Made: 19th September 2012

Laid before Parliament: 21st September 2012

Coming into force: 12th October 2012

The Secretary of State makes the following Regulations in exercise of the powers conferred by sections 56FC and 60 of the Electricity Act 1989[^f00001], and sections 41HC and 47 of the Gas Act 1986[^f00002].

PART 1 — Introductory

Citation and commencement

1

These Regulations may be cited as the Electricity and Gas (Competitive Tenders for Smart Meter Communication Licences) Regulations 2012 and shall come into force on 12th October 2012.

Interpretation

2

In these Regulations—

PART 2 — Scope of and requirement for a tender exercise

Scope of Regulations

3

Scope of a tender exercise and consideration of submissions to the competent authority

4

PART 3 — Conduct of a tender exercise

Conduct of a tender exercise

5

PART 4 — Stages of a tender exercise

Stages of a tender exercise

6

A tender exercise to be held in accordance with these Regulations shall comprise the following stages—

PART 5 — Commencement of a tender exercise

Commencement of a tender exercise

7

PART 6 — Qualification stage

Qualification and confidentiality

8

Determination of qualifying bidders at the qualification stage

9

PART 7 — Proposal stage

Proposal stage

10

Proposal stage: first tender exercise

11

Determination of preferred applicants at the proposal stage

12

PART 8 — Best and final offer stage

Best and final offer stage

13

Best and final offer stage: dialogue phase

14

Best and final offer stage: final offer phase

15

Best and final offer stage: evaluation

16

PART 9 — Preferred applicant stage

Notification of preferred applicant and reserve applicant

17

which the competent authority determines must be established prior to the grant of the electricity smart meter communication licence and the gas smart meter communication licence.

the competent authority may withdraw the notice given under paragraph (1) by giving a further notice to that effect.

as if that reserve applicant were the preferred applicant.

PART 10 — Notification of successful applicant

Notification of successful applicant

18

Information in respect of successful applicant

19

PART 11 — Withdrawal

Withdrawal

20

PART 12 — Cancellation

Cancellation

21

PART 13 — Disqualification from a tender exercise

Disqualification

22

it must disqualify that tender participant from the tender exercise by giving notice of that fact to that tender participant.

it may disqualify that tender participant from the tender exercise by giving notice of that fact to that tender participant.

PART 14 — Miscellaneous

Bidder groups

23

Changes to delivery of documents or actions

24

SCHEDULE 1 — Qualification stage

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 2 — Proposal stage

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 3 — Best and final offer stage

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 4 — Events of cancellation

The events in this Schedule are—

and

SCHEDULE 5 — Disqualification events

1

The events in this Schedule are that a tender participant or any person acting on behalf of a tender participant—

2

In this Schedule, “competition document” means a document to be submitted or which has been submitted to the competent authority by a tender participant in accordance with these Regulations.

3

In paragraph 1(e), “insider information” means information which—

4

In paragraph 1(i)—

5

A reference in this Schedule (other than in paragraph 1(h)), with respect to a tender exercise, to an action of or in relation to a tender participant includes a reference to an action of or in relation to a bidder, which occurs—

Signed

Verma — Parliamentary Under Secretary of State — Department of Energy and Climate Change — 19th September 2012

Explanatory note

(This note is not part of the Regulations)

EXPLANATORY NOTE

These Regulations set out the process for competitive tenders that will apply to the grant of smart meter communication licences under the Electricity Act 1989 and the Gas Act 1986.

Regulations 4 sets out that the tender exercise must be used to select the person to whom both a smart meter communication licence is to be granted under both the Electricity Act 1989 and the Gas Act 1986, and that the competent authority selecting that person must have regard to the need for the person awarded the licences to be suitable to be granted both.

Regulation 5 determines the which of the Secretary of State and the Authority is to run particular tender exercises (the “competent authority”).

Regulation 6 sets out the mandatory and discretionary stages of a tender exercise.

Regulation 7 gives the competent authority the discretion to determine when to hold a tender exercise, and requires the competent authority to publish a notice specifying the date on which the tender exercise will begin, or beginning it, including any additional information as is deemed necessary.

Regulations 8 and 9 describe the qualification stage of the tender exercise and how qualifying bidders will be determined. Schedule 1 sets out the information to be included in the qualification documentation.

