The Infrastructure Planning (Model Provisions) (England and Wales) Order 2009
- (a) enter on and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised project; and
- (b) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
- (2) Paragraph (1) shall not authorise the undertaker to take temporary possession of—
- (a) any house or garden belonging to a house; or
- (b) any building (other than a house) if it is for the time being occupied.
- (3) Not less than 28 days before entering on and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.
- (4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised project for which possession of the land was taken.
- (5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
- (6) The undertaker shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
- (7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.
- (8) Nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act (further provisions as to compensation for injurious affection) or under any other enactment in respect of loss or damage arising from the maintenance of the authorised project, other than loss or damage for which compensation is payable under paragraph (6).
- (9) Where the undertaker takes possession of land under this article, the undertaker shall not be required to acquire the land or any interest in it.
- (10) Section 13 of the 1965 Act (refusal to give possession to acquiring authority) shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 of the 2008 Act (application of compulsory acquisition provisions).
- (11) In this article “the maintenance period”, in relation to any part of the authorised project, means the period of 5 years beginning with the date on which that part of the authorised project is first opened for use.
Special category land
40
- (1) The special category land shall not vest in the undertaker until the undertaker has acquired the replacement land and [insert name of relevant body] has certified that a scheme for the provision of the replacement land as [common/open space/fuel or field garden allotment] has been implemented to its satisfaction.
- (2) On the requirements of paragraph (1) being satisfied, the replacement land shall vest in [insert name of relevant body] subject to the same rights, trusts and incidents as attached to the special category land; and the special category land shall be discharged from all rights, trusts and incidents to which it was previously subject.
- (3) In this article—
- “the special category land” means the land identified as forming part of a common, open space, or fuel or field garden allotment in the book of reference and on the plan entitled “Special Category Land Plan” attached to the land plan, which may be acquired compulsorily under this Order and for which replacement land is to be provided; and
- “the replacement land” means the land identified in the book of reference and on the plan entitled “Replacement Land Plan” attached to the land plan.
Statutory undertakers
41
The undertaker may—
- (a) acquire compulsorily the land belonging to statutory undertakers shown on the [insert name] plan within the limits of the land to be acquired and described in the book of reference;
- (b) extinguish the rights of, remove or reposition the apparatus belonging to statutory undertakers shown on the [insert name] plan and described in the book of reference; and
- (c) acquire compulsorily the new rights over land belonging to statutory undertakers shown on the [insert name] plan and described in the book of reference.
Apparatus and rights of statutory undertakers in stopped up streets
42
- (1) Where a street is stopped up under article 11 (stopping up of streets) any statutory utility whose apparatus is under, in, on, along or across the street shall have the same powers and rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been made.
- (2) Where a street is stopped up under article 11 any statutory utility whose apparatus is under, in, on, over, along or across the street may, and if reasonably requested to do so by the undertaker shall—
- (a) remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or
- (b) provide other apparatus in substitution for the existing apparatus and place it in such position as described in sub-paragraph (a).
- (3) Subject to the following provisions of this article, the undertaker shall pay to any statutory utility an amount equal to the cost reasonably incurred by the utility in or in connection with—
- (a) the execution of the relocation works required in consequence of the stopping up of the street; and
- (b) the doing of any other work or thing rendered necessary by the execution of the relocation works.
- (4) If in the course of the execution of relocation works under paragraph (2)—
- (a) apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from this paragraph, would be payable to the statutory utility by virtue of paragraph (3) shall be reduced by the amount of that excess.
- (5) For the purposes of paragraph (4)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus shall not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole shall be treated as if it also had been agreed or had been so determined.
- (6) An amount which, apart from this paragraph, would be payable to a statutory utility in respect of works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
- (7) Paragraphs (3) to (6) shall not apply where the authorised project constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead—
- (a) the allowable costs of the relocation works shall be determined in accordance with section 85 of that Act (sharing of cost of necessary measures) and any regulations for the time being having effect under that section; and
- (b) the allowable costs shall be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.
- (8) In this article—
- “apparatus” has the same meaning as in Part 3 of the 1991 Act;
- “relocation works” means work executed, or apparatus provided, under paragraph (2); and
- “statutory utility” means a statutory undertaker for the purposes of the 1980 Act or a public communications provider as defined in section 151(1) of the Communications Act 200363.
Recovery of costs of new connections
43
- (1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 41 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus shall be entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
- (2) Paragraph (1) shall not apply in the case of the removal of a public sewer but where such a sewer is removed under article 41, any person who is—
- (a) the owner or occupier of premises the drains of which communicated with that sewer; or
- (b) the owner of a private sewer which communicated with that sewer,
shall be entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
- (3) This article shall not have effect in relation to apparatus to which article 42 (apparatus and rights of statutory undertakers in stopped-up streets) or Part 3 of the 1991 Act applies.
- (4) In this article—
- “public communications provider” has the same meaning as in section 151(1) of the Communications Act 2003; and
- “public utility undertaker” has the same meaning as in the 1980 Act.
Miscellaneous and general
Deemed consent under section 34 of the Coast Protection Act 1949
44
The undertaker is granted deemed consent under section 34 of the Coast Protection Act 194964 to carry out the works described in Schedule H, subject to the requirements set out in that Schedule.
Deemed licence under Part 2 of the Food and Environment Protection Act 1985
45
The undertaker is granted a deemed licence under Part 2 of the Food and Environment Protection Act 198565 to carry out the works described in Schedule I, subject to the requirements set out in that Schedule.
