The Planning Act 2008 (“the Act”) provides for the granting of an order for development consent for development which is or forms part of a nationally significant infrastructure project. Development consent is required for certain types of energy, water, waste water, transport and waste projects. The Act also establishes the Infrastructure Planning Commission (“the Commission”) which is responsible for examining, and in most cases, determining applications for development consent. Section 4 of the Act enables the Secretary of State to make regulations for the charging of fees by the Commission in relation to the performance of any of its functions.

Reform history JSON API

Made: 25th January 2010

Laid before Parliament: 1st February 2010

Coming into force: 1st March 2010

The Secretary of State, in exercise of the powers conferred by sections 4 and 232(3) of the Planning Act 200836, makes the following Regulations:

PART 1 — Introduction

Citation and commencement

1

These Regulations may be cited as the Infrastructure Planning (Fees) Regulations 2010 and shall come into force on 1st March 2010.

Interpretation

2

PART 2 — Charging of fees by the Secretary of State

Fee in respect of pre-application services

2A

Fee in respect of authorisation under sections 52 and 53

3

Fee in respect of venue costs

4

Fee to accompany an application

5

Fee in respect of the initial decision

6

Fee in respect of handling an application

7

Initial payment in respect of the handling of an application

8

Final payment in respect of the handling of an application

9

less the initial payment referred to in regulation 8.

Direction made under section 35

10

Regulations 5 and 6 shall not apply in relation to any application for consent or authorisation which is treated as an application for an order granting development consent pursuant to a direction made by the Secretary of State under section 35ZA(3)(a) (directions under section 35: procedural matters).

Intervention by the Secretary of State under section 112

11

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Fees payable on or after 1st April 2018

12

PART 3 — Charging of fees by public authorities

Fees in relation to the provision of relevant services

12A

PART 4 — Review

Review

13

SCHEDULE 1 — Pre-application services

Description of pre-application services
Giving of advice to the applicant under section 51(1) (Advice to potential applicants and others).
Services provided to the applicant in relation to the environmental impact assessment process under the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017.
Services provided to the applicant in relation to section 98 (Timetable for examining, and reporting on, applications).
Services provided to the applicant in relation to any matters which the Secretary of State thinks may be both important and relevant to the Secretary of State’s decision under section 104 (Decisions in cases where national policy statement has effect) and section 105 (Decisions in cases where no national policy statement has effect).

SCHEDULE 2 — Prescribed Public Authorities

Signed

Signed by the authority of the Secretary of State for Communities and Local Government

Ian Austin — Parliamentary Under Secretary of State — Department for Communities and Local Government — 25th January 2010

Editorial notes

1

Reg. 1 in force at 1.3.2010, see reg. 1

2

Reg. 2 in force at 1.3.2010, see reg. 1

3

Reg. 9 in force at 1.3.2010, see reg. 1

4

Reg. 10 in force at 1.3.2010, see reg. 1

5

Reg. 3 in force at 1.3.2010, see reg. 1

6

Reg. 5 in force at 1.3.2010, see reg. 1

7

Reg. 6 in force at 1.3.2010, see reg. 1

8

Reg. 8 in force at 1.3.2010, see reg. 1

9

Reg. 4 in force at 1.3.2010, see reg. 1

10

Reg. 7 in force at 1.3.2010, see reg. 1

Explanatory note

(This note is not part of the Regulations)

EXPLANATORY NOTE

The Planning Act 2008 (“the Act”) provides for the granting of an order for development consent for development which is or forms part of a nationally significant infrastructure project. Development consent is required for certain types of energy, water, waste water, transport and waste projects. The Act also establishes the Infrastructure Planning Commission (“the Commission”) which is responsible for examining, and in most cases, determining applications for development consent. Section 4 of the Act enables the Secretary of State to make regulations for the charging of fees by the Commission in relation to the performance of any of its functions.

These Regulations make provision for the payment of fees by an applicant or potential applicant, to the Commission in respect of handling applications made under the Act. The Regulations specify the circumstances in which a fee may be charged, the amount payable and the effect where the fee is not received by the Commission. The Regulations also ensure the Commission can charge:

Provision is made for payment of a fee in relation to requests under sections 52 and 53 of the Act (regulation 3). In relation to an application for an order granting development consent a fee is payable on submission of the application (regulation 5), once the Examining authority is appointed (regulation 6), at the start of the examination of the application by the Commission (regulations 7 and 8) and on completion of examination (regulation 9). The fees paid during examination comprise of two payments which include the cost of the examination of the application as well as the costs of the decision following the examination. The rates set out in these regulations are based on a daily rate which normally accumulates for each day in the examination period (generally excluding weekends and public holidays), with 50% of the overall estimated fee paid at the start of the examination. Further fees are payable where the applicant does not provide the venue facilities for any hearing required in relation to the application for an order granting development consent; the Regulations make provision for payment, by the applicant, of the costs reasonably incurred by the Commission (regulation 4).

An impact assessment has been prepared in relation to these Regulations. This assessment has been placed in the library of each House of Parliament and copies may be obtained from the Nationally Significant Infrastructure Division, Department of Communities and Local Government, Eland House, Bressenden Place, London, SW1E 5DU (telephone 0303 444 1613).

Footnotes

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.