The Hornsea Two Offshore Wind Farm Order 2016

Type Statutory-Instrument
Publication 2016-08-16
Last updated 2018-05-08
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (2) Not more than 14 days after completion of the construction of the specified works, the promoting party must give the approving party written notice of such completion.

5

  • (1) Following receipt of the notification of the intention to commence the construction of the specified works under paragraph 4(1), the approving party must within 14 days give notice in writing to the promoting party that (acting reasonably)—
  • (a) it approves the plans; or
  • (b) it does not approve the plans and provide reasons for this.
  • (2) Where the approving party confirms that it does not approve the plans for the specified works, then both parties must, acting reasonably, enter into negotiations to seek to agree the plans.
  • (3) If following the expiry of 14 days from the date of notification under sub-paragraph (1)(b) no agreement has been reached, the matter must be determined in accordance with paragraph 22.

6

  • (1) Any specified works must be constructed—
  • (a) without unreasonable delay in accordance with the plans approved or settled under this Part; and
  • (b) to the reasonable satisfaction of the approving party.
  • (2) If any part of the specified works is constructed otherwise than in accordance with the requirements of this Part, the approving party may by notice in writing require the promoting party at the promoting party’s own expense to comply with the requirements of this Part or (if the promoting party so elects and the approving party in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the works and, where removal is required, to restore the site to its former condition to such extent and within such limits as the approving party reasonably requires.
  • (3) Subject to sub-paragraph (4), if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (2) is served on the promoting party, the promoting party has failed to begin taking steps to comply with the requirements of the notice and subsequently to make reasonably expeditious progress towards their implementation, the approving party may execute the works specified in the notice and any expenditure incurred by it in so doing is recoverable from the promoting party.
  • (4) In the event of any dispute as to whether sub-paragraph (2) is properly applicable to any works in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the approving party must not except in an emergency exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined.

7

The promoting party must at all reasonable times during construction of the specified works and thereafter allow the approving party, its servants and agents, access to the works and all reasonable facilities for inspection of the works.

8

  • (1) After the purpose of any temporary works has been accomplished, the promoting party must with all reasonable dispatch, or after a reasonable period of notice in writing from the approving party requiring the promoting party to do so, remove the temporary works or any materials relating to them which may have been placed in, on, under or over the grid connection land by or on behalf of the promoting party.
  • (2) If the promoting party fails to do so within a reasonable period after receiving notice under sub-paragraph (1), the approving party may remove them and may recover the reasonable costs of doing so from the promoting party.

9

  • (1) If any damage to the grid connection land or any apparatus of any approving party on the grid connection land or any interference or obstruction is caused by the carrying out of, or in consequence of the construction of specified works, the promoting party must, notwithstanding any approval, make good the damage to the reasonable satisfaction of the approving party and must pay to the approving party all reasonable expenses to which the approving party may be put and compensation for any loss which it may sustain by reason of the damage, interference or obstruction in accordance with paragraph 10.
  • (2) If the promoting party refuses or fails to do so, the approving party may cause the work to be done and may recover the reasonable cost of doing so from the promoting party.

10

  • (1) Without limiting the other provisions of this Part, the promoting party is responsible for, and must make good to the approving party, all losses, costs, charges, damages and expenses however caused (including a reasonable and proper proportion of the overhead charges of the approving party) that may reasonably be incurred by or occasioned to the approving party by reason of or arising from or in connection with—
  • (a) the perusal of plans and the inspection of the specified works by the approving party or its duly authorised representative;
  • (b) the construction or failure of the specified works, or the undertaking by the approving party of works or measures to prevent or remedy damage to any property of the approving party arising from such construction or failure;
  • (c) any act or omission of the promoting party or its servants or agents whilst engaged in the construction of any of the specified works.
  • (2) The approving party must give to the promoting party notice in writing of any claim or demand for which the promoting party may be liable under this paragraph, and no settlement or compromise of any such claim or demand may be made without the consent in writing of the promoting party.
  • (3) Nothing in this paragraph imposes any liability on the promoting party to the extent that any losses, costs, charges, damages, expenses, claims or demands referred to in sub-paragraph (1) are attributable to negligence on the part of the approving party or of any person in its employ or of its contractors or agents.

11

The fact that any work or thing has been executed or done with the consent of the approving party and in accordance with any conditions or restrictions prescribed by the approving party or in accordance with any plans approved by the approving party or to its satisfaction or in accordance with any directions or award of any arbitrator does not relieve the promoting party from any liability under this Part.

12

Any consent or approval of an approving party required under this Part—

  • (a) must not be unreasonably withheld or delayed; and
  • (b) may be given subject to reasonable conditions.

13

Any consent or approval of an approving party required under this Part is deemed to have been given if it is neither given nor refused within 28 days beginning with the date on which the application for consent or approval was submitted to the approving party.

14

Without limiting paragraph 12, it is not be reasonable for an approving party to withhold or delay any consent or approval under this Part in relation to specified works in, on, under, or over the grid connection land solely on the basis of thermal interaction between the circuit and any adjacent circuit, whether existing or proposed, where it has been demonstrated that there will be no material thermal interaction, which is deemed to have been demonstrated where the separation between the circuits is 6 metres or more (from the centre line of each circuit).

15

Without limiting paragraph 12, and in addition to the circumstances described in paragraph 14, it is not reasonable for the approving party to withhold or delay any consent or approval under this Part in relation to specified works in, on, under, or over the crossing zones solely on the basis of thermal interaction where the plans of the specified works submitted under paragraph 4 demonstrate that all reasonable steps have been taken to minimise thermal interaction between the circuit and any other circuit, whether existing or proposed.

16

With the exception of any duty owed by the approving party to the promoting party expressly provided for in the foregoing provisions of this Part, nothing in this Order must be construed as imposing on the approving party, either directly or indirectly, any form of duty or liability to which the approving party would not otherwise be subject which is enforceable by proceedings before any court.

17

Except as this Part provides, nothing in this Order affects prejudicially any statutory or other rights, powers or privileges vested in, or enjoyed by, the approving party at the commencement of this Order or any title of the approving party in, to or over any lands held or acquired by it.

18

In the event that the promoting party requires to alter the course of, modify, or remove any part of the drainage ditch the alteration, modification or removal works must be approved in writing by the approving party before the works are carried out, and such approval may not be unreasonably withheld or delayed but may be given subject to reasonable conditions.

19

The undertaker must ensure that the rate or volume of water discharged from the dominant land onto, over, across or through the servient land will not result in a significant increase in the exercise of the rights of the easement enjoyed by the dominant land on, over, across and through the servient land other than with the prior written approval of C.GEN.

