The Gas and Electricity Markets Authority[^f00001], with the approval of the Secretary of State[^f00002], makes the following Regulations in exercise of the powers conferred by sections 6C, 6D and 60 of the Electricity Act 1989[^f00003].

PART 1 — INTRODUCTORY

Citation, commencement and revocation

1

Saving and transitional provisions

2

Interpretation

3

PART 2 — CALCULATION AND PAYMENT OF COSTS INCURRED IN CONNECTION WITH TRANSMISSION ASSETS FOR A GENERATOR BUILD TENDER EXERCISE

Calculation of costs incurred in connection with transmission assets

4

the Authority must, as soon as reasonably practicable, assess the economic and efficient costs which ought to have been incurred in connection with the development and construction of those transmission assets.

Payment of costs incurred by the Authority in connection with transmission assets calculation of costs

5

give notice to the successful bidder to make a payment to the Authority of an amount equal to the Authority’s costs in undertaking the assessment.

PART 3 — CALCULATION AND PAYMENT OF COSTS INCURRED IN RELATION TO AN OFTO BUILD TENDER EXERCISE

Calculation of costs incurred in connection with preliminary works and construction phase contracts

6

Payment of costs incurred by the Authority in connection with calculations relating to preliminary works and construction phase contracts

7

PART 4 — QUALIFYING PROJECTS AND DEVELOPER PAYMENTS AND SECURITY

Qualifying projects

8

Developer’s payment for early evaluation of construction phase contracts

9

whichever occurs earlier.

Developer’s payment and security to commence tender exercise

10

PART 5 — ENTRY CONDITIONS

Entry conditions in respect of qualifying projects

11

PART 6 — COMMENCEMENT OF A TENDER ROUND

Commencement of a tender round

12

the Authority must publish a notice of its intention to commence a tender round in respect of those determined qualifying projects specifying the date on which the tender round is to commence.

PART 7 — STAGES OF A TENDER ROUND

Stages of a tender round

13

PART 8 — PRE-QUALIFICATION STAGE

Pre-qualification

14

Determination of qualifying bidders at the pre-qualification stage

15

PART 9 — QUALIFICATION TO TENDER STAGE

Qualification to tender

16

Determination of qualifying bidders to be invited to participate in the invitation to tender stage

17

PART 10 — INVITATION TO TENDER STAGE

Invitation to tender

18

Determination of preferred bidders at the invitation to tender stage

19

PART 11 — BEST AND FINAL OFFER STAGE

Best and final offer

20

PART 12 — PREFERRED BIDDER STAGE

Notification of preferred bidder and reserve bidder

21

the Authority may withdraw the notice published in accordance with paragraph (1) by publishing a further notice to that effect.

Particular obligations of the developer from preferred bidder stage

22

In order to facilitate the making of the Authority’s determination of the successful bidder to whom an offshore transmission licence is to be granted in respect of a particular qualifying project in accordance with regulation 28(2), the developer must from the date of the notice given in accordance with regulation 21(6) use its reasonable endeavours to—

PART 13 — WITHDRAWAL

Withdrawal

23

PART 14 — RE-RUN, CANCELLATION AND TREATMENT OF PAYMENTS AND SECURITY ON CANCELLATION

Re-run, and re-run leading to cancellation

24

Cancellation

25

Treatment of payments and security on cancellation

26

the Authority must reimburse a qualifying bidder, preferred bidder or successful bidder that has neither withdrawn nor been disqualified so much of its bid costs that do not exceed the maximum amount stated in the notice.

PART 15 — DISQUALIFICATION FROM A TENDER EXERCISE OR TENDER ROUND

Disqualification

27

PART 16 — NOTIFICATION OF SUCCESSFUL BIDDER

Notification of successful bidder

28

Information in respect of successful bidder

29

the Authority must reimburse a qualifying bidder who has received a notice in accordance with paragraph (1) so much of the bidder’s bid costs that do not exceed the maximum amount stated in the notice.

PART 17 — COST RECOVERY

Recovery of tender costs

30

so as to ensure that the Authority’s total tender costs have not been exceeded.

PART 18 — MISCELLANEOUS

Failure to make payments or provide security

31

Application for a decision by the Authority

32

Changes to bidder groups

33

Changes to delivery of documents or actions

34

Disapplication of certain provisions

35

SCHEDULE 1 — QUALIFYING PROJECTS

1

The requirements in this paragraph are that the developer has—

2

The requirements in this paragraph are that the developer has—

3

Where the Authority considers that the developer has not met a requirement in paragraph 1(a) or (d) or paragraph 2(c) or (d), it may deem a project to be a qualifying project with respect to the requirement, provided the developer gives an undertaking to meet the requirement within a period notified by the Authority to the developer.

SCHEDULE 2 — ENTRY CONDITIONS

1

The conditions in this paragraph are that the developer has—

2

The conditions in this paragraph are that the developer has—

SCHEDULE 3 — PRE-QUALIFICATION

1

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 4 — QUALIFICATION TO TENDER

1

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 5 — INVITATION TO TENDER

1

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 6 — BEST AND FINAL OFFER

1

The information specified in this Schedule in relation to a particular tender exercise is as follows—

SCHEDULE 7 — EVENTS OF RE-RUN

1

The events in this Schedule are—

SCHEDULE 8 — EVENTS OF CANCELLATION

1

The events in this Schedule are—

SCHEDULE 9 — EVENTS OF DISQUALIFICATION

1

The events in this Schedule in relation to a developer, bidder, qualifying bidder, preferred bidder, reserve bidder or successful bidder, as the case may be, are—

2

The events in this Schedule in relation to a developer are—

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.