The Boston Barrier Order 2017
- (4) If a specified undertaker in accordance with sub-paragraph (3) and in consequence of the works proposed by the Agency, reasonably requires the removal of any apparatus and gives written notice to the Agency of that requirement, paragraphs 1 to 6 apply as if the removal of the apparatus had been required by the Agency under paragraph 5(1).
- (5) Nothing in this paragraph precludes the Agency from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, new plans instead of the plans previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plans.
- (6) The Agency is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to the specified undertaker in question notice as soon as is reasonably practicable and plans of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
- (7) Nothing in sub-paragraph (6) entitles the Agency to carry out works to any apparatus but, upon receipt of notice from the Agency, the specified undertaker must proceed to carry out such works as may be required without unreasonable delay.
Expenses
8
- (1) Subject to the following provisions of this paragraph, the Agency must repay to a specified undertaker the reasonable expenses incurred by that specified undertaker in, or in connection with—
- (a) the inspection, removal and relaying or replacing, alteration or protection of any apparatus or the construction of any new apparatus under any provision of this Schedule (including any costs reasonably incurred or compensation properly paid in connection with the acquisition of facilities and rights or exercise of statutory powers for such apparatus);
- (b) the cutting off of any apparatus from any other apparatus, or the making safe of any redundant apparatus in consequence of the exercise by the Agency of any power under this Order; and
- (c) the survey of any land, apparatus or works; the inspection, superintendence and monitoring of works; or the installation or removal of any temporary works reasonably necessary in consequence of the exercise by the Agency of any power under this Order; and any other work or thing rendered reasonably necessary in consequence of the exercise by the Agency of any such power,
within a reasonable time of being notified by the specified undertaker that it has incurred such expenses.
- (2) The value of any apparatus removed under the provisions of this Schedule is to be deducted from any sum payable under sub-paragraph (1), that value being calculated after removal.
- (3) If in accordance with the provisions of this Schedule—
- (a) alternative apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions, except where this has been solely due to using the nearest currently available type; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the Agency or, in default of agreement, is not determined by arbitration in accordance with article 67 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to the specified undertaker in question by virtue of sub-paragraph (1), is to be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as placing of apparatus of greater dimensions than those of the existing apparatus, except in a case where the apparatus as so extended serves a purpose (either additional to or instead of that served by the existing apparatus) which was not served by the existing apparatus; and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a specified undertaker in respect of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the specified undertaker any financial benefit by deferment of the time for renewal of the apparatus in the normal course, be reduced by the amount which represents that benefit as calculated in accordance with the Code of Practice entitled “Measures Necessary where Apparatus is Affected by Major Works (Diversionary Works)” and dated June 1992 and approved by the Secretary of State on 30th June 1992, as revised and re-issued from time to time.
- (6) In any case where work is carried out by the Agency under paragraphs 5(6) to (8) and, if such work had been carried out by the specified undertaker, the repayment made to the specified undertaker under sub-paragraph (1) would fall to be reduced under sub-paragraphs (3) to (5), the specified undertaker must pay to the Agency such sum as represents the amount of that reduction.
Indemnity
9
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction, maintenance or failure of any of the authorised works, any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of a specified undertaker, or there is any interruption in any service provided, or in the supply of any goods, by any specified undertaker, the Agency must bear and pay the cost reasonably incurred by that specified undertaker in making good such damage or restoring the supply, and must—
- (a) make reasonable compensation to that specified undertaker for any other expenses, loss, damages, penalty or costs incurred by the specified undertaker; and
- (b) indemnify the specified undertaker against all claims, demands, proceedings, costs, damages and expenses which may be made or taken against or recovered from, or incurred by, the specified undertaker,
by reason or in consequence of any such damage or interruption; and the fact that any act or thing may have been done by the specified undertaker on behalf of the Agency or in accordance with plans approved by the specified undertaker or in accordance with any requirement of the specified undertaker or under its supervision does not, subject to sub-paragraph (2), excuse the Agency from any liability under the provisions of this paragraph.