20

The undertaker must not exercise the powers conferred by article 18 (compulsory acquisition of land) or article 19 (compulsory acquisition of rights) in respect of the Order land shown numbered 510 on the land plans to extinguish any rights that C.GEN has to connect into the North Killingholme National Grid substation.

21

The provisions of this Part enure for the benefit of the undertaker, C.GEN and any statutory successor of either that is licensed under section 6 of the 1989 Act and is in occupation or use of the Hornsea Project Substation Site, the grid connection land or any part of it pursuant to its undertaking.

22

Any dispute or difference arising between Optimus Wind, Breesea or any other party having powers under this Order in respect of the Order land shown numbered 503, 505, 506, 507 or 509 on the land plans by virtue of article 35 (transfer of benefit of Order) on the one hand (the “undertaker”) and C.GEN on the other as to their respective rights, duties and obligations under this Part or as to any matters arising out of it or in connection with the subject matter of this Part must be determined by a single arbitrator whose appointment is to be agreed on between the undertaker and C.GEN or, where agreement cannot be reached within 14 days, who is to be appointed on the application of either party (after notice in writing to the other party) by the President or Deputy President of the Royal Institute of Chartered Arbitrators.

PART 12 — Protection for Hornsea One companies

1

The provisions of this Part apply for the protection of the Hornsea One companies unless otherwise agreed in writing between the undertaker and the Hornsea One companies.

2

In this Part—

  • “apparatus” means the cables, structures or other infrastructure owned, occupied or maintained by any Hornsea One company or its successor in title, including any offshore transmission owner, within the Hornsea One Order land;
  • “construction” includes execution, placing, altering, replacing, reconstruction, relaying, maintenance, extensions, enlargement and removal; and “construct” and “constructed” must be construed accordingly;
  • “Hornsea One” means the wind farms to be constructed pursuant to the Hornsea One Order including, whether pursuant to the Hornsea One Order or otherwise, all elements of the connection of the wind farms to the National Grid at North Killingholme substation;
  • “Hornsea One company” means an undertaker with the benefit of all or part of the Hornsea One Order for the time being, being the holder of a licence under section 6 of the 1989 Act; and “Hornsea One companies” means all such undertakers;
  • “Hornsea One disposal areas” means disposal site reference HU209 and HU210 whose co-ordinates are specified in the deemed marine licence in Schedule 11 to the Hornsea One Order;
  • “Hornsea One Order” means the Hornsea One Offshore Wind Farm Order 2014;
  • “Hornsea One Order land” means the land within the Order limits defined in the Hornsea One Order together with the land edged red on plan HOW01095_4 submitted to support planning application reference PA/2015/0398 submitted to North Lincolnshire Council;
  • “plans” includes sections, drawings, specifications, designs, design data, software, soil reports, calculations, descriptions (including descriptions of methods of construction), staging proposals, programmes and details of the extent, timing and duration of any proposed occupation of the Hornsea One Order land;
  • “proposed Hornsea One circuit route” means the proposed route for any electrical circuit to serve Hornsea One as shown on plans produced to the undertaker by the relevant Hornsea One company pursuant to paragraph 16;
  • “relevant Hornsea One company” means the Hornsea One company whose undertaking includes the part of Hornsea One or the part of the Hornsea One Order land affected by the particular proposals of the undertaker;
  • “specified works” means so much of any works or operations authorised by this Order (or authorised by any planning permission or marine licence intended to operate in conjunction with this Order) as is— in, on, under, over or within 500 metres of a proposed Hornsea One circuit route or existing installed electrical circuit (seaward of MHWS); in, on, under, over or within 25 metres of a proposed Hornsea One circuit route or existing installed electrical circuit (landward of MHWS); or in, on, under, over or within 1,000 metres of other apparatus installed or to be installed as part of Hornsea One.

3

The consent of a Hornsea One company under this Part is not required where the Hornsea One Order has expired without the authorised development having been commenced pursuant to requirement 1 of Part 3 of Schedule 1 to the Hornsea One Order or the project has been abandoned.

4

Where conditions are included in any consent granted by a Hornsea One company pursuant to this Part, the undertaker must comply with the conditions if it chooses to implement or rely on the consent, unless the conditions are waived or varied in writing by the relevant Hornsea One company.

5

It is reasonable for the relevant Hornsea One company to require as a condition of granting consent under this Part that the undertaker enter into a cable proximity agreement on reasonable terms reflecting industry good practice if the undertaker proposes to install an electrical circuit at any point closer than 500 metres to the centre line of any electrical circuit installed to serve Hornsea One or is to cross a proposed Hornsea One circuit route.

6

The undertaker must not under the powers of this Order—

  • (a) acquire any of the Hornsea One Order land or acquire new or existing rights or interfere with existing rights or impose restrictive covenants or acquire any rights of temporary use over or in relation to the Hornsea One Order land without the consent of the relevant Hornsea One company, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions;
  • (b) carry out any specified works without the consent of the relevant Hornsea One company, which must not be unreasonably withheld or delayed but which may be made subject to reasonable conditions.

7

  • (1) Subject to obtaining consent pursuant to paragraph 6(b) and before beginning to construct any specified works, the undertaker must submit plans of the specified works to the relevant Hornsea One company and must submit such further particulars available to it that the relevant Hornsea One company may reasonably require.
  • (2) Any specified works must be constructed without unreasonable delay in accordance with the plans approved in writing by the relevant Hornsea One company.
  • (3) Any approval of the relevant Hornsea One company required under this paragraph may be made subject to such reasonable conditions as it may make for the protection of the Hornsea One Order Land, the apparatus and apparatus for Hornsea One not yet installed.
  • (4) If any part of the specified works is constructed otherwise than in accordance with the requirements of this Part, the relevant Hornsea One company may by notice in writing require the undertaker at the undertaker’s own expense to comply with the requirements of this Part.

8

The undertaker must give to the relevant Hornsea One company not less than 28 days’ written notice of its intention to commence the construction of the specified works and, not more than 28 days after completion of their construction, must give the relevant Hornsea One company written notice of the completion.

9

The undertaker must at all reasonable times during construction of the specified works and thereafter allow the relevant Hornsea One company and its servants and agents access to the works and all reasonable facilities for inspection of the works.

10

After the purpose of any temporary works has been accomplished, the undertaker must with all reasonable dispatch, or after a reasonable period of notice in writing from the relevant Hornsea One company requiring the undertaker so to do, remove the temporary works or any materials relating to them that may have been placed by or on behalf of the undertaker—

  • (a) in, on, under, over, or within 500 metres of a proposed Hornsea One circuit route or existing installed electrical circuit (seaward of MHWS); or
  • (b) in, on, under, over, or within 25 metres of a proposed Hornsea One circuit route or existing installed electrical circuit (landward of MHWS).