Regulation 10 describes the proposal stage of the tender exercise, and Schedule 2 sets out the information to be included in the proposal documentation.

Regulation 11 describes additional procedure for the proposal stage of the tender exercise used to select the person to whom the first electricity and gas smart meter communication licences are to be granted. The procedure allows for the competent authority to change and update information during the stage.

Regulation 12 describes how the preferred applicant may be selected at the proposal stage, or allows the competent authority to hold a discretionary best and final offer stage to be held. The competent authority may also select up to two reserve applicants. Where two reserve applicants are selected, the competent authority must determine which is the first reserve applicant, and which is the second reserve applicant.

Regulation 13 describes the best and final offer stage of a tender exercise, including how the qualifying bidders who are to take part in it are selected. Schedule 3 sets out the information in the best and final offer documentation. The best and final offer stage has two phases: a dialogue phase where the applicants and the competent authority discuss the requirements of the licence holder and proposal of the applicant; and a final offer phase involving the submission by the applicant of bids.

Regulation 14 describes the dialogue phase of the best and final offer stage.

Regulation 15 describes the final offer phase of the best and final offer stage.

Regulation 16 describes how the preferred applicants are selected at the end of the best and final offer stage. The competent authority may also select up to two reserve applicants. Where two reserve applicants are selected, the competent authority must determine which is the first reserve applicant, and which is the second reserve applicant.

Regulation 17 requires the competent authority to publish a notice of its selection of a preferred applicant. The preferred applicant may be required to satisfy certain matters before it becomes the successful bidder. The reserve bidder may be treated as the preferred bidder if the original preferred bidder fails to satisfy the matters withdraws or is disqualified from a tender exercise. Where there are two reserve applicants, the first reserve applicant is initially treated as the preferred bidder in preference to the second reserve applicant. The second reserve applicant may be treated as preferred bidder where the first reserve applicant fails to satisfy remaining matters that apply with respect to it becoming the successful applicant, or where it is disqualified or withdraws.

Regulation 18 requires the competent authority to publish a notice when it has selected the successful applicant.

Regulation 19 requires the competent authority to give details of the successful applicant to unsuccessful applicants and requires at least ten working days to elapse before the smart meter communication licences are granted to the successful applicant. The competent authority is required publish a notice to confirm its determination to grant the licences to the successful applicant.

Regulation 20 provides for participants to withdraw from a tender exercise.

Regulation 21 provides for the competent authority to cancel a tender exercise in the circumstances described in Schedule 4. A tender exercise may be re-run from a particular stage until a successful applicant is identified or a tender exercise can be determined as failed.

Regulation 22 allows the competent authority to disqualify a participant from a tender exercise in the circumstances described in Schedule 5.

Regulation 23 describes the rules for changes to bidder groups.

Regulation 24 covers the requirements for publications, and allows the competent authority to notify a participant of any changes to the delivery of documents or actions required.

A full impact assessment of the effect that this instrument will have on the costs of business and the voluntary sector is available from Smart Meter Programme, Department of Energy and Climate Change, 3 Whitehall Place, London SW1A 2AW and is published with the Explanatory Memorandum alongside the instrument on www.legislation.gov.uk.

Footnotes

[^f00001]: 1989 c. 29. Section 56FC was inserted by section 91 of and Schedule 4 to the Energy Act 2008 (c. 32). Section 60 was amended by section 3(2) of the Utilities Act 2000 (c. 27).

[^f00002]: 1986 c. 44. Section 41HC was inserted by section 91 of and Schedule 4 to the Energy Act 2008 (c. 32). Relevant amendments to section 47 were made by section 3(2) of the Utilities Act 2000 (c. 27) and section 10(1) of the Gas Act 1995 (c. 45).

[^f00003]: 1989 c. 29. Section 6(1)(f) was inserted by S.I. 2012/2400.

[^f00004]: 1986 c. 44. Section 7AB was inserted by S.I. 2012/2400.

[^f00005]: 1989 c. 29. Section 4(3G) was inserted by S.I. 2012/2400.

[^f00006]: 1986 c. 44. Section 5(11) was inserted by S.I. 2012/2400.

[^f00007]: 2010 c. 23.

