The North London Heat and Power Generating Station Order 2017
- (11) At all times when carrying out any works authorised under the Order, the undertaker must comply with the statutory undertaker’s policies for safe working in proximity to gas apparatus “Specification for safe working in the vicinity of National Grid, High pressure Gas pipelines and associated installation requirements for third parties T/SP/SSW22” and the Health and Safety Executive’s “HS(~G)47 Avoiding Danger from underground services”.
- (12) As soon as reasonably practicable after any ground subsidence event attributable to the authorised development, the undertaker must implement an appropriate ground mitigation scheme, provided that the statutory undertaker retains the right to carry out any further necessary protective works for the safeguarding of its apparatus and may recover any such costs in accordance with paragraph 12 (indemnity).
Retained apparatus: Protection: Electricity Undertakers
10
- (1) Not less than 56 days before the commencement of any specified works, the undertaker must submit to National Grid Electricity Transmission Plc (the “statutory undertaker”) a plan of the works to be carried out and seek from the statutory undertaker details of the underground extent of its electricity tower foundations. The statutory undertaker must not unreasonably withhold or delay its provision of those details.
- (2) The plan to be submitted to the statutory undertaker under sub-paragraph 10(1) must include a method statement and describe—
- (a) the exact position of the works;
- (b) the level at which these are proposed to be constructed or renewed;
- (c) the manner of their construction or renewal including details of excavation, positioning of plant;
- (d) the position of all apparatus;
- (e) by way of detailed drawings, every alteration proposed to be made to or close to any such apparatus;
- (f) any intended maintenance regimes; and
- (g) an assessment of risks of rise of earth issues.
- (3) In relation to any works which will or may be situated on, over, under or within 10 metres of any part of the foundations of an electricity tower or between any two or more electricity towers, the plan to be submitted under sub-paragraph 10(1) must, in addition to the matters set out in sub-paragraph 10(2), include a method statement describing—
- (a) details of any cable trench design including route, dimensions and clearance to pylon foundations;
- (b) how pylon foundations will not be affected prior to, during and post-construction;
- (c) details of load-bearing capacities of trenches;
- (d) details of cable installation methodology including access arrangements, jointing bays and backfill methodology;
- (e) a written management plan for high voltage hazard during construction and ongoing maintenance of the cable route;
- (f) written details of the operations and maintenance regime for the cable, including frequency and method of access;
- (g) an assessment of earth rise potential if reasonably required by the statutory undertaker’s engineers; and
- (h) evidence that trench-bearing capacity is to be designed to 26 tonnes to take the weight of overhead line construction traffic.
- (4) The undertaker must not commence any works to which sub-paragraphs 10(2) or 10(3) applies until the statutory undertaker has given written approval of the plan so submitted.
- (5) Any approval of the statutory undertaker required under sub-paragraphs 10(2) or 10(3)—
- (a) may be given subject to reasonable conditions for any purpose mentioned in sub-paragraphs 10(6) or 10(8); and
- (b) must not be unreasonably withheld or delayed.
- (6) In relation to any work to which sub-paragraphs 10(2) or 10(3) applies, the statutory undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its apparatus against interference or risk of damage or for the purpose of providing or securing proper and necessary means of access to any apparatus.
- (7) Works to which this paragraph applies must be carried out only in accordance with the plan, submitted under sub-paragraph 10(1), as approved or as amended from time to time by agreement between the undertaker and the statutory undertaker and in accordance with such reasonable requirements as may be made in accordance with sub-paragraphs 10(6) or 10(8) by the statutory undertaker for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and the statutory undertaker is entitled to watch and inspect the execution of those works.
- (8) Where the statutory undertaker requires any protective works to be carried out by itself or by the undertaker (whether of a temporary or permanent nature), such protective works, inclusive of any measures or schemes required and approved as part of the plan approved pursuant to this paragraph, must be carried out to the statutory undertaker’s satisfaction (the statutory undertaker’s confirmation of whether it is satisfied or not is not to be unreasonably withheld or delayed) prior to the commencement of any specified works (or any relevant part thereof) for which protective works are required, and the statutory undertaker must give at least 56 days’ notice of such works from the date of submission of a plan pursuant to this paragraph (except in an emergency).