- (2) Nothing in sub-paragraph (1) imposes any liability on the Agency with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of a specified undertaker, its officers, servants, contractors or agents.
- (3) A specified undertaker must give the Agency reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the Agency, which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
Access
10
If in consequence of the exercise of the powers conferred by this Order the access to any apparatus is materially obstructed the Agency must provide such alternative means of access to that apparatus as will enable the specified undertaker to maintain or use the apparatus no less effectively than was possible before the obstruction.
Cooperation
11
Where in consequence of the proposed construction of any of the authorised works, the Agency or the specified undertaker requires the removal of apparatus under paragraph 5(1) or the specified undertaker makes requirements for the protection or alteration of apparatus under paragraph 7(2), the Agency must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and the specified undertaker must use all reasonable endeavours to co-operate with the Agency for that purpose.
Exercise of safeguarding and survey powers
12
- (1) The Agency must, so far as is reasonably practicable, exercise the powers conferred by article 21 (protective works) so as not to obstruct or render less convenient the access to any apparatus.
- (2) The Agency must not, in the exercise of the powers conferred by section 11(3) (powers of entry) of the 1965 Act, as applied by this Order, or by article 23 (power to survey and investigate land, etc.), make any trial holes which interfere with any apparatus without the consent of the specified undertaker (which must not be unreasonably withheld).
Arbitration
13
Any difference arising between the Agency and a specified undertaker under this Schedule (other than a difference as to its meaning or construction) must be determined by arbitration in the manner provided by article 67 (arbitration) and in determining any difference under this Schedule the arbitrator may, if the arbitrator thinks fit, require the Agency to execute any temporary or other works so as to avoid, so far as may be reasonably possible, interference with the use of any apparatus.
SCHEDULE 8 — PROTECTION OF PORT OF BOSTON
1
The following provisions of this Schedule have effect unless otherwise agreed in writing between the Agency and the Harbour Authority.
2
In this Schedule—
- “accumulation” means any accumulation of silt or other material which constitutes an impediment to navigation;
- “construction” includes execution and placing, maintenance, extension, enlargement, alteration, replacement, relaying, and removal, and “construct” and “constructed” are to be construed accordingly;
- “erosion” means any erosion of the bed or banks of the river or any jetty or other structure of whatever nature owned or occupied by the Harbour Authority;
- “harbour property” means any land or works owned or administered by the Harbour Authority as part of its harbour undertaking at the Port of Boston;
- “plans” includes sections, descriptions, drawings, specifications and method statements;
- “specified work” means so much of any permanent or temporary work authorised by this Order (which includes, for the avoidance of doubt, any removal of gravel or other material, any dredging or similar work and any geotechnical investigations that may be undertaken) as is on, in, under or over— the surface of land below the level of mean high water springs forming part of the river; or any other harbour property.
3
- (1) The Agency must not exercise the powers conferred by this Order to acquire or take temporary possession of or acquire new rights over any land held by the Harbour Authority as part of its statutory undertaking except with the consent of the Harbour Authority.
- (2) The consent of the Harbour Authority under this paragraph must not be unreasonably withheld but may be given subject to such reasonable requirements as the Harbour Authority may make for the purpose of performing its statutory functions.
4
- (1) Before beginning any operations for the construction of any specified work (but this requirement does not apply to minor works of maintenance or repair), the Agency must submit to the Harbour Authority plans of the work and such further particulars available to it as the Harbour Authority may within 14 days of the submission of the plans reasonably require.
- (2) Any specified work must not be constructed except in accordance with such plans as may be approved in writing by the Harbour Authority or determined to be in accordance with article 67 (arbitration) of this Order.
- (3) Any approval of the Harbour Authority required under this paragraph must not be unreasonably withheld and—
- (a) shall be deemed to be given if it is neither given or refused (with an indication of the grounds for refusal) within 28 days of the submission of the plans or where further particulars are submitted under sub-paragraph (1), within 28 days of the submission of those particulars; and
- (b) may be given subject to such reasonable requirements as the Harbour Authority may make for the protection of—
- (i) navigation in, or the flow or regime of, the river; or
- (ii) the use of its land other than such parts as are required for the specified works for the purposes of performing its statutory functions.
