The Chiltern Railways (Bicester to Oxford Improvements) Order 2012
- (3) The value of any apparatus removed under the provisions of this Schedule is to be deducted from any sum payable under sub-paragraph (2), that value being calculated after removal.
- (4) If in accordance with the provisions of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the Company or, in default of agreement, is not determined by arbitration in accordance with article 57 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the undertaker in question by virtue of sub-paragraph (2), is to be reduced by the amount of that excess.
- (5) For the purposes of sub-paragraph (4)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
- (6) An amount which apart from this sub-paragraph would be payable to an undertaker in respect of works by virtue of sub-paragraph (2) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
10
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the works referred to in paragraph 6(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of an undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any undertaker, the Company must—
- (a) bear and pay the cost reasonably incurred by that undertaker in making good such damage or restoring the supply; and
- (b) make reasonable compensation to that undertaker for any other expenses, loss, damages, penalty or costs incurred by the undertaker,
by reason or in consequence of any such damage or interruption.
SCHEDULE 15 — FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
1
- (1) For the protection of the Agency, the following provisions have effect unless otherwise agreed in writing between the Company and the Agency.
- (2) In this Schedule—
- “the Agency” means the Environment Agency;
- “construction” includes execution, placing, altering, replacing, relaying and removal and “construct” and “constructed” are to be construed accordingly;
- “drainage work” means any watercourse and includes any land which provides or is expected to provide flood storage capacity for any watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage, flood defence or tidal monitoring;
- “the fishery” means any waters containing fish and the spawn, habitat or food of such fish;
- “plans” includes sections, drawings, specifications and method statements;
- “specified work” means so much of any work or operation authorised by this Order as is in, on, under, over or within 16 metres of a drainage work or is otherwise likely to— affect any drainage work or the volumetric rate of flow of water in or flowing to or from any drainage work; affect the flow, purity or quality of water in any watercourse or other surface waters or ground water; cause obstruction to the free passage of fish or damage to any fishery; or affect the conservation, distribution or use of water resources.
2
- (1) Before beginning to construct any specified work, the Company must submit to the Agency plans of the specified work and such further particulars available to it as the Agency may within 28 days of the submission of the plans reasonably require.
- (2) Any such specified work must not be constructed except in accordance with such plans as may be approved in writing by the Agency, or determined under paragraph 13.
- (3) Any approval of the Agency required under this paragraph—
- (a) must not be unreasonably withheld or delayed;
- (b) is deemed to have been given if it is neither given nor refused within 2 months of the submission of the plans for approval and, in the case of a refusal, accompanied by a statement of the grounds of refusal; and
- (c) may be given subject to such reasonable requirements as the Agency may make for the protection of any drainage work or the fishery or for the protection of water resources, or for the prevention of flooding or pollution or in the discharge of its environmental duties.
- (4) The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).
3
Without limitation on the scope of paragraph 2, the requirements which the Agency may make under that paragraph include conditions requiring the Company at its own expense to construct such protective works, whether temporary or permanent, during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—
- (a) to safeguard any drainage work against damage; or
- (b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,
by reason of any specified work.
4
- (1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 3, must be constructed—
- (a) without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under this Schedule; and
- (b) to the reasonable satisfaction of the Agency,
and an officer of the Agency is entitled to watch and inspect the construction of such works.
- (2) The Company must give to the Agency not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is brought into use.
- (3) If any part of a specified work or any protective work required by the Agency is constructed otherwise than in accordance with the requirements of this Schedule, the Agency may by notice in writing require the Company at the Company’s own expense to comply with the requirements of this Schedule or (if the Company so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
- (4) Subject to sub-paragraph (5) and paragraph 8, if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (3) is served upon the Company, it has failed to begin taking steps to comply with the requirements of the notice and subsequently to make reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any expenditure incurred by it in so doing is recoverable from the Company.
- (5) In the event of any dispute as to whether sub-paragraph (3) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency must not except in emergency exercise the powers conferred by sub-paragraph (4) until the dispute has been finally determined.
5
- (1) Subject to the provisions of this Schedule and except to the extent that the Agency or another person is liable to maintain any such work and is not precluded by the exercise of the powers conferred by this Order from so doing, the Company must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation or on land held by the Company for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
- (2) If any such drainage work which the Company is liable to maintain is not maintained to the reasonable satisfaction of the Agency, the Agency may by notice in writing require the Company to repair and restore the work, or any part of such work, or (if the Company so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work and restore the site to its former condition, to such extent and within such limits as the Agency reasonably requires.
