The River Humber Gas Pipeline Replacement Order 2016

Type Statutory-Instrument
Publication 2016-08-25
Last updated 2017-11-30
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API
  • (4) The Agency must use its reasonable endeavours to respond to the submission of any plans before the expiration of the period mentioned in sub-paragraph (3)(b).

3

Without limiting the scope of paragraph 17, the requirements which the Agency may make under that paragraph include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, during the construction of the specified works (including the provision of flood banks, walls or embankments or other new works and the strengthening, repair or renewal of existing banks, walls or embankments) as are reasonably necessary—

  • (a) to safeguard any drainage work against damage; or
  • (b) to secure that its efficiency for flood defence purposes is not impaired and that the risk of flooding is not otherwise increased,

by reason of any specified work.

4

  • (1) Subject to sub-paragraph (2), any specified work, and all protective works required by the Agency under paragraph 3, must be constructed—
  • (a) without unreasonable delay in accordance with the plans approved or deemed to have been approved or settled under this Part of this Schedule; and
  • (b) to the reasonable satisfaction of the Agency,

and an officer of the Agency is entitled to watch and inspect the construction of such works.

  • (2) The undertaker must give to the Agency not less than 14 days’ notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than seven days after the date on which it is brought into use.
  • (3) If the Agency shall reasonably require, the undertaker shall construct all or part of the protective works so that they are in place prior to the construction of specific works.
  • (4) If any part of a specified work or any protective work required by the Agency is constructed otherwise than in accordance with the requirements of this Part of this Schedule, the Agency may by notice in writing require the undertaker at the undertaker’s own expense to comply with the requirements of this Part of this Schedule or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent and within such limits as the Agency reasonably requires.
  • (5) Subject to sub-paragraph (6), if within a reasonable period, except in emergency, being not less than 28 days from the date when a notice under sub-paragraph (4) is served upon the undertaker, it has failed to begin taking steps to comply with the requirements of the notice and subsequently to make reasonably expeditious progress towards their implementation, the Agency may execute the works specified in the notice and any expenditure incurred by it in so doing is recoverable from the undertaker.
  • (6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Agency must not except in emergency exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined.

5

  • (1) Subject to sub-paragraph (5) the undertaker must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation on land held by the undertaker for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
  • (2) If any such drainage work which the relevant undertaker is liable to maintain is not maintained to the reasonable satisfaction of the Agency, the Agency may by notice in writing require the undertaker to repair and restore the work, or any part of such work, or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work and restore the site to its former condition, to such extent and within such limits as the Agency reasonably requires.
  • (3) If, within a reasonable period, except in emergency, being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from the undertaker.
  • (4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (2), the Agency must not except in a case of emergency exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined.
  • (5) This paragraph does not apply to drainage works which are vested in the Agency, or which the Agency or another person is liable to maintain and is not prescribed by the powers of the Order from doing so.

6

If by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or that drainage work is otherwise damaged, such impairment or damage must be made good by the undertaker to the reasonable satisfaction of the Agency and if the undertaker fails to do so, the Agency may make good the impairment or damage and recover from the undertaker the expense reasonably incurred by it in doing so.

7

  • (1) The undertaker must indemnify the Agency in respect of all costs, charges and expenses which the Agency may reasonably incur or have to pay or which it may sustain—
  • (a) in the examination or approval of plans under this Part of this Schedule;
  • (b) in the inspection of the construction of the specified works or any protective works required by the Agency under this Part of this Schedule; and
  • (c) the carrying out of any surveys or tests by the Agency which are reasonably required in connection with the construction of the specified works.
  • (2) Without prejudice to the other provisions of this Part, the undertaker must indemnify the Agency from all claims, proceedings, costs, damages, expenses or loss which may be made or taken against, recovered from, or incurred by, the Agency by reason of the construction of any of the specified works or any act or omission of the undertaker, its contractors, agents or employees whilst engaged upon the work.
  • (3) The undertaker shall not be liable under paragraph (2) to the limited extent that the liability is a result of negligence on the part of the Agency or its duly authorised representative, employee, contractor or agent.
  • (4) The Agency must give to the undertaker reasonable notice of any such claim or demand and no settlement or compromise may be made without the agreement of the undertaker which agreement must not be unreasonably withheld or delayed.

8

The fact that any work or thing has been executed or done by the undertaker in accordance with a plan approved or deemed to be approved by the Agency, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the undertaker from any liability under the provisions of this Part of this Schedule.

9

  • (1) The undertaker will not in the exercise of any powers conferred by this Order interfere with the Agency’s access to or maintenance of any drainage work unless a suitable alternative access is provided prior to and for the duration of any such interference.
  • (2) The undertaker must not exercise the power conferred by articles 15 (access to works), 27 (temporary use of land for carrying out the authorised project) and 28 (temporary use of land for maintaining the authorised project) so as to interfere with any drainage work unless the exercise of such powers is with the consent of the Agency and in accordance with paragraphs 17 to 24 of this Part.

10

Any dispute arising between the undertaker and the Agency under this Part of this Schedule, is to be determined by arbitration under article 46 (arbitration).