5
The Agency must give to the Harbour Authority not less than 14 days’ written notice of its intention to commence the construction of a specified work (but this requirement does not apply to minor works of maintenance or repair) and, not more than 14 days after completion of such construction, must give to the Harbour Authority written notice of such completion.
6
The Agency must carry out all operations for the construction of any specified works with all reasonable dispatch to the reasonable satisfaction of the Harbour Authority so that navigation in, or the flow or regime of, the river and the exercise of the Harbour Authority’s statutory functions do not suffer more interference than is reasonably practicable and the Harbour Authority shall be entitled by its officer at all reasonable times, on giving such notice as may be reasonable in the circumstances, to inspect and survey such operations.
7
After the purpose of any temporary works has been accomplished the Agency must with all reasonable dispatch, or after a reasonable period of notice in writing from the Harbour Authority requiring the Agency so to do, remove any such temporary works or any materials relating thereto which may have been placed below the level of high water by or on behalf of the Agency; and, on failing to so do within a reasonable period after receiving such notice, the Harbour Authority may remove the same and may recover the reasonable costs of so doing from the Agency.
8
- (1) If—
- (a) during the construction of a tidal work or within 10 years after the completion of that work and wholly or partly in consequence of its construction; or
- (b) during the exercise of the powers conferred by article 6 (power to dredge etc.) of this Order or within 10 years after and wholly or partly in consequence of the exercise of those powers,
there is caused or created an accumulation or erosion which results or is likely to result in interference with navigation or damage to harbour property, the Agency must, if so requested by the Harbour Authority acting reasonably and having regard in particular to its and the Agency’s statutory functions, remedy such accumulation or erosion to the extent attributable to such construction or exercise of powers in the manner specified in sub-paragraph (3) and, if it refuses or fails to do so, the Harbour Authority may itself cause the work to be done and may recover the reasonable cost of doing so from the Agency.
- (2) If any such accumulation or erosion in consequence of such construction or exercise of the powers conferred under article 6 (power to dredge etc.) arises within the said period of 10 years and is remedied in accordance with sub-paragraph (1), any recurrence of such accumulation or erosion must, from time to time, if reasonably so required to do by the Harbour Authority after notice in writing to it from the Agency and having regard in particular to its and the Agency’s statutory functions, be so remedied by the Agency during the said period of 10 years and at any time thereafter, save that the Agency’s obligation under this paragraph shall cease if, following the remedying of any accumulation or erosion, a period of 10 years elapses without any further accumulation or erosion being caused or created in consequence of such construction or exercise.
- (3) For the purposes of sub-paragraph (1) and (2) above—
- (a) in the case of an accumulation, the remedy must be its removal; and
- (b) in the case of erosion, the remedy must be the carrying out of such reconstruction works and other protective works or measures as may be necessary.
- (4) In the event that any surveys, inspection, tests or sampling establish that such accumulation or erosion may have been caused in any event by factors other than the construction of a tidal work or the exercise of the powers conferred by article 6 (power to dredge etc), the Agency is liable to remedy such accumulation or erosion only to the extent that the same is attributable to such construction or exercise.
- (5) For the purposes of sub-paragraph (1) the date of completion of a work is the date on which it is brought into use.
9
The Agency must pay to the Harbour Authority the reasonable costs of such alterations to the marking and lighting of the navigational channel of the river as may be necessary during or within five years of the completion of and in consequence of the construction of a tidal work and afford to the Harbour Authority such facilities as it may reasonably require for the placing and maintenance on any tidal work of signals, tide-boards, tide-gauges or other apparatus for the safety or benefit of navigation.
10
Without affecting the other provisions of this Schedule, the Agency must be responsible for, and make good to the Harbour Authority, all costs which may reasonably be incurred by or occasioned to the Harbour Authority by reason of or arising from or in connection with—
- (a) the carrying out of surveys, inspections, tests and sampling within and of the river (including the bed and banks of the river) where the Harbour Authority has reasonable cause to believe that the construction of any of the tidal works or the exercise of the powers conferred by article 6 (power to dredge etc.) of this Order is causing or has caused any such accumulation or erosion;
- (b) the surveillance, co-ordination and regulation of traffic within the Port of Boston which becomes reasonably necessary by reason of the exercise or the prospective exercise by the Agency of its powers to close the river or any part of the river to navigation under article 17 (temporary closing of the river in connection with works) of this Order.