- (3) Subject to paragraph 8, if, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) on the Company, the Company has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from the Company.
- (4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2) , the Agency must not except in a case of emergency exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined.
6
Subject to paragraph 8, if by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work is otherwise damaged, such impairment or damage must be made good by the Company to the reasonable satisfaction of the Agency and if the Company fails to do so, the Agency may make good the same and recover from the Company the expense reasonably incurred by it in so doing.
7
- (1) The Company must take all such measures as may be reasonably practicable to prevent any interruption of the free passage of fish in the fishery during the construction of any specified work.
- (2) If by reason of—
- (a) the construction of any specified work; or
- (b) the failure of any such work,
damage to the fishery is caused, or the Agency has reason to expect that such damage may be caused, the Agency may serve notice on the Company requiring it to take such steps as may be reasonably practicable to make good the damage, or, as the case may be, to protect the fishery against such damage.
- (3) Subject to paragraph 8, if within such time as may be reasonably practicable for that purpose after the receipt of written notice from the Agency of any damage or expected damage to a fishery, the Company fails to take such steps as are described in sub-paragraph (2), the Agency may take those steps and may recover from the Company the expense reasonably incurred by it in doing so.
- (4) Subject to paragraph 8, in any case where immediate action by the Agency is reasonably required in order to secure that the risk of damage to the fishery is avoided or reduced, the Agency may take such steps as are reasonable for the purpose, and may recover from the Company the reasonable cost of so doing provided that notice specifying those steps is served on the Company as soon as reasonably practicable after the Agency has taken, or commenced to take, the steps specified in the notice.
8
Nothing in paragraphs 4(4), 5(3), 6, 7(3) and (4) authorises the Agency to execute works on or affecting an operational railway without the prior consent in writing of the Company, such consent not to be unreasonably withheld or delayed.
9
The Company must indemnify the Agency in respect of all costs, charges and expenses which the Agency may reasonably incur or have to pay or which it may sustain—
- (a) in the examination or approval of plans under this Schedule; and
- (b) in the inspection of the construction of the specified works or any protective works required by the Agency under this Schedule.
10
- (1) Without prejudice to the other provisions of this Schedule, the Company must indemnify the Agency from all claims, demands, proceedings, costs, damages, expenses or loss, which may be made or taken against, recovered from, or incurred by, the Agency by reason of—
- (a) any damage to any drainage work so as to impair its efficiency for the purposes of flood defence;
- (b) any damage to the fishery;
- (c) any raising or lowering of the water table in land adjoining the authorised works or any sewers, drains and watercourses;
- (d) any flooding or increased flooding of any such lands; or
- (e) inadequate water quality in any watercourse or other surface waters or in any groundwater,
which is caused by the construction of any of the specified works or any act or omission of the Company, its contractors, agents or employees whilst engaged upon the work.
- (2) The Agency must give to the Company reasonable notice of any such claim or demand and no settlement or compromise may be made without the agreement of the Company which agreement must not be unreasonably withheld or delayed.
11
The fact that any work or thing has been executed or done by the Company in accordance with a plan approved or deemed to be approved by the Agency, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the Company from any liability under the provisions of this Schedule.
12
For the purposes of Chapter 2 of Part 2 of the Water Resources Act 199141 (abstraction and impounding of water) and section 109 of that Act (as to structures in, over or under watercourses) as applying to the construction of any specified work, any consent or approval given or deemed to be given by the Agency under this Schedule with respect to such construction is deemed also to constitute a licence under that Chapter to obstruct or impede the flow of inland waters at that point by means of impounding works or, as the case may be, a consent or approval under section 109.
13
Any dispute arising between the Company and the Agency under this Schedule, if the parties agree, is to be determined by arbitration under article 57 (arbitration), but otherwise is to be determined by the Secretary of State for Environment, Food and Rural Affairs and the Secretary of State for Transport acting jointly on a reference to them by the Company or the Agency, after notice in writing by one to the other.
SCHEDULE 16 — FOR THE PROTECTION OF NETWORK RAIL
1
For the protection of Network Rail, the following provisions have effect unless otherwise agreed in writing between the Company and Network Rail and in the case of paragraph 13, any other person on whom rights or obligations are conferred by that paragraph.