Felling or lopping of trees
46
- (1) The undertaker may fell or lop any tree or shrub near any part of the authorised project, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—
- (a) from obstructing or interfering with the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project; or
- (b) from constituting a danger to passengers or other persons using the authorised project.
- (2) In carrying out any activity authorised by paragraph (1), the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation to any person for any loss or damage arising from such activity.
- (3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act.
Trees subject to tree preservation orders
47
- (1) The undertaker may fell or lop any tree described in Schedule J and identified on the [insert name] plan, or cut back its roots if it reasonably believes it to be necessary in order to do so to prevent the tree or shrub—
- (a) from obstructing or interfering with the construction, maintenance or operation of the authorised project or any apparatus used in connection with the authorised project; or
- (b) from constituting a danger to passengers or other persons using the authorised project.
- (2) In carrying out any activity authorised by paragraph (1)—
- (a) the undertaker shall do no unnecessary damage to any tree or shrub and shall pay compensation to any person for any loss or damage arising from such activity; and
- (b) the duty contained in section 206(1) of the 1990 Act (replacement of trees) shall not apply.
- (3) The authority given by paragraph (1) shall constitute a deemed consent under the relevant tree preservation order.
- (4) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, shall be determined under Part 1 of the 1961 Act.
Railway and navigation undertakings
48
- (1) Subject to the following provisions of this article, the undertaker may not under article 10 (street works)break up or open a street where the street, not being a highway maintainable at public expense (within the meaning of the 1980 Act)—
- (a) is under the control or management of, or is maintainable by, railway or tramway undertakers or a navigation authority; or
- (b) forms part of a level crossing belonging to any such undertakers or to such an authority or to any other person,
except with the consent of the undertakers or authority or, as the case may be, of the person to whom the level crossing belongs.
- (2) Paragraph (1) shall not apply to the carrying out under this Order of emergency works, within the meaning of Part 3 of the 1991 Act.
- (3) A consent given for the purpose of paragraph (1) may be made subject to such reasonable conditions as may be specified by the person giving it but shall not be unreasonably withheld.
- (4) In this paragraph “navigation authority” means any person who has a duty or power under any enactment to work, maintain, conserve, improve or control any canal or other inland navigation, navigable river, estuary or harbour.
Application of landlord and tenant law
49
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised project or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised project, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person’s use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants shall prejudice the operation of any agreement to which this article applies.
- (3) Accordingly, no such enactment or rule of law shall apply in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for purposes of the 1990 Act
50
Development consent granted by this Order shall be treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as operational land for the purposes of that Act).
Defence to proceedings in respect of statutory nuisance
51
- (1) Where proceedings are brought under section 82(1) of the Environmental Protection Act 199066 (summary proceedings by person aggrieved by statutory nuisance) in relation to a nuisance falling within paragraph (g) of section 79(1) of that Act (noise emitted from premises so as to be prejudicial to health or a nuisance) no order shall be made, and no fine may be imposed, under section 82(2) of that Act if—
- (a) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project and that the nuisance is attributable to the carrying out of the authorised project in accordance with a notice served under section 60 (control of noise on construction site), or a consent given under section 61 (prior consent for work on construction site) or 65 (noise exceeding registered level), of the Control of Pollution Act 197467; or
- (ii) is a consequence of the construction or maintenance of the authorised project and that it cannot reasonably be avoided; or
- (b) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the use of the authorised project and that the nuisance is attributable to the use of the authorised project which is being used in accordance with a scheme of monitoring and attenuation of noise agreed with the Commission as described in requirement 25; or
- (ii) is a consequence of the use of the authorised project and that it cannot reasonably be avoided.
- (2) Section 61(9) (consent for work on construction site to include statement that it does not of itself constitute a defence to proceedings under section 82 of the Environmental Protection Act 1990) of the Control of Pollution Act 1974 and section 65(8) of that Act (corresponding provision in relation to consent for registered noise level to be exceeded), shall not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised project.
Protection of interests
52
Schedule L to this Order has effect.
Saving for Trinity House
53
Nothing in this Order prejudices or derogates from any of the rights, duties or privileges of Trinity House.
Disapplication of regulation 60 of the Conservation (Natural Habitats, &c.) Regulations 1994
54
- (1) Regulation 60 of the Conservation (Natural Habitats, &c.) Regulations 199468 (general development orders) (“the Habitats Regulations”) shall not apply to any planning permission which relates to the works authorised by article 7 (subsidiary works) and which is granted by article 3(1) of the Town and Country Planning (General Permitted Development) Order 1995 for the class of development described as permitted development in Part 11 of Schedule 2 to that Order.
- (2) Paragraph (1) does not apply if and to the extent that those works—
- (a) do not form part of the plan and project which was subject to an appropriate assessment in accordance with regulation 48 of the Habitats Regulations (assessment of implications for European Site) in connection with the making of this Order; and
- (b) are not the subject of a further consent, permission or authorisation by a competent authority as defined in the Habitats Regulations.
Planning, etc. jurisdiction
55
- (1) During the period beginning with the date when this Order comes into force and beginning on the accretion date, the area within the Order limits shall, for the purposes of the Control of Pollution Act 197469 and the Town and Country Planning Act 199070, be annexed to and incorporated with the district of [insert name of relevant planning authority].