11

  • (1) Any specified work capable of interfering with or risking damage to any drainage work for flood defence must not commence until a scheme for monitoring ground subsidence (referred to in this paragraph as “the monitoring scheme”) has been submitted to and approved by the Agency, such approval not to be unreasonably withheld or delayed.
  • (2) The monitoring scheme described in sub-paragraph (1) must set out—
  • (a) the drainage work which is to be subject to such monitoring;
  • (b) the extent of land to be monitored;
  • (c) the manner in which ground levels are to be monitored;
  • (d) the timescales of any monitoring activities; and
  • (e) the extent of ground subsidence which, if exceeded, will require the undertaker to submit for the Agency’s approval a ground subsidence mitigation scheme in respect of such subsidence in accordance with sub-paragraph (5).
  • (3) The Agency must give notice of its decision as to whether or not it approves the monitoring scheme within 21 days beginning with—
  • (a) where no further information is requested under sub-paragraph (4), the day immediately following that on which the application is received by the discharging authority; and
  • (b) where further information is requested under sub-paragraph (4), the day immediately following that on which further information has been supplied by the undertaker.
  • (4) Where an application has been made under sub-paragraph (1) the Agency may request such reasonable further information from the undertaker as it considers necessary to enable it to consider the application.
  • (5) As soon as reasonably practicable after any ground subsidence identified by the monitoring activities set out in the monitoring scheme has exceeded the level described in sub-paragraph (2)(e), a scheme setting out necessary mitigation measures (if any) for such ground subsidence (referred to in this paragraph as a “mitigation scheme”) must be submitted to the Agency for approval, such approval not to be unreasonably withheld or delayed; and any mitigation scheme must be implemented as approved, unless otherwise agreed in writing with the Agency.

12

Within the Order limits on the south bank of the estuary, from the crest of the flood defences to a point 750 metres landward (measured perpendicular to the flood defences) of the crest of the said defences, the pipeline shall be laid with a minimum cover of 1.7 metres above the pipeline.

PART 4 — For the protection of Anglian Water

1

  • (1) For the protection of Anglian Water, the following provisions shall, unless otherwise agreed in writing between the undertaker and Anglian Water, have effect.
  • (2) In this Part of this Schedule—
  • “apparatus” means any works, mains, pipes or other apparatus belonging to or maintained by Anglian Water for the purposes of water supply and sewerage and—any drain or works vested in Anglian Water under The Water Industry Act 1991; andany sewer which is so vested or is the subject of a notice of intention to adopt given under section 102 (4) of The Water Industry Act 1991 or an agreement to adopt made under section 104 of that Act,

and includes a sludge main, disposal main or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any sewer, drain, or works (within the meaning of section 219 of that Act) and any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus;

  • “alternative apparatus” means alternative apparatus adequate to enable Anglian Water to fulfil its statutory functions in not less efficient a manner than previously;
  • “functions” includes powers and duties;
  • “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land; and
  • “plan” includes sections, drawings, specifications and method statements.
  • (3) The undertaker shall not interfere with, build over or near to any apparatus within the Order land or execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within the standard protection strips which are the strips of land falling the following distances to either side of the medial line of any relevant pipe or apparatus; 2.25metres where the diameter of the pipe is less than 150 millimetres, 3 metres where the diameter of the pipe is between 150 and 450 millimetres, 4.5 metres where the diameter of the pipe is between 450 and 750 millimetres and 6 metres where the diameter of the pipe exceeds 750 millimetres unless otherwise agreed in writing with Anglian Water, such agreement not to be unreasonably withheld or delayed, and such provision being brought to the attention of any agent or contractor responsible for carrying out any work on behalf of the undertaker.
  • (4) The alteration, extension, removal or re-location of any apparatus shall not be implemented until—
  • (a) any requirement for any permits under the Environmental Permitting (England and Wales) Regulations 2016 or other legislations and any other associated consents are obtained, and any approval or agreement required from Anglian Water on alternative outfall locations as a result of such re-location are approved, such approvals from Anglian Water not to be unreasonably withheld or delayed; and
  • (b) the undertaker has made the appropriate application required under the Water Industry Act 1991 together with a plan and section of the works proposed and Anglian Water has agreed all of the contractual documentation required under the Water Industry Act 1991, such agreement not to be unreasonably withheld or delayed; and such works to be executed only in accordance with the plan, section and description submitted and in accordance with such reasonable requirements as may be made by Anglian Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it.
  • (5) In the situation, where in exercise of the powers conferred by the Order, the undertaker acquires any interest in any land in which apparatus is placed and such apparatus is to be relocated, extended, removed or altered in any way, no alteration or extension shall take place until Anglian Water has established to its reasonable satisfaction, contingency arrangements in order to conduct its functions for the duration of the works to relocate, extend, remove or alter the apparatus.
  • (6) Regardless of any provision in this Order or anything shown on any plan, the undertaker must not acquire any apparatus otherwise than by agreement, and before extinguishing any existing rights for Anglian Water to use, keep, inspect, renew and maintain its apparatus in the Order land, the undertaker shall, with the agreement of Anglian Water, create a new right to use, keep, inspect, renew and maintain the apparatus that is reasonably convenient for Anglian Water such agreement not to be unreasonably withheld or delayed, and to be subject to arbitration under article 46 (arbitration).
  • (7) If in consequence of the exercise of the powers conferred by the Order the access to any apparatus is materially obstructed the undertaker shall provide such alternative means of access to such apparatus as will enable Anglian Water to maintain or use the apparatus no less effectively than was possible before such obstruction.
  • (8) If in consequence of the exercise of the powers conferred by the Order, previously unmapped sewers, lateral drains or other apparatus are identified by the company, notification of the location of such assets will immediately be given to Anglian Water and afforded the same protection of other Anglian Water assets.
  • (9) If for any reason or in consequence of the construction of any of the works referred to in paragraphs (4) to (6) and (8) above any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker shall—
  • (a) bear and pay the cost reasonably incurred by Anglian Water in making good any damage or restoring the supply; and
  • (b) make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs incurred by Anglian Water by reason or in consequence of any such damage or interruption.

