The Hornsea One Offshore Wind Farm Order 2014
- (5) The following parameters apply in respect of the foundation methods used to fix offshore HVAC collector substations to the seabed—
- (a) where monopile foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,419 m²;
- (ii) the diameter of each foundation must not exceed 8.5 metres;
- (b) where jacket foundations (driven/drilled piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,924 m²;
- (ii) the number of piles per jacket must not exceed eight;
- (iii) the diameter of each pile must not exceed 3.5 metres;
- (c) where jacket foundations (suction piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 12,723 m²;
- (ii) the number of piles per jacket must not exceed eight;
- (iii) the diameter of each pile must not exceed 15 metres;
- (d) where gravity base foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 m²;
- (ii) the seabed levelling diameter must not exceed 70 metres;
- (iii) the cone diameter must not exceed 50 metres at its base.
- (6) The following parameters apply in respect of the foundation methods used to fix offshore HVDC converter stations to the seabed—
- (a) where jacket foundations (driven/drilled piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 4,330 m²;
- (ii) the number of piles per jacket must not exceed 18;
- (iii) the diameter of each pile must not exceed 3.5 metres;
- (b) where jacket foundations (suction piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 12,723 m²;
- (ii) the number of piles per jacket must not exceed eight;
- (iii) the diameter of each pile must not exceed 15 metres;
- (c) where gravity base foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 19,500 m²;
- (ii) the number of pontoons for each individual structure must not exceed two;
- (iii) the pontoons must not exceed 110 metres in length or 35 metres in width.
- (7) The following parameters apply in respect of the foundation methods used to fix the offshore reactive compensation substation to the seabed—
- (a) where monopile foundations are used—
- (i) the area occupied by the foundations and the scour protection must not exceed 1,419 m²;
- (ii) the diameter of each foundation must not exceed 8.5 metres;
- (b) where jacket foundations (driven/drilled piles) are used—
- (i) the area occupied by the foundations and the scour protection must not exceed 1,414 m²;
- (ii) the number of piles per jacket must not exceed eight;
- (iii) the diameter of each pile must not exceed three metres;
- (c) where jacket foundations (suction piles) are used—
- (i) the area occupied by the foundations and the scour protection must not exceed 6,362 m²;
- (ii) the number of piles per jacket must not exceed eight;
- (iii) the diameter of each pile must not exceed 15 metres;
- (d) where gravity base foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 m²;
- (ii) the seabed levelling diameter must not exceed 70 metres;
- (iii) the cone diameter must not exceed 50 metres at its base.
- (8) The combined total volume of scour protection for the wind turbine generators and the offshore accommodation platforms forming part of the authorised development must not exceed 3,226,187 m³.
Archaeology above mean low water level
5
- (1) No part of the authorised development above MLWS is to commence within the area of a local planning authority until a written scheme for the investigation of areas of archaeological interest above MLWS has been submitted to and approved by the local planning authority.
- (2) The scheme must identify areas where field work and/or a watching brief are required, and the measures to be taken to protect, record or preserve any significant archaeological remains that may be found.
- (3) Any archaeological works or watching brief carried out under the approved scheme must be by a suitably qualified person or body approved by the local planning authority.
- (4) Any archaeological works or watching brief must be carried out in accordance with the approved scheme.
Ecological management plan above mean low water level
6
- (1) No part of the authorised development above MLWS is to commence within the area of a local planning authority until a written ecological management plan relating to the land above MLWS based on the draft ecological management plan contained in volume 6 of the Environmental Statement and reflecting the survey results and ecological mitigation measures included in the environmental statement has been submitted to and approved by the local planning authority in consultation with Natural England, the Environment Agency, and to the extent that the plan relates to the intertidal area, the MMO.
- (2) The ecological management plan must include an implementation timetable and must be carried out as approved.
- (3) The ecological management plan must be submitted for approval at least four months prior to the intended start of construction unless otherwise agreed in writing by the local planning authority in consultation with Natural England.
Code of Construction Practice
7
- (1) No part of the authorised development above MLWS is to commence within the area of a local planning authority until a code of construction practice relating to the works authorised above MLWS based on the draft code of construction practice contained in volume 4 of the Environmental Statement has been submitted to and approved by the local planning authority such approval to be provided in the case of any construction traffic management plan submitted pursuant to sub-paragraph (e), and any travel plan submitted pursuant to sub-paragraph (l) in consultation with the relevant highway authority and the Highways Agency. The code of construction practice must include—
- (a) an external lighting scheme for the construction phase;
- (b) construction noise and vibration monitoring and management measures;
- (c) air quality and dust monitoring and management measures during construction;
- (d) a site waste management plan detailing sustainable site waste management measures;
- (e) a construction traffic management plan;
- (f) measures to prevent and control spillage of oil, chemicals and other potentially harmful liquids;
- (g) details of the storage of materials during construction;
- (h) measures for the protection of surface and ground water during construction;
- (i) a communication plan;
- (j) a Health and Safety Plan including details of how health and safety risks are identified and managed during construction;
- (k) details of screening and fencing to be installed during construction;
- (l) a travel plan for the construction workforce to include details of—
- (i) expected means of travel to and from the construction sites;
- (ii) numbers of construction staff, working hours and modal split;
- (iii) details of the number of car parking spaces to be provided on sites and if appropriate a car park management plan;
- (iv) specification of measures to encourage sustainable travel to and from the construction site for construction staff;
- (v) responsibility and timescales for implementing proposed measures;
- (vi) targets for vehicle trips and modal splits;
- (vii) formal monitoring regime for those targets; and
- (viii) details of mess/canteen facilities for staff.
- (2) All construction works must be undertaken in accordance with the approved code.
Landscaping
8
- (1) No part of the authorised development above MLWS is to commence within the area of a local planning authority until a written landscape scheme has been submitted to and approved by the local planning authority.
- (2) The written landscape scheme must include the provisions of the draft landscape scheme and management plan contained in Annex 6.4.16: Landscape Scheme and Management Plan of the Environmental Statement, subject to any variation approved by the local planning authority, and, in addition details of—
- (a) cultivation, importing of materials and other operations to ensure plant establishment;
- (b) proposed finished ground levels;
- (c) hard surfacing materials;
- (d) minor structures, refuse or other storage units, signs and lighting.
Implementation and maintenance of landscaping
9
- (1) The landscape works must be carried out in accordance with the relevant scheme approved under requirement 8.
- (2) Any tree or shrub planted as part of an approved landscape scheme that within a period of five years after planting, is removed, dies or becomes, in the opinion of the local planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted, unless alternative timing or a different specimen is otherwise approved by the local planning authority.
Decommissioning
10
No part of the authorised development below MHWS is to commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval in relation to that part.
Highway accesses
11
- (1) No permanent or temporary means of access to a highway to be used by vehicular traffic or any alteration to an existing means of access to a highway used by vehicular traffic is to commence until written details of the design and layout of such works have been submitted to and approved by the local planning authority in consultation with the relevant highway authority.
- (2) The highway accesses must be constructed in accordance with the approved details.
Contaminated land and groundwater
12
- (1) No part of the authorised development within the area of a local planning authority is to commence until a written scheme to deal with the contamination of any land, including groundwater within the Order limits which is likely to cause significant harm to persons or pollution of controlled waters or the environment has been submitted to, and approved by, the local planning authority in consultation with the Environment Agency and, to the extent that the plan relates to the intertidal area, the MMO.
- (2) The scheme must include an investigation and assessment report, prepared by a specialist consultant approved by the local planning authority, to identify the extent of any contamination and the remedial measures to be taken for that stage to render the land fit for its intended purpose, together with a management plan which sets out long-term measures with respect to any contaminants remaining on the site.
- (3) No remedial work constituting a material operation in respect of contamination of any land, including groundwater within the Order limits is to be carried out until the scheme has been approved.
