The Felixstowe Branch Line (Land Acquisition) Order 2014
Made: 8th July 2014
Coming into force: 29th July 2014
The Secretary of State, in exercise of the powers conferred by sections 1 and 5 of, and paragraphs 3 to 5, 7, 8, 11, and 16 of Schedule1 to, the 1992 Act, makes the following Order—
PART 1 — PRELIMINARY
Citation and commencement
1
This Order may be cited as the Felixstowe Branch Line (Land Acquisition) Order 2014 and comes into force on 29th July 2014.
Interpretation
2
- (1) In this Order—
- “the 1961 Act” means the Land Compensation Act 1961[^f00003];
- “the 1965 Act” means the Compulsory Purchase Act 1965[^f00004];
- “the 2008 Order” means the Felixstowe Branch Line and Ipswich Yard Improvement Order 2008[^f00005];
- “authorised works” means Works Nos. 2 to 6 (or any part of them) authorised by the 2008 Order or any other works adjacent to or in the Parish of Westerfield in the Borough of Ipswich within the Order limits, or any other works in Suffolk Coastal District within the Order limits authorised by the 2008 Order;
- “the book of reference” means the book of reference certified by the Secretary of State as the book of reference for the purposes of this Order;
- “the land plans” means the plans certified by the Secretary of State as the land plans for the purpose of this Order;
- “limits of deviation” means the limits of deviation for the authorised works shown on the land plans;
- “the limits of land to be acquired or used” means the limits of land to be acquired or used shown on the land plans;
- “the Order limits” means any limits of deviation and any limits of land to be acquired or used which are shown on the land plans;
- “tribunal” means the Lands Chamber of the Upper Tribunal; and
- “the undertaker” means The Felixstowe Dock and Railway Company being a company limited by shares and incorporated by The Felixstowe Railway and Pier Act 1875[^f00006].
- (2) References in this Order to rights over land include references to rights to do, or to place and maintain, anything in, on or under land or in the air-space over its surface.
- (3) References in this Order to numbered works are references to the works as numbered in Schedule 1 (scheduled works) to the 2008 Order.
- (4) All measurements stated in any description of lands in the book of reference are approximate.
PART 2 — ACQUISITION AND POSSESSION OF LAND
Powers of acquisition
Power to acquire land
3
- (1) The undertaker may acquire compulsorily so much of the land shown on the land plans within the Order limits and described in the book of reference as may be required for the purposes of the authorised works and may use any land so acquired for those purposes or for any other purposes that are ancillary to its railway undertaking.
- (2) This article is subject to article 8 (temporary use of land for construction of works).
Application of Part 1 of the 1965 Act
4
- (1) Part 1 of the 1965 Act, in so far as not modified by or inconsistent with the provisions of this Order, applies to the acquisition of land under this Order—
- (a) as it applies to a compulsory purchase to which the Acquisition of Land Act 1981[^f00007] applies; and
- (b) as if this Order were a compulsory purchase order under that Act.
- (2) Part 1 of the 1965 Act, as applied by paragraph (1), has effect as if section 4 (which provides a time limit for compulsory purchase of land) and paragraph 3(3) of Schedule 3 (which makes provision as to the giving of bonds) were omitted.
Application of the Compulsory Purchase (Vesting Declarations) Act 1981
5
- (1) The Compulsory Purchase (Vesting Declarations) Act 1981[^f00008] applies as if this Order were a compulsory purchase order.
- (2) The Compulsory Purchase (Vesting Declarations) Act 1981, as applied by paragraph (1), has effect with the following modifications.
- (3) In section 3 (preliminary notices) for subsection (1) substitute—
(1) Before making a declaration under section 4 with respect to any land which is subject to a compulsory purchase order the acquiring authority must include the particulars specified in subsection (3) in a notice which is— (a) given to every person with a relevant interest in the land with respect to which the declaration is to be made (other than a mortgagee who is not in possession); and (b) published in a local newspaper circulating in the area in which the land is situated.