- (9) If the statutory undertaker in accordance with sub-paragraphs 10(6) or 10(8) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs 7 to 9 apply as if the removal of the apparatus had been required by the undertaker under paragraph 7(2).
- (10) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 56 days before commencing the execution of the specified works, a new plan, instead of the plan previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan.
- (11) The undertaker is not required to comply with sub-paragraph 10(1) where it needs to carry out emergency works as defined in the 1991 Act, but in that case it must give to the statutory undertaker notice as soon as is reasonably practicable and a plan of those works and must—
- (a) comply with sub-paragraphs 10(6), 10(7) and 10(8) insofar as is reasonably practicable in the circumstances; and
- (b) comply with sub-paragraph 10(12) at all times.
- (12) At all times when carrying out any works authorised under the Order, the undertaker must comply with the statutory undertaker’s policies for development near overhead lines EN43-8 and the Health and Safety Executive’s guidance note 6 “Avoidance of Danger from Overhead Lines”.
Expenses
11
- (1) Subject to the following provisions of this paragraph, the undertaker must pay to the statutory undertaker on demand all charges, costs and expenses reasonably anticipated or reasonably and properly incurred by the statutory undertaker in, or in connection with, the inspection, removal, relaying or replacing, alteration or protection of any apparatus or the construction of any new or alternative apparatus which may be required in consequence of the carrying out of any authorised works including without limitation—
- (a) the cost of the carrying out of any diversion work;
- (b) the cutting off of any apparatus from any other apparatus or the making safe of redundant apparatus;
- (c) the carrying out of protective works;
- (d) the survey of any land, apparatus or works, the inspection and monitoring of works or the installation or removal of any temporary works reasonably necessary in consequence of the execution of any authorised works; and
- (e) the approval of plans.
- (2) There must be deducted from any sum payable under sub-paragraph 11(1) the value of any apparatus removed under the provisions of this Part, that value being calculated after removal.
- (3) If in accordance with the provisions of this Part—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was situated,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 34 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this Part exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to the statutory undertaker by virtue of sub-paragraph (1) must be reduced by the amount of that excess save where it is not possible in the circumstances to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs must be borne by the undertaker.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus must not be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to a statutory undertaker in respect of works by virtue of sub-paragraph (1) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the statutory undertaker any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
Indemnity
12
- (1) Subject to sub-paragraphs 12(2) and 12(3), if by reason or in consequence of the construction of any such works authorised by this Part or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by the undertaker) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part or any subsidence resulting from any of these works, any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of the statutory undertaker, or there is any interruption in any service provided, or in the supply of any goods, by the statutory undertaker, or the statutory undertaker becomes liable to pay any amount to any third party, the undertaker must—
- (a) bear and pay on demand the cost reasonably and properly incurred by the statutory undertaker in making good such damage or restoring the supply; and
- (b) indemnify the statutory undertaker for any other proper and reasonable expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from the statutory undertaker, by reason or in consequence of any such damage or interruption or the statutory undertaker becoming liable to any third party as aforesaid other than arising from any default of the statutory undertaker.
- (2) The fact that any act or thing may have been done by the statutory undertaker with the agreement of and on behalf of the undertaker or in accordance with a plan submitted by the undertaker and approved by the statutory undertaker or in accordance with any requirement of the statutory undertaker or under its supervision does not (unless sub-paragraph 12(3) applies), excuse the undertaker from liability under the provisions of sub-paragraph 12(1) unless the statutory undertaker fails to carry out and execute the works properly with due care and attention and in a skilful and workmanlike manner or in a manner that does not accord with the approved plan.
- (3) Nothing in sub-paragraph 12(1) imposes any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of the statutory undertaker, its officers, servants, contractors or agents; and
- (b) any authorised works or any other works authorised by this Part carried out by the statutory undertaker as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 of the 2008 Act or article 8 (consent to transfer benefit of Order) subject to the proviso that once such works become apparatus, any authorised works yet to be executed and not falling within this paragraph 12(3)(b) are subject to the full terms of this Part including this paragraph 12.