2
In this Schedule—
- “construction” includes execution, placing, alteration and reconstruction and “construct” and “constructed” have corresponding meanings;
- “the engineer” means an engineer appointed by Network Rail for the purposes of this Order;
- “network licence” means the network licence, as amended from time to time, granted to Network Rail by the Secretary of State in exercise of powers under section 8 of the Railways Act 199342
- “plans” includes sections, designs, drawings, specifications, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of railway property;
- “railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station or depot lease;
- “railway property” means any railway belonging to Network Rail and— any station, land, works, apparatus and equipment belonging to Network Rail or connected with any such railway; and any easement or other property interest held by or used for the benefit of Network Rail for the purposes of such railway or works, apparatus or equipment; and
- “specified work” means so much of any of the authorised works as is situated upon, across, under, over or within 15 metres of, or may in any way adversely affect, railway property.
3
- (1) Where under this Schedule Network Rail is required to give its consent or approval in respect of any matter, that consent or approval must not be unreasonably withheld or delayed but may be subject to reasonable conditions (while recognising that the engineer has sole discretion in matters relating to safety) and is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
- (2) In so far as any specified work or the acquisition or use of railway property is or may be subject to railway operational procedures, Network Rail must—
- (a) co-operate with the Company with a view to avoiding undue delay and securing conformity as between any plans approved by the engineer and requirements emanating from those procedures; and
- (b) use its reasonable endeavours to avoid any conflict arising between the application of those procedures and the proper implementation of the authorised works under this Order.
4
- (1) The Company must not exercise the powers conferred by article 21 (power to survey and investigate land, etc.) or the powers conferred by section 11(3) of the 1965 Act as applied by this Order in respect of any railway property unless the exercise of such powers is with the consent of Network Rail.
- (2) The Company must not in the exercise of the powers conferred by this Order prevent pedestrian or vehicular access to any railway property, unless preventing such access is with the consent of Network Rail.
- (3) The Company must not exercise the powers conferred by sections 271 or 272 of the 1990 Act, as applied by Schedule 13 (provisions relating to statutory undertakers, etc.), in relation to any right of access of Network Rail to railway property, but such right of access may be diverted with the consent of Network Rail.
- (4) The Company must not under the powers conferred by this Order acquire or use or acquire new rights over any railway property except with the consent of Network Rail.
5
- (1) The Company must before commencing construction of any specified work supply to Network Rail proper and sufficient plans of that work for the reasonable approval of the engineer and the specified work must not be commenced except in accordance with such plans as have been approved in writing by the engineer or settled by arbitration.
- (2) The approval of the engineer under sub-paragraph (1) must not be unreasonably withheld or delayed, and if by the end of the period of 28 days beginning with the date on which such plans have been supplied to Network Rail the engineer has not intimated disapproval of those plans and the grounds of disapproval the undertaker may serve upon the engineer written notice requiring the engineer to intimate approval or disapproval within a further period of 28 days beginning with the date upon which the engineer receives written notice from the undertaker. If by expiry of the further period of 28 days the engineer has not intimated approval or disapproval, the engineer is deemed to have approved the plans as submitted.
- (3) If by the end of the period of 56 days beginning with the date on which such plans have been supplied to Network Rail, Network Rail gives notice to the Company that Network Rail desires itself to construct any part of a specified work which in the opinion of the engineer will or may affect the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the Company desires such part of the specified work to be constructed, Network Rail must construct it on behalf of and to the reasonable satisfaction of the Company in accordance with the plans approved or deemed to be approved or settled under this paragraph.
- (4) When signifying approval of the plans the engineer may specify any protective works (whether temporary or permanent) which in the engineer’s opinion should be carried out before the commencement of the construction of a specified work to ensure the safety or stability of railway property or the continuation of safe and efficient operation of the railways of Network Rail or the services of operators using the same (including any relocation of works, apparatus and equipment necessitated by a specified work and the comfort and safety of passengers who may be affected by the specified works), and such protective works as may be reasonably necessary for those purposes are to be constructed by Network Rail but at the expense of the Company, or if Network Rail so desires such protective works must be carried out by the Company at its own expense without unnecessary delay, and the Company must not commence the construction of the specified works until the engineer has notified the Company that the protective works have been completed to the engineer’s reasonable satisfaction.