- (4) In that section, in subsection (2), for “(l)(b)” substitute “(1)”, and after “given” insert “and published”.
- (5) In that section, for subsections (5) and (6) substitute—
(5) For the purposes of this section, a person has a relevant interest in land if— (a) that person is for the time being entitled to dispose of the fee simple of the land, whether in possession or in reversion; or (b) that person holds, or is entitled to the rents and profits of, the land under a lease or agreement, the unexpired term of which exceeds one month.
- (6) In section 5 (earliest date for execution of declaration)—
- (a) in subsection (1), after “publication” insert “in a local newspaper circulating in the area in which the land is situated”; and
- (b) omit subsection (2).
- (7) In section 7 (constructive notice to treat) in subsection (l)(a), omit “(as modified by section 4 of the Acquisition of Land Act 1981)”.
- (8) References to the 1965 Act are to be construed as references to that Act as applied to the acquisition of land under article 3 (power to acquire land).
Power to acquire new rights
6
- (1) The undertaker may acquire compulsorily such easements or other rights over any land referred to in paragraph (1) of article 3 (power to acquire land) as may be required for any purpose for which that land may be acquired under that provision, by creating them as well as by acquiring easements or other rights already in existence.
- (2) Subject to section 8 of the 1965 Act (as substituted by paragraph 5 of Schedule 6 (modification of compensation and compulsory purchase enactments for creation of new rights) to the 2008 Order, as applied by article 15 (application of provisions of the 2008 Order)) where the undertaker acquires a right over land under paragraph (1) the undertaker is not required to acquire a greater interest in that land.
- (3) Schedule 6 to the 2008 Order, as applied by article 15, has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right.
Rights under or over streets
7
- (1) The undertaker may enter upon and appropriate so much of the subsoil of, or air-space over, any street within the Order limits as may be required for the purposes of the authorised works and may use the subsoil or air-space for those purposes or any other purpose ancillary to its railway undertaking.
- (2) Subject to paragraph (4), the power under paragraph (1) may be exercised in relation to a street without the undertaker being required to acquire any part of the street or any easement or right in the street.
- (3) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss by the exercise of that power, is entitled to compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.
- (4) Paragraph (2) does not apply in relation to—
- (a) any subway or underground building; or
- (b) any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.
- (5) Compensation is not payable under paragraph (3) to any person who is an undertaker to whom section 85 (sharing of cost of necessary measures) of the New Roads and Street Works Act 1991[^f00009] applies in respect of measures of which the allowable costs are to be borne in accordance with that section.
Temporary possession of land
Temporary use of land for construction of works
8
- (1) The undertaker may, in connection with the carrying out of the authorised works—
- (a) enter upon and take temporary possession of the land specified in columns (1) and (2) of the Schedule (land of which temporary possession may be taken) for the purpose specified in relation to that land in column (3) of the Schedule relating to the authorised works specified in column (4) of the Schedule;
- (b) remove any buildings and vegetation from that land;
- (c) construct temporary works (including the provision of means of access) and buildings on that land; and
- (d) use the land for the purposes of a working site with access to the working site in connection with the authorised works.
- (2) Not less than 14 days before entering upon and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (3) The undertaker may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the work specified in relation to that land in column (4) of the Schedule.
- (4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to replace a building removed under this article.
- (5) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.
- (6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.
- (7) Without affecting article 51 (no double recovery) of the 2008 Order as applied by article 15 (application of provisions of the 2008 Order), nothing in this article affects any liability to pay compensation under section 10(2) (further provision as to compensation for injurious affection) of the 1965 Act[^f00010] or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (5).
- (8) The powers of compulsory acquisition of land conferred by this Order do not apply in relation to the land referred to in paragraph (1) except that the undertaker is not precluded from acquiring new rights over any part of that land under article 6 (power to acquire new rights).
- (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
- (10) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act[^f00011] applies to the temporary use of land under this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 4(1) (application of Part 1 of the 1965 Act).