- (4) The statutory undertaker must give the undertaker reasonable written notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and taking into account undertaker’s representations.
Enactments and agreements
13
Save to the extent provided for to the contrary elsewhere in this Part or by agreement in writing between the statutory undertaker and the undertaker, nothing in this Part affects the provisions of any enactment or agreement regulating the relations between the undertaker and the statutory undertaker in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
14
- (1) Where in consequence of the proposed construction of any of the authorised works, the undertaker or the statutory undertaker requires the removal of apparatus under paragraph 7(2) or the statutory undertaker makes requirements for the protection or alteration of apparatus under paragraphs 9 or 10, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and taking into account the need to ensure the safe and efficient operation of the statutory undertaker’s undertaking, and the statutory undertaker must use its best endeavours to co-operate with the undertaker for that purpose.
- (2) To avoid doubt, whenever the statutory undertaker’s consent, agreement or approval is required in relation to plans, documents or other information submitted by the undertaker or the taking of action by the statutory undertaker, it must not be unreasonably withheld or delayed.
Access
15
If in consequence of the powers granted under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable the statutory undertaker to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
16
Any difference or dispute arising between the undertaker and the statutory undertaker under this Part must, unless otherwise agreed in writing between the undertaker and the statutory undertaker, be determined by arbitration in accordance with article 34 (arbitration).
Approval Process
17
When submitting the plans to the statutory undertaker for approval under paragraph 8 or paragraph 9 the undertaker must send the plans to the statutory undertaker in hard copy by recorded post and by email to such address as the statutory undertaker may notify the undertaker in writing from time to time and clearly bearing the name of the project and contact details for responses, unless otherwise agreed with statutory undertaker.
Signed
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
Giles Scott — Head of Energy Infrastructure Planning and Coal Liabilities — Department for Business, Energy and Industrial Strategy — 24th February 2017
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order grants development consent for, and authorises North London Waste Authority (referred to in this Order as the undertaker) to construct, operate and maintain, an electricity and heat generating station with a gross generating capacity of up to 70 megawatts of electricity fuelled by waste-derived fuels, together with associated development, in Edmonton, North London. The Order also permits the undertaker to acquire, compulsorily or by agreement, land and rights in land and to use land for this purpose.
A copy of the Order and of the plans and the book of reference mentioned in this Order and certified in accordance with article 33 of the Order (certification of documents and plans) may be inspected free of charge during working hours at the offices of North London Waste Authority, Unit 1B, Berol House, 25 Ashley Road, Tottenham Hale, London N17 9LJ and at the offices of Enfield Borough Council, Civic Centre, Silver Street, Enfield EN1 3XA.
Footnotes
[^f00001]: 2008 c.29 Parts 3 and 6 were amended by Section 137 and Schedule 13 to the Localism Act 2011 (c.20).
[^f00002]: S.I. 2009/2264, amended by the Localism Act 2011 (Infrastructure Planning) (Consequential Amendments) Regulations 2012 (S.I. 2012/635), Infrastructure Planning (Prescribed Consultees and Interested Parties etc) (Amendment Regulations 2012 (S.I. 2012/635), Infrastructure Planning (Prescribed Consultees and Interested Parties etc) (Amendment) Regulations 2013 (S.I. 2013/522), Infrastructure Planning (Applications: Prescribed Forms and Procedure) (Amendment) Regulations 2014 (S.I. 2014/2381) and the Infrastructure Planning (Environmental Impact Assessment) (Amendment) Regulations 2012 (S.I. 2012/787).
[^f00003]: 2008 c.29. Sections 86-98 as amended by the Localism Act 2011, Schedule 13 (S.I. 2010/103) and the Localism Act 2011 (Infrastructure Planning) (Consequential Amendments) Regulations 2012 (S.I. 2012/635).