11
- (1) The Agency must indemnify the Harbour Authority from all claims, demands, proceedings or damages, which may be made or given against, or recovered from the Harbour Authority and any costs or expense reasonably incurred by the Harbour Authority by reason of any damage to the bed or banks of the river or other harbour property which is caused by the construction, maintenance or failure of any specified work or any act or omission of the Agency, its contractors, agents or employees whilst engaged upon the work.
- (2) The Harbour Authority must give to the Agency reasonable notice of any such claim or demand and no settlement or compromise of any such claim or demand must be made without the consent of the Agency, which, if it notifies the Harbour Authority that it desires to do so, shall have the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
12
Nothing in paragraph 11 imposes any liability on the Agency with respect to any damage to the extent that it is attributable to any prior defect, want of maintenance or want of repair to the beds or banks of the river or other harbour property or to the act, neglect or default of the Harbour Authority, its officers, servants, contractors or agents but the fact that any work or thing has been executed or done in accordance with a plan approved or deemed to be approved by the Harbour Authority, or to its satisfaction, or in accordance with a determination under article 67 (arbitration) of the Order, does not (in the absence of negligence on the part of the Harbour Authority, its officers, servants, contractors or agents) relieve the Agency from any liability under the provisions of this Schedule.
13
Save to the extent expressly provided for nothing in this Order affects prejudicially any statutory or other rights, powers or privileges vested in, or enjoyed by, the Harbour Authority at the commencement of this Order.
SCHEDULE 9 — AMENDMENT OF LOCAL LEGISLATION
PART 1 — LOCAL ENACTMENTS
| Year | Chapter | Title | Section |
|---|---|---|---|
| 1812 | c. 105 | Boston Port and Harbour Act | 1 (works to be done for the improvement of the Harbour, &c.) 38 (power to remove goods lying on quays beyond forty-eight hours) 46 (penalty on throwing ballast or rubbish into the harbour) 48 (penalty on laying gravel, &c. nearer the front of any quays than three feet) 52 (persons destroying works, to be transported for seven years) |
| 1812 | c. 108 | Witham Navigation and Drainage Act | 93 (regulation as to mooring vessels and removing obstructions) 96 (penalty on persons misusing the locks , or doing other damage to the navigation) 97 (penalty on destroying the works) 98 (punishment of persons damaging fences) 99 (lords of manors and landowners may make wharfs) 100 (but if not done, the company may make wharfs, &c.) |
| 1880 | c. cliii | River Witham Outfall Improvement Act | 10 (maintenance of works) 23 (power to remove obstructions) |
| 1881 | c. cxii | Boston Dock Act | 5 (power to make dock and railway, &c.) 6 (power to make subsidiary works) |
| 1925 | c. lxxi | Land Drainage (Black Sluice) Provisional Order Confirmation Act | 9 (penalties for obstructing or injuring drains or banks) |
PART 2 — BYELAWS
| (1) Title | (2) Byelaw to be disapplied |
|---|---|
| Boston Dock Byelaws 1947 | Byelaw 17 (opening of gates and sluices) Byelaw 26 (deposit of refuse and rubbish) Byelaw 27 (master to deliver account of ballast and no ballast to be discharged without permission) Byelaw 28 (timber and goods) Byelaw 29 (obstruction, wilful damage, hindrance of corporation’s officers, etc.) Byelaw 40 (persons not to remain on gates or bridges whilst being swung) Byelaw 44 (vehicles, goods on quays, etc.) Byelaw 45 (vehicles and horses) |