PART 5 — For the protection of Centrica

1

For the protection of Centrica the following provisions, unless otherwise agreed in writing between the undertaker and Centrica, have effect.

Interpretation

2

In this Part of this Schedule—

  • “apparatus” means Centrica’s pipelines, cables, structures or other electrical, gas or telecommunication infrastructure owned, occupied or maintained by Centrica for the purposes of its undertaking including the pipeline;
  • “Centrica” means Centrica Plc and all of its subsidiaries and group companies, including but not limited to Centrica Storage Limited, or any successor company performing the same functions; and
  • “pipeline” means the Centrica condensate pipeline 200NB.

Creation of rights and access for Centrica

3

  • (1) Before extinguishing any existing rights for Centrica to keep, inspect, renew, maintain and decommission its apparatus on, over or in the Order land or to cross the Order land to access its apparatus, the undertaker at its expense, with the agreement of Centrica, must create a new right, which is consistent with the existing right being extinguished, to keep, inspect, renew, maintain and decommission the apparatus in the same location or a new right of access that it reasonably convenient for Centrica, such agreement not to be unreasonably withheld or delayed.
  • (2) The undertaker will not in the exercise of any powers conferred by this Order unreasonably interfere with Centrica’s access to inspect, renew, maintain or decommission the pipeline unless a suitable alternative access is provided at the undertaker’s expense prior to and for the duration of any such interference.

Apparatus

4

  • (1) Save where paragraph 36 of this Part applies, no works are to commence within 10 metres of apparatus until a construction method statement to protect the apparatus has been prepared by the undertaker and submitted to and agreed with Centrica (such agreement not to be unreasonably withheld or delayed).
  • (2) The construction method statement must include provisions in respect of—
  • (a) the location and methods of reinforcement of crossing points over the apparatus and restrictions on building and altering the ground level over the apparatus elsewhere.
  • (b) a mechanism for the enforcement of the relevant undertaker’s use of designated crossing points over the apparatus and the agreed reinforcement methods; and
  • (c) adoption of a prior notification and consent regime which would require the relevant undertaker to—
  • (i) obtain Centrica’s consent to the carrying out of the proposed development within the vicinity of the apparatus, such consent not to be unreasonably withheld; and
  • (ii) notify Centrica of its intention to carry out any development within the vicinity of the apparatus, such notification to be provided at least 7 days prior to any such development occurring; and

the authorised project must be carried out in accordance with the approved construction method statement.

  • (3) At all times when carrying out any works authorised under the Order the undertaker must comply with the undertaker’s policies for safe working in proximity to gas apparatus “Specification for safe working in the vicinity of National Grid high pressure gas pipelines and associated installation requirements for third parties T/SP/SSW22”.
  • (4) Prior to any works authorised under the Order within 50 yards of the pipeline being carried out, a crossing agreement shall be entered into between the undertaker and Centrica governing the works to be undertaken, and any future works undertaken in the Notification Area (as defined in the crossing agreement) by the undertaker, in a form acceptable to and to be approved by Centrica.

Ground Subsidence Monitoring Scheme

5

  • (1) Any authorised works within 100 metres of any apparatus or alternative apparatus capable of interfering with or risking damage to the apparatus or alternative apparatus must not commence until a scheme for monitoring ground subsidence (“referred to in this paragraph as the monitoring scheme”) has been submitted to and approved by Centrica, such approval not to be unreasonably withheld or delayed.
  • (2) The monitoring scheme described in sub-paragraph (1) must set out—
  • (a) the apparatus which is to be subject to such monitoring;
  • (b) the extent of land to be monitored;
  • (c) the manner in which ground levels are to be monitored;
  • (d) the timescales of any monitoring activities; and
  • (e) the extent of ground subsidence which, if exceeded, will require the undertaker to submit for Centrica’s approval a ground subsidence mitigation scheme in respect of such subsidence in accordance with sub-paragraph (3).
  • (3) The monitoring scheme required by sub paragraphs (1) and (2) must be submitted at least 28 days prior to the commencement of any works authorised by this Order or comprised within the authorised project to which sub-paragraph (1) applies. Any requirements of Centrica will be notified within 10 days of receipt of the monitoring scheme. Thereafter the monitoring scheme must be implemented at the cost of the undertaker as approved, unless otherwise agreed in writing with Centrica.
  • (4) As soon as reasonably practicable after any ground subsidence identified by the monitoring activities set out in the monitoring scheme has exceeded the level described in sub-paragraph (2)(e), a scheme setting out necessary mitigation measures (if any) for such ground subsidence (referred to in this paragraph as a “mitigation scheme”) must be submitted to Centrica for approval, such approval not to be unreasonably withheld or delayed; and any mitigation scheme must be implemented at the cost of the undertaker as approved, unless otherwise agreed in writing with Centrica save that Centrica retains the right to carry out any further necessary protective works for the safeguarding of their apparatus.
  • (5) If the monitoring scheme or mitigation scheme would conflict with any aspect of any ground subsidence monitoring scheme or ground subsidence mitigation scheme approved by the relevant planning authority pursuant to Schedule 3 (requirements) the undertaker may submit a revised monitoring scheme or mitigation scheme to Centrica for its approval, such approval not to be unreasonably withheld or delayed; and the revised monitoring scheme or mitigation scheme must be implemented as approved, unless otherwise agreed in writing with Centrica.