- (4) In carrying out the works for the authorised development, the undertaker must not conduct horizontal directional drilling operations unless the scheme includes a hydrogeological risk assessment demonstrating that such operations are unlikely to cause an unacceptable risk to groundwater quality.
- (5) Remediation must be carried out in accordance with the approved scheme.
Surface water drainage
13
- (1) No part of the electrical transmission station is to commence until a detailed surface water drainage scheme based on sustainable drainage principles and an assessment of the hydrological and hydrogeological context of the electrical transmission station have been submitted to and approved in writing by the local planning authority, in consultation with the Environment Agency and the drainage board within the meaning of section 25 of the Land Drainage Act 1991.
- (2) Construction of the electrical transmission station must be carried out in accordance with the scheme.
Colour and detailed design approval – electrical transmission station
14
- (1) Unless otherwise agreed by the local planning authority, the electrical transmission station comprised in Work No. 10 must be coloured using one or more of the following colours—
- Bluebell (RAL Code 270 50 30)
- Lilac (RAL Code 270 60 25)
- Chalk Blue (RAL Code 270 70 20)
- Baltic Blue (RAL Code 270 80 15)
- White Lilac (RAL Code 270 85 10)
- Blue White (RAL Code 270 90 05)
- (2) Notwithstanding sub-paragraph (1), construction of Work No. 10 must not commence until details of the layout, scale and external appearance of that work have been submitted to and approved by the relevant planning authority.
- (3) The construction of Work No. 10 must be carried out in accordance with the approved details.
Prohibited access
15
- (1) The undertaker must not use the access road along the crest of the sea defences within the plots numbered 37 - 40 on the land plans during the construction of Work Nos. 6 to 8.
- (2) Except in an emergency, the access road along the sea defences within the plots numbered 37 – 40 on the land plans may not be used by the undertaker following the construction of Work Nos. 6 to 8 until a scheme for the protection of the sea defences from use of the access road by the undertaker during the operation and maintenance of the authorised project has been submitted to and approved in writing by the Environment Agency.
- (3) If the Environment Agency fails to notify the undertaker of its decision on whether to give approval within 28 days of receiving the scheme for approval the Environment Agency is deemed to have given approval.
- (4) The use of the access road must be in accordance with the approved scheme.
Port traffic management plan
16
- (1) No part of the authorised development below MLWS (excluding ducting and related works which are an integral part of works landward of MLWS) is to commence until a traffic management plan for the onshore port-related traffic to and from the selected base port or ports for construction, operation or both of the relevant part of the authorised development, and relating to the relevant part of the authorised development, has been submitted to and approved in writing by the relevant planning authority in consultation with the relevant highway authority, or the relevant planning authority has confirmed in writing, after consultation with the relevant highway authority, that no traffic management plan is required.
- (2) All traffic management plans must be implemented as approved at all times specified within the relevant traffic management plan during the construction, operation or both of the authorised development.
- (3) For the purposes of this requirement—
- “relevant highway authority” means the highway authority or authorities in whose area the relevant port is located;
- “relevant planning authority” means the local planning authority or authorities in whose area the relevant port is located;
- “selected base port” or “ports” means a port or ports situated in England or Wales and used by management personnel for construction of the authorised project or for the ongoing operational management of the authorised project.
Co-operation
17
- (1) Prior to the submission of the pre-construction plans and documentation required to be submitted to the MMO for approval under Condition 13 of each of the deemed marine licences set out in Schedules 8 to 11 the undertaker who is the licence-holder under the relevant licence must provide a copy of the plans and documentation to the other undertakers.
- (2) The other undertakers must provide any comments on the plans and documentation to the licence-holder within 14 days of receipt of the plans and documentation.
- (3) The licence-holder shall participate in liaison meetings with other undertakers as requested from time to time by the MMO in writing in advance, which meetings shall be chaired by the MMO and shall consider such matters as are determined by the MMO relating to the efficient operation of a deemed marine licence where it has an impact on the efficient operation of any other deemed marine licence issued under this Order (including as varied or transferred).
Control of noise during operational phase
18
The combined noise rating level from the electrical transmission station, converter and associated plant, emitted during normal operation, shall not exceed 35 dB LAr,Tr at any residential property. The definition of rating level shall be as described in BS 4142:1997. The noise limit only applies to residential properties that have planning permission on 30th July 2013.
Employment and skills plan
19
- (1) No part of the authorised development is to commence until an employment and skills plan has been submitted to and approved by North Lincolnshire Council in consultation with the Humber Local Enterprise Partnership.
- (2) The plan must include—
- (a) proposals for the provision of information to the Humber Local Enterprise Partnership on the employment and supply chain opportunities associated with the construction, operation and maintenance of the authorised development including details of the core qualifications and skillsets required to access those opportunities;
- (b) proposals for local advertising of employment and supply chain opportunities during the construction of the authorised development;
- (c) proposals for the undertaker to provide outreach employment presentations during the period of construction of the authorised development at appropriate times and locations; and
- (d) proposals for local advertising of employment and supply chain opportunities during the operation of the authorised development.
- (3) The approved employment and skills plan must be implemented and maintained during the construction and operation of the authorised development.
- (4) For the purposes of this requirement, “Humber Local Enterprise Partnership” means the local enterprise partnership established in June 2011 with the objective of promoting and developing the natural economic area surrounding the Humber estuary and in the event that this local enterprise partnership is no longer in existence means the local planning authority.
North Coates airfield
20
No part of the authorised development is to commence within half a mile of the perimeter of the North Coates airfield until a plan to secure its safe operation during the construction and operation of the authorised project has been submitted to and approved by the Secretary of State following consultation by the Secretary of State with the operator of North Coates airfield and the Civil Aviation Authority.
Requirement for written approval
21
Where under any of the requirements the approval or agreement of the Secretary of State, the local planning authority or another person or body is required, that approval or agreement must be given in writing.
Amendments to approved details
22
- (1) With respect to any requirement which requires the authorised development to be carried out in accordance with the details of a plan, scheme or code approved by the local planning authority or any other person or body, the approved details, or plan, scheme or code are to be taken to include any amendments that may subsequently be approved in writing by the local planning authority or that other person or body.
- (2) Where such details, plan, scheme or code are required to be approved in consultation with another body, any amendments of that document must also be approved in consultation with that body.