6
- (1) Any specified work and any protective works to be constructed by virtue of paragraph 5(4) must, when commenced, be constructed without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under paragraph 5—
- (a) under the supervision (where appropriate and if given) and to the reasonable satisfaction of the engineer;
- (b) in such manner as to cause as little damage as is possible to railway property; and
- (c) so far as is reasonably practicable, so as not to interfere with or obstruct the free, uninterrupted and safe use of any railway of Network Rail or the traffic on it and the use by passengers of railway property.
- (2) If any damage to railway property or any such interference or obstruction is caused by the carrying out of, or in consequence of the construction of, a specified work, the Company must, regardless of any approval described in paragraph 6(1), make good such damage and pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may sustain by reason of any such damage, interference or obstruction.
- (3) Nothing in this Schedule imposes—
- (a) any liability on the Company with respect to any damage, costs, expenses or loss attributable to the negligence of Network Rail or its servants, contractors or agents; or
- (b) any liability on Network Rail with respect to any damage, costs, expenses or loss attributable to the negligence of the Company or its servants, contractors or agents.
7
The Company must—
- (a) at all times afford reasonable facilities to the engineer for access to a specified work during its construction; and
- (b) supply the engineer with all such information as the engineer may reasonably require with regard to a specified work or the method of constructing it.
8
Network Rail must at all times afford reasonable facilities to the Company and its agents for access to any works carried out by Network Rail under this Schedule during their construction and must supply the Company with such information as it may reasonably require with regard to such works or the method of constructing them.
9
- (1) If any permanent or temporary alterations or additions to railway property, or any protective works under paragraph 5(4), are reasonably necessary during the construction of a specified work, or during a period of 12 months after the opening for public use of any authorised work that includes a specified work, in consequence of the construction of that specified work, such alterations and additions may be carried out by Network Rail and if Network Rail gives to the Company reasonable notice of its intention to carry out such alterations or additions, the Company must pay to Network Rail all costs reasonably and properly incurred in constructing those alterations or additions including, in respect of any such alterations and additions as are to be permanent, a capitalised sum representing the increase of the costs which may be expected to be reasonably incurred by Network Rail in maintaining, working and, when necessary, renewing any such alterations or additions.
- (2) If during the construction of a specified work by the Company, Network Rail gives notice to the Company that Network Rail desires itself to construct that part of the specified work which in the opinion of the engineer is endangering the stability of railway property or the safe operation of traffic on the railways of Network Rail then, if the Company desires that part of the specified work to be constructed, Network Rail must assume construction of that part of the specified work and the Company must, regardless of any such approval of a specified work under paragraph 5(1), pay to Network Rail all reasonable expenses to which Network Rail may be put and compensation for any loss which it may suffer by reason of the execution by Network Rail of that specified work.
- (3) If the cost of maintaining, working or renewing railway property is reduced in consequence of any such alterations or additions a capitalised sum representing such saving must be set off against-any sum payable by the Company to Network Rail under this paragraph.
10
The Company must repay to Network Rail all fees, costs, charges and expenses reasonably and properly incurred by Network Rail—
- (a) in constructing any part of a specified work on behalf of the Company as provided by paragraph 5(3) or in constructing any protective works under the provisions of paragraph 5(4) including, in respect of any permanent protective works, a capitalised sum representing the cost of maintaining and renewing those works;
- (b) in respect of the approval by the engineer of plans submitted by the Company and the supervision by the engineer of the construction of a specified work and otherwise in connection with the implementation of the provisions of this Schedule;
- (c) in respect of the employment or procurement of the services of any inspectors and other persons whom it is reasonably necessary to appoint for inspecting, watching and lighting railway property and for preventing, so far as may be reasonably practicable, interference, obstruction, danger or accident arising from the construction or failure of a specified work;
- (d) in respect of any additional temporary lighting of railway property in the vicinity of the specified works, being lighting made reasonably necessary by reason or consequence of the construction or failure of a specified work; and
- (e) in respect of any special traffic working resulting from any speed restrictions which may, in the opinion of the engineer, require to be imposed by reason or in consequence of the construction or failure of a specified work or from the substitution or diversion of services which may be reasonably necessary for the same reason.
11
If at any time after the completion of a specified work, not being a work vested in Network Rail, Network Rail gives notice to the Company informing it that the state of maintenance of any part of the specified work appears to be such as adversely affects the operation of railway property, the Company must, on receipt of such notice, take such steps as may be reasonably necessary to put that specified work in such state of maintenance as not adversely to affect railway property.