Cathodic Protection Testing

6

  • (1) Where in the reasonable opinion of Centrica—
  • (a) the authorised project might interfere with the existing cathodic protection forming part of a pipeline; or
  • (b) a pipeline might interfere with the proposed or existing cathodic protection forming part of the authorised project,

7

  • (1) In the event that the undertaker uses an alternative cathodic protection design for the authorised works to that shown on the works plans, not less than 56 days before the commencement of any authorised works, the undertaker shall submit to Centrica plans detailing alterations to the cathodic protection design and setting out a pre- and post- construction monitoring scheme to assess any interactions with apparatus or alternative apparatus.
  • (2) The undertaker must not commence any works to which sub-paragraph (1) applies until Centrica has given written approval of the plans and monitoring scheme submitted.
  • (3) Any approval of Centrica required under sub-paragraph (2)—
  • (a) may be given subject to reasonable conditions for the protection of apparatus; and
  • (b) must not be unreasonably withheld.
  • (4) The undertaker must implement the works and the monitoring scheme as approved under sub-paragraph (1) in the construction and maintenance of the authorised works.

Removal of apparatus

8

  • (1) If the undertaker acquires or overrides any interest in the land in which apparatus is laid, the apparatus shall not be removed under this Part of this Schedule and any right of Centrica to keep, inspect, renew or maintain the apparatus in that land shall not be extinguished until alternative apparatus has been constructed at the undertaker’s expense, and is in operation to the reasonable satisfaction of Centrica in accordance with sub-paragraphs (2) to (5) inclusive.
  • (2) If, for the purpose of executing any works in, on, under or over any land purchased, held, appropriated or used under this Order, the undertaker required the removal of apparatus in that land, it shall give Centrica 56 days’ advance written notice of that requirement, together with a plan of the work proposed, and of the proposed position of the alternative apparatus to be provided or constructed and in that case (or if in consequence of the exercise of any powers conferred by this Order Centrica reasonably needs to remove any apparatus) the relevant undertaker shall, subject to sub-paragraph (3), afford to Centrica to their satisfaction, (taking into account paragraph 37(1) below) the necessary facilities and rights for—
  • (a) the construction of an alternative apparatus in other land of the undertaker or Centrica; and
  • (b) subsequently for the operation or maintenance of that alternative apparatus.
  • (3) If alternative apparatus or any part of such apparatus is to be constructed elsewhere than in other land of the undertaker or Centrica, or the undertaker is unable to afford such facilities and rights as are mentioned in sub-paragraph (2), in the land in which the alternative apparatus or part of such apparatus is to be constructed, Centrica shall, on receipt of written notice to that effect from the undertaker and at the undertakers cost, take such steps as are reasonable in the circumstances in an endeavour to obtain the necessary facilities and rights in the land in which the alternative apparatus is to be constructed save that this obligation shall not extend to the requirement for Centrica to seek compulsory purchase powers to this end unless it elects to do so.
  • (4) Any alternative apparatus to be constructed in land of the relevant undertaker or Centrica under this Part of this Schedule must be constructed in such a manner and in such line or situation as may be agreed between Centrica and the undertaker.
  • (5) Centrica shall, after the alternative apparatus to be provided or constructed has been agreed, and subject to the grant to Centrica of any such facilities and rights as are referred to in sub-paragraph (2) or (3), proceed without unnecessary delay, at the cost of the undertaker, construct and bring into operation the alternative apparatus and subsequently to remove any apparatus required by the undertaker to be removed under this Part of this Schedule.

Facilities and rights for alternative apparatus

9

  • (1) Where in accordance with the provisions of this Part of this Schedule, the undertaker affords to Centrica facilities and rights for the construction, operation and maintenance in land of the undertaker of alternative apparatus in substitution for the apparatus to be removed, those facilities and rights shall be granted upon such terms and conditions as may be agreed between the undertaker and Centrica and shall be no less favourable on the whole than the facilities and rights enjoyed by it in respect of the apparatus to be removed unless agreed by Centrica.
  • (2) If the facilities and rights to be afforded by the undertaker and agreed with Centrica under (1) above in respect of any alternative apparatus, and the terms and conditions subject to which those facilities and rights are to be granted, are less favourable on the whole to Centrica than the facilities and rights enjoyed by it in respect of the apparatus to be removed and the terms and conditions to which those facilities and rights are subject, the matter must be referred to arbitration and, the arbitrator must make such provision for the payment of compensation by the relevant undertaker to Centrica as appears to the arbitrator to be reasonable having regard to all the circumstances of the particular case.

Costs

10

If for any reason or in consequence of the construction, operation or maintenance of the authorised project, any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Centrica, the undertaker must bear and pay the cost reasonably incurred by Centrica in making good any damage by reason or in consequence of such damage.

Requirement for agreement

11

Regardless of any provision in this Order or anything shown on the land plans or contained in the book of reference, the undertaker must not acquire any apparatus or override any easement or other interest of Centrica or acquire any land or other interest of Centrica or create any new rights over the same otherwise than by agreement of Centrica, which agreement must not be unreasonably withheld.