- (2) In this article “accretion date” means the date when the works authorised by this Order have been completed or, if earlier, the date when the benefits and rights granted by this Order cease to have effect pursuant to article 4 (period for completion of work).
Certification of plans etc
56
- (1) The undertaker shall, as soon as practicable after the making of this Order, submit to the decision-maker copies of—
- (a) the book of reference;
- (b) the land plan;
- (c) the rights plan;
- (d) the works plan;
- (e) the sections; and
- (f) any other plans or documents referred to in this Order,
for certification that they are true copies of the documents referred to in this Order.
- (2) A plan or document so certified shall be admissible in any proceedings as evidence of the contents of the document of which it is a copy.
Arbitration
57
Any difference under any provision of this Order, unless otherwise provided for, shall be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the [insert appropriate body].
Schedule A — AUTHORISED PROJECT
Part 1 — AUTHORISED DEVELOPMENT
[NOTE: This Part should describe as fully as possible the elements of the proposed project (including any associated development), which are development for the purposes of section 32 of the 2008 Act, for which development consent is sought. It should not include any elements of development which would be authorised by specific provisions in the Order.]
Part 2 — ANCILLARY WORKS
[NOTE: This Part should describe as fully as possible the ancillary works for which consent is sought and which are not development within the meaning of section 32 of the 2008 Act and which are not be the subject of a separate provision [article] in this Order.]
Schedule B — STREETS SUBJECT TO STREET WORKS
| (1) | (2) |
|---|---|
| Area | Street subject to street works |
Schedule C — STREETS TO BE STOPPED UP
Part 1 — STREETS FOR WHICH A SUBSTITUTE IS TO BE PROVIDED
| (1) | (2) | (3) | (4) |
|---|---|---|---|
| Area | Street to be stopped up | Extent of stopping up | New street to be substituted |
Part 2 — STREETS FOR WHICH NO SUBSTITUTE IS TO BE PROVIDED
| (1) | (2) | (3) |
|---|---|---|
| Area | Street to be stopped up | Extent of stopping up |
Schedule D — STREETS TO BE TEMPORARILY STOPPED UP
| (1) | (2) | (3) |
|---|---|---|
| Area | Street to be temporarily stopped up | Extent of temporary stopping up |
Schedule E — ACCESS TO WORKS
| (1) | (2) |
|---|---|
| Area | Description of access |
Schedule F — LAND OF WHICH ONLY SUBSOIL MORE THAN 9 METRES BENEATH SURFACE MAY BE ACQUIRED
| (1) | (2) |
|---|---|
| Area | Number of and shown on land plan |
Schedule G — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
| (1) | (2) | (3) | (4) |
|---|---|---|---|
| Area | Number of land shown on land plan | Purpose for which temporary possession may be taken | Relevant part of the Authorised project |
Schedule H — DEEMED CONSENT UNDER COAST PROTECTION ACT 1949
[Insert details of deemed consent]
Schedule I — DEEMED LICENCE UNDER THE FOOD AND ENVIRONMENT PROTECTION ACT 1985
[Insert details of deemed licence]
Schedule J — TREES SUBJECT TO TREE PRESERVATION ORDERS
| (1) | (2) | (3) |
|---|---|---|
| Type of tree | Number[reference] of tree shown on land plan | Work to be carried out |
Schedule K — LIMITS OF HARBOUR
[Insert details of limits of harbour]
Schedule L — PROTECTIVE PROVISIONS
[Insert details of protective provisions]
SCHEDULE 4 — Model provisions in respect of requirements
Interpretation
1
In this Schedule—
- “the 1990 Act” means the Town and Country Planning Act 1990;
- “the 2008 Act” means the Planning Act 2008;
- “authorised development” means the development and associated development described in Part 1 of Schedule A (authorised project) [and any other development authorised by this Order], which is development within the meaning of section 32 of the 2008 Act;
- “the authorised project” means the authorised development and the ancillary works authorised by this Order;
- “the code of construction practice” means the code of construction practice agreed by [insert relevant body] on [insert date];
- “the environmental document” means the document certified as the environmental document by the decision-maker for the purposes of this Order;
- “highway” and “highway authority” have the same meaning as in the Highways Act 1980;
- “the Order limits” means the limits shown on the works plan within which the authorised project may be carried out;
- “relevant planning authority” means— the district planning authority for the area in which the land to which the provisions of this Order apply is situated unless the provisions relate to the construction or alteration of a hazardous waste facility, in which case it means the county planning authority; a National Park Authority; the Broads Authority; and the Greater London Authority if the land to which the provisions of this Order or requirements apply is situated in Greater London;
- “stage” means a defined section or part of the authorised development, the extent of which is shown in a scheme submitted to and approved by the Commission pursuant to requirement 3 (stages of authorised development).
Time limits
2
The authorised development must be begun within [insert number] years of the date of this Order.
Stages of authorised development
3
No authorised development shall commence until a written scheme setting out all the stages of the authorised development has, after consultation with the relevant planning authority and highway authority, been submitted to and approved by the Commission.
Detailed design approval
4
No [stage of the] authorised development shall commence until [for that stage] written details of the following have, after consultation with the relevant planning authority, been submitted to and approved by the Commission—
- [or
5
No [stage of the] authorised development shall commence until details of the layout, scale and external appearance of the following elements of the authorised development [within that stage] have, after consultation with the relevant planning authority, been submitted to and approved by the Commission]
6
The authorised development must be carried out in accordance with the approved details.