[^f00004]: S.I. 2009/2263 as amended by the Localism Act 2011 (Infrastructure Planning) (Consequential Amendments) Regulations 2012 (S.I. 2012/635) and Infrastructure Planning (Environmental Impact Assessment) (Amendment) Regulations 2012 (S.I. 2012/787).
[^f00005]: 1961 c.33. Section 1 and subsections (A1), (1) and (3)-(6) of section 4 were amended by articles 5(1), (2) (6) of, and paragraphs 31, 37(a), 37(b), 38, 39(a), 39(b), 39(c), of Schedule 1 and Schedule 5 of Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307). There are other amendments to the 1961 Act which are not relevant to this Order.
[^f00006]: 1965 c.56. Subsections (1)-(3) of section 1 and section 30 were amended by subsections (1) and (3) of section 34 of, and paragraph 14 of Schedule 4 to, and Schedule 6 to, the Acquisition of Land Act 1981 (c.67). Subsection (4) of section 1 was amended by section 4 of and paragraph 13(1)(a) and (b) of Schedule 2 to the Planning (Consequential Provisions) Act 1990 (c. 11). Subsection (5) of section 1 was amended by section 109 of and paragraph 124 of Schedule 10 to, the Courts Act 2003 (c.39). Section 3 was amended by section 70 of, and paragraph 3 of Schedule 15 to, the Planning and Compensation Act 1991(c.34). Section 4 and subsection (2) of section 11 were amended by section 3 of, and Part 1 of Schedule 1 to, the Housing (Consequential Provisions) Act 1985 (c.71). Section 5 was amended by section 67 of the Planning and Compensation Act 1991 (c.34). Subsection (2A)(d) and 2(d) of section 5, section 6, subsections (1) and (3) of section 8 and subsection (1) of section 10, subsection (3) of section 11, subsection (1) of section 15, subsection (1) of section 16, subsection (2) of section 17, subsections (1) and (2)(b) of section 18, subsection (2) of section 19 and subsection (3) of section 20 were amended by articles 5(1), (2) and (6) of, and paragraphs 59, 61, 62, 63, 65, 66, 67, 68, 69 ad 70 of Schedule 1 to, and Schedule 5 to the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307). Subsection (3) of section 10 was amended by section 4 of, and paragraph 13(2)(a) and (b) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11). Subsection (1) of section 11 and sections 31 and 32 were amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c.67) and by sections 14 and 70 of, and paragraphs 12(1) and 12(2) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (2006 No.1). Section 12 was amended by section 56(2) of, and Part 1 to Schedule 9 to, the Courts Act 1971 (c.23). Section 13 was amended by sections 62 and 139 of, and paragraphs 27 and 28(1) and (2) to, the Tribunals, Courts and Enforcement Act 2007 (c.15). Subsection 2 of section 20 was amended by section 70 of, and paragraph 4 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). Subsections 3 and 4 of section 23 and subsection (1) of section 25 were amended by section 59 of, and paragraph 4 of part 2 of Schedule 11 to, the Constitutional Reform Act 2005 (c.4). Section 31 was also amended by section 70 of, and paragraph 19 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). There are other amendments to the 1965 Act which are not relevant to this Order.
[^f00007]: 1980 c.66. Section 1(1) was amended by section 21(2) of the New Roads and Street Works Act 1991 (c.22); sections 1(2), 1(3) and 1(4) were amended by section 8 of, and paragraph (1) of Schedule 4 to, the Local Government Act 1985 (c.51); section 1(2A) was inserted, and section 1(3) was amended, by section 259(1), (2) and (3) of the Greater London Authority Act 1999 (c.29); sections 1(3A) and 1(5) were inserted by section 22(1) of, and paragraph 1 of Schedule 7 to, the Local Government (Wales) Act 1994 (c.19). Section 36(2) was amended by section 4(1) of, and paragraphs 47(a) and (b) of Schedule 2 to, the Housing (Consequential Provisions) Act 1985 (c.71), by S.I. 2006/1177, by section 4 of, and paragraph 45(3) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11); section 36(3A) was inserted by section 64(4) of the Transport and Works Act 1992 and was amended by S.I. 2006/1177; section 36(6) was amended by section 8 of, and paragraph 7 of Schedule 4 to, the Local Government Act 1985 (c.51); and section 36(7) was inserted by section 22(1) of, and paragraph 4 of Schedule 7 to, the Local Government (Wales) Act 1994 (c.19). Section 329 was amended by section 112(4) of, and Schedule 18 to, the Electricity Act 1989 (c.29) and by section 190(3) of, and Part 1 of Schedule 27 to, the Water Act 1989 (c.15). There are other amendments to the 1980 Act which are not relevant to this Order.
