The Environmental Permitting (England and Wales) Regulations 2007
Made: 13th December 2007
Coming into force: 6th April 2008
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 1 — General
Citation, commencement and extent
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: general
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: activities, installations and mobile plant
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: excluded waste operation
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: exempt waste operation
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: local authority
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: operator
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: regulated facility
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation: relevant function
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Giving notices, notifications and directions, and the submission of forms
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 2 — Environmental Permits
CHAPTER 1 — Application of these Regulations to the Crown and requirement for an environmental permit
Application of these Regulations to the Crown
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Requirement for an environmental permit
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 2 — Grant of an environmental permit
Grant of an environmental permit
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Content and form of an environmental permit
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Conditions in relation to certain land
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Mobile plant operating on the site of another regulated facility: conflict of permit conditions
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Single site permits etc.
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Consolidation of an environmental permit
18
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Subsistence of an environmental permit
19
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 3 — Variation, transfer, revocation and surrender of an environmental permit
Variation of an environmental permit
20
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Transfer of an environmental permit
21
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocation of an environmental permit: general
22
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocation of an environmental permit: steps to be taken after the revocation takes effect
23
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Notification of the surrender of an environmental permit
24
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application to surrender an environmental permit
25
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 4 — Standard rules
Preparation and revision of standard rules
26
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Standard rules as conditions of an environmental permit
27
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Notification of revisions of standard rules
28
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocation of standard rules
29
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Variation of an environmental permit: revocation of standard rules
30
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 5 — Appeals in relation to environmental permits
Appeals to an appropriate authority
31
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 3 — Discharge of functions in relation to a regulated facility
Discharge of functions
32
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Direction to a regulator: discharge of functions by a different regulator
33
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Review of environmental permits and inspection of regulated facilities
34
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Provision in relation to types of regulated facility
35
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 4 — Enforcement and offences
Enforcement notices
36
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Suspension notices
37
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Offences
38
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Penalties
39
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Defence: acts done in an emergency
40
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Offences by bodies corporate
41
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Enforcement by the High Court
42
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Admissibility of evidence
43
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power of court to order cause of offence to be remedied
44
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 5 — Public Registers
Interpretation of this Part
45
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Duty of the regulator to maintain a public register
46
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exclusion from public registers of information affecting national security
47
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exclusion from public registers of confidential information
48
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure if the regulator considers that information may be confidential
49
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Duty to determine confidentiality
50
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Determination of confidentiality
51
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Procedure following a determination
52
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Appeals in relation to confidentiality
53
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Consequences of an appeal
54
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reconsideration of confidentiality
55
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Directions of the appropriate authority in relation to confidentiality
56
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 6 — Powers and functions of the regulator and the appropriate authority
Power of the regulator to prevent or remedy pollution
57
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Environment Agency: notices in relation to emissions to water
58
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Environment Agency: public participation statement
59
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Power to require the provision of information
60
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Directions to a regulator: general
61
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Reference of applications to an appropriate authority
62
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Directions to the Agency: installations outside the United Kingdom
63
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Guidance to regulators and exemption registration authorities
64
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fees and charges in relation to local authorities
65
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Plans relating to emissions
66
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 7 — Miscellaneous and transitional provision, savings, consequential amendments, revocations and repeals
Interpretation of this Part
67
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Further provision in relation to waste
68
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Transitional provision: general
69
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Transitional provision: conversion of permits and licences subject to certain applications
70
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Transitional provision: conversion of PPC permits resulting from applications in relation to existing Part A installations and mobile plant
71
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Savings
72
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Consequential amendments
73
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Revocations and repeals
74
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE 1 — Activities
PART 1 — Interpretation and application: general
Interpretation
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Activities falling within more than one Part description
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application of activities falling within Sections 1.1 to 6.9 of Part 2
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Capacity: Part A(1) and A(2) descriptions
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Operation below thresholds: effect on the installation
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Application of Part B activities: releases into the air
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
References to releases into water
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
References to certain substances
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
PART 2 — Activities
CHAPTER 1 — Energy activities
SECTION 1.1 — Combustion activities
1
In this Section “recovered oil” means waste oil which has been processed before being used.
Part A(1)
- (a) Burning any fuel in an appliance with a rated thermal input of 50 or more megawatts.
- (b) Unless carried on as part of a Part A(2) or Part B activity, burning any—
- (i) waste oil;
- (ii) recovered oil; or
- (iii) fuel manufactured from, or comprising, any other waste,
in an appliance with a rated thermal input of 3 or more megawatts, but less than 50 megawatts.
1
For the purpose of paragraph (a), where two or more appliances with an aggregate rated thermal input of 50 megawatts or more are operated on the same site by the same operator those appliances must be treated as a single appliance with a rated thermal input of 50 megawatts or more.