Temporary use of land for maintenance of works
9
- (1) Subject to paragraph (2), at any time during the maintenance period relating to any of the authorised works, the undertaker may—
- (a) enter upon and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the work or any ancillary works connected with it; and
- (b) construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
- (2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
- (a) any house or garden belonging to a house; or
- (b) any building (other than a house) if it is for the time being occupied.
- (3) Not less than 28 days before entering upon and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land.
- (4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of works for which possession of the land was taken.
- (5) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
- (6) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.
- (7) Any dispute as to a person’s entitlement to compensation under paragraph (6), or as to the amount of the compensation, is to be determined under Part 1 of the 1961 Act.
- (8) Without affecting article 51 (no double recovery) of the 2008 Order as applied by article 15 (application of provisions of the 2008 Order), nothing in this article affects any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (6).
- (9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
- (10) Section 13 of the 1965 Act applies to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 4(1) (application of Part 1 of the 1965 Act).
- (11) In this article “the maintenance period”, in relation to an authorised work, means the period of 5 years beginning with the date on which the work is opened for use.
Compensation
Disregard of certain interests and improvements
10
- (1) In assessing the compensation payable to any person on the acquisition from that person of any land under this Order, the tribunal must not take into account—
- (a) any interest in land; or
- (b) any enhancement of the value of any interest in land by reason of any building erected, works executed or improvement or alteration made on relevant land,
if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of the works or the making of the improvement or alteration was not reasonably necessary and was undertaken with a view to obtaining compensation or increased compensation.
- (2) In paragraph (1) “relevant land” means the land acquired from the person concerned or any other land with which that person is, or was at the time when the building was erected, the works executed or the improvement or alteration made, directly or indirectly concerned.
Set-off for enhancement in value of retained land
11
- (1) In assessing the compensation payable to any person in respect of the acquisition from that person under this Order of any land (including the subsoil) the tribunal must set off against the value of the land so acquired any increase in value of any contiguous or adjacent land belonging to that person in the same capacity which will accrue to that person by reason of the construction of the authorised works.
- (2) In assessing the compensation payable to any person in respect of the acquisition from that person of any new rights over land (including the subsoil) under article 6 (power to acquire new rights), the tribunal must set off against the value of the rights so acquired—
- (a) any increase in the value of the land over which the new rights are required; and
- (b) any increase in value of any contiguous or adjacent land belonging to that person in the same capacity,
which will accrue to that person by reason of the construction of the authorised works.
- (3) The 1961 Act has effect, subject to paragraphs (1) and (2), as if this Order were a local enactment for the purposes of that Act.
Supplementary
Acquisition of part of certain properties
12
- (1) This article applies instead of section 8(1) (other provisions as to divided land) of the 1965 Act[^f00012] (as applied by article 4 (application of Part 1 of the 1965 Act)) in any case where—
- (a) a notice to treat is served on a person (“the owner”) under the 1965 Act (as applied) in respect of land forming only part of a house, building or manufactory or of land consisting of a house with a park or garden (“the land subject to the notice to treat”); and
- (b) a copy of this article is served on the owner with the notice to treat.
- (2) In such a case, the owner may, within the period of 21 days beginning with the day on which the notice was served, serve on the undertaker a counter-notice objecting to the sale of the land subject to the notice to treat which states that the owner is willing and able to sell the whole (“the land subject to the counter-notice”).
- (3) If no such counter-notice is served within that period, the owner is required to sell the land subject to the notice to treat.
- (4) If such a counter-notice is served within that period, the question whether the owner is required to sell only the land subject to the notice to treat is, unless the undertaker agrees to take the land subject to the counter-notice, to be referred to the tribunal.
- (5) If on such a reference the tribunal determine that the land subject to the notice to treat can be taken—
- (a) without material detriment to the remainder of the land subject to the counter-notice; or
- (b) in the case of part of land consisting of a house with a park or garden, without material detriment to the remainder of the land subject to the counter-notice and without seriously affecting the amenity and convenience of the house,
the owner is required to sell the land subject to the notice to treat.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.