Disputes

12

Any dispute arising between the undertaker and Centrica under this Part of this Schedule must be determined by arbitration as provided in article 46 (arbitration) unless otherwise agreed in writing between the undertaker and Centrica.

SCHEDULE 11 — Modification of compensation and compulsory purchase enactments for the creation of new rights

Compensation enactments

1

The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right as they apply as respects compensation on the compulsory purchase of land and interests in land.

2

  • (1) Without prejudice to the generality of paragraph 1, the Land Compensation Act 197332 has effect subject to the modifications set out in sub-paragraphs (2) and (3).
  • (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 of the 1965 Act as substituted by paragraph 4—
  • (a) for the words “land is acquired or taken” there are substituted the words “a right or restrictive covenant over land is purchased from or imposed on”; and
  • (b) for the words “acquired or taken from him” there are substituted the words “over which the right is exercisable or the restrictive covenant enforceable”.
  • (3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—
  • (a) for the word “part” in paragraphs (a) and (b) there are substituted the words “a right over or restrictive covenant affecting land consisting”;
  • (b) for the word “severance” there is substituted the words “right or restrictive covenant over or affecting the whole of the house, building or manufactory or of the house and the park or garden”;
  • (c) for the words “part proposed” there are substituted the words “right or restrictive covenant proposed”; and
  • (d) for the words “part is” there are substituted the words “right or restrictive covenant is”.

Application of the 1965 Act

3

  • (1) The 1965 Act has effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right, or to the imposition under this Order of a restrictive covenant, as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are read (according to the requirements of the particular context) as referring to, or as including references to—
  • (a) the right acquired or to be acquired; or
  • (b) the land over which the right is or is to be exercisable.
  • (2) Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act applies in relation to the compulsory acquisition under this Order of a right by the creation of a new right with the modifications specified in the following provisions of this Schedule.

4

For section 7 of the 1965 Act (measure of compensation) there is substituted the following section—

(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.

5

The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—

  • (a) section 9(4) (failure by owners to convey);
  • (b) paragraph 10(3) of Schedule 1 (owners under incapacity);
  • (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
  • (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),

are modified to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.

6

Section 11 of the 1965 Act (powers of entry) is modified to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right, it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant (which is deemed for this purpose to have been created on the date of service of the notice); and sections 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are modified correspondingly.

7

Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.

8

Section 22 of the 1965 Act (protection of acquiring authority’s possession where by inadvertence an estate, right or interest has not been got in) is modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.

SCHEDULE 12 — Procedure in relation to certain approvals etc.

Determination of applications for specified consents

1

  • (1) Subject paragraph (2), where an application has been made to the discharging authority for any specified consent, the discharging authority must give notice to the undertaker of its decision on the application within a period of 8 weeks beginning with—
  • (a) where no further information is requested under paragraph (3), the day immediately following that on which the application is received by the discharging authority;
  • (b) where further information is requested under paragraph (3), the day immediately following that on which further information has been supplied by the undertaker; or
  • (2) For the 8 weeks in paragraph (1), a longer period may be substituted where agreed in writing between the undertaker and the discharging authority.
  • (3) Where an application has been made under paragraph (1) the discharging authority may request such reasonable further information from the undertaker as it considers is necessary to enable it to consider the application.
  • (4) If the discharging authority considers further information is necessary and this Order does not specify that consultation with a consultee is required, the discharging authority may notify the undertaker in writing specifying the further information required.
  • (5) If a provision of this Order relating to a specified consent specifies that consultation with a consultee is required, the discharging authority must issue the consultation to the consultee and may notify the undertaker in writing specifying any further information requested by the consultee.

Fees

2

  • (1) Where an application is made to a relevant planning authority for any consent, agreement or approval required by a requirement listed in Schedule 3 (requirements) to this Order, a fee of £97 (or such other fee as may be prescribed in regulations made pursuant to sections 303 (fees for planning applications etc.) and 333(2A) (regulations and orders) of the 1990 Act for the confirmation by a local planning authority of compliance with a condition attached to a planning permission) must be paid to the discharging authority.
  • (2) Any fee paid under this Schedule must be refunded to the undertaker within 4 weeks of the discharging authority failing to determine the application within 8 weeks or the period agreed under paragraph 1(2) from the date on which it is received, unless within that period the undertaker agrees in writing that the fee may be retained by the discharging authority and credited in respect of a future application.