| Black Sluice Internal Drainage Board Complete Land Drainage Byelaws 1988 | Byelaw 3 (Control of introduction of water and increase in flow or volume of water) Byelaw 4 (Control of sluices, etc.) Byelaw 6 (Diversion or stopping up of watercourses) Byelaw 7 (Detrimental substances not to be put into watercourses) Byelaw 10 (No obstructions within 9 metres of the edge of watercourse) Byelaw 14 (Vehicles not to be driven on banks) Byelaw 15 (Banks not to be used for storage) Byelaw 16 (Not to dredge or raise gravel, sand, etc.) Byelaw 17 (Fences, excavations, pipes, etc.) Byelaw 18 (Tidal outfalls) Byelaw 19 (Interference with sluices) Byelaw 20 (Mooring of vessels) Byelaw 21 (Unattended vessels) Byelaw 24 (Damage to property of the Board) |
| Witham Fourth District Internal Drainage Board Byelaws 1989 | Byelaw 3 (Control of introduction of water and increase in flow or volume of water) Byelaw 4 (Control of sluices, etc.) Byelaw 6 (Diversion or stopping up of watercourses) Byelaw 10 (No obstructions within 9 metres of the edge of watercourse) Byelaw 14 (Vehicles not to be driven on banks) Byelaw 15 (Banks not to be used for storage) Byelaw 16 (Not to dredge or raise gravel, sand, etc.) Byelaw 17 (Fences, excavations, pipes, etc.) Byelaw 18 (Tidal outfalls) Byelaw 19 (Interference with sluices) Byelaw 20 (Mooring of vessels) Byelaw 21 (Unattended vessels) Byelaw 24 (Damage to property of the Board) |
Signed
David Cooper — A Senior Civil Servant, for and on behalf of the — Secretary of State for Environment, Food and Rural Affairs — 12th December 2017
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order authorises the Environment Agency (“the Agency”) to construct and operate a new tidal barrier with a moveable gate across the river Witham (also known in this location as the Haven) in Boston, Lincolnshire, together with a new building to enable operation of the barrier, new flood defence walls on both banks of the Haven, a replacement gate across the entrance to the existing Wet Dock and to execute ancillary works, including dredging of the river.
The purpose of this Order is to improve the current standard of protection from tidal flooding within Boston, Lincolnshire. The Order confers the necessary powers on the Agency to acquire, compulsorily or by agreement, land and rights in land and to use land for the purposes of the works and confers other powers in connection with the construction, operation and maintenance of the works.
A copy of the Order plans and the book of reference referred to in this Order and certified in accordance with article 66 of this Order (Certification of plans, etc.) may be inspected free of charge during normal working hours at the offices of the Environment Agency at Kingfisher House, Goldhay Way, Orton Goldhay, Peterborough, Cambridgeshire PE2 5ZR.
Footnotes
1992 c. 42. Section 5 was amended by S.I. 2012/1659.
S.I. 1992/3230 as amended by S.I. 1997/2906.
1981 c. 67. The definition of “owner” was amended by paragraph 9 of Schedule 15 to the Planning and Compensation Act 1992 (c.34). There are other amendments to section 7 which are not relevant to the Order.
Section 64 was amended by Schedule 17 to the Local Government Act 1965 (c. 51) and Schedule 9 to the 1991 Act.
Section 184 was amended by section 4 of, and Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and Schedule 8 to the New Roads and Street Works Act 1991 (c. 22) and sections 35 and 46 of the Criminal Justice Act 1982 (c.48).
Section 56 was amended by section 43 of, and Schedule 1 to, the Traffic Management Act 2004 (c.18).
Section 56A was inserted by section 44 of the Traffic Management Act 2004 (c. 18).
Section 58 was amended by section 51 of, and Schedule 1 to, the Traffic Management Act 2004 (c. 18).
Section 58A was inserted by section 52 of the Traffic Management Act 2004 (c. 18).
Schedule 3A was inserted by Schedule 4 to the Traffic Management Act 2004 (c. 18).
Sections 54, 55, 57, 60, 68 and 69 were amended by sections 40(1) and (2) of, and Schedule 1 to, the Traffic Management Act 2004 (c. 18).
As also amended by section 49(1) of the Traffic Management Act 2004 (c. 18).