11

With the exception of any duty owed by the relevant Hornsea One company to the undertaker expressly provided for in the foregoing provisions of this Part, nothing in this Order must be construed as imposing on the relevant Hornsea One company, either directly or indirectly, any form of duty or liability to which the relevant Hornsea One company would not otherwise be subject which is enforceable by proceedings before any court.

12

The undertaker must consult the relevant Hornsea One company in relation to any draft disposal plan which proposes to deposit material within the Hornsea One disposal areas and must make such amendments as are reasonably requested by the relevant Hornsea One company before submission to the MMO for approval.

13

Subject to complying with all relevant health and safety considerations, the undertaker must permit representatives of the relevant Hornsea One company on any vessel carrying out dredging or disposal activities related to the Hornsea One disposal areas to monitor and verify the dredging and disposal carried out in terms of location, method, timing, quantity, nature of materials and other relevant matters.

14

The undertaker must give reasonable notice in writing to the relevant Hornsea One company of the intended departure of all vessels referred to in paragraph 13 together with written information concerning the proposed dredging and disposal activities and must comply with all reasonable requests from the relevant Hornsea One company to enable the verification referred to in that paragraph to be carried out effectively and efficiently.

15

The undertaker must provide to the relevant Hornsea One company a copy of each disposal return required to be submitted to the MMO pursuant to the approved disposal plan under this Order relevant to the Hornsea One disposal areas, such returns to include, without limitation, the actual volumes of materials disposed of, the disposal locations, the approved monitoring plan and the results of monitoring conducted.

16

To ensure its compliance with this Part, the undertaker must before carrying out any works or operations pursuant to this Order request up-to-date written confirmation from the relevant Hornsea One company of the precise route of any existing installed apparatus and any proposed Hornsea One circuit route or other apparatus to be installed by the relevant Hornsea One company.

17

The undertaker and the Hornsea One companies must each act in good faith and use reasonable endeavours to co-operate with, and provide assistance to, each other as may be required to give effect to the provisions of this Part.

18

Any dispute arising between the undertaker and the relevant Hornsea One company under this Part must be determined by arbitration under article 41 (arbitration).

SCHEDULE 13 — Documents to be certified

1

The land plans listed below—

PINS Document No. Description of Plan Report No. Version
4.1 Land plans: key plan UK06-060700-DRW-0001 2
4.1 Land plans: offshore plans – page 1 UK06-060700-DRW-0001 2
4.1 Land plans: offshore plans – page 2 UK06-060700-DRW-0001 1
4.1 Land plans: offshore plans – page 3 UK06-060700-DRW-0001 1
4.1 Land plans: intertidal plans – page 1 UK06-060700-DRW-0001 1
4.1 Land plans: intertidal plans – page 2 UK06-060700-DRW-0001 1
4.1 Land plans: intertidal plans – page 3 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 1 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 2 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 3 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 4 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 5 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 6 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 7 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 8 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 9 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 10 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 11 UK06-060700-DRW-0001 2
4.1 Land plans: onshore plans – page 12 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 13 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 14 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 15 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 16 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 17 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 18 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 19 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 20 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 21 UK06-060700-DRW-0001 2
4.1 Land plans: onshore plans – page 22 UK06-060700-DRW-0001 2
4.1 Land plans: onshore plans – page 23 UK06-060700-DRW-0001 2
4.1 Land plans: onshore plans – page 24 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 25 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 26 UK06-060700-DRW-0001 1
4.1 Land plans: onshore plans – page 27 UK06-060700-DRW-0001 2
4.1 Land plans: inset plans – page 1 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 2 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 3 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 4 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 5 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 6 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 7 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 8 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 9 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 10 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 11 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 12 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 13 UK06-060700-DRW-0001 2
4.1 Land plans: inset plans – page 14 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 15 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 16 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 17 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 18 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 19 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 20 UK06-060700-DRW-0001 2
4.1 Land plans: inset plans – page 21 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 22 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 23 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 24 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 25 UK06-060700-DRW-0001 1
4.1 Land plans: inset plans – page 26 UK06-060700-DRW-0001 1

2

The offshore works plans listed below—

PINS Document No. Description of Plan Report No. Version
5.1 Works plans: master index sheets UK06-060700-DRW-0003 3
5.1 Offshore works plans: map index sheet UK06-060700-DRW-0002 3
5.1 Offshore works plans – sheet 1 UK06-060700-DRW-0002 3
5.1 Offshore works plans – sheet 2 UK06-060700-DRW-0002 3
5.1 Offshore works plans – sheet 3 UK06-060700-DRW-0002 2
5.1 Offshore works plans – sheet 4 UK06-060700-DRW-0002 2
5.1 List of co-ordinates for offshore works and disposal areas – pages i to xi UK06-060700-DRW-0002 2

3

The intertidal works plans listed below—

PINS Document No. Description of Plan Report No. Version
5.3 Works plans: master index sheets UK06-060700-DRW-0003 3
5.3 Intertidal works plans: map index sheet UK06-060700-DRW-0004 1
5.3 Intertidal works plans – sheet 1 UK06-060700-DRW-0004 1
5.3 Intertidal works plans – sheet 2 UK06-060700-DRW-0004 1
5.3 Intertidal works plans – sheet 3 UK06-060700-DRW-0004 1
5.3 Intertidal works plans – sheet 4 UK06-060700-DRW-0004 1
5.3 List of co-ordinates for intertidal works UK06-060700-DRW-0004 1

4

The onshore works plans listed below—

PINS Document No. Description of Plan Report No. Version
5.2 Works plans: master index sheets UK06-060700-DRW-0003 3
5.2 Onshore works plans: map index sheet UK06-060700-DRW-0003 2
5.2 Onshore works plans – sheet 1 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 2 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 3 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 4 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 5 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 6 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 7 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 8 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 9 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 10 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 11 UK06-060700-DRW-0003 2
5.2 Onshore works plans – sheet 12 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 13 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 14 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 15 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 16 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 17 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 18 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 19 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 20 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 21 UK06-060700-DRW-0003 2
5.2 Onshore works plans – sheet 22 UK06-060700-DRW-0003 2
5.2 Onshore works plans – sheet 23 UK06-060700-DRW-0003 2
5.2 Onshore works plans – sheet 24 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 25 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 26 UK06-060700-DRW-0003 1
5.2 Onshore works plans – sheet 27 UK06-060700-DRW-0003 2
5.2 List of co-ordinates for onshore works – pages i to iv UK06-060700-DRW-0003 2

5

The compensation compounds plan listed below—

PINS Document No. Description of Plan Report No. Version
7.4.5.6 Compensation compounds plan – sheet 1 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 2 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 3 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 4 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 5 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 6 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 7 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 8 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 9 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 10 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 11 UK06-050709-DRW-0001 2
7.4.5.6 Compensation compounds plan – sheet 12 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 13 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 14 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 15 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 16 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 17 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 18 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 19 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 20 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 21 UK06-050709-DRW-0001 2
7.4.5.6 Compensation compounds plan – sheet 22 UK06-050709-DRW-0001 2
7.4.5.6 Compensation compounds plan – sheet 23 UK06-050709-DRW-0001 2
7.4.5.6 Compensation compounds plan – sheet 24 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 25 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 26 UK06-050709-DRW-0001 1
7.4.5.6 Compensation compounds plan – sheet 27 UK06-050709-DRW-0001 1

6

The environmental statement that accompanied the application.