Appeals

3

  • (1) The undertaker may appeal if—
  • (a) the discharging authority refuses an application for any specified consent or grants it subject to conditions;
  • (b) the discharging authority does not give notice of its decision to the undertaker within the period specified in sub-paragraph 1(1);
  • (c) having received a request for further information under paragraph 1(3) the undertaker considers that either the whole or part of the specified information requested by the discharging authority is not necessary for consideration of the application; or
  • (d) having received any further information requested, the discharging authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
  • (2) The procedure for appeals is as follows—
  • (a) the undertaker must submit to the Secretary of State a copy of the application submitted to the discharging authority and any supporting documents which the undertaker may wish to provide (“the appeal documents”);
  • (b) the undertaker must on the same day provide copies of the appeal documents to the discharging authority and (if applicable) the consultee;
  • (c) as soon as is practicable after receiving the appeals documents the Secretary of State must appoint a person to determine the appeal (“the appointed person”) and notify the appeal parties of the identity of the appointed person and the address to which all correspondence for the appointed person should be sent;
  • (d) the discharging authority and (if applicable) the consultee may submit any written representations in respect of the appeal to the appointed person within 10 business days beginning with the first day immediately following the date on which the appeal parties are notified of the appointment of the appointed person and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
  • (e) the appeal parties may make any counter-submissions to the appointed person within 10 business days beginning with the first day immediately following the date of receipt of written representations pursuant to paragraph (d) above; and
  • (f) the appointed person must make a decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable.
  • (3) If the appointed person considers that further information is necessary to consider the appeal, the appointed person must as soon as practicable notify the appeal parties in writing specifying the further information required, the appeal party from whom the information is sought, and the date by which the information must be submitted.
  • (4) Any further information required pursuant to sub-paragraph (3) must be provided by the party from whom the information is sought to the appointed person and to other appeal parties by the date specified by the appointed person.
  • (5) The appeal parties may submit written representations to the appointed person concerning matters contained in the further information.
  • (6) Any such representations must be submitted to the appointed person and made available to all appeal parties within 10 business days of the date mentioned in sub-paragraph (3).

Outcome of Appeals

4

  • (1) On an appeal under paragraph 2, the appointed person may—
  • (a) allow or dismiss the appeal; or
  • (b) reverse or vary any part of the decision of the discharging authority (whether the appeal relates to that part of it or not),

and may deal with the application as if it had been made to the appointed person in the first instance.

  • (2) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the time limits prescribed or set by the appointed person under this paragraph.
  • (3) The appointed person may proceed to a decision even though no written representations have been made within those time limits if it appears to the appointed person that there is sufficient material to enable a decision to be made on the merits of the case.
  • (4) The decision of the appointed person on an appeal is final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
  • (5) Any approval given by the appointed person pursuant to this Schedule is deemed to be an approval for the purposes of this Order and any other enactment which required the specified consent as if it had been given by the discharging authority.
  • (6) The discharging authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) does not affect or invalidate the effect of the appointed person’s determination.
  • (7) Except where a direction is given pursuant to sub-paragraph (8) requiring the costs of the appointed person to be paid by the discharging authority, the reasonable costs of the appointed person must be met by the undertaker.
  • (8) On application by the discharging authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid.
  • (9) In considering whether to make any such direction and the terms on which it is made, the appointed person must have regard to Communities and Local Government Circular 03/2009 or any circular or guidance which may from time to time replace it.
  • (10) Where the undertaker appeals under paragraph 2—
  • (a) this Schedule applies instead of article 46 (arbitration); and
  • (b) in respect of any specified consent required pursuant to sections 54 to 106 of the 1991 act, this Schedule applies instead of section 99 (arbitration) of that Act.

Interpretation of this Schedule

5

In this Schedule—

  • “the appeal parties” means the discharging authority, the consultee and the undertaker;
  • “business day” means Monday to Friday excluding bank holidays;
  • “consultee” means any body named in a provision of this Order relating to a specified consent which is the subject of an appeal as a body to be consulted by the discharging authority in determining that specified consent;
  • “discharging authority” means the body responsible for determining whether a specified consent should be given or the local authority in the exercise of functions set out in sections 60 or 61 of the 1974 Act;
  • “specified consent” means any— agreement, certificate, consent, permission, expression of satisfaction or other approval required by— a requirement listed in Schedule 3 (requirements) of this Order; a document referred to in any requirement listed in Schedule 3 to this Order; and article 41(3)(b) (felling or lopping of trees or shrubs); or agreement, certificate, consent, permission, expression of satisfaction or other approval of the highway authority, street authority (where it is also the highway authority for the same area) or traffic authority required pursuant to articles— 11 (street works) (including pursuant to sections 54 to 106 of the 1991 Act as applied by article 11(3)); 12 (power to alter layout, etc. of streets); 13 (construction and maintenance of new, altered or diverted streets); 14 (temporary stopping up of streets and public rights of way); 16 (traffic regulation); or 19 (authority to survey and investigate the land).

Signed

Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy

Giles Scott — Head of Energy Infrastructure Planning and Coal Liabilities — Department for Business, Energy and Industrial Strategy — 25th August 2016

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order authorises National Grid Gas plc (referred to as “the undertaker”) to construct and operate a high-pressure gas transmission pipeline and associated infrastructure from Paull Above Ground Installation (AGI) to Goxhill AGI within the authorities of the East Riding of Yorkshire and North Lincolnshire.

This Order permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for the construction and operation of the pipeline and associated infrastructure. The Order also makes provision in connection with the maintenance of the pipeline and associated infrastructure.

This Order also grants a deemed marine licence under Part 4 of the Marine and Coastal Access Act 2009 in connection with the pipeline and associated infrastructure.

A copy of the plans and the book of reference mentioned in this Order and certified in accordance with article 44 of this Order (certification of plans, etc.) may be inspected free of charge during working hours at: Barton Local Link, Providence House, Holydyke, Barton Upon Humber, DN18 5PR; Hedon Customer Service Centre, 2 New Road, Hedon, HU12 8EN; Goxhill Library, The Parish Room, Howe Lane, Goxhill, DN19 7HS; and, Thorngumbald Mobile Library.

Footnotes

12

1981 c.67. The definition of “owner” was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34), Sch.15(I) para.9.

13

Section 48 was amended by the Local Transport Act 2008 (c.26), Pt 7 s.124(2).