As also amended by section 49(2) and 51(9) of the Traffic Management Act 2004 (c. 18).
As also amended by section 52(3) of the Traffic Management Act 2004 (c. 18).
As amended by section 42 of the Traffic Management Act 2004 (c. 18).
1975 c. 23. Section A1 was inserted by section 33 of the Flood and Water Management Act 2010 (c. 29).
Section 24(1) was amended by S.I. 1996/593.
Section 25 was amended by section 2 of the Water Act 2003 and S.I. 2013/755.
Section 48A was inserted by section 24(1) of the Water Act 2003 (c. 37).
Section 90(2A) was inserted by section 16(1) of the Transport and Works Act 1992 (c. 42).
Section 4 was substituted by section 182(1) of the Housing and Planning Act 2016 (c. 22).
Section 4A(1) was inserted by section 202(1) of the Housing and Planning Act 2016 (c. 22).
Section 22 was amended by Schedule 8 to the Tribunals, Courts and Enforcement Act 2007 (c. 15).
Schedule 2A was inserted by paragraph 3 of Part 1 to Schedule 17 of the Housing and Planning Act 2016 (c. 22).
Section 5 was amended by Schedule 15 to the Housing and Planning Act 2016 (c. 22).
Section 5A was inserted by section 182(2) of the Housing and Planning Act 2016 (c. 22).
Section 5B(1) was inserted by section 202(2) of the Housing and Planning Act 2016 (c. 22).
Section 7(1) was substituted by Schedule 18 of the Housing and Plananing Act 2016 (c. 22).
1986 c. 44, as amended by section 76(2) of the Utilities Act 2000 (c. 27).
1991 c. 56, as amended by section 36(2) of the Water Act 2003 (c. 37)..
Section 97 was amended by Schedule 22 to the Localism Act 2011 (c. 20), Schedule 8 to the Housing and Regeneration Act 2008 (c. 17) and Schedule 15 to the Government of Wales Act 1998 (c. 38).
Section 11 was amended by sections 186(2), 187(2) and 188 of, and Schedule 14 to, the Housing and Planning Act 2016 (c.22), Schedule 4 to, the Acquisition of Land Act 1981 (c. 67) and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.
Section 4 was amended by sections 186(2), 187(2) and 188 of, and Schedule 14 to, the Housing and Planning Act 2016 (c.22).
Section 11 was amended by sections 186(2), 187(2) and 188 of, and Schedule 14 to the Housing and Planning Act 2016 (c.22), section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.
Section 13 was amended by sections 62(3) and 139 of, and paragraphs 27 and 28 of Schedule 13, and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
Section 10 was amended by section 4 of, and paragraph 13(2) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and S.I. 2009/1307.
Section 11 was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1) and S.I. 2009/1307.
Section 272 was amended by paragraphs 103(1) and (2) of Schedule 17 to the Communications Act 2003 (c. 21).
Section 32 was amended by Schedule 17 to the Local Government Act 1985 (c. 51) and by paragraph 39 of Schedule 8 to the New Roads and Street Works Act 1991 (c. 22).
1990 c. 43. Section 82 was amended by section 5(2) of the Noise and Statutory Nuisance Act 1993 (c. 40) and paragraph 6 of Schedule 17 to the Environment Act 1995 (c. 25).
Section 79(1) was amended by section 2(2) of the Noise and Statutory Nuisance Act 1993, section 120 of, and paragraph 2(a) of Schedule 17 and paragraph 89(2) of Schedule 22 to, the Environment Act 1995, sections 101(2) and 102(2) of the Clean Neighbourhoods and Environment Act 2005 (c. 16) and sections 109(2), 110(2), 111(2) and 112(2)(a) of the Public Health etc. (Scotland) Act 2008 (asp. 5).
Section 61 was amended by Schedule 7 to the Building Act 1984 (c. 55), paragraph 15(3) of Schedule 15 to the Environmental Protection Act 1990 (c. 43), Schedule 24 to the Environment Act 1995 and paragraph 10 of Schedule 6 to the Building (Scotland) Act 2003 (asp. 8).