Editorial notes

[^key-b6667157c954f9cd96153ab1d9f0defd]: Reg. 1 in force at 12.10.2012, see reg. 1

[^key-d63d222fd024b44de9982aab43f7dc08]: Reg. 2 in force at 12.10.2012, see reg. 1

[^key-a0000926122d7127b811b9962fdb16b1]: Reg. 3 in force at 12.10.2012, see reg. 1

[^key-65606e27c159ad5349d677e49de858de]: Reg. 4 in force at 12.10.2012, see reg. 1

[^key-e0d92e1d298be1e166fbff35e5db832d]: Reg. 5 in force at 12.10.2012, see reg. 1

[^key-078c97ac58e0b6963accf9f70081a573]: Reg. 6 in force at 12.10.2012, see reg. 1

[^key-89e54b951db96a47e242fde31856517a]: Reg. 7 in force at 12.10.2012, see reg. 1

[^key-ad6955d52961f7f971d31c36cfb06fdb]: Reg. 8 in force at 12.10.2012, see reg. 1

[^key-33a9824c90dbdb1d88114b6347c01cf3]: Reg. 9 in force at 12.10.2012, see reg. 1

[^key-ec2d556b0c580fbd1533e0310b9dde75]: Reg. 10 in force at 12.10.2012, see reg. 1

[^key-0f727a71881d586494a9759ba23f11e2]: Reg. 11 in force at 12.10.2012, see reg. 1

[^key-8f217e2ad7bc62a4c9f5ca7b854300ff]: Reg. 12 in force at 12.10.2012, see reg. 1

[^key-2be4306352cc9da1c082632ac281685e]: Reg. 13 in force at 12.10.2012, see reg. 1

[^key-739d76fc01eb1cb3ce499a6e9e013fa0]: Reg. 14 in force at 12.10.2012, see reg. 1

[^key-4419d929cba1e35cef5cb41ad512d530]: Reg. 15 in force at 12.10.2012, see reg. 1

[^key-bc89149a1a68fcf041dac10c98603ab9]: Reg. 16 in force at 12.10.2012, see reg. 1

[^key-72c8f21d489857333bd5f8eaf786361c]: Reg. 17 in force at 12.10.2012, see reg. 1

[^key-be880493534b5f5c348371a32fe3c357]: Reg. 18 in force at 12.10.2012, see reg. 1

[^key-d207cff6ba80ea781a179e1672488b30]: Reg. 19 in force at 12.10.2012, see reg. 1

[^key-80af192575f6041f880b0116d3e23948]: Reg. 20 in force at 12.10.2012, see reg. 1

[^key-ebfc7f7841086d9a2c97499a741ce627]: Reg. 21 in force at 12.10.2012, see reg. 1

[^key-e5124d89771c6a724987ad39108e4daf]: Reg. 22 in force at 12.10.2012, see reg. 1

[^key-ff07d53cb684e6a5bd6a7c78a25b998d]: Reg. 23 in force at 12.10.2012, see reg. 1

[^key-0f5e7b23dd6aa62da0d42dd067101022]: Reg. 24 in force at 12.10.2012, see reg. 1

[^key-6c7e23d9f55ea226d511bbf06ecb0f33]: Sch. 5 para. 1 in force at 12.10.2012, see reg. 1

[^key-fac0de4129b947d34cc42279e8d31aa8]: Sch. 5 para. 2 in force at 12.10.2012, see reg. 1

[^key-0048568871db6cd21eeaeacb949f7f62]: Sch. 5 para. 3 in force at 12.10.2012, see reg. 1

[^key-2248743dc921b50514d57b45aa7e4e31]: Sch. 5 para. 4 in force at 12.10.2012, see reg. 1

[^key-e3144fcc4a0d9e495dc3b9ece8ad1cb7]: Sch. 5 para. 5 in force at 12.10.2012, see reg. 1

[^key-e67943568169b3319b97ad92cec38f14]: Sch. 1 in force at 12.10.2012, see reg. 1

[^key-234544a9751ff02209774ff8df15b51c]: Sch. 2 in force at 12.10.2012, see reg. 1

[^key-16dcb351cc568e2838ce1f6b6c468e6d]: Sch. 3 in force at 12.10.2012, see reg. 1

[^key-77a56008b54eab9cbdb72a0284940722]: Sch. 4 in force at 12.10.2012, see reg. 1

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.