12
Any additional expenses which Network Rail may reasonably incur in altering, reconstructing, working or maintaining railway property under any powers existing at the making of this Order by reason of the existence of a specified work, provided that 56 days’ previous notice of the commencement of such alteration, reconstruction, working or maintenance has been given to the Company, are to be repaid by the Company to Network Rail.
13
- (1) The Company must pay to Network Rail all costs, charges, damages and expenses not otherwise provided for in this Schedule (but subject to article 56 (no double recovery)) which may be occasioned to or reasonably and properly incurred by Network Rail—
- (a) by reason of the construction, working or maintenance of a specified work or the failure of such a work; or
- (b) by reason of any act or omission of the Company or of any person in its employ or of its contractors or others whilst engaged upon a specified work;
and the Company must indemnify Network Rail from and against all claims and demands arising out of or in connection with a specified work or any such failure, act or omission; and the fact that any act or thing may have been done by Network Rail on behalf of the Company or in accordance with plans approved by the engineer or in accordance with any requirement of the engineer or under the engineer’s supervision will not (if it was done without negligence on the part of Network Rail or of any person in its employ or of its contractors or agents) excuse the Company from any liability under the provisions of this sub-paragraph.
- (2) Network Rail must give the Company reasonable notice of any such claim or demand and must make no settlement or compromise of such a claim or demand without the prior consent of the Company.
- (3) The sums payable by the Company under sub-paragraph (1) may include a sum equivalent to the relevant costs.
- (4) Subject to the terms of any agreement between Network Rail and a train operator regarding the timing or method of payment of the relevant costs in respect of that train operator, Network Rail Infrastructure Limited must promptly pay to each train operator the amount of any sums which Network Rail Infrastructure Limited receives under sub-paragraph (1) which relates to the relevant costs of that train operator.
- (5) The obligation under sub-paragraph (3) to pay Network Rail the relevant costs will, in the event of default, be enforceable directly by any train operator concerned to the extent that the relevant costs would be payable to that operator under sub-paragraph (4).
- (6) In this paragraph—
- “the relevant costs” means the costs, direct losses and expenses (including loss of revenue) reasonably incurred by each train operator as a consequence of any restriction of the use of Network Rail’s railway network as a result of the construction, maintenance or failure of a specified work or any such act or omission as mentioned in sub-paragraph (1); and
- “train operator” means any person who is authorised to act as the operator of a train by a licence under section 8 of the Railways Act 1993.
14
Network Rail must, on receipt of a request from the Company, from time to time provide the Company free of charge with written estimates of the costs, charges, expenses and other liabilities for which the Company is or will become liable under this Schedule (including the amount of the relevant costs mentioned in paragraph 13) and with such information as may reasonably enable the Company to assess the reasonableness of any such estimate or claim made or to be made under this Schedule (including any claim relating to those relevant costs).
15
In the assessment of any sums payable to Network Rail under this Schedule there must not be taken into account any increase in the sums claimed that is attributable to any action taken by or any agreement entered into by Network Rail if that action or agreement was not reasonably necessary and was taken or entered into with a view to obtaining the payment of those sums by the Company under this Schedule or increasing the sums so payable.
16
The Company must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 54 (certification of plans etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in the form of a computer disc with read only memory.
SCHEDULE 17 — FOR THE PROTECTION OF THE CANAL & RIVER TRUST
1
- (1) For the protection of the Canal & River Trust, the following provisions, have effect unless otherwise agreed in writing between the Company and the Trust.
- (2) In this Schedule—
- “the canal” means any canal or waterway owned or managed by the Trust, and includes any works connected with any such canal or waterway for the maintenance of which the Trust is responsible and any lands held or used by the Trust for the purposes of the canal;
- “canal work” means so much of any specified work or any other work of which the Company is in possession under the powers conferred by this Order as is in or over the canal;
- “construction” includes execution, placing, altering, replacing and relaying and includes removal;
- “detriment” means any damage to the canal or any other property of the Trust and, without limitation on the scope of the meaning, includes— the erosion of the bed or banks of the canal, or the impairment of the stability of any works, lands or premises forming part of the canal; the silting of the canal or the deposit of materials in it so as to materially damage the canal; the pollution of the canal; any material alteration of the water level of the canal, or material interference with the supply of water to the canal, or drainage of water from the canal; and any material harm to the ecology of the canal (including any material adverse impact on any site of special scientific interest comprised in the canal);
- “non-canal work” means so much of any specified work or any other work of which the Company is in possession under the powers conferred by this Order as is not in or over the canal;
- “plans” includes sections, drawings, specifications and method statements;
- “specified work” means so much of any permanent or temporary work authorised by this Order as is in, across, under, or within 15 metres of, or may in any way affect, the canal but does not include painting;
- “stoppage season” means a period of 5 calendar months running consecutively from 1 November until 31 March inclusive; and
- “the Trust” means the Canal & River Trust.