- (3) Any amendments to or variations from the approved details must be in accordance with the principles and assessments set out in the environmental statement. Such agreement may only be given in relation to immaterial changes where it has been demonstrated to the satisfaction of the relevant planning authority or that other person that the subject matter of the agreement sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
SCHEDULE 2 — Streets subject to street works
| (1) | (2) |
|---|---|
| Area | Streets subject to street works |
| District of East Lindsey | Permissive Footpath along Sea Wall |
| District of East Lindsey | Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north |
| District of East Lindsey | Sea Lane |
| District of East Lindsey | Tetn/19/1 (Public Footpath) |
| District of East Lindsey | North Coates Road |
| District of East Lindsey | Tetn/13/5 (Public Footpath) |
| District of East Lindsey | Unnamed highway east of New Delights access |
| District of East Lindsey | Tetney Lock Road |
| District of East Lindsey | Humberston Road |
| District of East Lindsey | Tetn/14/4 (Public Footpath) |
| District of East Lindsey | Holton Road |
| District of East Lindsey | HoLC/5/4 (Public Footpath) |
| District of East Lindsey | Station Road |
| District of East Lindsey | HoLC/4/1 (Public Footpath) |
| District of East Lindsey | Louth Road (A16) |
| District of East Lindsey | HoLC/10/1 (Public Footpath) |
| District of East Lindsey | Tetn/343/1 (Public Footpath) |
| District of East Lindsey | Tetn/12/5 (Public Footpath) |
| North East Lincolnshire | FP84 (Public Footpath) |
| North East Lincolnshire | Waithe Lane |
| North East Lincolnshire | Waithe Lane |
| North East Lincolnshire | BW75 (Public Bridleway) |
| North East Lincolnshire | Waltham Road (B1203) |
| North East Lincolnshire | Waltham Road (C148) |
| North East Lincolnshire | FP95 (Public Footpath) |
| North East Lincolnshire | Bradley Road |
| North East Lincolnshire | BW93 (Public Bridleway) |
| North East Lincolnshire | BW97 (Public Bridleway) |
| North East Lincolnshire | FP96 (Public Footpath) |
| North East Lincolnshire | Grimsby Road (A46) |
| North East Lincolnshire | FP103 (Public Footpath) |
| North East Lincolnshire | FP110 (Public Footpath) |
| North East Lincolnshire | Aylesby Road |
| North East Lincolnshire | BW108 (Public Bridleway) |
| North East Lincolnshire | Beech Holt Lane/Nooking Lane |
| District of West Lindsey | Wells Road |
| North East Lincolnshire | Riby Road (A1173) |
| North East Lincolnshire | FP26 (Public Footpath) |
| North East Lincolnshire | Keelby Road |
| North East Lincolnshire | Roxton Road |
| North East Lincolnshire | Station Road (B1210) |
| North East Lincolnshire | Immingham Road (B1210) |
| North East Lincolnshire | FP8 (Public Footpath) |
| North East Lincolnshire | FP7 (Public Footpath) |
| North East Lincolnshire | Killingholme Road |
| North East Lincolnshire | FP24 (Public Footpath) |
| North East Lincolnshire | FP4 (Public Footpath) |
| North East Lincolnshire | A180 |
| North Lincolnshire Council | 94 (Public Footpath) |
| North Lincolnshire Council | Faulding Lane |
| North Lincolnshire Council | Habrough Road |
| North Lincolnshire Council | Ulceby Road (A160) |
| North Lincolnshire Council | Top Road |
| North Lincolnshire Council | 87 (Public Footpath) |
| North Lincolnshire Council | Nicholson Road |
| North Lincolnshire Council | Chase Hill Road |
| North Lincolnshire Council | Brick Lane |
| North Lincolnshire Council | 86 (Public Footpath) |
| North Lincolnshire Council | 79 (Public Footpath) |
SCHEDULE 3 — Streets to be temporarily stopped up
| (1) | (2) | (3) |
|---|---|---|
| Area | Street to be temporarily stopped up | Extent of temporary stopping up |
| District of East Lindsey | Permissive Footpath | Between points F1 and F2 as shown in a dotted red line on sheet 1 of the onshore works plans |
| District of East Lindsey | Permissive Footpath | Between points F3 and F4 as shown in a dotted red line on sheet 1 of the onshore works plans |
| District of East Lindsey | Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north | Between points 1 and 2 as shown hatched on sheet 2 of the onshore works plans |
| District of East Lindsey | Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north | Between points 3 and 4 as shown hatched on sheet 2 of the onshore works plans |
| District of East Lindsey | Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries and area to the north | Between points 5 and 6 as shown hatched on sheet 2 of the onshore works plans |
| District of East Lindsey | Sea Lane | Between points 7 and 8 as shown hatched on sheet 2 of the onshore works plans |
| District of East Lindsey | Footpath Tetn/19/1 | Between points F5 and F6 as shown in a dotted red line on sheet 3 of the onshore works plans |
| District of East Lindsey | Footpath Tetn/19/1 | Between points F7 and F8 as shown in a dotted red line on sheet 3 of the onshore works plans |
| District of East Lindsey | North Coates Road | Between points 9 and 10 as shown hatched on sheet 4 of the onshore works plans |
| District of East Lindsey | Footpath Tetn/13/5 | Between points F9 and F10 as shown in a dotted red line on sheet 4 of the onshore works plans |
| District of East Lindsey | Unnamed highway east of New Delights access | Between points 11 and 12 as shown hatched on sheet 4 of the onshore works plans |
| District of East Lindsey | Unnamed highway east of New Delights access | Between points 13 and 14 as shown hatched on sheet 4 of the onshore works plans |
| District of East Lindsey | Unnamed highway east of New Delights access | Between points 15 and 16 as shown hatched on Sheet 4 of the onshore works plans |
| District of East Lindsey | Unnamed highway east of New Delights access | Between points 105 and 106 as shown hatched on sheet 5 of the onshore works plans |
| District of East Lindsey | Tetney Lock Road | Between points 17 and 18 as shown hatched on sheet 5 of the onshore works plans |
| District of East Lindsey | Tetney Lock Road | Between points 19 and 20 as shown hatched on sheet 5 of the onshore works plans |
| District of East Lindsey | Tetney Lock Road | Between points 21 and 22 as shown hatched on sheet 5 of the onshore works plans |
| District of East Lindsey | Humberston Road | Between points 23 and 24 as shown hatched on sheet 5 of the onshore works plans |
| District of East Lindsey | Footpath Tetn/14/4 | Between points F11 and F12 as shown in a dotted red line on sheet 6 of the onshore works plans |
| District of East Lindsey | Holton Road | Between points 25 and 26 as shown hatched on sheet 6 of the onshore works plans |
| District of East Lindsey | Footpath HoLC/5/4 | Between points F13 and F14 as shown in a dotted red line on sheet 7 of the onshore works plans |
| District of East Lindsey | Footpath HoLC/5/4 | Between points F14 and F15 as shown in a dotted red line on sheet 7 of the onshore works plans |
| District of East Lindsey | Station Road | Between points 27 and 28 as shown hatched on sheet 7 of the onshore works plans |
| District of East Lindsey | Station Road | Between points 29 and 30 as shown hatched on sheet 7 of the onshore works plans |
| District of East Lindsey | Station Road | Between points 31 and 32 as shown hatched on sheet 7 of the onshore works plans |
| District of East Lindsey | Footpath HoLC/4/1 | Between points F16 and F17 as shown in a dotted red line on sheet 7 of the onshore works plans |
| District of East Lindsey | Louth Road (A16) | Between points 33 and 34 as shown hatched on sheet 7 of the onshore works plans |
| District of East Lindsey | Louth Road (A16) | Between points 109 and 110 as shown hatched on sheet 7 of the onshore works plans |
| District of East Lindsey | Footpath HoLC/10/1 | Between points F18 and F19 as shown in a dotted red line on sheet 8 of the onshore works plans |
| North East Lincolnshire | Footpath FP84 | Between points F20 and F21 as shown in a dotted red line on sheet 8 of the onshore works plans |
| North East Lincolnshire | Waithe Lane | Between points 35 and 36 as shown hatched on sheet 8 of the onshore works plans |
| North East Lincolnshire | Waithe Lane | Between points 37 and 38 as shown hatched on sheet 9 of the onshore works plans |
| North East Lincolnshire | Bridleway BW75 | Between points F22 and F23 as shown in a dotted red line on sheet 9 of the onshore works plans |
| North East Lincolnshire | Waltham Road (B1203) | Between points 39 and 108 as shown hatched on sheet 9 of the onshore works plans |
| North East Lincolnshire | Waltham Road (B1203) | Between points 39 and 40 as shown hatched on sheet 9 of the onshore works plans |
| North East Lincolnshire | Waltham Road (B1203) | Between points 41 and 42 as shown hatched on sheet 9 of the onshore works plans |
| North East Lincolnshire | Waltham Road (C148) | Between points 43 and 44 as shown hatched on sheet 10 of the onshore works plans |
| North East Lincolnshire | Footpath FP95 | Between points F24 and F25 as shown in a dotted red line on sheet 12 of the onshore works plans |
| North East Lincolnshire | Footpath FP95 | Between points F26 and F27 as shown in a dotted red line on sheet 12 of the onshore works plans |
| North East Lincolnshire | Bradley Road | Between points 45 and 46 as shown hatched on sheet 11 of the onshore works plans |
| North East Lincolnshire | Bradley Road | Between points 47 and 48 as shown hatched on sheet 12 of the onshore works plans |
| North East Lincolnshire | Bradley Road | Between points 49 and 50 as shown hatched on sheet 12 of the onshore works plans |
| North East Lincolnshire | Bridleway BW93 | Between points F28 and F29 as shown in a dotted red line on sheet 12 of the onshore works plans |
