works shall be such a lateral distance from those works on every side as is equal at every point along those works to one half of the depth of the seam below the natural surface of the ground at that point or forty yards, whichever is the greater.
Extinguishment of private rights of way
5
- (1) All private rights of way over any land which may be acquired compulsorily under this Act shall be extinguished on the acquisition of the land, whether compulsorily or by agreement, or on the entry on the land in pursuance of section 11(1) of the Compulsory Purchase Act 1965, as applied by section 37 of this Act, whichever is sooner.
- (2) Any person who suffers loss by the extinguishment of any right under this paragraph shall be entitled to compensation.
Provisions as to compensation
6
- (1) In determining a question with respect to compensation claimed in consequence of the compulsory acquisition of land under this Act, the Upper Tribunal shall not take into account—
- (a) any interest in land; or
- (b) any enhancement of the value of any interest in land by reason of any building erected, works executed or improvement or alteration made, whether on the land acquired or on any other land with which the claimant is (or was at the time of the erection, execution or making of the building, works, improvement or alteration) directly or indirectly concerned;
if the tribunal are satisfied that the creation of the interest, or (as the case may be) the erection of the building, the execution of the works or the making of the improvement or alteration was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.
- (2) Any dispute as to a person’s entitlement to compensation under any provision of this paragraph, or as to the amount of the compensation, shall be determined under and in accordance with Part I of the Land Compensation Act 1961.
Correction of deposited plans
7
- (1) If the deposited plans or the book of reference to those plans are inaccurate in their description of any land, or in their statement or description of the ownership or occupation of any land, the appropriate authority, after giving not less than ten days’ notice to the owner, lessee and occupier of the land in question, may apply to two justices having jurisdiction in the place where the land is situated for the correction thereof.
- (2) If on any such application it appears to the justices that the misstatement or wrong description arose from mistake or inadvertence, the justices shall certify accordingly and shall in their certificate state in what respect any matter is misstated or wrongly described.
- (3) The certificate shall be deposited in the office of the Clerk of the Parliaments and a copy thereof in the Private Bill Office of the House of Commons and with the proper officer of each County Council or London Borough Council in whose area is situated the land to which the certificate relates, and thereupon the deposited plans or the book of reference thereto (as the case may be) shall be deemed to be corrected according to the certificate, and it shall be lawful for the appropriate authority, in accordance with the certificate, to proceed under this Act as if the deposited plans or the book of reference had always been in the corrected form.
- (4) A person with whom a copy of the certificate is deposited under this paragraph shall keep it with the documents to which it relates.
Adaptation of Part I of the Compulsory Purchase Act 1965
8
In relation to the compulsory creation and acquisition of an easement or right in land (in any enactment amended by this paragraph referred to as “a right over land”) by virtue of paragraph 2 above, Part I of the Compulsory Purchase Act 1965 applies with the following modifications—
- (a) For section 7 (which relates to compensation) there shall be substituted the following—
(7) (1) In assessing the compensation to be paid by the acquiring authority under this Act regard shall be had not only to the extent (if any) to which the value of the land over which the right is purchased is depreciated by the purchase but also to the damage, if any, to be sustained by the owner of the land by reason of injurious affection of other land of the owner by the exercise of the right. (2) The modifications subject to which subsection (1) of section 44 of the Land Compensation Act 1973 is to have effect, as applied by subsection (2) of that section to compensation for injurious affection under this section, are that for the words “land is acquired or taken” there shall be substituted “a right over land is purchased” and for the words “acquired or taken from him” there shall be substituted “over which the right is exercisable”.
