  • (1) On signifying their approval of the plans the Railways Board may specify any protective works, whether temporary or permanent, which in their opinion should be carried out before the construction of the specified works to ensure the safety and stability of railway property.
  • (2) Such protective works as may reasonably be necessary for those purposes shall be constructed by the Railways Board with all reasonable dispatch, and the Secretary of State shall not commence the construction of the specified works until the Railways Board shall have notified him that the protective works have been completed.
5

The Secretary of State shall give to the engineer of the Railways Board not less than 28 days’ notice of his intention to commence the construction of any of the authorised works and, except in emergency (when he shall give such notice as may be reasonably practicable), of his intention to carry out any maintenance operations in so far as those operations affect or interfere with railway property.

6
  • (1) The construction of the authorised works shall, when commenced, be carried out with all reasonable dispatch in accordance with the plans approved or deemed to be approved or settled as mentioned in paragraph 3 above and under the supervision (if given), and to the reasonable satisfaction, of the engineer of the Railways Board, and in such manner as to cause as little damage to railway property as may be and as little interference as may be with the conduct of traffic on the railways of the Railways Board.
  • (2) If any damage to railway property or any such interference shall be caused by the carrying out of the authorised works, the Secretary of State shall make good such damage and pay to the Railways Board reasonable expenses which they may incur and compensation for any loss which they may sustain by reason of any such damage or interference.
  • (3) Nothing in this paragraph shall impose any liability of the Secretary of State with respect to any damage, costs, expenses or loss attributable to the act, neglect or default of the Railways Board or their servants, contractors or agents.
7

The Secretary of State shall at all times afford reasonable facilities to the engineer of the Railways Board for access to the authorised works during their construction or when maintenance operations are being carried out and shall supply to him all such information as he may reasonably require with regard to the authorised works and their method of construction or with regard to the maintenance operations.

8
  • (1) If any alteration or addition, whether permanent or temporary, to railway property shall be reasonably necessary during the construction of the specified works, or during a period of twelve months after their completion in consequence of their construction, such alterations and additions may be carried out by the Railways Board.
  • (2) If the Railways Board give to the Secretary of State reasonable notice of their intention to carry out such alterations or additions, he shall pay to the Railways Board the reasonable cost of the alterations or additions including, in respect of permanent alterations and additions, a capitalised sum representing any increase in the costs which may be expected to be reasonably incurred by the Railways Board in maintaining, working and, when necessary, renewing any such alterations or additions.
  • (3) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions, a capitalised sum representing such saving shall be set off against any sum payable by the Secretary of State to the Railways Board under this Part of this Schedule.
9

The Secretary of State shall pay to the Railways Board costs reasonably incurred by the Railways Board—

  • (a) in constructing any protective works under paragraph 4 above including, in respect of any permanent protective works, a capitalised sum representing the costs which may be expected to be reasonably incurred by the Railways Board in maintaining and renewing such works;
  • (b) in respect of the employment of any inspectors, signalmen, watchmen and other persons whom it shall be reasonably necessary to appoint for inspecting, watching and lighting railway property and signalling railway traffic and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction of the specified works or any maintenance operations;
  • (c) in respect of any special traffic working upon any existing railways of the Railways Board resulting from any speed restrictions, or any substitution or diversion of services, which may, in the opinion of the Railways Board, be required by reason or in consequence of the construction of the specified works or any maintenance operations;
  • (d) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or in consequence of the construction of the specified works or any maintenance operations;
  • (e) in respect of the supervision by the engineer of the Railways Board of the construction of the specified works or any maintenance operations.
10
  • (1) Subject to sub-paragraph (2) below, the Secretary of State shall be responsible for, and make good to the Railways Board, costs, charges, damages and expenses not otherwise provided for in this Part of this Schedule which may be occasioned to, or reasonably incurred by, the Railways Board—
  • (a) by reason of the construction of the authorised works or any maintenance operations; or
  • (b) by reason of any act or omission of the Secretary of State, or of any person in his employ, or of his contractors or others whilst engaged in the construction of the authorised works or in carrying out any maintenance operations;

and the Secretary of State shall indemnify the Railways Board from and against claims and demands arising out of, or in connection with, the construction of the authorised works, the carrying out of any such operations or any such act or omission.

  • (2) The fact that any act or thing may have been done in accordance with plans approved by the engineer of the Railways Board, or in accordance with any requirement made by him, or under his supervision, shall not (if it was not attributable to the act, neglect or default of the Railways Board, or of any person in their employ, or of their contractors or agents) excuse the Secretary of State from any liability under this Part of this Schedule.
  • (3) The Railways Board shall give to the Secretary of State reasonable notice of any claim or demand referred to in sub-paragraph (1) above and no settlement or compromise of any such claim or demand shall be made without his prior consent.
11

If the Railways Board give notice to the Secretary of State that the state of repair of the authorised works prejudicially affects railway property, the Secretary of State shall take such steps as may be reasonably necessary to avoid that effect on railway property.