14

1990 c.43; section 82 is amended by section 5 of the Noise and Statutory Nuisance Act 1993 (c.40), Schedule 17 to the Environmental Act 1995 (c.25) and section 103 of the Clean Neighbourhoods and Environment Act 2005 (c.16).

15

1974 c.40. Sections 61(9) and 65(8) were amended by section 162 of, and paragraph 15 of Schedule 3 to, the Environmental Protection Act 1990, c.25. There are other amendments to the 1974 Act which are not relevant to this Order.

16

Section 48 is amended by the Local Transport Act 2008 (c.26) s.124(2); section 51 is amended by Schedule 1 to the Traffic Management Act 2004 (c.18).

18

1991 c.56. Section 106 was amended by section 35(8)(a) of the Competition and Service (Utilities) Act 1992 (c.43) and by sections 36(2) and 99 of the Water Act 2003 (c.37). There are other amendments to this section which are not relevant to this Order.

20

1857 c.81; section 25 is amended by the Criminal Justice Act 1982 (c.48) s.46.

22

There are amendments that are not relevant to this Order.

23

Section 13 is amended by section 139 of the Tribunals, Courts and Enforcement Act 2007 (c.15).

30

See section 106.

Editorial notes

33

Art. 1 in force at 15.9.2016, see art. 1

34

Art. 2 in force at 15.9.2016, see art. 1

35

Art. 3 in force at 15.9.2016, see art. 1

36

Art. 4 in force at 15.9.2016, see art. 1

37

Art. 5 in force at 15.9.2016, see art. 1

38

Art. 6 in force at 15.9.2016, see art. 1

39

Art. 7 in force at 15.9.2016, see art. 1

40

Art. 8 in force at 15.9.2016, see art. 1

41

Art. 9 in force at 15.9.2016, see art. 1

42

Art. 10 in force at 15.9.2016, see art. 1

43

Art. 11 in force at 15.9.2016, see art. 1

44

Art. 12 in force at 15.9.2016, see art. 1

45

Art. 13 in force at 15.9.2016, see art. 1

46

Art. 14 in force at 15.9.2016, see art. 1

47

Art. 15 in force at 15.9.2016, see art. 1

48

Art. 16 in force at 15.9.2016, see art. 1

49

Art. 17 in force at 15.9.2016, see art. 1

50

Art. 18 in force at 15.9.2016, see art. 1

51

Art. 19 in force at 15.9.2016, see art. 1

52

Art. 20 in force at 15.9.2016, see art. 1

53

Art. 21 in force at 15.9.2016, see art. 1

54

Art. 22 in force at 15.9.2016, see art. 1

55

Art. 23 in force at 15.9.2016, see art. 1

56

Art. 24 in force at 15.9.2016, see art. 1

57

Art. 25 in force at 15.9.2016, see art. 1

58

Art. 26 in force at 15.9.2016, see art. 1

59

Art. 27 in force at 15.9.2016, see art. 1

60

Art. 28 in force at 15.9.2016, see art. 1

61

Art. 29 in force at 15.9.2016, see art. 1

62

Art. 30 in force at 15.9.2016, see art. 1

63

Art. 31 in force at 15.9.2016, see art. 1

64

Art. 32 in force at 15.9.2016, see art. 1

65

Art. 33 in force at 15.9.2016, see art. 1

66

Art. 34 in force at 15.9.2016, see art. 1

67

Art. 35 in force at 15.9.2016, see art. 1

68

Art. 36 in force at 15.9.2016, see art. 1

69

Art. 37 in force at 15.9.2016, see art. 1

70

Art. 38 in force at 15.9.2016, see art. 1

71

Art. 39 in force at 15.9.2016, see art. 1

72

Art. 40 in force at 15.9.2016, see art. 1

73

Art. 41 in force at 15.9.2016, see art. 1

74

Art. 42 in force at 15.9.2016, see art. 1

75

Art. 43 in force at 15.9.2016, see art. 1

76

Art. 44 in force at 15.9.2016, see art. 1

77

Art. 45 in force at 15.9.2016, see art. 1

78

Art. 46 in force at 15.9.2016, see art. 1

79

Art. 47 in force at 15.9.2016, see art. 1

80

Sch. 1 para. 1 in force at 15.9.2016, see art. 1

81

Sch. 1 para. 2 in force at 15.9.2016, see art. 1

82

Sch. 3 para. 1 in force at 15.9.2016, see art. 1

83

Sch. 3 para. 2 in force at 15.9.2016, see art. 1

84

Sch. 3 para. 3 in force at 15.9.2016, see art. 1

85

Sch. 3 para. 4 in force at 15.9.2016, see art. 1

86

Sch. 3 para. 5 in force at 15.9.2016, see art. 1

87

Sch. 3 para. 6 in force at 15.9.2016, see art. 1

88

Sch. 3 para. 7 in force at 15.9.2016, see art. 1

89

Sch. 3 para. 8 in force at 15.9.2016, see art. 1

90

Sch. 3 para. 9 in force at 15.9.2016, see art. 1

91