;
- (b) For section 8(1) (which relates to cases in which a vendor cannot be required to sell part only of a building or garden) there shall be substituted the following—
(8) (1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or factory or of a park or garden belonging to a house (hereafter in this subsection referred to as “the relevant land”)— (a) a question of disputed compensation in respect of the purchase of the right would apart from this section fall to be determined by the Upper Tribunal (hereafter in this section referred to as “the Tribunal”); and (b) before the Tribunal has determined that question the person satisfies the Tribunal that he has an interest which he is able and willing to sell in the whole of the relevant land; and— (i) where that land consists of a house, building or factory, that it cannot be made subject to the right without material detriment to it; or (ii) where that land consists of such a park or garden, that it cannot be made subject to the right without seriously affecting the amenity or convenience of the house to which it belongs; the compulsory purchase order shall, in relation to that person, cease to authorise the purchase of the right and be deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice shall be deemed to have been served in respect of that interest on such date as the Tribunal directs. (1A) Any question as to the extent of the land in which the compulsory purchase order is deemed to authorise the purchase of an interest by virtue of subsection (1) above shall be determined by the Tribunal. (1B) Where in consequence of a determination of the Tribunal that it is satisfied as mentioned in subsection (1) above the compulsory purchase order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of six weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the acquiring authority to withdraw the notice. (1C) The modifications subject to which subsection (1) of section 58 of the Land Compensation Act 1973 is to have effect, as applied by subsection (2) of that section to the duty of the Tribunal in determining whether it is satisfied as mentioned in subsection (1) above, are that at the beginning of paragraphs (a) and (b) there shall be inserted the words “a right over”, for the word “severance” there shall be substituted “right on the whole of the house, building or factory or of the house and the park or garden” and for the words “part proposed” and “part is” there shall be substituted respectively “rights proposed” and “right is”.
;
- (c) The following provisions stating the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land, namely—
shall be so modified as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be purchased compulsorily is vested absolutely in the acquiring authority;
- (d) Section 11 (powers of entry) shall be so modified as to secure that, as from the date on which the acquiring authority have served notice to treat in respect of any right, they have power, exercisable in the like circumstances and subject to the like conditions, to enter for the purpose of exercising that right (which shall be deemed for this purpose to have been created on the date of service of the notice); and sections 12 (penalty for unauthorised entry) and 13 (entry on enforcement officer's or sheriff's warrant in the event of obstruction) shall be modified correspondingly;
- (e) Section 20 (compensation for short term tenants) shall apply with the modifications necessary to secure that persons with such interests as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition of the interests but taking into account only the extent (if any) of such interference with such interests as is actually caused, or likely to be caused, by the exercise of the right in question;
- (f) Section 22 (protection of acquiring authority’s possession of land where by inadvertence an interest in the land has not been purchased) shall be so modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right in question, subject to compliance with that section as respects compensation; and
- (g) Paragraph 2(1) of Schedule 1 (power of owners to sell to the acquiring authority) shall be modified to empower all persons who are seised or possessed of or entitled to any of the land over which a right is required by the acquiring authority to grant that right to the authority and to enter all necessary agreements for the purpose.
SCHEDULE 6
Tunnel system railway to be a “railway” under the Regulation of Railways Act 1871
1
In section 2 of the Regulation of Railways Act 1871 (interpretation of terms), in the definition of “railway” there shall be inserted after the word “Parliament”, where it first occurs, the words “ the Channel Tunnel Act 1987 ”.
Disapplication of enactments in the case of the Concessionaires and through service operators
2
Section 4 (duty of railway company to make returns of overtime worked by certain employees) . . . of the Regulation of Railways Act 1889 and the Railway Companies (Accounts and Returns) Act 1911 shall not apply to the Concessionaires or to any through service operator.
Extension of enactments in relation to through service operators
3
In the following enactments, the expressions “company” and “railway company” shall be treated as including (in so far as they do not already do so) any through service operator—
Modification of enactments applying to Concessionaires and through service operators
4
- (1) In their application to—
- (a) the Concessionaires or any through service operator;
- (b) any railway of the Concessionaires or any station or other works or premises connected therewith; or
- (c) any train of the Concessionaires or any through service operator;
the enactments specified in column (1) of the following table (which create the offences broadly described in column (2) of the table) shall each have effect as if the maximum fine which may be imposed on summary conviction of any offence specified in the enactment were, instead of that specified in column (3) of the table, a fine not exceeding the level specified in column (4) of the table.