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Part B
Unless falling within Part A(1)(a) of this Section—
- (a) Burning any fuel (other than a fuel mentioned in Part A(1)(b)) in—
- (i) a boiler;
- (ii) a furnace;
- (iii) a gas turbine; or
- (iv) a compression ignition engine,
with a net rated thermal input of 20 or more megawatts, but a rated thermal input of less than 50 megawatts.
- (b) Burning any—
- (i) waste oil;
- (ii) recovered oil;
- (iii) solid fuel which has been manufactured from waste by an activity involving the application of heat,
in an appliance with a rated thermal input of less than 3 megawatts.
- (c) Burning fuel manufactured from or including waste (other than a fuel mentioned in paragraph (b)) in any appliance with a net rated thermal input of 0.4 or more megawatts, but a rated thermal input of less than 3 megawatts—
- (i) which is used together with other appliances which each have a rated thermal input of less than 3 megawatts; and
- (ii) where the aggregate net rated thermal input of all the appliances is at least 0.4 megawatts.
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SECTION 1.2 — Gasification, Liquefaction and Refining Activities
Part A(1)
- (a) Refining gas where this is likely to involve the use of 1,000 or more tonnes of gas in any period of 12 months.
- (b) Reforming natural gas.
- (c) Operating coke ovens.
- (d) Coal or lignite gasification.
- (e) Producing gas from oil or other carbonaceous material or from mixtures thereof, other than from sewage, unless the production is carried out as part of an activity which is a combustion activity (whether or not that combustion activity is described in Section 1.1).
- (f) Purifying or refining any product of any of the activities falling within paragraphs (a) to (e) or converting it into a different product.
- (g) Refining mineral oils.
- (h) The loading, unloading, handling or storage of, or the physical, chemical or thermal treatment of—
- (i) crude oil;
- (ii) stabilised crude petroleum;
- (iii) crude shale oil;
- (iv) where related to another activity described in this paragraph, any associated gas or condensate; or
- (v) emulsified hydrocarbons intended for use as a fuel.
- (i) The further refining, conversion or use (otherwise than as a fuel or solvent) of the product of any activity falling within paragraphs (g) or (h) in the manufacture of a chemical.
- (j) Activities involving the pyrolysis, carbonisation, distillation, liquefaction, gasification, partial oxidation, or other heat treatment of—
- (i) coal (other than the drying of coal);
- (ii) lignite;
- (iii) oil;
- (iv) other carbonaceous material; or
- (v) mixtures thereof,otherwise than with a view to making charcoal.
- (k) Odorising natural gas or liquefied petroleum gas where that activity is related to a Part A activity.
1
Paragraph (j) does not include—
- (a) the use of any substance as a fuel;
- (b) the incineration of any substance as a waste;
- (c) any activity for the treatment of sewage or sewage sludge.
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Part A(2)
- (a) Refining gas where this activity does not fall within Part A(1)(a) of this Section.
Part B
- (a) Odorising natural gas or liquefied petroleum gas, except where that activity is related to a Part A activity.
- (b) Blending odorant for use with natural gas or liquefied petroleum gas.
- (c) The storage of petrol in stationary storage tanks at a terminal, or the loading or unloading at a terminal of petrol into or from road tankers, rail tankers or inland waterway vessels.
- (d) The unloading of petrol into stationary storage tanks at a service station, if the total quantity of petrol unloaded into such tanks at the service station in any period of 12 months is likely to be 500m3 or more.
- (e) Motor vehicle refuelling activities at an existing service station after the prescribed date, if the petrol refuelling throughput at the existing service station in any period of 12 months is, or is likely to be, 3500m3 or more.
- (f) Motor vehicle refuelling activities at new service stations, if the petrol refuelling throughput at the service station in any period of 12 months is likely to be 500m3 or more.
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
CHAPTER 2 — Production and Processing of Metals
SECTION 2.1 — Ferrous Metals
1
In this Section, “ferrous alloy” means an alloy of which iron is the largest constituent, or equal to the largest constituent, by weight, whether or not that alloy also has a non-ferrous metal content greater than any percentage specified in Section 2.2.
Part A(1)
- (a) Roasting or sintering metal ore, including sulphide ore, or any mixture of iron ore with or without other materials.
- (b) Producing, melting or refining iron or steel or any ferrous alloy, including continuous casting, except where the only furnaces used are—
- (i) electric arc furnaces with a designed holding capacity of less than 7 tonnes, or
- (ii) cupola, crucible, reverbatory, rotary, induction, vacuum, electro-slag or resistance furnaces.
- (c) Processing ferrous metals and their alloys by using hot-rolling mills with a production capacity of more than 20 tonnes of crude steel per hour.
- (d) Loading, unloading or otherwise handling or storing more than 500,000 tonnes in total in any period of 12 months of iron ore, except in the course of mining operations, or burnt pyrites.
Part A(2)
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.