Crossrail Act 2008

Type Public General Act
Publication 2008-07-22
State In force
Department Statute Law Database
Reform history JSON API

Works

Construction and maintenance of scheduled works

1

Works: further and supplementary provisions

2

Schedule 2 (which contains further and supplementary provisions about works) has effect.

Highways

3

Schedule 3 (which makes provision in relation to highways in connection with the works authorised by this Act) has effect.

Overhead lines

4

is installed above land within the limits of deviation for the scheduled works or within the limits of land to be acquired or used.

Land

Temporary possession and use

5

Schedule 5 (which contains provisions about temporary possession and use of land for the purposes of this Act) has effect.

Acquisition of land within limits shown on deposited plans

6

Acquisition of land not subject to the power under section 6(1)

7

Extinguishment of private rights of way

8

the references to the appropriate time are to the time of entry under that provision.

Extinguishment of rights of statutory undertakers etc.

9

Planning

Planning: general

10

and it is not exempt development within the meaning of those regulations.

Permitted development: time limit

11

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.