| North East Lincolnshire | Footpath FP95 | Between points F30 and F31 as shown in a dotted red line on sheet 13 of the onshore works plans |
| North East Lincolnshire | Bridleway BW97 | Between points F32 and F33 as shown in a dotted red line on sheet 14 of the onshore works plans |
| North East Lincolnshire | Footpath FP96 | Between points F34 and F35 as shown in a dotted red line on sheet 14 of the onshore works plans |
| North East Lincolnshire | Grimsby Road (A46) | Between points 51 and 52 as shown hatched on sheet 14 of the onshore works plans |
| North East Lincolnshire | Grimsby Road (A46) | Between points 53 and 54 as shown hatched on sheet 14 of the onshore works plans |
| North East Lincolnshire | Grimsby Road (A46) | Between points 55 and 56 as shown hatched on sheet 14 of the onshore works plans |
| North East Lincolnshire | Footpath FP103 | Between points F36 and F37 as shown in a dotted red line on sheet 15 of the onshore works plans |
| North East Lincolnshire | Footpath FP110 | Between points F38 and F39 as shown in a dotted red line on sheet 15 of the onshore works plans |
| North East Lincolnshire | Aylesby Road | Between points 57 and 58 as shown hatched on sheet 15 of the onshore works plans |
| North East Lincolnshire | Bridleway BW108 | Between points F40 and F41 as shown in a dotted red line on sheet 15 of the onshore works plans |
| North East Lincolnshire | Beech Holt Lane/Nooking Lane | Between points 59 and 60 as shown hatched on sheet 16 of the onshore works plans |
| West Lindsey District | Wells Road | Between points 61 and 62 as shown hatched on sheet 17 of the onshore works plans |
| North East Lincolnshire | Riby Road (A1173) | Between points 63 and 64 as shown hatched on sheet 18 of the onshore works plans |
| North East Lincolnshire | Footpath FP26 | Between points F42 and F43 as shown in a dotted red line on sheet 19 of the onshore works plans |
| North East Lincolnshire | Keelby Road | Between points 65 and 66 as shown hatched on sheet 19 of the onshore works plans |
| North East Lincolnshire | Keelby Road | Between points 65 and 107 as shown hatched on sheet 19 of the onshore works plans |
| North East Lincolnshire | Keelby Road | Between points 101 and 102 as shown hatched on sheet 19 of the onshore works plans |
| North East Lincolnshire | Roxton Road | Between points 67 and 68 as shown hatched on sheet 20 of the onshore works plans |
| North East Lincolnshire | Roxton Road | Between points 69 and 70 as shown hatched on sheet 20 of the onshore works plans |
| North East Lincolnshire | Station Road (B1210) | Between points 71 and 72 as shown hatched on sheet 22 of the onshore works plans |
| North East Lincolnshire | Immingham Road (B1210) | Between points 73 and 74 as shown hatched on sheet 23 of the onshore works plans |
| North East Lincolnshire | Immingham Road (B1210) | Between points 75 and 76 as shown hatched on sheet 23 of the onshore works plans |
| North East Lincolnshire | Footpath FP8 | Between points F44 and F45 as shown in a dotted red line on sheet 23 of the onshore works plans |
| North East Lincolnshire | Footpath FP7 | Between points F46 and F47 as shown in a dotted red line on sheet 23 of the onshore works plans |
| North East Lincolnshire | Killingholme Road | Between points 77 and 78 as shown hatched on sheet 23 of the onshore works plans |
| North Lincolnshire | Footpath 94 | Between points F48 and F49 as shown in a dotted red line on sheet 24 of the onshore works plans |
| North Lincolnshire | Faulding Lane | Between points 79 and 80 as shown hatched on sheet 24 of the onshore works plans |
| North Lincolnshire | Habrough Road | Between points 81 and 82 as shown hatched on sheet 24 of the onshore works plans |
| North Lincolnshire | Habrough Road | Between points 83 and 84 as shown hatched on sheet 24 of the onshore works plans |
| North Lincolnshire | Habrough Road | Between points 85 and 86 as shown hatched on sheet 24 of the onshore works plans |
| North Lincolnshire | Ulceby Road (A160) | Between points 87 and 88 as shown hatched on sheet 24 of the onshore works plans |
| North Lincolnshire | Top Road | Between points 89 and 90 as shown hatched on sheet 25 of the onshore works plans |
| North Lincolnshire | Footpath 87 | Between points F50 and F52 as shown in a dotted red line on sheet 25 of the onshore works plans |
| North Lincolnshire | Footpath 87 | Between points F51 and F52 as shown in a dotted red line on sheet 25 of the onshore works plans |
| North Lincolnshire | Nicholson Road | Between points 91 and 92 as shown hatched on sheet 25 of the onshore works plans |
| North Lincolnshire | Nicholson Road | Between points 92 and 111 as shown hatched on sheet 25 of the onshore works plans |
| North Lincolnshire | Nicholson Road | Between points 103 and 104 as shown hatched on sheet 25 of the onshore works plans |
| North Lincolnshire | Chase Hill Road | Between points 93 and 94 as shown hatched on sheet 26 of the onshore works plans |
| North Lincolnshire | Chase Hill Road | Between points 95 and 96 as shown hatched on sheet 26 of the onshore works plans |
| North Lincolnshire | Brick Lane | Between points 97 and 98 as shown hatched on sheet 26 and 27 of the onshore works plans |
| North Lincolnshire | Footpath 86 | Between points F53 and F54 as shown in a dotted red line on sheet 27 of the onshore works plans |
| North Lincolnshire | Footpath 79 | Between points F55 and F56 as shown in a dotted red line on sheet 27 of the onshore works plans |
| North Lincolnshire | Footpath 86 | Between points F57 and F58 as shown in a dotted red line on sheet 27 of the onshore works plans |
| North Lincolnshire | Chase Hill Road | Between points 99 and 100 as shown hatched on sheet 27 of the onshore works plans |
SCHEDULE 4 — Access to works
| (1) | (2) |
|---|---|
| Area | Description of access |
| District of East Lindsey | Between point A1 (north side of Sheep Marsh Lane) shown on sheet 1 of the onshore works plans and Works Nos. 7, 8, 9 |
| District of East Lindsey | Between point A2 (Unnamed highway north of Sheep Marsh Lane providing access to Poplar Piggeries) shown on sheet 2 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A3 (south side of North Coates Road) shown on sheet 4 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A4 (north side of unnamed highway east of New Delights access) shown on sheet 4 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A5 (north side of Tetney Lock Road east of New Delights access) shown on sheet 5 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A6 (north side of unnamed highway east of New Delights access) shown on sheet 5 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A7 (north side of Tetney Lock Road west of Cow Marsh Lane) shown on sheet 5 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A8 (west side of Holton Road) shown on sheet 6 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A9 (east side of Holton Road west of Grange Farm Cottage) shown on sheet 6 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A10 (north side of Station Road) shown on sheet 7 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A11 (north side of Station Road to the west of the dismantled railway line) shown on sheet 7 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A12 (north side of Station Road) shown on sheet 7 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A13 (north side of Station Road) shown on sheet 7 of the onshore works plans and Work No. 9 |
| District of East Lindsey | Between point A14 (west side of A16) shown on sheet 8 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A15 (west side of B1203) shown on sheet 9 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A16 (east side of B1203) shown on sheet 9 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A17 (north side of C148 Waltham Road) shown on sheet 10 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A18 (south side of C148 Waltham Road) shown on sheet 10 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A19 (west side of Bradley Road north of Waltham) shown on sheet 11 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A20 (west side of Bradley Road Netherwood Farm north access point) shown on sheet 12 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A21 (west side of Bradley Road Netherwood Farm south access point) shown on sheet 12 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A22 (north-west side of A46 east of Laceby) shown on sheet 14 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A23 (south-east side of A46 east of Laceby) shown on sheet 14 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A24 (south-east side of Aylesby Road) shown on sheet 15 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A25 (north side of Beach Holt Lane/Nooking Lane west of Aylesby) shown on sheet 16 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A26 (north-west side of Wells Road) shown on sheet 17 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A27 (south-east side of Wells Road) shown on sheet 17 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A28 (west side of A1173 at Stallingborough Grange Farm) shown on sheet 18 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A29 (east side of A1173) shown on sheet 18 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A30 (south-east side of Keelby Road south-west of Wood View) shown on sheet 19 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A31 (north-west side of Keelby Road south-west of Wood View) shown on sheet 19 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A32 (north-west side of Keelby Road in the vicinity of Wood View) shown on sheet 19 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A33 (east side of Roxton Road north of railway) shown on sheet 20 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A34 (west side of Roxton Road north of railway) shown on sheet 20 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A35 (south-east side of Roxton Road south of railway) shown on sheet 20 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A36 (south side of B1210 Station Road south of A180) shown on sheet 22 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A37 (north side of B1210 Immingham Road) shown on sheet 23 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A38 (south side of B1210 Immingham Road) shown on sheet 23 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A39 (south side of B1210 Immingham Road west of School Cottages) shown on sheet 23 of the onshore works plans and Work No. 9 |