7

The book of reference dated December 2015 (version 4).

8

The outline code of construction practice dated January 2015.

9

The outline ecological management plan dated November 2015 (version 2).

10

The outline landscape scheme and management plan dated January 2015.

11

The outline employment and skills plan dated November 2015 (referred to as the “Outline Supply Chain and Skills Plan”).

12

The in-principle monitoring plan dated November 2015 (version 2).

13

The C.GEN protective provisions plan submitted on 24th September 2015 (referred to as the “Hornsea Protective Provisions Plan”).

14

Plan HOW01095_4 submitted to North Lincolnshire Council to support planning application reference PA/2015/0398 (referred to in paragraph 2 of Part 12 of Schedule 12).

Signed

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Giles Scott — Head of Energy Infrastructure Planning and Coal Liabilities — Department for Business, Energy and Industrial Strategy — 16th August 2016

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order grants development consent for, and authorises the construction, operation and maintenance of up to 2 offshore wind farms with a combined capacity of up to 1,800 megawatts in the North Sea approximately 89 kilometres off the coast of Yorkshire together with associated development. This Order imposes requirements in connection with the development and authorises the compulsory purchase of land (including rights in land) and the right to use land and to override easements and other rights.

This Order also grants deemed marine licences under Part 4 of the Marine and Coastal Access Act 2009 in connection with the wind farms. The marine licences impose conditions in connection with the deposits and works for which they grant consent.

A copy of the plans and book of reference referred to in this Order and certified in accordance with article 40 (certification of plans, etc.) may be inspected free of charge at the offices of Dong Energy at 5 Howick Place, London SW1P 1WG.

Footnotes

[^f00001]: 2008 c.29. Section 37 was amended by section 137(5) of, and paragraph 5 of Schedule 13 to, the Localism Act 2011 (c.20). Section 74(2) was amended by paragraph 29(2) of that Schedule. Section 104(2) was amended by paragraph 49 of that Schedule and section 58 of the Marine and Coastal Access Act 2009 (c.23). Section 114 was amended by paragraph 55 of Schedule 13 to the Localism Act 2011. Section 120 was amended by section 140 of, and paragraph 60 of Schedule 13 to, that Act.

[^f00002]: S.I. 2009/2263. Regulation 3 was amended by S.I. 2012/635 and 2012/787.

[^f00003]: 1961 c.33.

[^f00004]: 1965 c.56.

[^f00005]: 1980 c.66.

[^f00006]: 1981 c.66.

[^f00007]: 1989 c.29.

[^f00008]: 1990 c.8.

[^f00009]: 1991 c.22.

[^f00010]: 2003 c.21.

[^f00011]: 2004 c.20.

[^f00012]: 2009 c.23.

[^f00013]: The registered office of Breesea Limited is 5 Howick Place, London SW1P 1WG.

[^f00014]: “Highway” is defined in section 328(1). For “highway authority”, see section 1.

[^f00015]: S.I. 2014/3331, amended by S.I. 2015/1280 and 2016/471.

[^f00016]: The registered office of Heron Wind Limited is 5 Howick Place, London SW1P 1WG.

[^f00017]: 1991 c.57. “Main river” is defined in section 113(1). The definition was amended by section 59(3) of the Water Act 2014 (c.21).

[^f00018]: The registered office of Optimus Wind Limited is 5 Howick Place, London SW1P 1WG.

[^f00019]: Section 48 was amended by section 124(2) of the Local Transport Act 2008 (c.26).

[^f00020]: “Street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c.7).

[^f00022]: Paragraph 5 was amended by section 100 of the Natural Environment and Rural Communities Act 2006 (c.16), section 84(2) of, and paragraph 3 of Schedule 11 to, the Marine and Coastal Access Act 2009, paragraph 49 of Schedule 2 to the Flood and Water Management Act 2010 (c.29) and paragraph 315 of Schedule 2 to S.I. 2013/755. Paragraph 6 was amended by paragraph 26 of Schedule 15 to the Environment Act 1995 (c.25) and section 224 of, and paragraph 24 of Schedule 16 and Part 5 of Schedule 22 to, the Marine and Coastal Access Act 2009. Paragraph 6A was inserted by section 103(3) of the Environment Act 1995.

[^f00023]: 1991 c.59. Section 23 was amended by paragraph 192 of Schedule 22 to the Environment Act 1995, paragraph 32 of Schedule 2 to the Flood and Water Management Act 2010 and S.I. 2013/755. Section 66 was amended by paragraph 38 of Schedule 2 to the Flood and Water Management Act 2010 and by section 86(3) of the Water Act 2014.

[^f00024]: 15 and 16 Vict. c. cxxx.

[^f00025]: 62 and 63 Vict. c. cci.

[^f00026]: 5 Edw. 7 c. clxxix.

[^f00027]: 1990 c.43. Section 82(1) was amended by paragraph 6 of Schedule 17 to the Environment Act 1995. Section 82(2) was amended by section 5(2) of the Noise and Statutory Nuisance Act 1993 (c.40) and paragraph 6 of Schedule 17 to the Environment Act 1995.

[^f00028]: 1974 c.40. Section 61 was amended by Schedule 7 to the Building Act 1984 (c.55), paragraph 15 of Schedule 15 to the Environmental Protection Act 1990 and Schedule 24 to the Environment Act 1995.

[^f00029]: “Apparatus” is defined in sections 89(3) and 105(1).

[^f00030]: Sections 54, 55, 57, 59, 60, 68 and 69 were amended by the Traffic Management Act 2004 (c.18).

[^f00031]: 1991 c.56. Section 106 was amended by section 35(8)(a) of the Competition and Service (Utilities) Act 1992 (c.43) and sections 36(2) and 99 of the Water Act 2003 (c.37). There are other amendments to this section which are not relevant to this Order.

[^f00032]: 1964 c.40.

[^f00033]: “Sewerage undertaker” is defined in Schedule 1 to the Interpretation Act 1978 (c.30).