Provision of landscaping
7
No [stage of the] authorised development shall until commence a written landscaping scheme [for that stage] has, after consultation with the relevant planning authority, been submitted to and approved by the Commission. The landscaping scheme must include details of all proposed hard and soft landscaping works, including—
- (a) location, number, species, size and planting density of any proposed planting;
- (b) cultivation, importing of materials and other operations to ensure plant establishment;
- (c) proposed finished ground levels;
- (d) hard surfacing materials;
- (e) vehicular and pedestrian access, parking and circulation areas;
- (f) minor structures, such as furniture, refuse or other storage units, signs and lighting;
- (g) proposed and existing functional services above and below ground, including drainage, power and communications cables and pipelines, manholes and supports;
- (h) details of existing trees to be retained, with measures for their protection during the construction period;
- (i) retained historic landscape features and proposals for restoration, where relevant; and
- (j) implementation timetables for all landscaping works.
Implementation and maintenance of landscaping
8
- (1) All landscaping works must be carried out in accordance with the landscaping scheme approved under requirement 7 and to a reasonable standard in accordance with the relevant recommendations of appropriate British Standards or other recognised codes of good practice.
- (2) The landscaping works must be carried out in accordance with implementation timetables approved under requirement 6.
- (3) Any tree or shrub planted as part of an approved landscaping scheme that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the Commission, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless otherwise approved by the Commission.
Trees
9
- (1) No [stage of the] authorised development shall commence until written details of any proposed tree planting and the proposed times of planting have, after consultation with the relevant planning authority, been approved in writing by the Commission; and all tree planting shall be carried out in accordance with those details and at those times.
- (2) If within a period of [two years] beginning with the date of the planting of any tree that tree, or any tree planted in replacement for it, is removed, uprooted or destroyed or dies, [or becomes, in the opinion of the Commission, seriously damaged or defective,] another tree of the same species and size as that originally planted shall be planted at the same place, unless the Commission gives its written consent to a variation.
Highway accesses
10
- (1) No [stage of the] authorised development shall commence until [for that stage,] written details of the siting, design and layout of any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic, has, after consultation with the relevant planning authority and highway authority, been submitted to and approved by the Commission.
- (2) The highway accesses must be constructed in accordance with the approved details.
- (3) No [stage of the] authorised development shall be begun until [for that stage,] a written Access Management Scheme has, after consultation with the relevant planning authority and highway authority, been submitted to and approved by the Commission.
- (4) The Access Management Scheme must be carried out in accordance with the approved details.
Public rights of way
11
- (1) No [stage of the] authorised development shall commence that would affect [insert details of relevant right of way] until a written implementation plan and specification for the making up of an alternative right of way has, after consultation with the relevant planning authority and highway authority, been submitted to and approved by the Commission.
- (2) The alternative [insert details of relevant right of way] shall be implemented in accordance with the approved plan and specification.
Fencing – special roads
12
- (1) No [stage of the] authorised development shall commence until written details of the design and construction of any boundary fencing for special roads have, after consultation with the relevant planning authority and highway authority, been submitted to and approved by the Commission.
- (2) The authorised development shall be carried out in accordance with the approved design and construction.
- (3) “Special road” has the same meaning as in section 329 of the Highways Act 1980.
Fencing and other means of enclosure
13
- (1) No [stage of the] authorised development shall commence until written details of all proposed permanent and temporary fences, walls or other means of enclosure [for that stage] have, after consultation with the relevant planning authority, been submitted to and approved by the Commission.
- (2) The [insert description], and any construction sites, must remain securely fenced at all times during construction of the authorised development.
- (3) Any temporary fencing must be removed on completion of the authorised development.
- (4) Any approved permanent fencing of the new [insert description] must be completed before the [insert description] is brought into use.
Surface water drainage
14
- (1) No [stage of the] authorised development shall commence until [for that stage,] written details of the surface and foul water drainage system (including means of pollution control) have, after consultation with the relevant planning authority and the sewerage and drainage authority, been submitted to and approved by the Commission.
- (2) The surface and foul water drainage system must be constructed in accordance with the approved details.
Contaminated land and groundwater
15
- (1) No [stage of the] authorised development shall commence until a written scheme [applicable to that stage,] to deal with the contamination of any land, including groundwater, within the Order limits which is likely to cause significant harm to persons or pollution of controlled waters or the environment has, after consultation with the relevant planning authority and the Environment Agency, been submitted to and approved by the Commission.
- (2) The scheme shall include an investigation and assessment report, prepared by a specialist consultant approved by the relevant planning authority, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
- (3) Remediation must be carried out in accordance with the approved scheme.
Archaeology
16
- (1) No [stage of the] authorised development shall commence until [for that stage,] a written scheme for the investigation of areas of archaeological interest [as identified in section [ ]of the environmental document] has, after consultation with the relevant planning authority, been submitted to and approved by the Commission.
- (2) The scheme shall identify areas where field work and/or a watching brief are required, and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.
- (3) Any archaeological works or watching brief carried out under the scheme must be by a suitably qualified person or body approved by the Commission.
- (4) Any archaeological works or watching brief must be carried out in accordance with the approved scheme.
Ecological management plan
17
- (1) No [stage of the] authorised development shall commence until a written ecological management plan [for that stage] reflecting the survey results and ecological mitigation and enhancement measures included in the environmental document, after consultation with the relevant planning authority, shall be submitted to and approved by the Commission.
- (2) The ecological management plan shall include an implementation timetable and must be carried out as approved.