12

Any difference arising between the Secretary of State and the Railways Board under this Part of this Schedule shall be determined by arbitration.

Part IV — Protection of Sewers and Land Drainage

1
  • (1) The following provisions of this Part of this Schedule shall, unless otherwise agreed in writing between the Secretary of State and the protected authority, have effect for the protection of land drainage works and sewers.
  • (2) In this Part of this Schedule—
  • “drainage work” means any work vested in or under the control of the protected authority for the purposes of their land drainage functions as defined in the Land Drainage Act 1976 and includes a watercourse as so defined;
  • “plans”, in relation to any specified work, means detailed plans, drawings, sections and specifications describing the position and manner in which, and the level at which, the work is proposed to be carried out and the position of all drainage works and sewers of the protected authority within the limits of deviation for that work, and shall comprise detailed drawings of every alteration which is to be made in any such drainage works and sewers by carrying out of the specified work;
  • “the protected authority” means the Anglian Water Authority and the Southern Water Authority, or either of them, in their capacities as—
  • (a) authorities responsible for sewerage and sewage disposal; and
  • (b) authorities responsible for land drainage, including defence against sea water;
  • “sewer” includes any main used for the conveyance of sewage sludge or sewage effluent, any drain or sewer forming or intended to form part of the general sewerage system of the protected authority, and any storm outflow or outfall or any other apparatus or structure vested in, or maintained by, the protected authority for the purposes of sewerage or sewage disposal; and
  • “specified work” means Work No. 3, and any works carried out within the limits of deviation for that work for the purpose of or in connection with the construction, maintenance or improvement of any part of the crossing which comprises that work or the tunnels;

but in paragraphs 2 and 5 to 7 below references to a specified work are references to so much only of any such work as is over, or within 15 metres of, any drainage work or sewer.

2

For the purpose of the preparation of the plans for any specified work the protected authority shall, on application by the Secretary of State, permit him or his agents to have access to plans in the possession of the protected authority and to any of their drainage works and sewers.

3

The carrying out of the works authorised by this Act shall not prevent the continued operation of the sewage pumping station of the Anglian Water Authority on the lands shown on the deposited plans numbered 14 in the Borough of Thurrock but nothing in this paragraph shall prevent the acquisition by the Secretary of State of such part of the said land, or of such rights in that land, as can be taken without preventing the continued operation of that pumping station.

4

In the design and carrying out of the works authorised by this Act the Secretary of State shall secure that no additional quantities of surface water are drained to the Mar Dyke in the Borough of Thurrock.

5
  • (1) Not less than 56 days before commencing the construction of any specified work, the Secretary of State shall submit to the protected authority for their approval plans for the work and such further particulars available to him as the protected authority may, within 28 days of the submission of the plans, reasonably require.
  • (2) The protected authority’s approval of plans submitted under sub-paragraph (1) above shall not be unreasonably withheld; and if within 56 days after the submission of the plans the protected authority have not approved or disapproved them, they shall be deemed to have approved them.
6

The Secretary of State shall give to the protected authority not less than 28 days’ notice of his intention to commence the construction or renewal of a specified work and, except in case of emergency (when he shall give such notice as may be reasonably practicable), of his intention to carry out works of maintenance of a specified work.

7

In carrying out any specified work the Secretary of State shall comply with all reasonable requirements of the protected authority of which due notice is given to him, and shall provide new, altered or substituted drainage works or sewers, or works for the protection of any drainage works or sewers of the protected authority, in such manner as the protected authority shall reasonably require to safeguard any drainage work against damage or to secure that its efficiency for land drainage purposes is not impaired or, as the case may be, to protect and prevent damage or impediment to any sewer, by reason of the specified work.

8

All works for the provision of new, altered or substituted drainage works or sewers or protective works in pursuance of paragraph 7 above shall be carried out to the reasonable satisfaction of the protected authority and, where so required by the protected authority, by or under the supervision (if given) of an officer of the protected authority duly appointed for the purpose; and all reasonable costs and expenses to which the protected authority may be put by reason of such works, whether in the course of the carrying out of the works, or in the preparation or examination of plans or designs or in such supervision, or otherwise, shall be payable to the protected authority by the Secretary of State.

9

When works for the provision of any such new, altered or substituted drainage works or sewers or protective works in pursuance of paragraph 7 above have been completed they shall be maintainable by the protected authority.