2
The Company must not under the powers conferred by article 22 (power to acquire land) acquire compulsorily any land of the Trust without the consent of the Trust.
3
- (1) Subject to sub-paragraph (2), the Company must not under the powers conferred by article 22 (power to acquire land) acquire compulsorily any easement or other right over any land of the Trust other than such easements or other rights over any such land, as are reasonably necessary for, or in connection with, the construction, maintenance or operation of the authorised works.
- (2) The Company must not acquire any such easement or other right that would impede navigation (such that minimum clear headroom is reduced to below 3 metres above water level or the navigable width of the canal is reduced below that existing on the date on which this Order is made) at any point along the length of the canal.
4
Before beginning to construct any specified work, the Company must submit to the Trust plans of the work and such further particulars available to it as the Trust may within 14 days of the submission of the plans reasonably require.
5
Any specified work must not be constructed except in accordance with such plans as may be approved in writing by the Trust or determined under article 57 (arbitration).
6
Any approval of the Trust required under paragraph 5 must not be unreasonably withheld and—
- (a) is deemed to have been given if it is neither given nor refused (with an indication of the grounds for refusal) within 28 days of the submission of the plans for approval or where further particulars are submitted under paragraph 4, within 28 days of the submission of those particulars; and
- (b) may be given subject to such reasonable requirements as the Trust may make for the purpose of ensuring the safety or stability of the canal, including requirements as to the construction of protective works.
7
Any specified work, and any protective works required by the Trust under paragraph 6(b), must be constructed without unnecessary delay to the reasonable satisfaction of the Trust, and in such manner as to cause as little damage to the canal as may be reasonably practicable and as little interference as may be reasonably practicable with the passage of vessels using the canal, and an officer of the Trust is entitled at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect the construction of such work or works.
8
The Company must give to the Trust not less than 56 days’ notice in writing of its intention to commence construction of any specified work or any protective works and also, except in emergency (when the Company must give such notice as may be reasonably practicable), of its intention to carry out any works for the repair or maintenance of any specified work in so far as such works of repair or maintenance affect or interfere with the canal.
9
The Company must not—
- (a) temporarily close the canal; or
- (b) temporarily obstruct navigation along the canal;
other than during the stoppage season and must give to the Trust notice in writing of its intention to close temporarily or obstruct temporarily the canal by 1 May immediately prior to the relevant stoppage season.
10
The Company must not exercise the maintenance powers conferred by articles 5 (power to construct and maintain works) and 30 (temporary use of land for maintenance of works) in relation to the canal unless such exercise is with the consent of the Trust.
11
The Company must bear the reasonable costs of the carrying out, by a qualified surveyor or engineer (“the surveyor”) to be appointed by the Trust and Company, of surveys of so much of the canal as will or may be affected by the specified works—
- (a) before commencement of the initial construction of any part of the specified works; and
- (b) following completion of the specified works,
and if the Trust and the Company do not agree on the appointment of the surveyor under this paragraph an arbitrator is to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.
12
For the purposes of the surveys the Company—
- (a) on being given reasonable notice (save in the case of emergency, when immediate access must be afforded) must afford reasonable access to the site of the specified works and to any land and existing works of the Company which may provide support for the canal as will or may be affected by the specified works; and
- (b) as soon as reasonably practicable must supply the surveyor with all such information as the surveyor may reasonably require with regard to such land and existing works of the Company and to the specified works or the method of construction of the specified works.
13
The surveyor must provide copies of a report of the surveys to both the Trust and the Company without unnecessary delay.
14
Where, in the reasonable opinion of the Trust, the surveys show that the specified works are likely to cause detriment to the canal then, at the request of the Trust and at its own expense, the Company must take steps to remedy such detriment to the reasonable satisfaction of the Trust.