Code of construction practice
18
Construction works shall be carried out in accordance with the agreed code of construction practice, unless otherwise agreed by the Commission, after consultation with relevant planning authority.
- [or
19
- (1) No [stage of the] authorised development shall commence until a code of construction practice shall, after consultation with the relevant planning authority, be submitted to and approved by the Commission.
- (2) All construction works shall be undertaken in accordance with the approved code, unless otherwise agreed by the Commission.]
[Note: The code should specify measures designed to minimise the impacts of construction works, such as means of minimising pollution from dust, noise, vibration and lighting, wheel cleansing facilities, routes for construction traffic, working hours etc. To the extent that it does not, or does not do so adequately, separate conditions are likely to be required, some of which are indicated below].
Design of roads
20
- (1) No [stage of the] authorised development consisting of the construction or alteration of a street which is a trunk road or including any traffic management and control measures shall commence until written details of the design of the street shall, after consultation with the Highways Agency, be submitted to and approved by the Commission.
- (2) The [authorised development] construction or alteration of the street or the taking of traffic management and control measures shall be carried out in accordance with the approved design.
External lighting
21
No [stage of the] authorised development, shall commence until written details of any external lighting to be installed at any of the construction sites [within that stage], including measures to prevent light spillage, shall, after consultation with the relevant planning authority and the highway authority, be submitted to and approved by the Commission; and any approved means of lighting must subsequently be installed and retained for the duration of the construction period.
Construction traffic
22
- (1) No [stage of the] authorised development shall commence until written details of the preferred route to be used by construction traffic shall, after consultation with the relevant planning authority and the highway authority, be submitted to and approved by the Commission.
- (2) Notices shall be erected and maintained throughout the period of construction at every construction site exit, indicating to drivers the route agreed by the Commission for traffic entering and leaving the site.
Control of noise during construction and maintenance
23
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for noise management during construction and maintenance [of that stage] has been submitted to and approved by the Commission.
- (2) The scheme shall set out the particulars of—
- (a) the works, and the method by which they are to be carried out;
- (b) the noise attenuation measures to be taken to minimise noise resulting from the works, including any noise limits; and
- (c) a scheme for monitoring the noise during the works to ensure compliance with the noise limits and the effectiveness of the attenuation measures.
- (3) The approved noise management scheme must be implemented before and maintained during construction and maintenance of the [relevant stage of the] authorised development.
- (4) The construction and maintenance works must be undertaken in accordance with the approved noise management scheme.
Construction hours
24
- (1) Construction work shall not take place other than between [0800 and 1800 hours on weekdays and 0800 and 1300 hours on Saturdays, excluding public holidays], unless otherwise agreed by the Commission.
- (2) Nothing in paragraph (1) precludes a start-up period from [0730 to 0800] and a shut down period from [1800 to 1830] on weekdays (excluding public holidays).
Control of noise during operational phase
25
- (1) No authorised development shall commence operation until, after consultation with the relevant planning authority, a written scheme for noise management including monitoring and attenuation for the use of the authorised project has been submitted to and approved by the Commission.
- (2) The noise management scheme must be implemented as approved and maintained for the duration of use of the authorised project.
Control of odour emissions
26
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for the management and mitigation of odour emissions has been submitted to and approved by the Commission.
- (2) The approved scheme for the management and mitigation of odour emissions must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.
Control of artificial light emissions
27
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for the management and mitigation of artificial light emissions has been submitted to and approved by the Commission.
- (2) The approved scheme for the management and mitigation of artificial light emissions must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.
Control of dust emissions
28
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for the management and mitigation of dust emissions has been submitted to and approved by the Commission.
- (2) The approved scheme for the management and mitigation of dust emissions must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development
Control of smoke emissions
29
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for the management and mitigation of smoke emissions has been submitted to and approved by the Commission.
- (2) The approved scheme for the management and mitigation of smoke emissions must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.
Control of steam emissions
30
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme for the management and mitigation of steam emissions has been submitted to and approved by the Commission.
- (2) The approved scheme for the management and mitigation of steam emissions must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.
Control of insects
31
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority, a written scheme to ensure the prevention of infestation or emanation of insects from the authorised development has been submitted to and approved by the Commission.
- (2) The approved scheme for the prevention of infestation or emanation of insects must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.
- (3) For the purposes of this requirement, “insects” excludes insects that are wild animals included in Schedule 5 to the Wildlife and Countryside Act 198171 (animals which are protected), unless they are included in respect of section 9(5) of that Act only.
Accumulations and deposits
32
- (1) No [stage of the] authorised development shall commence until, after consultation with the relevant planning authority,a written scheme for the management of any accumulations [or] and deposits whose effects may be harmful or visible or otherwise noticeable from outside the Order limits has been submitted to and approved by the Commission.
- (2) The approved scheme for the management of accumulations and deposits must be implemented before and maintained during the construction, operation and decommissioning of the [relevant stage of the] authorised development.
Travel plan
33
- (1) No [stage of the] of the authorised development shall be begun until, after consultation with the relevant planning authority and the highway authority, a travel plan [for the contractor’s workforce], which must include details of the expected means of travel to and from [the authorised [project]][the construction site] and any parking to be provided, has been submitted to and approved by the Commission.
- (2) No part of the authorised project shall be brought into use until, after consultation with the relevant planning authority and the highway authority, a travel plan, which must include details of the expected means of travel to and from the authorised project and any parking to be provided, has been submitted to and approved by the Commission.