[^f00034]: Section 152 was amended by S.I. 2009/1307.

[^f00035]: Section 4 is amended, from a date to be appointed, by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c.22).

[^f00036]: Section 11(1) was amended by paragraph 14 of Schedule 4 to the Acquisition of Land Act 1981 and paragraph 12 of Schedule 5 to the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No. 1).

[^f00037]: Section 138 was amended by section 23(4) of the Growth and Industry Act 2013 (c.27).

[^f00038]: Section 125 was amended by paragraph 17 of Schedule 16 to the Housing and Planning Act 2016.

[^f00039]: Section 13 was amended by section 139 of, and paragraph 28(2) of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c.15).

[^f00040]: “Public utility undertaker” is defined in section 329.

[^f00041]: S.I. 1997/1160.

[^f00042]: Section 78 was amended by section 43(2) of the Planning and Compulsory Purchase Act 2004 (c.5), paragraph 3(b) of Schedule 10 to the Planning Act 2008, section 123(3) of, and paragraph 11 of Schedule 12 to, the Localism Act 2011, paragraph 8 of Schedule 1 to the Growth and Infrastructure Act 2013, paragraph 12 of Schedule 4 to the Infrastructure Act 2015 and paragraph 21 of Schedule 12 to the Housing and Planning Act 2016. Section 79 was amended by section 18 of, and paragraph 19 of Schedule 7 to, the Planning and Compensation Act 1991 (c.34), paragraph 4 of Schedule 10 to the Planning Act 2008 and paragraph 23 of Schedule 12 to the Housing and Planning Act 2016.

[^f00043]: S.I. 2009/3015.

[^f00044]: See section 104(1).

[^f00045]: The document is available from:

[^f00046]: 1973 c.26.

[^f00047]: Section 13 was amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c.15) and by paragraph 28 of Schedule 13 and Part 3 of Schedule 23 to that Act.

[^f00048]: Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 (c.34) and paragraph 70 of Schedule 1 to S.I. 2009/1307.

[^f00049]: Section 108 was amended by section 69(5) of the Energy Act 2008.

[^f00050]: See https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/441130/371.pdf.

[^f00051]: S.I. 2002/1355, amended by S.I. 2011/982.

[^f00052]: S.I. 2007/1842, amended by S.I. 2009/7, 2010/491 and 2012/1928.

[^f00053]: See http://jncc.defra.gov.uk/default.aspx?page=7059.

[^f00054]: See section 72(1).

[^f00055]: 1993 c.43. Section 8 was amended by paragraph 4 of Schedule 17 and Part 4 of Schedule 31 to the Transport Act 2000 (c.38), paragraphs 3 and 5 of Schedule 2 to the Railways and Transport Safety Act 2003 (c.20), paragraph 3 of Schedule 1 and Part 1 of Schedule 13 to the Railways Act 2005 (c.14) and Part 1of Schedule 1 to S.I. 2015/1682.

[^f00056]: 2006 c.46.

[^f00057]: “Access agreement” is defined in section 83. The definition was amended by section 230 of the Transport Act 2000.

[^f00058]: Section 272 was amended by paragraph 103 of Schedule 17 to the Communications Act 2003.

[^f00059]: Paragraph 1(3A) was added to the code (Schedule 2 to the Telecommunications Act 1984) by paragraph 4 of Schedule 3 to the Communications Act 2003.

[^f00060]: “The electronic communications code” is defined in section 106(1).

[^f00061]: 1984 c.12.

[^f00062]: See section 64. The definition of “electrical plant” was amended by paragraph 38(3) of Schedule 6 to the Utilities Act 2000 (c.27).

[^f00063]: Section 51A was inserted by section 92(1) of the Water Act 2003.

[^f00064]: Section 102(4) was amended by section 96 of the Water Act 2003. Section 104 was amended by section 96 of, and Part 3 of Schedule 9 to, the Water Act 2003 and by section 42(3) of the Flood and Water Management Act 2010.

[^f00065]: 1986 c.44. “Gas transporter” is defined in section 7. A new section 7 was substituted by section 5 of the Gas Act 1995 (c.45) and was further amended by section 76 of the Utilities Act 2000.

[^f00066]: “Water undertaker” is defined in Schedule 1 to the Interpretation Act 1978.

[^f00067]: 1962 c.58. Section 65(2) was amended by paragraph 6 of Schedule 2 to the Energy Act 2011 (c.16) and S.I. 2000/1937 and 2011/2305.

Editorial notes

[^key-294d0f902f906a92dbf0449bdcc4ae2b]: Art. 1 in force at 7.9.2016, see art. 1(2)

[^key-7e3a6e773047340b15246183e054f9f9]: Art. 2 in force at 7.9.2016, see art. 1(2)

[^key-c9afc2f7a99ebc1a4625975e8e4600ee]: Art. 3 in force at 7.9.2016, see art. 1(2)

[^key-87e464948a2c5a5d370138f1dcdc0fae]: Art. 4 in force at 7.9.2016, see art. 1(2)

[^key-0041150e11e86c627d4b56a32c787aef]: Art. 5 in force at 7.9.2016, see art. 1(2)

[^key-f85ce51105243d40cabe4faf68ae370d]: Art. 6 in force at 7.9.2016, see art. 1(2)

[^key-7d67d33a3ce03344ff4aca983c1ea965]: Art. 7 in force at 7.9.2016, see art. 1(2)

[^key-c9377824c44063ff01579fbb9d511f82]: Art. 8 in force at 7.9.2016, see art. 1(2)

[^key-32136676eb101c7f475fa82cd50f8b95]: Art. 9 in force at 7.9.2016, see art. 1(2)

[^key-e51cbfd1b5b3c50c7ac9c3704309e8eb]: Art. 10 in force at 7.9.2016, see art. 1(2)

[^key-b69171f71e4cbca35089f53d6a7f14bd]: Art. 11 in force at 7.9.2016, see art. 1(2)

[^key-eaabaf3d71890f33bb489072b0dc6a17]: Art. 12 in force at 7.9.2016, see art. 1(2)

[^key-d5defee16b3c4d32f50adc2145651e22]: Art. 13 in force at 7.9.2016, see art. 1(2)

[^key-d1627df3a7d07f6c611e0b46d885f070]: Art. 14 in force at 7.9.2016, see art. 1(2)

[^key-3fda0e5206b77e3140b623ff71f51464]: Art. 15 in force at 7.9.2016, see art. 1(2)

[^key-d6ff001853b8ecc51f8c351f718642e5]: Art. 16 in force at 7.9.2016, see art. 1(2)

[^key-6e817017e6693936b24ac174bc9c1be4]: Art. 17 in force at 7.9.2016, see art. 1(2)