Section 11 was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c.67), section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c. 71), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006(No. 1) and S.I 2009/1307.
Section 12 was amended by section 56(2) of, and Part 1 of Schedule 9 to, the Courts Act 1971 (c. 23).
Section 13 was amended by sections 62(3), 139(4) to (9) and 146 of, and paragraphs 27 and 28 of Schedule 13 and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 and S.I. 2009/1307.
1981 c. 66, as amended by Part 7 of the Housing and Planning Act 2016 (c. 22).
Section 279(3) was amended by paragraphs 103(1) and (2), and section 280 was amended by paragraph 104, of Schedule 17 to the Communications Act 2003. Sections 280 and 282 were amended by S.I. 2009/1307.
1980 c. 66 as amended by section 190(3) of, and Part 1 of Schedule 27 to, the Water Act 1989 (c. 15) and section 112(4) of, and Schedule 18 to, the Electricity Act 1989 (c. 29).
Editorial notes
Art. 1 in force at 2.1.2018, see art. 1
Art. 2 in force at 2.1.2018, see art. 1
Art. 3 in force at 2.1.2018, see art. 1
Art. 4 in force at 2.1.2018, see art. 1
Art. 5 in force at 2.1.2018, see art. 1
Art. 6 in force at 2.1.2018, see art. 1
Art. 7 in force at 2.1.2018, see art. 1
Art. 8 in force at 2.1.2018, see art. 1
Art. 9 in force at 2.1.2018, see art. 1
Art. 10 in force at 2.1.2018, see art. 1
Art. 11 in force at 2.1.2018, see art. 1
Art. 12 in force at 2.1.2018, see art. 1
Art. 13 in force at 2.1.2018, see art. 1
Art. 14 in force at 2.1.2018, see art. 1
Art. 15 in force at 2.1.2018, see art. 1
Art. 16 in force at 2.1.2018, see art. 1
Art. 17 in force at 2.1.2018, see art. 1
Art. 18 in force at 2.1.2018, see art. 1
Art. 19 in force at 2.1.2018, see art. 1
Art. 20 in force at 2.1.2018, see art. 1
Art. 21 in force at 2.1.2018, see art. 1
Art. 22 in force at 2.1.2018, see art. 1
Art. 23 in force at 2.1.2018, see art. 1
Art. 24 in force at 2.1.2018, see art. 1
Art. 25 in force at 2.1.2018, see art. 1
Art. 26 in force at 2.1.2018, see art. 1
Art. 27 in force at 2.1.2018, see art. 1
Art. 28 in force at 2.1.2018, see art. 1
Art. 29 in force at 2.1.2018, see art. 1
Art. 30 in force at 2.1.2018, see art. 1
Art. 31 in force at 2.1.2018, see art. 1
Art. 32 in force at 2.1.2018, see art. 1
Art. 33 in force at 2.1.2018, see art. 1
Art. 34 in force at 2.1.2018, see art. 1
Art. 35 in force at 2.1.2018, see art. 1
Art. 36 in force at 2.1.2018, see art. 1
Art. 37 in force at 2.1.2018, see art. 1
Art. 38 in force at 2.1.2018, see art. 1
Art. 39 in force at 2.1.2018, see art. 1
Art. 40 in force at 2.1.2018, see art. 1
Art. 41 in force at 2.1.2018, see art. 1
Art. 42 in force at 2.1.2018, see art. 1
Art. 43 in force at 2.1.2018, see art. 1
Art. 44 in force at 2.1.2018, see art. 1
Art. 45 in force at 2.1.2018, see art. 1
Art. 46 in force at 2.1.2018, see art. 1
Art. 47 in force at 2.1.2018, see art. 1
Art. 48 in force at 2.1.2018, see art. 1
Art. 49 in force at 2.1.2018, see art. 1
Art. 50 in force at 2.1.2018, see art. 1