- (3) The plan approved under paragraph (1) must be implemented during the construction of the authorised development and the plan approved under paragraph (2) must be implemented [within one month of the authorised project being brought into use] and shall continue to be implemented for as long as the authorised project is used.
European protected species
34
- (1) No [stage of the] authorised development shall commence until [further] survey work has been carried out to establish whether a European protected species is present on any of the land affected, or likely to be affected, by the authorised development or in any of the trees to be lopped or felled or buildings to be demolished during [that stage of] the authorised development.
- (2) Where a European protected species is shown to be present, no authorised development [of that stage] shall be begun until, after consultation with the relevant planning authority, Natural England and the Secretary of State for the Environment, Food and Rural Affairs, a scheme of protection and mitigation measures has been submitted to and approved by the Commission; and the authorised development shall be carried out in accordance with the approved scheme.
- (3) “European protected species” has the same meaning as in regulations 38 and 42 of the Conservation (Natural Habitats, &c.) Regulations 199472.
Restoration of land used temporarily for construction
35
Any land within the Order limits which is used temporarily for construction must be reinstated to its former condition, or such condition as the Commission may approve, within [six] months of completion of authorised development.
Requirement for written approval
36
Where under any of the above requirements the approval or agreement of the Commission or another person is required, that approval or agreement must be given in writing.
Amendments to approved details
37
With respect to any requirement which requires the authorised development to be carried out in accordance with the details approved by the Commission, the approved details shall be taken to include any amendments that may subsequently be approved in writing by the Commission.
Requirement for consent of Civil Aviation Authority and Ministry of Defence
38
No [stage of the] authorised development shall commence until [for that stage], after consultation with the Civil Aviation Authority and the Ministry of Defence, written details for the operation of the authorised project [and its effect on radar] have been submitted to and agreed by the Commission.
[Note: This requirement is only relevant in the context of authorised development that involves a wind farm.]
Signed
Signed by authority of the Secretary of State for Communities and Local Government
Bill McKenzie — Parliamentary Under Secretary of State — Department for Communities and Local Government — 1st September 2009
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
The Planning Act 2008 (“the 2008 Act”) established the Infrastructure Planning Commission (“the Commission”) and provides for the granting of development consent for certain types of nationally significant infrastructure project. Development consent is granted in the form of an Order made by the Commission or the Secretary of State.
This Order prescribes model provisions for inclusion in the draft Order, which the Infrastructure Planning (Applications and Procedure) Regulations 2009 (S.I. 2009/2264) require to accompany an application for an order granting development consent. These model provisions may also be included in orders made by the Commission under section114 of the 2008 Act, which grant development consent for nationally significant infrastructure projects. The Commission must have regard to the prescribed model provisions when making an order granting development consent but is not compelled to use them: the Commission may omit them entirely from orders if the model provisions are not appropriate or may adapt them to meet specific requirements.
Schedule 1 sets out general model provisions, which may be included in orders relating to all nationally significant infrastructure projects. These model provisions include an interpretation provision, which sets out general definitions, provisions in respect of street works, stopping up of streets, agreements with street authorities, access to works, the compulsory purchase of land and rights over the land or lesser interests in land and the extinguishment or suspension of rights over land.
Schedule 2 sets out model provisions relevant to orders granting development consent for railways. These include provisions in respect of the incorporation of the Railways Clauses Consolidation Act 1845 (c.20), level crossings and the operation and use of railways.
Schedule 3 sets out model provisions relevant to orders granting development consent for harbours. These include an interpretation provision, which sets out definitions relevant to harbours, provisions in respect of the incorporation of the Harbours, Docks and Piers Clauses Act 1847 (c.27), the limits of the harbour, tidal works and the right to dredge.
Schedule 4 sets out model provisions in respect of the requirements which can be included in orders granting development consent under section 120 of the 2008 Act.
An Impact Assessment has not been prepared for this Order as there is no additional impact on business, charities or the public sector beyond that examined in the Impact Assessment that accompanied the Planning Bill when it was introduced in Parliament on 27th November 2007. That Impact Assessment can be found on the Communities and Local Government website (http://www.communities.gov.uk).
Footnotes
1961 c.33. Section 2(2) was amended by section 193 of, and paragraph 5 of Schedule 33 to, the Local Government, Planning and Land Act 1980 (c.65). There are other amendments to the 1961 Act which are not relevant to this Order.
1965 c.56. Section 3 was amended by section 70 of, and paragraph 3 of Schedule 15 to, the Planning and Compensation Act 1991(c.34). Section 4 was amended by section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c.71). Section 5 was amended by sections 67 and 80 of, and Part 2 of Schedule 18 to, the Planning and Compensation Act 1991 (c.34). Subsection (1) of section 11 and sections 3, 31 and 32 were amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c.67) and by section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). Section 12 was amended by section 56(2) of, and Part 1 to Schedule 9 to, the Courts Act 1971 (c.23). Section 13 was amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c.15). Section 20 was amended by section 70 of, and paragraph 14 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). Sections 9, 25 and 29 were amended by the Statute Law (Repeals) Act 1973 (c.39). Section 31 was also amended by section 70 of, and paragraph 19 of Schedule15 to, the Planning and Compensation Act 1991 (c.34) and by section 14 of, and paragraph 12(2) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). There are other amendments to the 1965 Act which are not relevant to this Order.