[^key-1b44fd4588453c9ae23702b2f2ca75a0]: Art. 18 in force at 7.9.2016, see art. 1(2)

[^key-5f25f9aa22e0b455f3f0e03530efea77]: Art. 19 in force at 7.9.2016, see art. 1(2)

[^key-0c1917121879f852f1e0683f124b7048]: Art. 20 in force at 7.9.2016, see art. 1(2)

[^key-ee00c22832df7ed6237e1a94e9aba4e8]: Art. 21 in force at 7.9.2016, see art. 1(2)

[^key-9f3a3691e3b2bf68d525922a2155aaf8]: Art. 22 in force at 7.9.2016, see art. 1(2)

[^key-a3f07826bee55390a80211c9dda6a45f]: Art. 23 in force at 7.9.2016, see art. 1(2)

[^key-f11dc6580f03591a24637d4754b70115]: Art. 24 in force at 7.9.2016, see art. 1(2)

[^key-572e31d6e2ed61430c13f4e5e6091894]: Art. 25 in force at 7.9.2016, see art. 1(2)

[^key-362103e2e15049975b96778482aa20d9]: Art. 26 in force at 7.9.2016, see art. 1(2)

[^key-9621461092a39518e06153cb615523ff]: Art. 27 in force at 7.9.2016, see art. 1(2)

[^key-392d04a0d20e7ecf1940f34d1fcae34f]: Art. 28 in force at 7.9.2016, see art. 1(2)

[^key-20ec5c01e796b1572ab240c5aa5ce25f]: Art. 29 in force at 7.9.2016, see art. 1(2)

[^key-3f63b32e642835fadc4d255f27dac1a4]: Art. 30 in force at 7.9.2016, see art. 1(2)

[^key-49a428d9fca8b36cb9853f46d1a80888]: Art. 31 in force at 7.9.2016, see art. 1(2)

[^key-bef17ae9761d2d0ef0f2f76f18804abb]: Art. 32 in force at 7.9.2016, see art. 1(2)

[^key-be00b9f7c5666c14c312d41b442bd3c3]: Art. 33 in force at 7.9.2016, see art. 1(2)

[^key-08855d09f0e99070eeb5ff4a8dea597e]: Art. 34 in force at 7.9.2016, see art. 1(2)

[^key-16b216f91ddcc2aca8dfd8e1e03f3014]: Art. 35 in force at 7.9.2016, see art. 1(2)

[^key-1dcca7687b1a31d8fbdbe2684a02d568]: Art. 36 in force at 7.9.2016, see art. 1(2)

[^key-35c3f5b99fd48e97addc9d05276bafd6]: Art. 37 in force at 7.9.2016, see art. 1(2)

[^key-f304e5ca4f080b90da69da58a45efb1a]: Art. 38 in force at 7.9.2016, see art. 1(2)

[^key-fc408f213bfdfa76754e8e60f58476fd]: Art. 39 in force at 7.9.2016, see art. 1(2)

[^key-c9e804f3c13ce8aaf9994a70370cf9cd]: Art. 40 in force at 7.9.2016, see art. 1(2)

[^key-d634bf618c005701ff570b045306dd5d]: Art. 41 in force at 7.9.2016, see art. 1(2)

[^key-a41973d1154a6651457a0a17f6489706]: Sch. 1 Pt. 1 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-2f5ce92f7cf6018a514b37067c85f79f]: Sch. 1 Pt. 1 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-7d77f945cd65c2f680350c9b1c8ac35a]: Sch. 1 Pt. 1 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-776927f1e8a7a30949671fa799fac338]: Sch. 1 Pt. 1 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-33aedc2ee05131e61cf2622e7609e469]: Sch. 1 Pt. 3 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-ce1e30a1d4b1b290be15277112d96e22]: Sch. 1 Pt. 3 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-01ea6aeacca36bedf2160826b08c4d79]: Sch. 1 Pt. 3 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-0955f419683a5f7e951ad9ba1b026338]: Sch. 1 Pt. 3 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-4555b11c42468efe3306cbc9e44ade89]: Sch. 1 para. 5 in force at 7.9.2016, see art. 1(2)

[^key-5d825722d1a40a10521898355bf021f6]: Sch. 1 para. 6 in force at 7.9.2016, see art. 1(2)

[^key-7073b44dccf47582ff6f27d6612b4e63]: Sch. 1 para. 7 in force at 7.9.2016, see art. 1(2)

[^key-3afc50b47f684641587b989b81da6851]: Sch. 1 para. 8 in force at 7.9.2016, see art. 1(2)

[^key-312da4f81e1e2e17d1d38be7f9c9add5]: Sch. 1 para. 9 in force at 7.9.2016, see art. 1(2)

[^key-489e3ac3daf278ed09acc6a5feee240e]: Sch. 1 para. 10 in force at 7.9.2016, see art. 1(2)

[^key-f034f0539ade0a73196818cd620bf132]: Sch. 1 para. 11 in force at 7.9.2016, see art. 1(2)

[^key-b09ab7924f1e2446bb6b9cd66eaa0d5f]: Sch. 1 para. 12 in force at 7.9.2016, see art. 1(2)

[^key-22ce8ab9483ea2f62ba87b278aa7a2e7]: Sch. 1 para. 13 in force at 7.9.2016, see art. 1(2)

[^key-36b16ff070403caf6eac5fe6bba13ff1]: Sch. 1 para. 14 in force at 7.9.2016, see art. 1(2)

[^key-2d29a3a9abea7966b4464f793ecdd511]: Sch. 1 para. 15 in force at 7.9.2016, see art. 1(2)

[^key-34419f5a4d23b9084528eafa82bfb182]: Sch. 1 para. 16 in force at 7.9.2016, see art. 1(2)

[^key-8d393b05beee12166d50236bf7e8c0dd]: Sch. 1 para. 17 in force at 7.9.2016, see art. 1(2)

[^key-82f5b895560b2e971e6b47042127ed0b]: Sch. 1 para. 18 in force at 7.9.2016, see art. 1(2)

[^key-fc02fd48e630e3f8ba7bc7adcb2a839c]: Sch. 1 para. 19 in force at 7.9.2016, see art. 1(2)

[^key-96b20e9c4fd6c8db536e50c71794fa38]: Sch. 1 para. 20 in force at 7.9.2016, see art. 1(2)

[^key-554bf9979ee182fc6a2f08f937de1a63]: Sch. 1 para. 21 in force at 7.9.2016, see art. 1(2)

[^key-5f8e86f04008d8a3cb53e723d8107c3e]: Sch. 1 para. 22 in force at 7.9.2016, see art. 1(2)