| (1) | (2) | (3) | (4) |
|---|---|---|---|
| Enactment | Description of offence | Maximum fine otherwise applicable (level on standard scale) | Maximum fine (level on standard scale) |
| Section 16 of the Railway Regulation Act 1840. | Obstruction of officers of railway company or trespass upon railway. | Level 1 | Level 3 |
| Section 17 of the Railway Regulation Act 1842. | Misconduct of persons employed on railways. | Level 1 | Level 3 |
| Section 22 of the Regulation of Railways Act 1868. | Provision and improper use of means of communication. | Level 1 | Level 2 |
| The Regulation of Railways Act 1889— | The Regulation of Railways Act 1889— | The Regulation of Railways Act 1889— | The Regulation of Railways Act 1889— |
| section 5(1). | Failure to produce ticket, to pay fare or to give name and address. | Level 1 | Level 2 |
| section 5(3). | Travel with intent to avoid payment of fare. | Level 2 | Level 3 |
- (2) In such application—
- (a) section 16 of the Act of 1840 shall have effect as if the court had, as an alternative to imposing a fine, the power to award imprisonment for a period not exceeding one month; and
- (b) section 17 of the Act of 1842 shall have effect as if, instead of the power to award imprisonment for a period not exceeding two months, the court had power to award imprisonment for a period not exceeding three months; and
- (c) section 5(2) of the Act of 1889 (power to arrest passenger who fails to produce ticket and refuses to give his name and address) shall have effect as if after the word “refuses” there were inserted the words “ or fails ”.
Extension of sections 55 and 56 of the British Transport Commission Act 1949 in relation to the tunnel system railway
5
Sections 55 (penalty for trespass on railways, etc.) and 56 (penalty for stone throwing, etc., on railways) of the British Transport Commission Act 1949 shall apply in relation to any railway, siding, tunnel, railway embankment, cutting or similar work comprised in the tunnel system as they apply in relation to any railway, siding, tunnel, railway embankment, cutting or similar work belonging to a successor of the British Railways Board within the meaning of the Railways Act 1993 (Consequential Modifications) (No.2) Order 1999 .
Interpretation
6
In this Schedule “through service operator” means a person, other than the Concessionaires or the Railways Board, operating services for the carriage of passengers or goods by rail by way of the tunnel system.
SCHEDULE 7
Part I — Highways and Traffic
1
- (1) The following provisions of this Part of this Schedule shall, unless otherwise agreed in writing between the appropriate authority and the highway authority concerned, have effect for the protection of the highway authorities referred to in this Part.
- (2) In this Part of this Schedule—
- “appropriate authority” does not include the Secretary of State or the County Council;
- “highway” means a highway maintainable by the highway authority;
- “highway authority” means—
- (a) in the case of a trunk road, the Secretary of State ; and
- (b) in the case of other highways, the local highway authority.
2
Wherever in this Part of this Schedule provision is made with respect to the approval or consent of the highway authority, that approval or consent shall be in writing and subject to such reasonable terms and conditions as the highway authority may require, but shall not be unreasonably withheld.
3
Before carrying out any work for the construction or maintenance of any part of the works authorised by this Act which will involve interference with a highway, or the traffic in any highway, or before temporarily stopping up any highway, the appropriate authority shall consult the highway authority—
- (a) as to the time when the work shall be commenced, and as to the extent of the surface of the highway which it may be reasonably necessary for the appropriate authority to occupy, or the nature of the interference which may be caused to traffic in the carrying out of the work, or as to the time during which, and the extent to which, the highway shall be stopped up (as the case may be); and
- (b) as to the conditions under which the work shall be carried out or the highway shall be stopped up (as the case may be);
so as to reduce so far as possible inconvenience to the public and to ensure the safety of the public.
4
- (1) Any such work involving interference with a highway shall not be carried out, the surface of the highway shall not be occupied, the highway shall not be stopped up by the appropriate authority and the interference with traffic shall not be caused except at such time, to such extent and in accordance with such conditions as may be submitted to and approved by the highway authority.
- (2) If, within 28 days after the submission to them of proposals for compliance with this paragraph, the highway authority have not approved them or disapproved them, they shall be deemed to have approved the proposals as submitted.
5
The highway authority may require that the works authorised by this Act, so far as they involve any serious interference with the movement of traffic in any highway, shall be carried on, so far as reasonably practicable, continuously day and night and the appropriate authority shall take all such steps as may be reasonably necessary to reduce so far as possible the period of such interference.
6
It shall not be lawful for the appropriate authority in exercise of their powers under this Act to place any hoardings on any part of any highway except for such period and in such manner as shall be reasonably necessary.
7
- (1) The appropriate authority shall not, without the consent of the highway authority, make a junction between any road and a highway or an intended highway except in accordance with plans, sections and specifications submitted to and approved by the highway authority and if, within 28 days after such plans, sections and specifications have been submitted, the highway authority have not approved or disapproved them, they shall be deemed to have approved the plans, sections and specifications as submitted.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.