| North East Lincolnshire | Between point A40 (east side of Killingholme Road, south of Mill House) shown on sheet 23 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A41 (south side of Faulding Lane) shown on sheet 24 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A42 (south-west side of Habrough Road north of Faulding Lane) shown on sheet 24 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A43 (south-west side of Habrough Road) shown on sheet 24 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A44 (south-west side of Habrough Road south-east of A160/Habrough Road roundabout) shown on sheet 24 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A45 (north side of A160 west of A160/Habrough Road roundabout) shown on sheet 24 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A46 (east side of Top Road) shown on sheet 25 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A47 (south side of Nicholson Road/Church Lane) shown on sheet 25 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A48 (north side of Nicholson Road/Church Lane) shown on sheet 25 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A49 (south side of Chase Hill Road west of Eastfield Road) shown on sheet 26 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A50 (north side of Chase Hill Road west of Eastfield Road) shown on sheet 26 of the onshore works plans and Work No. 9 |
| North Lincolnshire | Between point A51 (Brick Lane, north side of Chase Hill Road) shown on sheet 26 of the onshore works plans and Work No. 9 |
SCHEDULE 5 — Land in which only new rights etc., may be acquired
| (1) | (2) |
|---|---|
| Number of land shown on land plans | Purpose for which rights may be acquired |
| 1 – 210 – 14 | To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 160 metre corridor within the Order Land and to obtain access for such purposes |
| 3 – 916 – 21 | To ground and lay anchor for vessels within the Order Land |
| 1522407 – 408 | To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within the Order Land and to obtain access for such purposes |
| 23409 | To install, maintain and use an access track and to obtain access for such purposes |
| 25 – 26 | To install, retain, maintain and operate transition jointing bays for the connection of offshore cable circuits to onshore cable circuits and apparatus (and to impose requirements for their protection) within an up to 150 metre corridor within the Order Land and to obtain access for such purposes |
| 27 – 2957 – 5863 – 6668 – 727477 – 8087919497104 – 105107 – 108111 – 113122 – 126128 – 130133140 – 141145148151 – 152154156162164 – 171173 – 178180183 – 185187 – 192196199 – 200205 – 209212 – 213216218 – 220227232 – 233235238240242 – 243245 – 247251 – 258261267 – 268271 – 272274277279283287293 – 294296 – 297314 – 315319 – 320324331 – 332337 – 338346351353 – 354357359 – 362364 – 365368 – 370373 – 375378 – 380383386390 – 397400403 | To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30 metre corridor within the Order Land and to obtain access for such purposes |
| 37 – 40 | To install, maintain and use an access track and to obtain access for the purposes only of maintaining and operating the authorised project |
| 226 | To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30 metre corridor within the Order Land and to obtain access for such purposes but not extending to breaking open the surface of the Order Land |
| 313352 | To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within an up to 30 metre corridor within the Order land |
| 406 | To install, retain, maintain and operate apparatus (and to impose requirements for its protection) within the Order land and to install, maintain and use an access track and to obtain access for such purposes |
| 410415 | To install, retain, maintain and operate services (and to impose requirements for their protection) within the Order land and to install, maintain and use an access track and to obtain access for such purposes |
SCHEDULE 6 — Modification of compensation and compulsory purchase enactments for creation of new rights
PART 1 — Compensation enactments
1
The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right as they apply as respects compensation on the compulsory purchase of land and interests in land.
2
- (1) Without prejudice to the generality of paragraph 1, the Land Compensation Act 1973[^f00029] has effect subject to the modifications set out in sub-paragraphs (2) and (3).
- (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—
- (a) for the words “land is acquired or taken” there are substituted the words “a right over land is purchased from or imposed on”; and
- (b) for the words “acquired or taken from him” there are substituted the words “over which the right is exercisable”.
- (3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—
- (a) for the word “part” in paragraphs (a) and (b) there are substituted the words “a right over land consisting”;
- (b) for the word “severance” there are substituted the words “right over the whole of the house, building or manufactory or of the house and the park or garden”;
- (c) for the words “part proposed” there are substituted the words “right proposed”; and
- (d) for the words “part is” there are substituted the words “right is”.
PART 2 — Application of the 1965 Act
1
- (1) The 1965 Act has effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are read (according to the requirements of the particular context) as referring to, or as including references to—
- (a) the right acquired or to be acquired; or
- (b) the land over which the right is or is to be exercisable.
- (2) Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act applies in relation to the compulsory acquisition under this Order of a right by the creation of a new right with the modifications specified in the following provisions of this Schedule.
2
For section 7 of the 1965 Act (measure of compensation) there is substituted the following section—
(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired is to be imposed is depreciated by the acquisition of the right but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.
3
For section 8 of the 1965 Act (provisions as to divided land) there is substituted the following section—
(8) (1) Where in consequence of the service on a person under section 5 of this Act of a notice to treat in respect of a right over land consisting of a house, building or manufactory or of a park or garden belonging to a house (“the relevant land”)— (a) a question of disputed compensation in respect of the purchase of the right would apart from this section fall to be determined by the Upper Tribunal (“the tribunal”); and (b) before the tribunal has determined that question the tribunal is satisfied that the person has an interest in the whole of the relevant land and is able and willing to sell that interest and— (i) where that land consists of a house, building or manufactory, that the right cannot be purchased without material detriment to that land; or (ii) where that land consists of such a park or garden, that the right cannot be purchased without seriously affecting the amenity or convenience of the house to which that land belongs, the Hornsea One Offshore Wind Farm Order 2014 (“the Order”), in relation to that person, ceases to authorise the purchase of the right and is instead deemed to authorise the purchase of that person’s interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice is deemed to have been served in respect of that interest on such date as the tribunal directs. (2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) is to be determined by the tribunal. (3) Where the Order is deemed by virtue of subsection (1) to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of six weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice.
4
The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
- (a) section 9(4) (failure by owners to convey);
- (b) paragraph 10(3) of Schedule 1 (owners under incapacity);
- (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
- (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land);
are modified so as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or which is to be imposed is vested absolutely in the acquiring authority.
5
Section 11 of the 1965 Act (powers of entry) is so modified as to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right, it has power, exercisable in equivalent circumstances and subject to equivalent conditions to those provided for in that section, to enter for the purpose of exercising that right; and sections 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are modified correspondingly.
6
Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right in question.
7
Section 22 of the 1965 Act (interests omitted from purchase) is modified so as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.