[^key-c21c0e317cbfdd9c6b093176525617c2]: Sch. 1 para. 23 in force at 7.9.2016, see art. 1(2)

[^key-9b4bb11c41d5ab3a5723b9ea7f1968ee]: Sch. 1 para. 24 in force at 7.9.2016, see art. 1(2)

[^key-cbc2a917117b1e0594e20a5cf2376215]: Sch. 1 para. 25 in force at 7.9.2016, see art. 1(2)

[^key-8a465c85cb4e745557d6c7f5eaef3f6b]: Sch. 1 para. 26 in force at 7.9.2016, see art. 1(2)

[^key-24545abb6e43a8b7d783092375e376bf]: Sch. 1 para. 27 in force at 7.9.2016, see art. 1(2)

[^key-caff279ed72021c6e0c6b1d0e37cdd6e]: Sch. 6 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-0e4130a1819e63c7ef87f46a29584dc9]: Sch. 6 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-7eb6fb647935ee036698ddc9cc47c6f2]: Sch. 6 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-c7cf255c5e9b52cf5eccdac1ced6948a]: Sch. 6 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-7d87652263efcb02878cef76ee409e4b]: Sch. 6 para. 5 in force at 7.9.2016, see art. 1(2)

[^key-61c496a8f96bae4f5630467daf2712b1]: Sch. 6 para. 6 in force at 7.9.2016, see art. 1(2)

[^key-c92eb52988afd8f1b69703a972c8cadf]: Sch. 6 para. 7 in force at 7.9.2016, see art. 1(2)

[^key-686df61c3b31aaa8ed4e2870ebfbd8b6]: Sch. 6 para. 8 in force at 7.9.2016, see art. 1(2)

[^key-4981e81e912212cdc8e0db64659a8e01]: Sch. 6 para. 9 in force at 7.9.2016, see art. 1(2)

[^key-30e9523d2987a77592886d8f76887e01]: Sch. 8 Pt. 1 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-1c1e3de89ecfd99441ba3f78d5502deb]: Sch. 8 Pt. 1 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-93c54b2536c682e73d9b654411c949cf]: Sch. 8 Pt. 1 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-50f72ff9ffaa0e353e13f11fcbe601e4]: Sch. 8 Pt. 1 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-0fc7bc43805f9df712e8f8be55880764]: Sch. 8 Pt. 2 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-daef4c2f5e33c28cefdf5713b7f866db]: Sch. 8 Pt. 2 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-e672d83adec26388608973604ca83474]: Sch. 8 Pt. 2 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-02c6bfe4e4af9b8f2d846207921372c9]: Sch. 8 Pt. 2 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-fc037b7eb87b41e825ad6fe88097a094]: Sch. 8 para. 5 in force at 7.9.2016, see art. 1(2)

[^key-d7f809dc2703f5f16341f14fb37815c4]: Sch. 8 para. 6 in force at 7.9.2016, see art. 1(2)

[^key-10beb6d1a107ad216382f20435f7b601]: Sch. 8 para. 7 in force at 7.9.2016, see art. 1(2)

[^key-ea5c73623428b2da21bd58f67eba013a]: Sch. 8 para. 8 in force at 7.9.2016, see art. 1(2)

[^key-6d6ea78c73fa1feead229e00580ddc9f]: Sch. 8 para. 9 in force at 7.9.2016, see art. 1(2)

[^key-37c861366b36dbe34371be08616de3f9]: Sch. 8 para. 10 in force at 7.9.2016, see art. 1(2)

[^key-6cb29501ef196356d5f7245fc7c9aeef]: Sch. 8 para. 11 in force at 7.9.2016, see art. 1(2)

[^key-c80bcc52388760a9c5be0c657a71f07d]: Sch. 8 para. 12 in force at 7.9.2016, see art. 1(2)

[^key-f8f18dfd8f9f526fcb21916e4a43a794]: Sch. 8 para. 13 in force at 7.9.2016, see art. 1(2)

[^key-2b9aee045db765cf8fa9b5be6b58c0a5]: Sch. 8 para. 14 in force at 7.9.2016, see art. 1(2)

[^key-390e8adac3daa702d32044e7a4b8ff95]: Sch. 8 para. 15 in force at 7.9.2016, see art. 1(2)

[^key-d6909717595051f1ca4139b12e0702fe]: Sch. 8 para. 16 in force at 7.9.2016, see art. 1(2)

[^key-3523bd1c61682989493d87c1df5350e2]: Sch. 8 para. 17 in force at 7.9.2016, see art. 1(2)

[^key-4529cfdd97ac80465f7060a786a4ec88]: Sch. 9 Pt. 1 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-70939e765287e209b3648e78dc2117a1]: Sch. 9 Pt. 1 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-65ddcec1c63005e0327277cf62c2abcc]: Sch. 9 Pt. 1 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-83791626ce4025c65a908bcc6e924ecd]: Sch. 9 Pt. 1 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-fb73dbc23933a7d80d45254f117f21c0]: Sch. 9 Pt. 2 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-5b10a5e71c1f127d772f4e7343cd9bdd]: Sch. 9 Pt. 2 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-face7bc5ae94e24679ddd7f5c5b08440]: Sch. 9 Pt. 2 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-15557d197f477f6af816a83aebaf2df3]: Sch. 9 Pt. 2 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-1bf335f3709f5bf53304305eac1d2422]: Sch. 9 para. 5 in force at 7.9.2016, see art. 1(2)

[^key-8e86c0d0dee5f902e96093592f742738]: Sch. 9 para. 6 in force at 7.9.2016, see art. 1(2)

[^key-8a9aebf1ddb9d63cc81b37e43e27dc4d]: Sch. 9 para. 7 in force at 7.9.2016, see art. 1(2)

[^key-c0e62ec3278aa704a60c4b4065ebb362]: Sch. 9 para. 8 in force at 7.9.2016, see art. 1(2)

[^key-df188a782ad33324a79dc5edbdab1f23]: Sch. 9 para. 9 in force at 7.9.2016, see art. 1(2)

[^key-9850d29f8ca3a8a5d3f5df856a3009c3]: Sch. 9 para. 10 in force at 7.9.2016, see art. 1(2)

[^key-8eb3770c790dbe80b2cc89eada3c0152]: Sch. 9 para. 11 in force at 7.9.2016, see art. 1(2)

[^key-0f53f466bf1abc4ae8cbb1ae43056c90]: Sch. 9 para. 12 in force at 7.9.2016, see art. 1(2)

[^key-9e06149be08cef42099600f9c00cd78e]: Sch. 9 para. 13 in force at 7.9.2016, see art. 1(2)

[^key-6e5d6e609265e843e12c92ed792a8740]: Sch. 9 para. 14 in force at 7.9.2016, see art. 1(2)

