The Energy Savings Opportunity Scheme Regulations 2014

Type Statutory-Instrument
Publication 2014-06-24
Last updated 2025-02-24
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
Information in relation to responsible undertaking Column 1 - to be included in ESOS report under regulation 27A(4) Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
name yes yes yes
email address and telephone number no yes no
registered office (where applicable) no yes yes
principal place of activity, where the responsible undertaking has no registered office no yes yes
company registration number (where applicable) no yes yes
trading or other name by which the responsible undertaking is commonly known (where applicable) no yes yes
name, postal address, email address and telephone number of at least two individuals who will act as contacts for the responsible undertaking, one of whom is the responsible officer no yes no
where the responsible undertaking has a parent undertaking to which these Regulations do not extend (the “global parent”), the name of the global parent, and the trading or other name of the group of undertakings of which the global parent is the parent no yes yes
standard industrial classification code or other equivalent industrial classification of the responsible undertaking and (where different) of other relevant undertakings where complying as one participant no yes yes
reasons for classification of the responsible undertaking as a large undertaking, or small or medium undertaking as determined in accordance with Schedule 1 no yes yes
Information in relation to the participant Column 1 - to be included in ESOS report under regulation 27A(4) Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
the number of relevant undertakings comprising the participant yes yes yes
the names and companies house registration numbers (where applicable) of the relevant undertakings comprising the participant no yes >yes
where paragraph 1 of Schedule 2 applies, the fact that an agreement under paragraph 2 of Schedule 2 has been made, and the names of the relevant highest parents no yes yes
the name of any relevant undertaking that has ceased to be part of the participant since the qualification date by virtue of paragraph 3 or 7 of Schedule 2 no yes yes
corporate group structure chart or other information setting out the relationship between the relevant undertakings complying with the Scheme as one participant, including the responsible undertaking, any franchisees, any relevant undertaking that has ceased to be part of the participant since the qualification date by virtue of paragraph 3 or 7 of Schedule 2 and any parent undertaking of the responsible undertaking to which these Regulations do not extend yes yes yes
Information in relation to the responsible officer Column 1 - to be included in ESOS report under regulation 27A(4) Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
name yes yes no
full title or position in the participant or relevant undertaking yes yes yes
contact details no yes no
date on which the responsible officer considered the recommendations of the audit in accordance with regulation 31(b) no yes yes
Information in relation to lead assessor Column 1 - to be included in ESOS report under regulation 27A(4) Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
name yes yes no
the approved register yes yes yes
whether the lead assessor is employed by the participant or by an undertaking which is a group undertaking in respect of the participant no yes yes
Information in relation to a specified person Column 1 - to be included in ESOS report under regulation 27A(4) Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
name of each natural person who has carried out a significant proportion of the site visits required by regulation 26(3A), gathered a significant amount of the data used for carrying out the energy audit, or drafted significant parts of the ESOS report (a “specified person”) yes, where recorded yes, where recorded no
whether the specified person is employed by the participant, or an undertaking which is a group undertaking in respect of the participant no yes, where recorded no
Information in relation to the ESOS assessment Column 1 - intentionally left blank Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
whether, and if so to what extent, the participant has relied on Part 6 in complying with the Scheme - yes yes
details of estimates produced in accordance with Part 4 and required to be notified under regulation 21A - yes yes
details of site visits required to be recorded under regulation 26(9)(e) and (f). - yes yes
where applicable, that the energy audit does not include an analysis based on energy consumption profiles (as defined in accordance with regulation 27(3)) - yes no
where applicable, information relating to non-disclosure of information to a group undertaking as specified in regulation 27C(3)(b) - yes no
where applicable, details of the extent to which and the reasons why 12 months’ verifiable data was not used as required to be recorded under regulation 26(9)(g) - yes no
Information related to the participant’s energy consumption Column 1 - intentionally left blank Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
the participant’s total energy consumption in kWh calculated in accordance with Chapter 2 of Part 4 - yes yes
the amount of the participant’s total energy consumption that is attributable to each organisational purpose as calculated in accordance with regulation 25B(1)(b) - yes no
where applicable, the participant’s significant energy consumption in kWh - yes yes
where applicable, the amount of the participant’s significant energy consumption in kWh that is attributable to each organisational purpose as calculated in accordance with regulation 25B(1)(a) - yes no
where applicable, the percentage of the participant’s total energy consumption that is accounted for by the participant’s areas of significant energy consumption - yes yes
the energy intensity ratios calculated in accordance with regulation 25C - yes yes
Information related to energy saving opportunities Column 1 - intentionally left blank Column 2 - to be notified to the scheme administrator under regulation 29 Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
the sum of all the estimates made in accordance with regulation 27(1)(d)(vi) (annual reductions in energy spend and energy consumption). - yes yes
for each organisational purpose, the sum of the estimates made in accordance with regulation 27(1)(d)(vi) in respect of any energy saving opportunities that are identified in accordance with regulation 27(1)(d)(i) as most closely relating to that organisational purpose - yes no
for each energy saving category, the sum of the estimates made in accordance with regulation 27(1)(d)(vi) in respect of any energy saving opportunities that are identified in accordance with regulation 27(1)(d)(ii) as most closely relating to that energy saving category - yes no
the estimate of energy savings achieved, as produced in accordance with 27B(1) - yes yes
the estimates of the proportion of the energy savings that relate to each organisational purpose, in accordance with 27B(2)(a) - yes no
Information Column 1 - intentionally left blank Column 2 - to be notified to the scheme administrator under regulation 29(ab) Column 3 - to be published by the scheme administrator under regulation 10
--- --- --- ---
where compliance is by virtue of regulation 33 (ISO 50001 certification), the details specified in regulation 27A(7)(a) and (c) - yes yes
where compliance is by virtue of regulation 34 (Display Energy Certificates and Green Deal Assessment), the details specified in regulation 27A(7)(b) and (c) - yes yes
the estimate of energy savings achieved, as produced in accordance with regulation 27B(1) - yes yes
the estimates of the proportion of the energy savings that relate to each organisational purpose, as produced in accordance with 27B(2)(a) - yes no
for each organisational purpose the sum of the estimates made in accordance with regulation 27A(7)(e)(ii) in respect of any energy saving measures that are identified in accordance with regulation 27A(7)(e)(i) as most closely relating to that organisational purpose - yes no
the sum of the estimates made in accordance with regulation 27A(7)(e)(ii) in respect of all the energy saving measures identified in accordance with regulation 27A(7)(d) - yes yes
for each energy saving category, the sum of the estimates made in accordance with regulation 27A(7)(e)(ii) in respect of any energy saving measures that are identified in accordance with regulation 27A(7)(e)(i) as most closely relating to that energy saving category - yes no
4
  • (1) Part 6 applies with the following modifications—
  • (a) regulation 34A applies with the modification that any reference to “participant” should be read as a reference to relevant trust asset;
  • (b) regulation 34B applies with the modification that any reference to “participant” should be read as a reference to relevant trust asset.
5
  • (1) Schedule 3 applies with the following modifications—
  • (a) in Table F for “the participant” there is substituted “the relevant trust asset”;
  • (b) Table G applies with the modification that any reference to the participant is to be read as a reference to the relevant trust asset.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.