SCHEDULE 7 — Land of which temporary possession may be taken
PART 1
| (1) | (2) | (3) | (4) |
|---|---|---|---|
| Area | Number of land shown on land plans | Purpose for which temporary possession may be taken | Relevant part of the Authorised project |
| District of East Lindsey | 24 | Worksite and access for the construction and carrying out of the authorised project | Works Nos. 7, 8 and 9 |
| District of East Lindsey | 30 – 3335 – 3661 – 6275 – 7681 – 868898 – 102109 – 110121131146153157 – 159161 | Worksite and access for the construction and carrying out of the authorised project | Work No. 9 |
| District of East Lindsey | 4144 – 4547- 49 | Laying and use of temporary vehicular access track | Works Nos. 7, 8 and 9 |
| District of East Lindsey | 50 – 56607389 – 9092 – 9395 – 96103114 – 116127132134136 – 137139142 – 143150155 | Laying and use of temporary vehicular access track | Work No. 9 |
| District of East Lindsey | 81144147149160 | Laying of temporary public footpaths and bridleways | Work No. 9 |
| North East Lincolnshire | 163201239241270325 | Laying of temporary public footpaths and bridleways | Work No. 9 |
| North East Lincolnshire | 172182186193 – 195197201214 – 215228 – 231234236 – 237244248259 – 260264 – 266269 – 270273278280 – 282284 – 286288 – 289295304306 – 307312316 – 317321 – 323325 – 326328 | Worksite and access for the construction and carrying out of the authorised project | Work No. 9 |
| North East Lincolnshire | 179181198217221 – 225241262275 – 276292300302 – 303305309318330 | Laying and use of temporary vehicular access track | Work No. 9 |
| North Lincolnshire | 333 – 335341 – 342345347 – 350356358366 – 367371 – 372381 – 382387 – 388398 – 399401 – 402 | Worksite and access for the construction and carrying out of the authorised project | Work No. 9 |
| North Lincolnshire | 336339 – 340343 – 344355 – 356358363376 – 377384 – 385 | Laying and use of temporary vehicular access track | Work No. 9 |
| North Lincolnshire | 405 | Worksite and access for the construction and carrying out of the authorised project | Works Nos. 9, 10 and 11 |
| North Lincolnshire | 411 – 414416 | Laying and use of temporary vehicular access track | Works Nos. 10, 11 and 12 |
PART 2
| (1) | (2) |
|---|---|
| Area | Number of land shown on land plans |
| District of East Lindsey | 3442 – 4346596787117 – 120135138 |
| North East Lincolnshire | 202 – 204210 – 211249 – 250263290 – 291298 – 299301308310 – 311327329 |
| North Lincolnshire | 389 |
SCHEDULE 8 — Deemed Marine Licences under the Marine and Coastal Access Act 2009 – Deemed Marine Licence 1
PART 1 — Licensed marine activities
Interpretation
1
- (1) In this licence—
- “the 2008 Act” means the Planning Act 2008;
- “the 2009 Act” means the Marine and Coastal Access Act 2009;
- “ancillary vessel” means any vessel other than a construction vessel or a survey vessel;
- “ancillary works” means the ancillary works described in paragraph 2 of this Part of this licence which are not development within the meaning of section 32 of the 2008 Act;
- “Annex I Habitat” means such habitat as defined under the EU Council Directive 92/43/EEC on the Conservation of Natural Habitats and of Wild Fauna and Flora[^f00030];
- “authorised deposits” means the substances and articles specified in paragraph 2(3) of Part 1 of this licence;
- “authorised development” means the development described in Part 1 of Schedule 1 of the Order, which is development within the meaning of section 32 of the 2008 Act;
- “authorised project” means the authorised development and the ancillary works authorised by the Order;
- “authorised scheme” means Work No. 1 described in paragraph 2 of this Part of this licence;
- “commence” means the first carrying out of any part of the licensed activities, save for pre-construction surveys and monitoring, and “commencement” shall be construed accordingly;
- “construction vessel” means any vessel involved in the course of or used for the construction and/or maintenance of the authorised project;
- “debris” means items or equipment of a significant size left on the seabed being lost from survey or construction vessels;
- “electrical circuit” means a number of electrical conductors necessary to transmit electricity between two points within the authorised project; this comprises, in the case of HVAC transmission, three conductors which may be bundled as one cable, and, in the case of HVDC transmission two conductors, which may be attached together or take the form of single cables: the circuit may include one or more auxiliary cables (normally fibre optic cables) for the purpose of control, monitoring, protection or general communications;
- “enforcement officer” means a person authorised to carry out enforcement duties under Part 4, Chapter 3 of the 2009 Act;
- “the Environmental Statement” means the document certified as the environmental statement by the Secretary of State for the purposes of the Order;
- “gravity base foundation” means either— a structure principally of concrete and/or steel which rests on the seabed due either to its own weight and that of added ballast or to the weight of water above it, and may include associated equipment including suction piles, J-tubes and access platforms; or a structure principally of concrete and/or steel consisting of a platform supported on two pontoons to which the platform is connected by columns which may be connected by braces;
- “HVAC” means high voltage alternating current;
- “HVDC” means high voltage direct current;
- “inter-array electrical circuits” means the circuits described in paragraph 2(2)(b) of Part 1 of this licence;
- “jacket foundation” means a lattice construction comprising tubular members and joints which are fixed to the seabed with piles (either driven/drilled piles or suction piles) and which will include platforms and J-tubes and may include braced monopiles and a transition piece;
- “the Kingfisher Fortnightly Bulletin” means the bulletin published by the Humber Seafood Institute or such other alternative publication approved in writing by the MMO;
- “licensed activities” means the activities specified in Part 1 of this licence;
- “the licence conditions” means the conditions set out in Part 2 of this licence;
- “licence-holder” means Heron Wind Limited;
- “maintain” includes, to the extent assessed in the environmental statement— inspect, repair, adjust and alter; and in respect of any of the ancillary works and any component part of any wind turbine generator, offshore accommodation platform, offshore HVAC collector substation, offshore HVDC converter station or offshore reactive compensation substation described in Part 1 of Schedule 1 (authorised development) of the Order also includes remove, reconstruct and replace, but does not include the alteration, removal or replacement of foundations; and “maintenance” shall be construed accordingly;
- “the Marine Management Organisation” or “MMO” means the body created under the 2009 Act which is responsible for the monitoring and enforcement of this licence or any successor to its statutory functions;
- “the Maritime and Coastguard Agency” or “MCA” means the executive agency of the Department for Transport or any successor to its statutory functions;
- “mean high water springs” or “MHWS” means the highest level which spring tides reach on average over a period of time;
- “mean low water springs” or “MLWS” means the lowest level which spring tides reach on average over a period of time;
- “monopile foundation” comprises a large diameter steel or concrete tube or pile driven vertically into the seabed, J-tubes and platforms and may include external structural devices such as bracing members or steel anchor wires and a transition piece;
- “Natural England” means the body established by section 1 of the Natural Environment and Rural Communities Act 2006 or any successor to its statutory functions;
- “Notice to Mariners” includes any Notice to Mariners which may be issued by Admiralty, Trinity House, Queen’s harbourmasters, government departments and harbour and pilotage authorities;
- “offshore accommodation platform” means a platform housing or incorporating temporary accommodation, landing ports for vessels and/or helicopters, standby electricity generation equipment, marking and lighting and other equipment facilities to assist in the co-ordination of marine activities related to the authorised scheme;
- “offshore HVAC collector substation” means a structure serving as a collection point for the inter-array electrical circuits and containing equipment with the purpose of transforming the electricity generated at the wind turbines to a higher voltage; it may also include a helicopter platform;
- “offshore HVDC converter station” means a structure which contains equipment to convert HVAC electricity to HVDC electricity; it may also include a helicopter platform;
- “the offshore works plans” means the part of the works plans described as the offshore works plans;
- “the Order limits” means the limits shown on the works plans within which the authorised project may be carried out;
- “the Order” means the Hornsea One Offshore Wind Farm Order 2014;
- “the project description” means the document certified as the project description by the Secretary of State for the purposes of the Order and submitted with the application on 30th July 2013 (Chapter Three, Volume One of the Environmental Statement);