[^key-b326928ff2230b0b66edbab21c1d8deb]: Sch. 9 para. 15 in force at 7.9.2016, see art. 1(2)

[^key-18b36972c6283a960b6fee8b71a34810]: Sch. 9 para. 16 in force at 7.9.2016, see art. 1(2)

[^key-046774923bbe17b6e0c484f4226313e8]: Sch. 9 para. 17 in force at 7.9.2016, see art. 1(2)

[^key-2898c640f6c4012c4e934ff5a6de8a13]: Sch. 9 para. 18 in force at 7.9.2016, see art. 1(2)

[^key-10ffcf09785617d01e55d612227c1ecf]: Sch. 10 Pt. 1 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-ed762a125adefa72526ff9af22f8ff0a]: Sch. 10 Pt. 1 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-0751e31c8beca56207e6d0eef60ca391]: Sch. 10 Pt. 1 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-c01dfc8534af61f0fbc01a88fcf60eaf]: Sch. 10 Pt. 1 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-1dbf72791155881bb865bf428dddd8c8]: Sch. 10 Pt. 2 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-95bc9a3101f54ba07a458fa8d7add924]: Sch. 10 Pt. 2 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-88407c39f20487d8436459f583a1e883]: Sch. 10 Pt. 2 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-df9fa9eef680ca817ae9ccb3e0709068]: Sch. 10 Pt. 2 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-61637dc6fe34c868f18dea37b3ac99d6]: Sch. 10 para. 5 in force at 7.9.2016, see art. 1(2)

[^key-ca723db40b4acb5faf065115fbe4ce9e]: Sch. 10 para. 6 in force at 7.9.2016, see art. 1(2)

[^key-6a9c7be3edcc700b9cabd7c27cb2b9b0]: Sch. 10 para. 7 in force at 7.9.2016, see art. 1(2)

[^key-159709e3f60c2718dca1edacf7e19d4a]: Sch. 10 para. 8 in force at 7.9.2016, see art. 1(2)

[^key-d24cc3d95424bd8bf84b21e0ce4ed99a]: Sch. 10 para. 9 in force at 7.9.2016, see art. 1(2)

[^key-b197e3cf1809b8c5b8d28367877114bb]: Sch. 10 para. 10 in force at 7.9.2016, see art. 1(2)

[^key-6c81b6b496b63260b1486d908b880a31]: Sch. 10 para. 11 in force at 7.9.2016, see art. 1(2)

[^key-f4c79d71b632c7fc6e9c3a22e2526ac0]: Sch. 10 para. 12 in force at 7.9.2016, see art. 1(2)

[^key-6c56661f98385d3db91e6f126bd8d32d]: Sch. 10 para. 13 in force at 7.9.2016, see art. 1(2)

[^key-7ddd1931c91e5908ad38b33fea007098]: Sch. 10 para. 14 in force at 7.9.2016, see art. 1(2)

[^key-06e01586a9c079e6b0ed587b72d4677a]: Sch. 10 para. 15 in force at 7.9.2016, see art. 1(2)

[^key-00346a6d449f7c364df4d8880a85db53]: Sch. 10 para. 16 in force at 7.9.2016, see art. 1(2)

[^key-ae871299bc574283e919e3f4b54bccf6]: Sch. 10 para. 17 in force at 7.9.2016, see art. 1(2)

[^key-c403aae0e1902fbbbf4586f868b5696b]: Sch. 11 Pt. 1 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-870331e9b9e8ae675d4363db7ff1740d]: Sch. 11 Pt. 1 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-f3b2b57eb2efbd661323320472c0f49a]: Sch. 11 Pt. 1 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-3ecc34b11395b69b740f0cd4906e7094]: Sch. 11 Pt. 1 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-5dc5011d9628da7ff2c9397fa0108816]: Sch. 11 Pt. 2 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-7973208e205c49bf85d55ea90c6a54ee]: Sch. 11 Pt. 2 para. 2 in force at 7.9.2016, see art. 1(2)

[^key-80ee2ae0a8ddd3fb078befe63dadbb7a]: Sch. 11 Pt. 2 para. 3 in force at 7.9.2016, see art. 1(2)

[^key-c2485ef5ab14c577ab9ea97b9f2f4cf8]: Sch. 11 Pt. 2 para. 4 in force at 7.9.2016, see art. 1(2)

[^key-fdb257c9e22e421efe462f9d30917db2]: Sch. 11 para. 5 in force at 7.9.2016, see art. 1(2)

[^key-d2f6761b7b8717487bf3f04ed2eced35]: Sch. 11 para. 6 in force at 7.9.2016, see art. 1(2)

[^key-eb4b09021c7f9b5b20951e8448068ef0]: Sch. 11 para. 7 in force at 7.9.2016, see art. 1(2)

[^key-be7290390058f56259c8c5515d38365c]: Sch. 11 para. 8 in force at 7.9.2016, see art. 1(2)

[^key-7b31bdfd177d03b3f54da3aafc58a3ea]: Sch. 11 para. 9 in force at 7.9.2016, see art. 1(2)

[^key-6211be2b2ac2a9c8aaa3a9682aeb27ee]: Sch. 11 para. 10 in force at 7.9.2016, see art. 1(2)

[^key-c6c444c91b64334f7328c405e5a6439a]: Sch. 11 para. 11 in force at 7.9.2016, see art. 1(2)

[^key-1672e1339af60c9fb775192e8e898102]: Sch. 11 para. 12 in force at 7.9.2016, see art. 1(2)

[^key-8edf4412c63c8df9df38e3687da07eb3]: Sch. 11 para. 13 in force at 7.9.2016, see art. 1(2)

[^key-31490b332a8cfde52730ef34007ea6d0]: Sch. 11 para. 14 in force at 7.9.2016, see art. 1(2)

[^key-4ed58103c08d5df77cdeba5855318b3b]: Sch. 11 para. 15 in force at 7.9.2016, see art. 1(2)

[^key-c7340662a12947b80568030e61b20988]: Sch. 11 para. 16 in force at 7.9.2016, see art. 1(2)

[^key-b1b2a6acbe978e8dd5dfe5b8942600d2]: Sch. 11 para. 17 in force at 7.9.2016, see art. 1(2)

[^key-ae2d5bdde28f4e4cc2221e3cdce02c9a]: Sch. 11 para. 18 in force at 7.9.2016, see art. 1(2)

[^key-cfa0635572b6038214f12ea9a3d6e429]: Sch. 12 Pt. 1 para. 1 in force at 7.9.2016, see art. 1(2)

[^key-3e4846b39efb8d708af291d025566980]: Sch. 12 Pt. 1 para. 2 in force at 7.9.2016, see art. 1(2)

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.