1980 c.66. Section 1(1) was amended by section 21(2) of the New Roads and Street Works Act 1991 (c.22); sections 1(2), 1(3) and1 (4) were amended by section 8 of, and paragraph (1) of Schedule 4 to, the Local Government Act 1985 (c.51); section 1(2A) was inserted, and section 1(3) was amended, by section 259 (1), (2) and (3) of the Greater London Authority Act 1999 (c.29); sections 1(3A) and 1(5) were inserted by section 22(1) of, and paragraph 1 of Schedule 7 to, the Local Government (Wales) Act 1994 (c.19). Section 36(2) was amended by section 4(1) of, and paragraphs 47(a) and (b) of Schedule 2 to, the Housing (Consequential Provisions) Act 1985 (c.71), by S.I. 2006/1177, by section 4 of, and paragraph 45(3) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11), by section 64(1) (2) and (3) of the Transport and Works Act (c.42) and by section 57 of, and paragraph 5 of Part 1 of Schedule 6 to, the Countryside and Rights of Way Act 2000 (c.37); section 36(3A) was inserted by section 64(4) of the Transport and Works Act 1992 and was amended by S.I. 2006/1177; section 36(6) was amended by section 8 of, and paragraph 7 of Schedule 4 to, the Local Government Act 1985 (c.51); and section 36(7) was inserted by section 22(1) of, and paragraph 4 of Schedule 7 to, the Local Government (Wales) Act 1994 (c.19). Section 329 was amended by section 112(4) of, and Schedule 18 to, the Electricity Act 1989 (c.29) and by section 190(3) of, and Part 1 of Schedule 27 to, the Water Act 1989 (c.15). There are other amendments to the 1980 Act which are not relevant to this Order.
1990 c.8. Section 206(1) was amended by section 192(8) of, and paragraphs 7 and 11 of Schedule 8 to, the Planning Act 2008 (c29) (date in force to be appointed see section 241(3), (4)(a), (c) of the 2008 Act). There are other amendments to the 1990 Act which are not relevant to this Order.
1991 c.22. Section 48(3A) was inserted by section 124 of the Local Transport Act 2008 (c.26). Sections 79(4), 80(4), and 83(4) were amended by section 40 of, and Schedule 1 to, the Traffic Management Act 2004 (c.18).
1981 c.67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). There are other amendments to the 1981 Act which are not relevant to this Order.
1990 c.43. There are amendments to this Act which are not relevant to this Order.
1974 c.40. Sections 61(9) and 65(8) were amended by section 162 of, and paragraph 15 of Schedule 3 to, the Environmental Protection Act 1990, c.25. There are other amendments to the 1974 Act which are not relevant to this Order.
1991 c.56. Section 106 was amended by sections 36(2) and 99 of the Water Act 2003 (c.37). There are other amendments to this section which are not relevant to this Order.
1991 c.57. 1991 c.57. Section 85(1) was amended by paragraphs 21(1) and (2) of Part 1 of Schedule 21 to S.I. 2007/3538.
1964 c.40. Paragraph 9B was inserted into Schedule 2 by the Transport and Works Act 1992 (c.42), section 63(1) and Schedule 3, paragraph 9(1) and (5). There are other amendments to the 1964 Act which are not relevant to this Order.
1857 c.81. There are amendments to this Act which are not relevant to this Order.
1981 c.67. Sub-paragraph (5) of paragraph 1 of Part 1 of Schedule 2 was amended by section 67 of, andparagraph 27(3) of Schedule 9 to, the Coal Industry Act 1994 (c.21) and paragraph 8 of Part 3 of Schedule was amended by section 46 of the Criminal Justice Act 1982 (c.48). There are other amendments to the 1981 Act which are not relevant to this Order.
1981 c.66. Sections 2 and 116 were amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11). There are other amendments to the 1981Act which are not relevant to this Order.
1981 c. 66. Sections 2(3), 6(2) and 11(6) were amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11). Section 15 was amended by sections 56 and 321(1) of, and Schedules 8 and 16 to, the Housing and Regeneration Act 2008 (c. 17). Paragraph 1 of Schedule 2 was amended by section 76 of, and Part 2 of Schedule 9 to, the Housing Act 1988 (c 50); section 161(4) of, and Schedule 19 to, the Leasehold Reform, Housing and Urban Development Act 1993 (c. 28); and sections 56 and 321(1) of, and Schedule 8 to, the Housing and Regeneration Act 2008. Paragraph 3 of Schedule 2 was amended by section 76 of, and Schedule 9 to, the Housing Act 1988 and section 56 of, and Schedule 8 to, the Housing and Regeneration Act 2008. Paragraph 2 of Schedule 3 was repealed by section 277 of, and Schedule 9 to, the Inheritance Tax Act 1984 (c. 51). There are other amendments to the 1981 Act which are not relevant to this Order.
2003 c.21. There are amendments to this Act which are not relevant to this Order.
1949 c.74. Section 34 has been amended by section 36 of the Merchant Shipping Act 1988 (c.12). There are other amendments to the 1949 Act which are not relevant to this Order.
1985 c.48. Sections 5 and 6 in Part 2 have been amended by sections 146(2) and 162 of, and Part 8 of Schedule 16 to, the Environmental Protection Act 1990 (c. 43). There are other amendments to the 1985 Act which are not relevant to this Order.
1961 c.33. Section 2(2) was amended by section 193 of, and paragraph 5 of Schedule 33 to, the Local Government, Planning and Land Act 1980 (c.65). There are other amendments to the 1980 Act which are not relevant to this Order.