- “suction pile” means a large diameter steel cylinder which is fixed to the base of the foundation and partially penetrates the seabed and remains in place using its weight and hydrostatic pressure differential;
- “survey vessels” means the vessels licensed to carry out environmental or engineering surveys;
- “Trinity House” means the Corporation of Trinity House of Deptford Strond;
- “the UK Hydrographic Office” means the Hydrographic Office of the Ministry of Defence, Taunton, Somerset TA1 2DN or any replacement body or successor to its functions;
- “vessel” means every description of vessel, however propelled or moved, and includes a non-displacement craft, a personal watercraft, a seaplane on the surface of the water, a hydrofoil vessel, a hovercraft or any other amphibious vehicle and any other thing constructed or adapted for movement through, in, on or over water and which is at the time in, on or over water and including ancillary vessels and construction vessels;
- “VHF” means very high frequency;
- “Wind Farm Area 1” means the area within the limits of deviation for Work No. 1 of which the co-ordinates are specified in Part 1 of Schedule 1 of the Order and shown on the works plans;
- “Wind Farm Area 2” means the area within the limits of deviation for Work No. 2 of which the co-ordinates are specified in Part 1 of Schedule 1 of the Order and shown on the works plans;
- “Wind Farm Area 3” means the area within the limits of deviation for Work No. 3 of which the co-ordinates are specified in Part 1 of Schedule 1 of the Order and shown on the works plans;
- “wind turbine generator” or “wind turbine” means a structure comprising any or all of a tower, rotor, blades, nacelle and ancillary electrical and other equipment or structures which may include lighting and a helicopter platform, fixed to a foundation;
- “working day” means any day other than a Saturday, Sunday or public holiday in England and Wales;
- “Work No. 1” means an offshore wind generating station within Wind Farm Area 1 and described as Work No. 1 in paragraph 2 of Part 1 of this licence;
- “Work No. 2” means an offshore wind generating station within Wind Farm Area 2 and described as Work No. 2 in Part 1 of Schedule 1 of the Order;
- “Work No. 3” means an offshore wind generating station within Wind Farm Area 3 and described as Work No. 3 in Part 1 of Schedule 1 of the Order;
- “Work No. 4” means up to five offshore HVAC collector substations and, in the event that the mode of transmission is HVDC, up to two offshore HVDC converter stations together with a network of electrical circuits connecting the structures within Work No. 4;
- “the works plans” means the plans certified as the works plans by the Secretary of State for the purposes of the Order divided into three parts and described as the offshore works plans, the intertidal works plans and the onshore works plans.
- (2) A reference to any statute, order, regulation or similar instrument shall be construed as a reference to a statute, order, regulation or instrument as amended by any subsequent statute, order, regulation or instrument or as contained in any subsequent re-enactment.
- (3) Unless otherwise indicated—
- (a) all times shall be taken to be Greenwich Mean Time (GMT);
- (b) all co-ordinates shall be taken to be latitude and longitude degrees, minutes and seconds to three decimal places in WGS84 Datum.
- (4) Except where otherwise notified in writing by the relevant organisation, the primary point of contact with the organisations listed below and the address for returns and correspondence shall be—
- (a)
- (b)
- (c)
- (d)
- (e)
- (f)
- (g)
- (h)
- (i)
Details of licensed activities
2
- (1) This licence authorises the licence-holder (and any agent or contractor acting on their behalf) to carry out the following licensable marine activities pursuant to section 66(1) of the 2009 Act, subject to the licence conditions—
- (a) the deposit at sea of the substances and articles specified in sub-paragraph (3) below;
- (b) the construction of works in or over the sea and/or on or under the sea bed;
- (c) dredging;
- (d) the removal of sediment samples for the purposes of informing environmental monitoring under this licence during pre-construction, construction and operation;
- (e) the disposal at disposal site reference HU206 (Hornsea Project One Subzone 1) of—
- (i) in the event that an offshore accommodation platform is constructed under this licence up to 434,004 m³ or, if no part of Work No.3 is constructed, up to 641,385 m³, of inert material of natural origin produced during construction drilling and seabed preparation for foundation works comprised in Work No. 1; or
- (ii) in the event that no offshore accommodation platform is constructed under this licence up to 414,762 m³ or, if no part of Work No.3 is constructed, up to 622,143 m³, of inert material of natural origin produced during construction drilling and seabed preparation for foundation works comprised in Work No. 1; and
- (f) the removal of the substances and articles specified in sub-paragraph (3) below.
- (2) Such activities are authorised in relation to the construction, maintenance and operation of—
Duration
3
This licence shall remain in force until the authorised scheme has been decommissioned in accordance with a programme approved by the Secretary of State under section 106 of the Energy Act 2004, including any modification to the programme under section 108, and the completion of such programme has been confirmed by the Secretary of State in writing.
PART 2 — Licence conditions
Design parameters
1
- (1) All wind turbine generators forming part of Work No. 1 must not—
- (a) be less than 82 metres to the turbine hub when measured from MHWS;
- (b) exceed a height of 200 metres from MHWS to the upper tip of the vertical blade;
- (c) exceed a rotor diameter of 178 metres;
- (d) be less than 22 metres from MHWS to the lowest point of the rotating blade; or
- (e) be less than 924 metres from the nearest wind turbine generator in all directions.
- (2) References to the location of a wind turbine generator are references to the centre point of the turbine.
2
Any offshore accommodation platform forming part of Work No. 1 must not—
- (a) exceed 60 metres in height above MHWS;
- (b) have a platform which at its greatest extent exceeds, 3,600 m² or 60 metres in width.
3
The diameter of the electrical circuits comprising the electrical circuits within Work No. 1 must not exceed 170 mm.
4
The electrical circuits comprised in Work No. 1 must be installed by use of, or a combination of, ploughing, trenching, jetting, rock-cutting, dredging, surface laying with post lay burial, and where ground conditions make burial impracticable, by surface laying.
5
- (1) The licence-holder must in fixing to the seabed any structures comprised in Work No. 1 use one of the following methods—
- (a) monopile foundations;
- (b) jacket foundations supported by piles; or
- (c) gravity base foundations.
- (2) The following parameters apply in respect of the foundation methods used to fix wind turbine generators comprised in Work No. 1 to the seabed—
- (a) where monopile foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,419 m²;
- (ii) the diameter of each foundation must not exceed 8.5 metres;
- (b) where jacket foundations (driven/drilled piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 707 m² per wind turbine;
- (ii) the number of piles per jacket must not exceed four;
- (iii) the diameter of each pile must not exceed three metres;
- (c) where jacket foundations (suction piles) are used—
- (i) the area occupied by the foundations and scour protection for each individual structure must not exceed 6,362 m²;
- (ii) the number of piles per jacket must not exceed four;
- (iii) the diameter of each pile must not exceed 15 metres;
- (d) where gravity base foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 m²;
- (ii) the seabed levelling diameter must not exceed 70 metres;
- (iii) the cone diameter must not exceed 50 metres at its base.
- (3) The following parameters apply in respect of the foundation methods used to fix offshore accommodation platforms comprised in Work No. 1 to the seabed—
- (a) where monopile foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,419 m²;
- (ii) the diameter of each foundation must not exceed 8.5 metres;
- (b) where jacket foundations (driven/drilled piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 1,414 m²;
- (ii) the number of piles must not exceed eight;
- (iii) the diameter of each pile must not exceed three metres;
- (c) where jacket foundations (suction piles) are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 m²;
- (ii) the number of piles per jacket must not exceed eight;
- (iii) the diameter of each pile must not exceed 15 metres;
- (d) where gravity base foundations are used—
- (i) the area occupied by the foundations and the scour protection for each individual structure must not exceed 6,362 m²;
- (ii) the seabed levelling diameter must not exceed 70 metres;
- (iii) the cone diameter must not exceed 50 metres at its base.
- (4) The combined total volume of scour protection for the wind turbine generators and the offshore accommodation platform forming part of Work No. 1 must not exceed 1,079,839 m³ or, if no part of Work No.3 is constructed, must not exceed 1,613,093 m³.