Sch. 3 para. 10 in force at 15.9.2016, see art. 1

92

Sch. 3 para. 11 in force at 15.9.2016, see art. 1

93

Sch. 3 para. 12 in force at 15.9.2016, see art. 1

94

Sch. 3 para. 13 in force at 15.9.2016, see art. 1

95

Sch. 3 para. 14 in force at 15.9.2016, see art. 1

96

Sch. 3 para. 15 in force at 15.9.2016, see art. 1

97

Sch. 3 para. 16 in force at 15.9.2016, see art. 1

98

Sch. 3 para. 17 in force at 15.9.2016, see art. 1

99

Sch. 3 para. 18 in force at 15.9.2016, see art. 1

100

Sch. 3 para. 19 in force at 15.9.2016, see art. 1

101

Sch. 3 para. 20 in force at 15.9.2016, see art. 1

102

Sch. 3 para. 21 in force at 15.9.2016, see art. 1

103

Sch. 9 para. 1 in force at 15.9.2016, see art. 1

104

Sch. 9 para. 2 in force at 15.9.2016, see art. 1

105

Sch. 9 para. 3 in force at 15.9.2016, see art. 1

106

Sch. 9 para. 4 in force at 15.9.2016, see art. 1

107

Sch. 9 para. 5 in force at 15.9.2016, see art. 1

108

Sch. 9 para. 6 in force at 15.9.2016, see art. 1

109

Sch. 9 para. 7 in force at 15.9.2016, see art. 1

110

Sch. 9 para. 8 in force at 15.9.2016, see art. 1

111

Sch. 9 para. 9 in force at 15.9.2016, see art. 1

112

Sch. 10 Pt. 1 para. 1 in force at 15.9.2016, see art. 1

113

Sch. 10 Pt. 1 para. 2 in force at 15.9.2016, see art. 1

114

Sch. 10 Pt. 1 para. 3 in force at 15.9.2016, see art. 1

115

Sch. 10 Pt. 1 para. 4 in force at 15.9.2016, see art. 1

116

Sch. 10 Pt. 1 para. 5 in force at 15.9.2016, see art. 1

117

Sch. 10 Pt. 1 para. 6 in force at 15.9.2016, see art. 1

118

Sch. 10 Pt. 1 para. 7 in force at 15.9.2016, see art. 1

119

Sch. 10 Pt. 1 para. 8 in force at 15.9.2016, see art. 1

120

Sch. 10 Pt. 1 para. 9 in force at 15.9.2016, see art. 1

121

Sch. 10 Pt. 1 para. 10 in force at 15.9.2016, see art. 1

122

Sch. 10 Pt. 2 para. 1 in force at 15.9.2016, see art. 1

123

Sch. 10 Pt. 2 para. 2 in force at 15.9.2016, see art. 1

124

Sch. 10 Pt. 2 para. 3 in force at 15.9.2016, see art. 1

125

Sch. 10 Pt. 2 para. 4 in force at 15.9.2016, see art. 1

126

Sch. 10 Pt. 2 para. 5 in force at 15.9.2016, see art. 1

127

Sch. 10 Pt. 3 para. 1 in force at 15.9.2016, see art. 1

128

Sch. 10 Pt. 3 para. 2 in force at 15.9.2016, see art. 1

129

Sch. 10 Pt. 3 para. 3 in force at 15.9.2016, see art. 1

130

Sch. 10 Pt. 3 para. 4 in force at 15.9.2016, see art. 1

131

Sch. 10 Pt. 3 para. 5 in force at 15.9.2016, see art. 1

132

Sch. 10 Pt. 3 para. 6 in force at 15.9.2016, see art. 1

133

Sch. 10 Pt. 3 para. 7 in force at 15.9.2016, see art. 1

134

Sch. 10 Pt. 3 para. 8 in force at 15.9.2016, see art. 1

135

Sch. 10 Pt. 3 para. 9 in force at 15.9.2016, see art. 1

136

Sch. 10 Pt. 3 para. 10 in force at 15.9.2016, see art. 1

137

Sch. 10 Pt. 3 para. 11 in force at 15.9.2016, see art. 1

138

Sch. 10 Pt. 3 para. 12 in force at 15.9.2016, see art. 1

139

Sch. 10 Pt. 4 para. 1 in force at 15.9.2016, see art. 1

140

Sch. 10 Pt. 5 para. 1 in force at 15.9.2016, see art. 1

141

Sch. 10 Pt. 5 para. 2 in force at 15.9.2016, see art. 1

142

Sch. 10 Pt. 5 para. 3 in force at 15.9.2016, see art. 1

143

Sch. 10 Pt. 5 para. 4 in force at 15.9.2016, see art. 1

144

Sch. 10 Pt. 5 para. 5 in force at 15.9.2016, see art. 1

145

Sch. 10 Pt. 5 para. 6 in force at 15.9.2016, see art. 1

146

Sch. 10 Pt. 5 para. 7 in force at 15.9.2016, see art. 1

147

Sch. 10 Pt. 5 para. 8 in force at 15.9.2016, see art. 1

148

Sch. 10 Pt. 5 para. 9 in force at 15.9.2016, see art. 1

149

Sch. 10 Pt. 5 para. 10 in force at 15.9.2016, see art. 1

150

Sch. 10 Pt. 5 para. 11 in force at 15.9.2016, see art. 1

151

Sch. 10 Pt. 5 para. 12 in force at 15.9.2016, see art. 1

152

Sch. 11 para. 1 in force at 15.9.2016, see art. 1

153

Sch. 11 para. 2 in force at 15.9.2016, see art. 1

154

Sch. 11 para. 3 in force at 15.9.2016, see art. 1

155

Sch. 11 para. 4 in force at 15.9.2016, see art. 1

156

Sch. 11 para. 5 in force at 15.9.2016, see art. 1

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.