10

If by reason of the carrying out of a specified work, or the failure of a specified work, any sewer is damaged, the efficiency of a drainage work for land drainage purposes is impaired or a drainage work is otherwise damaged, the damage shall be made good by the Secretary of State to the reasonable satisfaction of the protected authority or, failing that, the protected authority may make good the damage and recover from the Secretary of State costs reasonably incurred in so doing.

11
  • (1) The Secretary of State shall indemnify the protected authority against all claims, demands, costs, expenses, damages or loss which may be made on or against the protected authority or which the protected authority may incur or which they may sustain in consequence of any damage of, or interference with, a drainage work or sewer which may be caused by the construction of a specified work, or of the failure or want of maintenance of such a work, or any subsidence caused by the construction of any specified work or any act or omission of the Secretary of State, his contractors, agents, workmen or servants, while engaged upon the specified work.
  • (2) The protected authority shall give to the Secretary of State reasonable notice of any such claim or demand and no settlement or compromise shall be made without the agreement in writing of the Secretary of State.
  • (3) Nothing in this paragraph shall impose any liability on the Secretary of State with respect to any claim, demand, costs, expenses, damage or loss which is attributable to the act, neglect or default of the protected authority or their servants or agents.
12

Nothing in section 23 of this Act shall preclude the protected authority or their officers, servants or agents from having, for the purposes of inspecting, repairing, maintaining, removing or replacing any drainage work or sewer, reasonable access to any part in which the work or sewer is situated of any road which forms part of any of the approach roads.

13
  • (1) An officer of the protected authority duly appointed for the purpose may, subject to sub-paragraph (2) below, enter upon and inspect any specified work or any other works constructed under this Part of this Schedule.
  • (2) Entry upon any specified work under sub-paragraph (1) above shall be subject to supervision and control by the Secretary of State but shall be afforded by him at any reasonable time at which it is required.
14

Any difference arising between the Secretary of State and the protected authority under this Part of this Schedule shall be determined by arbitration.

Part V — Protection of RTZ Estates Limited

1
  • (1) The following provisions of this Part of this Schedule shall, unless otherwise agreed in writing between the Secretary of State and the protected body, have effect for the protection of the interests of that body in the protected premises.
  • (2) In this Part of this Schedule—
  • “the protected body” means RTZ Estates Limited and includes the successors in title to, and assigns of the interest of, that company as owner and occupier of the protected premises;
  • “the protected premises” means the lands numbered on the deposited plans 20 in the Borough of Thurrock and the jetty;
  • “the jetty” means the existing jetty of the company within the lands numbered on the deposited plans 21 in the Borough of Thurrock.
2
  • (1) Subject to sub-paragraph (3) below, the Secretary of State shall be responsible for, and make good to the protected body, costs, charges, losses and expenses which may be occasioned to, or reasonably incurred by, the protected body—
  • (a) by reason of any damage to the property of the protected body caused by the execution of the works mentioned in paragraph 11 of Part VIII of Schedule 1 to the 1984 Act or the failure of any such works; or
  • (b) by reason of any act or omission of the Secretary of State, or of any person in his employ or of his contractors or others in the course of the improvement or maintenance of those works.
  • (2) Without prejudice to the generality of sub-paragraph (1) above, the costs, losses and expenses there referred to include any costs and expenses reasonably incurred or losses suffered by the protected body by reason of—
  • (a) any damage to the railway embankment between the jetty and the southern side of the Tilbury Branch Railway or to the railway, and the oil and other pipelines and services, on or in that embankment; and
  • (b) any interruption to or interference with the use of the jetty or the operation of the said railway, pipelines and services;

caused by the execution of the works referred to in sub-paragraph (1)(a) above or by any settlement or subsidence of those works or movement of soil attributable to the construction of those works.

  • (3) The protected body shall give to the Secretary of State reasonable notice of any claim or demand in respect of which the Secretary of State may be liable under sub-paragraph (1) above and no settlement or compromise of any such claim or demand shall be made without his prior consent.
3

Any difference arising between the Secretary of State and the protected body under this Part of this Schedule shall be determined by arbitration.

Construction of the scheduled works.

In the borough of Thurrock in the county of Essex and in the borough of Dartford (parish of Stone) in the county of Kent—

Note: In the foregoing table the references to the footpath DR36 are to the footpath so numbered on the list of footpaths maintained by the Kent County Council.