15
The Company must not deposit any polluting material on, in or over the canal and must not without the consent of the Trust—
- (a) deposit any other materials on, in or over the canal (other than materials comprised in a specified work); or
- (b) regardless of anything in article 19 (discharge of water), discharge any water directly or indirectly into the canal.
16
Any consent of the Trust required under paragraph 15 must not be unreasonably withheld and—
- (a) is deemed to have been given if it is neither given nor refused within 28 days of the submission of the request for it; and
- (b) may be given subject to such reasonable requirements as the Trust may make—
- (i) in the case of a deposit, so as to ensure that the use of the canal is not obstructed or rendered less safe, and
- (ii) in the case of a discharge, concerning the reimbursement by the Company of expenses incurred by the Trust in disposing of the water so discharged, being expenses which the Trust would not have incurred but for the discharge.
17
In its application to the discharge of water into the canal, article 19(6) (discharge of water) has effect subject to the terms of any requirements attached to the consent under paragraph 16 and, where such discharge includes a deposit to which consent has been given under paragraph 15, to any requirements attached to that consent.
18
If any canal work is abandoned, the Trust may by notice in writing require the Company to take such reasonable steps as may be specified in the notice to remove the work and (to such extent as the Trust reasonably requires) to restore the site to its former condition.
19
If any canal work is in such condition that it is, or is likely to become, a danger to or to interfere with navigation, the Trust may by notice in writing require the Company to take such reasonable steps as may be specified in the notice—
- (a) to repair and restore the work or part of it; or
- (b) if the Company so elects, to remove the work and (to such extent as the Trust reasonably requires) to restore the site to its former condition.
20
If—
- (a) a work which consists of a canal work and a non-canal work is abandoned or falls into decay; and
- (b) the non-canal work is in such a condition as to interfere with the right of navigation in the relevant canal or as to interfere with the rights of access or use of land adjacent to the relevant canal;
the Trust may include the non-canal work, or any part of it, in any notice under paragraph 19.
21
If after such reasonable period as may be specified in a notice under paragraph 19 the Company has failed to begin taking steps to comply with the requirements of the notice or after beginning has failed to make reasonably expeditious progress towards their implementation, the Trust may carry out the works specified in the notice and any expenditure reasonably incurred by it in so doing is recoverable from the Company.
22
The Company must indemnify the Trust from all claims, demands, proceedings or damages, which may be made or given against, or recovered from the Trust by reason of any damage to the canal which is caused by the construction of any specified work or protective work or any act or omission of the Company, its contractors, agents or employees whilst engaged upon the work and from any costs reasonably incurred in making good such damage.
23
The Trust must give to the Company reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand is to be made without the consent of the Company which, if it notifies the Trust that it desires to do so, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
24
Nothing in paragraph 22 imposes any liability on the Company with respect to any damage to the extent that it is attributable to the act, neglect or default of the Trust, its officers, servants, contractors or agents but the fact that any work or thing has been executed or done in accordance with a plan approved or deemed to be approved by the Trust, or to its satisfaction, or in accordance with a determination in accordance with the article 57 (arbitration), does not (in the absence of negligence on the part of the Trust, its officers, servants, contractors or agents) relieve the Company from any liability under the provisions of this Schedule.
Signed
Signed by authority of the Secretary of State
Martin Woods — Head of the Transport and Works Act Orders Unit — Department for Transport — 23rd October 2012
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises The Chiltern Railway Company Limited to construct a new railway (including the reconstruction of existing railway) and associated works between Bicester and Oxford together with the construction or reconstruction of stations at Bicester Town, Islip, Water Eaton and Oxford in order to facilitate the operation of direct railway services between London Marylebone, High Wycombe, Bicester Town and Oxford. The Order authorises the acquisition and use of land for the purposes of the works and confers powers in connection with the construction and operation of the railway.
Copies of the deposited plans and deposited sections are available for inspection at the registered office of The Chiltern Railway Company Limited, Great Central House, Marylebone Station, Melcombe Place, London NW1 6JJ.
Footnotes
1992 c. 42. Part 1 of this Act is amended by S.I. 1995/1541, 1998/2226, 2000/3199 and 2006/958.
1993 c. 43. As amended by the Transport Act 2000 (c. 38) and the Railways Act 2005 (c. 14).
1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c. 45), and was further amended by section 76 of the Utilities Act 2000 (c. 27).
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.