The City of Manchester (Bradford Mill Bridge) Scheme 1992 Confirmation Instrument 1992
Made: 17th June 1992
The Secretary of State for Transport makes this Instrument in exercise of his powers conferred by Section 106 of the Highways Act 1980[^f00001], and now vested in him[^f00002], and of all other enabling powers:—
1
The City of Manchester (Bradford Mill Bridge) Scheme 1992 is hereby confirmed.
2
The said Scheme as confirmed (hereinafter referred to as “the scheme”) is set out in the Schedule hereto and copies of the scheme with its accompanying plans are deposited at the offices of the Department of Transport, 43 Marsham Street, London SW1P 3PY and at the offices of Manchester City Council, Chief Executives Department, PO Box 532, Town Hall, Manchester M60 2LA.
3
The Scheme will become operative on the date on which notice that it has been confirmed is first published in accordance with paragraph 1 of Schedule 2 to the Highways Act 1980.
4
This Instrument may be cited as the City of Manchester (Bradford Mill Bridge) Scheme 1992 Confirmation Instrument 1992.
THE SCHEDULE — CITY OF MANCHESTER (BRADFORD MILL BRIDGE) SCHEME 1992
The Council of the City of Manchester (hereinafter referred to as “the Council”) make this Scheme in exercise of their powers under Section 106 of the Highways Act 1980 and all other enabling powers:—
1 The Council are authorised to construct over the navigable waters of the Ashton Canal the bridge specified in the Schedule to this Scheme as part of the highway which they are proposing to construct between Gibbon Street and Stuart Street in the City of Manchester.
2 This Scheme may be cited as the City of Manchester (Bradford Mill Bridge) Scheme 1992.
SCHEDULE — WITH KEY PLAN (PLAN "A'), SITE PLANS (PLANS "B' AND "C') AND ELEVATION (PLAN "D') ATTACHED
From a point south-west of the canal whose co-ordinates are 387246.55E, 398700.37N to a point north-east of the canal whose co-ordinates are 387256.75E, 398715.04N.
- CONSTRUCTION Precast prestressed concrete beams with insitu reinforced concrete slab deck on reinforced concrete abutments faced with brickwork.
- SPAN 17.80 metres clear square span (17.869 metres skew span).
- WIDTH 7.3 metres single carriageway with 2 No. 3.0 metre footways (13.3 metres overall width).
- HEADROOM 3.28 metres minimum headroom over the centre 5 metre width of the canal above the nominal water level of 63.1 metres A.O.D. and 2.67 metres minimum headroom over the canal towpath.
- WATERWAY The existing canal, walls and towpath will be unaltered.
Signed
Signed by authority of theSecretary of State for Transport
P. A. Shaw — Regional Director Northern Region — Department of Transport — 17th June 1992
Footnotes
[^f00001]: 1980 c. 66.
[^f00002]: S.I. 1981/238. 3258]
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.