1965 c.56. Section 3 was amended by section 70 of, and paragraph 3 of Schedule 15 to, the (c..34). Section 4 was amended by section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c.71). Section 5 was amended by sections 67 and 80 of, and Part 2 of Schedule 18 to, the Planning and Compensation Act 1991 (c.34). Section 11(1) and sections 3, 31 and 32 were amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67) and by section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). Section 12 was amended by section 56(2) of, and Part 1 to Schedule 9 to, the Courts Act 1971 (c.23). Section 13 was amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c.15). Section 20 was amended by section 70 of, and paragraph 14 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). Sections 9, 25 and 29 were amended by the Statute Law (Repeals) Act 1973 (c.39). Section 31 was also amended by section 70 of, and paragraph 19 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34) and by section 14 of, and paragraph 12(2) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). There are other amendments to the 1965 Act which are not relevant to this Order.
1980 c.66. Section 1(1) was amended by section 21(2) of the New Roads and Street Works Act 1991 (c.22); sections 1(2), (3) and (4) were amended by section 8 of, and paragraph (1) of Schedule 4 to, the Local Government Act 1985 (c.51); section 1(2A) was inserted by, and section 1(3) was amended by, section 259 (1), (2) and (3) of the Greater London Authority Act 1999 (c.29); sections 1(3A) and 1(5) were inserted by section 22(1) of, and paragraph 1 of Schedule 7 to the Local Government (Wales) Act 1994 (c.19). Section 36(2) was amended by section 4(1) of, and paragraphs 47 (a) and (b) of Schedule 2 to, the Housing (Consequential Provisions) Act 1985 (c.71), by S.I. 2006/1177, by section 4 of and paragraph 45(3) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11), by section 64(1) (2) and (3) of the Transport and Works Act (c.42) and by section 57 of, and paragraph 5 of Part 1 of Schedule 6 to, the Countryside and Rights of Way Act 2000 (c.37); section 36(3A) was inserted by section 64(4) of the Transport and Works Act 1992 and was amended by S.I. 2006/1177; section 36(6) was amended by section 8 of, and paragraph 7 of Schedule 4 to, the Local Government Act 1985 (c.51); and section 36(7) was inserted by section 22(1) of, and paragraph 4 of Schedule 7 to, the Local Government (Wales) Act 1994 (c.19). Section 329 was amended by section 112(4) of, and Schedule 18 to, the Electricity Act 1989 (c.29) and by section 190(3) of, and Part 1 of Schedule 27 to, the Water Act 1989 (c.15). There are other amendments to the 1980 Act which are not relevant to this Order.
1990 c.8. Section 206(1) was amended by section 192(8) to, and paragraphs 7 and 11 of Schedule 8 to, the Planning Act 2008 (c29) (date in force to be appointed see section 241(3), (4)(a),(c) of the 2008 Act). There are other amendments to the 1990 Act which are not relevant to this Order.
1991 c.22. Section 48(3A) was inserted by section 124 of the Local Transport Act 2008 (c.26). Sections 79(4), 80(4), and 83(4) were amended by section 40 of, and Schedule 1 to, the Traffic Management Act 2004 (c.18).
1981 c.67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). There are other amendments to the 1981 Act which are not relevant to this Order.
1845 c. 20. Section 46 was amended by sections 109(1) and (3) of, and paragraph 22 of Schedule 8, and Schedule 10 to, the Courts Act 2003 (c.39). Section 58 was amended by section 46 of, and Part 3 of Schedule 7 to, the Justices of the Peace Act 1949 (c.101). Section 78 was amended by section 39(3) of, and Schedule 7 to, the Compulsory Purchase Act 1968 (c.56) and articles 5(1) and (2) of, and paras 1 and 3 of Schedule 7 to, S.I. 2009/1307. Section 105 was amended by section 46 of, and Part 3 of Schedule 7 to, the Justices of the Peace Act 1949 (c.101), and section 31(6) of the Criminal Law Act 1977 (c.45), and sections 37 and 49 of the Criminal Justice Act 1982 (c.48). There are other amendments to the 1845 Act not relevant to this Order.
1923 c. 20. Section 15 was amended by section 10(1) of the Decimal Currency Act 1969 (c.19).
1991 c.56. Section 106 was amended by the Water Act 2003 (c.37), sections 36(2) and 99 subject to the transitional provisions contained in article 6 of, and Schedule 3 to, S.I. 2004/641. There are other amendments to section 106 which are not relevant to this Order.
1991 c.57. Section 85(1) was amended by paragraphs 21(1) and (2) in Part 1 of Schedule 21 to S.I. 2007/3538.
1964 c.40. Paragraph 9B was inserted into Schedule 2 by the Transport and Works Act 1992 (c.42), section 63(1) and Schedule 3, paragraph 9(1) and (5).
1857 c.81. There are amendments to this Act which are not relevant to this Order.
1981 c.67. Sub-paragraph (5) of paragraph 1 of Part 1 of Schedule 2 was amended by section 67 of, andparagraph 27(3) of Schedule 9 to, the Coal Industry Act 1994 (c.21) and paragraph 8 of Part 3 of Schedule was amended by section 46 of the Criminal Justice Act 1982 (c.48). There are other amendments to the 1981 Act which are not relevant to this Order.
1981 c.66. Sections 2 and 116 were amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11). There are other amendments to the 1981Act which are not relevant to this Order.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.