Art. 51 in force at 2.1.2018, see art. 1
Art. 52 in force at 2.1.2018, see art. 1
Art. 53 in force at 2.1.2018, see art. 1
Art. 54 in force at 2.1.2018, see art. 1
Art. 55 in force at 2.1.2018, see art. 1
Art. 56 in force at 2.1.2018, see art. 1
Art. 57 in force at 2.1.2018, see art. 1
Art. 58 in force at 2.1.2018, see art. 1
Art. 59 in force at 2.1.2018, see art. 1
Art. 60 in force at 2.1.2018, see art. 1
Art. 61 in force at 2.1.2018, see art. 1
Art. 62 in force at 2.1.2018, see art. 1
Art. 63 in force at 2.1.2018, see art. 1
Art. 64 in force at 2.1.2018, see art. 1
Art. 65 in force at 2.1.2018, see art. 1
Art. 66 in force at 2.1.2018, see art. 1
Art. 67 in force at 2.1.2018, see art. 1
Art. 68 in force at 2.1.2018, see art. 1
Art. 69 in force at 2.1.2018, see art. 1
Sch. 3 para. 1 in force at 2.1.2018, see art. 1
Sch. 3 para. 2 in force at 2.1.2018, see art. 1
Sch. 3 para. 3 in force at 2.1.2018, see art. 1
Sch. 3 para. 4 in force at 2.1.2018, see art. 1
Sch. 3 para. 5 in force at 2.1.2018, see art. 1
Sch. 3 para. 6 in force at 2.1.2018, see art. 1
Sch. 3 para. 7 in force at 2.1.2018, see art. 1
Sch. 3 para. 8 in force at 2.1.2018, see art. 1
Sch. 3 para. 9 in force at 2.1.2018, see art. 1
Sch. 3 para. 10 in force at 2.1.2018, see art. 1
Sch. 6 para. 1 in force at 2.1.2018, see art. 1
Sch. 7 para. 1 in force at 2.1.2018, see art. 1
Sch. 7 para. 2 in force at 2.1.2018, see art. 1
Sch. 7 para. 3 in force at 2.1.2018, see art. 1
Sch. 7 para. 4 in force at 2.1.2018, see art. 1
Sch. 7 para. 5 in force at 2.1.2018, see art. 1
Sch. 7 para. 6 in force at 2.1.2018, see art. 1
Sch. 7 para. 7 in force at 2.1.2018, see art. 1
Sch. 7 para. 8 in force at 2.1.2018, see art. 1
Sch. 7 para. 9 in force at 2.1.2018, see art. 1
Sch. 7 para. 10 in force at 2.1.2018, see art. 1
Sch. 7 para. 11 in force at 2.1.2018, see art. 1
Sch. 7 para. 12 in force at 2.1.2018, see art. 1
Sch. 7 para. 13 in force at 2.1.2018, see art. 1
Sch. 8 para. 1 in force at 2.1.2018, see art. 1
Sch. 8 para. 2 in force at 2.1.2018, see art. 1
Sch. 8 para. 3 in force at 2.1.2018, see art. 1
Sch. 8 para. 4 in force at 2.1.2018, see art. 1
Sch. 8 para. 5 in force at 2.1.2018, see art. 1
Sch. 8 para. 6 in force at 2.1.2018, see art. 1
Sch. 8 para. 7 in force at 2.1.2018, see art. 1
Sch. 8 para. 8 in force at 2.1.2018, see art. 1
Sch. 8 para. 9 in force at 2.1.2018, see art. 1
Sch. 8 para. 10 in force at 2.1.2018, see art. 1
Sch. 8 para. 11 in force at 2.1.2018, see art. 1
Sch. 8 para. 12 in force at 2.1.2018, see art. 1
Sch. 8 para. 13 in force at 2.1.2018, see art. 1
Sch. 1 in force at 2.1.2018, see art. 1
Sch. 2 in force at 2.1.2018, see art. 1
Sch. 4 in force at 2.1.2018, see art. 1
Sch. 5 in force at 2.1.2018, see art. 1
Sch. 9 Pt. 1 in force at 2.1.2018, see art. 1
Sch. 9 Pt. 2 in force at 2.1.2018, see art. 1
Order excluded in part (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 41 (with arts. 5, 53, Sch. 8 paras. 6, 64)
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.