Made: 31st January 1994

Laid before Parliament: 8th February 1994

Coming into force: 5th April 1994

The Secretary of State, in exercise of the powers conferred by section 41 of the Transport and Works Act 1992[^f00001], after consultation in accordance with section 57 of that Act, hereby makes the following Regulations:

Citation and commencement

1

These Regulations may be cited as the Railways and Other Transport Systems (Approval of Works, Plant and Equipment) Regulations 1994 and shall come into force on 5th April 1994.

Interpretation

2

In these Regulations, unless the context otherwise requires—

Prescribed modes of guided transport

3

The modes of guided transport described in Schedule 1 are hereby prescribed for the purposes of section 41 of the Act.

Requirement for approval

4

which are capable of materially affecting the safe operation of a relevant transport system, are first brought into use for the purposes of that system.

Procedure for obtaining approval

5

Type approval of plant and equipment

6

Use of type approved plant or equipment

7

the Secretary of State may dispense with the requirements of paragraphs (2) and (3) of regulation 5 to the extent that they relate to that plant or equipment.

Compliance with external standards, etc.

8

provided that the proposed standard, code of practice, technical specification or procedure of manufacture provides, in use, equivalent levels of safety, suitability and fitness for purpose.

Relevant operational limitations

9

An application for approval which—

shall be construed as an application for approval for the new works, plant or equipment or the altered works, plant or equipment to be brought into use subject to that relevant operational limitation.

Dispensations

10

dispense with compliance with such of the requirements of these Regulations as may be specified in the notice subject to such conditions, if any, as may be so specified.

Compliance with provisions not otherwise applicable

11

require compliance with such provisions of these Regulations that would not otherwise apply as are specified in the notice.

Information

12

No person shall, in connection with any application for approval, give to the Secretary of State information which is false in any material particular.

Offences

13

shall be guilty of an offence.

SCHEDULE 1 — PRESCRIBED MODES OF GUIDED TRANSPORT

PART I — THE MODES

1

Magnetic levitation

2

Monorail

3

Road-based with cable guidance

4

Road-based with rail guidance

5

Road-based with side guidance

6

Track-based with side guidance

PART II — INTERPRETATION

1

In this Schedule—

2

In this Schedule, references to “mode” are to be construed as a mode of guided transport which employs vehicles used wholly or mainly for the carriage of passengers and “road” has the same meaning as in the Road Traffic Regulation Act 1984[^f00004].

SCHEDULE 2 — DOCUMENTS TO ACCOMPANY AN APPLICATION FOR APPROVAL

PART I — — WORKS

Applications for approval of works shall be accompanied by—

PART II— — FIXED PLANT AND EQUIPMENT

A

All applications for approval of fixed plant and (or) equipment shall be accompanied by:

B

Applications for approval of signalling plant and (or) equipment shall additionally be accompanied by:

C

Applications for approval of all plant and (or) equipment employing electric traction shall additionally be accompanied by:

D

Applications for approval of schemes employing an overhead line system shall additionally be accompanied by documents setting out details of the following:

E

Applications for approval of schemes employing a conductor-rail system shall additionally be accompanied by:

PART III— — MOVEABLE PLANT AND EQUIPMENT

Applications for the approval of moveable plant and (or) equipment shall be accompanied by:

PART IV— — ALTERED WORKS, PLANT AND EQUIPMENT

All applications for approval of alterations to works, plant or equipment shall be accompanied by:

SCHEDULE 3 — FORM OF CERTIFICATE OF CONFORMITY FOR PLANT OR EQUIPMENT

THE RAILWAYS AND OTHER TRANSPORT SYSTEMS (APPROVAL OF WORKS, PLANT AND EQUIPMENT) REGULATIONS 1994

CERTIFICATE OF CONFORMITY FOR PLANT OR EQUIPMENT

FIRST SCHEDULE

(Description and indentification no. of [plant][equipment] which is the subject of the certificate)

SECOND SCHEDULE

(Relevant operational limitations on the use for which the prototype was approved)

Signed

Signed by authority of the Secretary of State for Transport

Roger Freeman — Minister of State, — Department of Transport — 31st January l994

Explanatory note

(This note is not part of the Regulations)

These Regulations make it necessary to obtain the approval of the Secretary of State before new works, plant or equipment or an alteration to any existing works, plant or equipment may be brought into use for the purposes of a relevant transport system. They replace less comprehensive provisions contained in section 25 of the Tramways Act 1870 (c. 78) and section 41 of the Road and Rail Traffic Act 1933 (c. 53).

The transport systems to which the Regulations apply are railways, tramways, trolley vehicle systems and the modes of guided transport described in Schedule 1.

Regulation 4 introduces the requirement to obtain approval. The works, plant or equipment, or the alteration thereto, has to be such as to be capable of materially affecting the safe operation of the transport system concerned. The term “equipment” includes a vehicle. There are exceptions to the need to secure approval in the case of trains using the Channel Tunnel (for which special provision is made in other legislation) and in certain circumstances in the case of vehicles which have to comply with construction and use requirements imposed by or under the Road Traffic Act l988. The regulation also specifies when the requirement for approval takes effect and deals with testing and similar matters.

Regulation 5 sets out the procedure for obtaining approval and the information which the Secretary of State may require in order to consider an application. This information includes,,in appropriate cases, the documents listed in Schedule 2.

Regulation 6 provides for the Secretary of State to give manufacturers of plant or equipment type approval of prototypes and regulation 7 specifies the procedure to be followed when an operator proposes to bring into use any plant or equipment which conforms with such a prototype. If the application is accompanied by a certificate given by the manufacturer that the plant or equipment conforms with the approved prototype, the procedure laid down in regulation 5 may be dispensed with. The form of such a certificate is set out in Schedule 3.

Where works, plant or equipment meet the specifications, standards, codes or tests recognised by other member States of the European Union, regulation 8 requires the Secretary of State not to refuse approval in such circumstances provided that equivalent levels of safety, suitability and fitness appertain.

Regulation 9 is concerned with relevant operational limitations. These are limitations to which an approval may be subjected in respect of speed, weight, number, duration or other factors, as specified in regulation 2: If an application states that it is intended to impose such a limitation or is accompanied by a certificate under regulation 7 which states that the item in question conforms with such a limitation, then the application is to be taken as being subject to that limitation.

Regulation 10 confers on the Secretary of State power to dispense with compliance of any of the requirements, either by individual or general notification. Regulation 11 gives the Secretary of State power to require, by individual or general notification, compliance with provisions of the Regulations which would not otherwise apply.

Regulation 12 relates to the giving of false information and regulation 13 imposes offences for contravention of the Regulations.

EN 45000 referred to in Regulation 8(2) is a European Standard, copies of which are obtainable from H M Stationery Office. The British Standard equivalent is BS 7500, copies of which can be obtained from any sales outlets operated by the British Standards institute or by post from them at Linford Wood, Milton Keynes, MK14 6LE.

An assessment of the cost to business of complying with these Regulations can be obtained from Railways Division 1A, Room S19/18, Department of Transport, 2 Marsham Street, London, SW1P 3EB, telephone number (071) 276 4815. Copies of the assessment have also been placed in the libraries of both Houses of Parliament.

Footnotes

[^f00001]: 1992 c. 42.

[^f00002]: 1987 c. 53.

[^f00003]: 1988 c. 52.

[^f00004]: 1984 c. 27.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.