The Site Waste Management Plans Regulations 2008
Made: 8th February 2008
Laid before Parliament: 15th February 2008
Coming into force: 6th April 2008
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Citation, application and commencement
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Interpretation
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Exemptions
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Appointment of principal contractor
4
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Preparation of a site waste management plan
5
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Requirements for a site waste management plan
6
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Updating a site waste management plan for a project of £500,000 or less
7
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Updating a site waste management plan for a project worth more than £500,000
8
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Availability of the plan
9
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Keeping plans
10
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional duties
11
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
False statements
12
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Obstruction
13
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Penalties
14
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Enforcement
15
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Fixed penalty notices
16
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Transitional provisions
17
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
SCHEDULE — Additional duties
Additional duties on the principal contractor
1
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional duties on the client
2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Additional duties on both the client and the principal contractor
3
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Signed
Joan Ruddock — Parliamentary Under Secretary of State — Department for Environment, Food and Rural Affairs — 2008-02-08
Explanatory note
(This note is not part of the Regulations)
EXPLANATORY NOTE
These Regulations require any person intending to carry out a construction project with an estimated cost greater than £300,000 to prepare a site waste management plan.
The plan must be updated in accordance with the Regulations, with different requirements depending on whether the cost of the project is greater than £500,000.
The Regulations are enforced by the Environment Agency and the local authority.
Breach of the Regulations is an offence punishable—
- (a) on summary conviction, by a fine not exceeding £50,000, or
- (b) on conviction on indictment, by a fine.
An impact assessment of the effect that this instrument will have on the costs of business and the voluntary sector is available on the Defra website.
Footnotes
[^f00001]: 2005 c. 16.
[^f00003]: 1990 c. 43.
[^f00004]: S. I. 1991/2839.
[^f00005]: 1995 c. 25.
Editorial notes
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.