- (5) In the event that no offshore accommodation platform is constructed under this licence, the combined total volume of scour protection for the wind turbine generators forming part of Work No. 1 must not exceed 1,066,508 m³ or, if no part of Work No. 3 is constructed, must not exceed 1,599,762 m³.
Notifications and inspections
6
- (1) The licence-holder shall ensure that—
- (a) a copy of this licence and any subsequent amendments or revisions to it are provided to—
- (i) all agents and contractors notified to the MMO in accordance with the conditions of this licence; and
- (ii) the masters and transport managers responsible for the vehicles notified to the MMO in accordance with the conditions of this licence.
- (b) Within 28 days of receipt of a copy of this licence those persons referred to in sub-paragraph (a) shall provide a completed confirmation form to the MMO confirming their understanding of the terms and conditions of this licence.
- (2) Only those persons and vessels notified to the MMO in accordance with condition 16 are permitted to carry out the licensed activities.
- (3) Copies of this licence shall also be available for inspection at the following locations—
- (a) the licence-holder’s registered address;
- (b) any site office located at or adjacent to the construction site and used by the licence-holder or its agents and contractors responsible for the loading, transportation or deposit for the authorised deposits; and
- (c) on board each vessel or at the office of any transport manager with responsibility for vessels from which authorised deposits are to be made.
- (4) The documents referred to in paragraph (1)(a) shall be available for inspection by an enforcement officer at the locations set out in paragraph (3) above at any time.
- (5) The licence-holder must provide access, and if necessary appropriate transportation, to the offshore construction site or any other associated works or vessels to facilitate any inspection that the MMO considers necessary to inspect the works during construction and operation of the authorised scheme.
- (6) The licence-holder must inform the MMO in writing at least five working days prior to the commencement of the licensed activities or any phase of them.
- (7) Prior to the commencement of the licensed activities the licence-holder must publish in the Kingfisher Fortnightly Bulletin details of the vessel routes, timings and locations relating to the construction of the authorised scheme.
- (8) The licence-holder shall ensure that a Notice to Mariners is issued at least ten days prior to the commencement of the licensed activities advising of the commencement of licensed activities within Wind Farm Area 1 and the expected vessel routes from the local service ports to the turbine locations.
- (9) The Notices to Mariners must be updated and reissued not less frequently than weekly and supplemented with VHF radio broadcasts agreed with the MCA in accordance with the construction and monitoring programme approved under licence condition 13(2)(a). Copies of all notices shall be provided to the MMO.
- (10) The licence-holder must notify—
- (a) the UK Hydrographic Office of commencement (within two weeks), progress and completion (within two weeks) of the authorised scheme in order that all necessary amendments to nautical charts are made; and
- (b) the MMO once the authorised scheme is completed and any required lighting or marking has been established.
Aids to navigation
7
The licence-holder must during the whole period from the start of construction of the authorised scheme seaward of MHWS to the completion of decommissioning—
- (a) exhibit such lights, marks, sounds, signals and other aids to navigation and take such other steps for the prevention of danger to navigation as Trinity House may from time to time direct;
- (b) colour all structures in the authorised scheme as directed by Trinity House;
- (c) notify Trinity House as soon as reasonably practicable of both the progress and completion of the authorised scheme (or any phase of it) and any aids to navigation established from time to time;
- (d) provide reports on the working condition of aids to navigation periodically as requested by Trinity House;
- (e) notify Trinity House and the MMO of any failure of the aids to navigation and the timescales in which such failure will be remedied, as soon as possible and no later than 24 hours following the licence-holder becoming aware of any such failure.
Provision against danger to navigation
8
In case of injury to, or destruction or decay of, the authorised scheme or any part of it seaward of MHWS the licence-holder must as soon as reasonably practicable, and no later than 24 hours following the licence-holder becoming aware of any such injury, destruction or decay, notify Trinity House and must lay down such buoys, exhibit such lights and take such other steps for the prevention of danger to navigation as Trinity House may from time to time direct.
Navigational Practice, Safety and Emergency Response
9
- (1) No part of the authorised scheme seaward of MHWS is to commence until the Secretary of State, in consultation with the MCA, has given written approval for an Emergency Response and Co-operation Plan which includes full details of the emergency co-operation plans for the construction, operation and decommissioning phases of that part of the authorised scheme in accordance with the MCA recommendations contained within MGN 371 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues”.
- (2) No authorised scheme seaward of MHWS is to commence until the Secretary of State, in consultation with the MCA, has confirmed in writing that the licence-holder has taken into account and, so far as is applicable to that stage of the development, adequately addressed all MCA recommendations as appropriate to the authorised scheme contained within MGN 371 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues” (including its annexes).
- (3) The Emergency Response and Co-operation Plan must be implemented as approved, unless otherwise agreed in writing by the Secretary of State, in consultation with the MCA.
- (4) The licence-holder must during the whole period from the start of construction of the authorised scheme seaward of MHWS to the completion of decommissioning provide relevant information to the MCA to assist in the timely and efficient issuing of notices to mariners and other navigational warnings of the position and nature of the works, such information to be provided to mariners in the shipping and fishing industry as well as to recreational mariners.
Colour and lighting
10
Except as otherwise required by Trinity House under condition 7, the licence-holder must colour all structures comprised in Work No. 1 submarine grey (colour code RAL 7035).
Chemicals, drilling and debris
11
- (1) All chemicals used in the construction of the authorised scheme shall be selected from the List of Notified Chemicals approved for use by the offshore oil and gas industry under the Offshore Chemicals Regulations 2002[^f00031] (as amended), unless otherwise agreed in writing by the MMO.
- (2) The licence-holder shall ensure that any coatings or treatments are suitable for use in the marine environment and are used in accordance with guidelines approved by Health and Safety Executive or the Environment Agency Pollution Prevention Guidelines.
- (3) The storage, handling, transport and use of fuels, lubricants, chemicals and other substances shall be undertaken so as to prevent releases into the marine environment including bunding of 110 per cent of the total volume of all reservoirs and containers.
- (4) Where foundation drilling works are proposed, in the event that any system other than water based mud is proposed the MMO’s written approval in relation to the proposed disposal of any arisings shall be obtained before the drilling commences, which disposal may also require a marine licence.
- (5) The licence-holder shall ensure that any debris arising from the construction of the authorised scheme or temporary works placed below MHWS are removed on completion of the authorised scheme, where practicable.
- (6) Prior to the commencement of the licensed activities the licence-holder must submit to the MMO an audit sheet covering all aspects of the construction of the authorised scheme and no works shall commence until the audit sheet content has been agreed with the MMO. The audit sheet shall include details of—
- (a) loading facilities;
- (b) vessels;
- (c) equipment;
- (d) shipment routes;
- (e) working schedules; and
- (f) all components and materials to be used in the construction of the authorised scheme.
- (7) The audit sheet shall be maintained throughout the construction of the authorised scheme and the MMO shall be notified of any changes on a fortnightly basis.
- (8) In the event that the MMO becomes aware that any of the materials on the audit sheet cannot be accounted for it shall require the licence-holder to carry out a side scan sonar survey to plot all obstructions across Wind Farm Area 1 where construction works and related activities have been carried out under this licence. Local fishermen shall be invited to send a representative to be present during the survey. Any new obstructions that the MMO believes to be associated with the authorised scheme shall be removed at the licence-holder’s expense, where practicable.
- (9) The licence-holder shall inform the MMO of the location and quantities of inert material disposed of each month under this licence, by submission of a disposal return by 31st January each year for disposals occurring during the months July to December inclusive of the preceding year, and by 31st July each year for disposals occurring during the months January to June inclusive of that year.
- (10) The licence-holder shall ensure that only inert material of natural origin, produced during construction drilling and seabed preparation for foundation works comprised in Work No. 1, and drilling mud shall be disposed of at disposal site reference HU206 (Hornsea Project One Subzone 1).
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.