Editorial notes

1

Act partly in force at Royal Assent see s. 47(2); Act wholly in force 31.7.1988 see ss. 4, 47(2)

5

Power of appointment conferred by s. 4(1) fully exercised: 31.7.1988 appointed by S.I. 1988/1129

11

S. 17: power previously exercised by S.I. 1988/1364, 1989/1402 and 1990/1597

12

S. 17(4): s. 17(4) power exercised by S.I. 1991/1808

13

1948 c. 5. (12, 13 & 14 Geo 6)

14

S. 19(d) words substituted (1.9.1994) by 1994 c. 22, ss. 63, 66, Sch. 3 para. 23(a) (with s. 57(4) )

15

S. 19(e) words substituted (1.9.1994) by 1994 c. 22, ss. 63, 66, Sch. 3 para. 23(b) (with s. 57(4) )

20

S. 25: power previously exercised by S.I. 1989/2372 and 1990/1598

21

S. 25(1)(2): s. 25(1)(with ss. 25(2), 26(1)(3)(d), 44(3) and 46(1)) power exercised by S.I.1991/1805

22

S. 26: power previously exercised by S.I. 1989/2372 and 1990/1598

23

S. 26(1)(3)(d): s. 25(1)(with ss. 25(2), 26(1)(3)(d), 44(3) and 46(1)) power exercised by S.I.1991/1805

27
34

S. 44: power previoulsy exercised by S.I. 1989/2372 and 1990/1598

35

S. 44(3): s. 25(1)(with ss. 25(2), 26(1)(3)(d), 44(3) and 46(1)) power exercised by S.I.1991/1805

36

S. 46: power previously exercised by S.I. 1989/2372 and 1990/1598

37

S. 46(1): s. 25(1)(with ss. 25(2), 26(1)(3)(d), 44(3) and 46(1)) power exercised by S.I.1991/1805

54

Words substituted by S.I. 1990/577, art. 2 Sch.

55

Entry substituted by S.I. 1990/577, art. 2 Sch.

56

1937 c. cxxvii.

59

S. 19(a)(ii) substituted (7.9.2004 for E. for specified purposes, 1.10.2004 for E. in so far as not already in force, 10.11.2004 for W.) by Fire and Rescue Services Act 2004 (c. 21), s. 61, Sch. 1 para. 66; S.I. 2004/2304, art. 2; S.I. 2004/2917, art. 2

61

Words in Sch. 5 para. 3(1) substituted (with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), reg. 1(2), Sch. 2 para. 5(2)

62

Words in Sch. 5 para. 4 substituted (with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), reg. 1(2), Sch. 2 para. 5(2)

63

Words in Sch. 5 para. 4 substituted (with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), reg. 1(2), Sch. 2 para. 5(3)

64

Words in Sch. 5 para. 6(2) substituted (with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), reg. 1(2), Sch. 2 para. 5(4)(a)

65

Sch. 5 para. 6(3) inserted (with application in accordance with reg. 21(1) of the amending S.I.) by The Transfer of Undertakings (Protection of Employment) Regulations 2006 (S.I. 2006/246), reg. 1(2), Sch. 2 para. 5(4)(b)

72

Words in s. 19(b) omitted (1.4.2013) by virtue of Health and Social Care Act 2012 (c. 7), s. 306(4), Sch. 5 para. 43(a); S.I. 2013/160, art. 2(2) (with arts. 7-9)

74

Words in s. 19(b) omitted (1.4.2013) by virtue of Health and Social Care Act 2012 (c. 7), s. 306(4), Sch. 5 para. 43(c); S.I. 2013/160, art. 2(2) (with arts. 7-9)

75

Words in s. 33(2) inserted (with effect in accordance with reg. 1(4) of the amending S.I.) by The Companies Act 2006 (Strategic Report and Directors' Report) Regulations 2013 (S.I. 2013/1970), reg. 1(2)(3), Sch. para. 28

Offences by bodies corporate.

In the borough of Thurrock in the county of Essex and in the borough of Dartford (parish of Stone) in the county of Kent—

Accounts of Secretary of State.

In the borough of Thurrock in the county of Essex—

46A
  • (1) This section applies in any period in which, by virtue of an appointment under section 1 of the Infrastructure Act 2015, a strategic highways company is the highway authority for the highways comprised in the tunnel crossing or the bridge.
  • (2) The reference to the Secretary of State in section 12(4) (crossing operator) is to be read as a reference to the strategic highways company.
  • (3) References to the Secretary of State in the following provisions are to be read as references to the strategic highways company—
  • (a) section 24(1)(a) and (b) (special traffic restrictions);
  • (b) section 27(1) and (2) (bicycles);
  • (c) section 37 (powers in relation to River Thames);
  • (d) section 38 (restriction on works on crossing);
  • (e) Schedule 7 (protective provisions), except—
  • (i) paragraph 2 of Part 1, and
  • (ii) paragraph 2 of Part 3.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.