[^f00008]: 1990 c.8. Subsection (4)(aa) of section 56 was added by Planning and Compensation Act 1991 (c.34). Subsection (5)(a) of section 56 was amended by subsection (2)(a) of section 40 of the Planning and Compulsory Purchase Act 2004 (c.5) and subsection (1) of section 30 of, and paragraphs 2 and 3 of part 2 of Schedule 4 to, the Infrastructure Act 2015 (c.7). Subsection (5)(b) of section 56 was amended by subsection (4) of section 31 of, and paragraphs 8 and 10 of Schedule 6 to, Planning and Compensation Act 1991 (c.34). Subsections (3), (4), (6) and (7) of section 198 were amended by subsection (1) of section 192 and subsection (2)(a) of section 238 of, and paragraphs 7 and 8 of Schedule 8 to, and Schedule 13 to, the 2008 Act. Subsection (4)(a) of section 198 was amended by sections 31, 32, 42 and 84 of, and paragraphs 8 and 20 of Schedule 6 and paragraphs 8 and 34 of Schedule 7 to and Parts 1 and 2 of Schedule 19 to, the Planning and Compensation Act 1991 (c.34). Subsections (8) and (9) of section 198 were amended by subsection (3) of section 42 to the Planning and Compulsory Purchase Act 2004 (c.5). There are other amendments to the 1990 Act which are not relevant to this Order.
[^f00009]: 1991 c.22. Sections 48(3A) and 50(1A), were inserted by section 124 of the Local Transport Act 2008 (c.26). Sections 49, subsection (3) of section 63, subsection 7A(a) of section 74, subsections (2) and (10)(a) and section 86 were amended by subsection (6) of section 1 of, and paragraphs 113, 117 - 121 of part 2 of Schedule 1 to, the Infrastructure Act 2015 (c.7) Sections 51, 53-60, 65-69, subsections (1A), (4), (4B) and (6) of section 70, 71-72, 73A-73F, subsections (3)(b) and (7B) of section 74, 75, 78A, 39-80, 83, 88, subsection (2) of section 89, 90, 92-93, 95A and 96-97 were amended by sections 40, 42-45, 47-56, 58 and 59 of, and Schedule 1 to, the Traffic Management Act 2004 (c.18). Subsection (5) of section 63 was added by section 32 of, and paragraph 27 of schedule 3 to, the Flood and Water Management Act 2010 (c.29). Subsection (4) of section 64 was added by section 81 of, and paragraph 7 of Schedule 2 to, the Road Traffic Act 1991 (c.40). Subsections (3) and (4A) of section 70 were amended by regulation 17E of The Street Works (Registers, Notices, Directions and Designations) (England) Regulations 2007 (S.I. 2007/1951). Subsections (2A), (3), (3)(b), (4), (5A)-(5C), (7), (7A) and (7B) were amended by sections 256 and 274 of, and part V(2) of Schedule 31 to, the Transport Act 2000 (c.38). Subsection (1)(a) of section 89 was amended by subsection (1) of section 2 of, and paragraph 57(1) of Schedule 1 to, the Water Consolidation (Consequential Provisions) Act 1991 (c.60). There are other amendments to the 1991 Act which are not relevant to this Order.
[^f00010]: 1981 c. 67. Section 4 was amended by articles 5(1), (2) and (6) of, paragraphs 149 and 150 of Schedule 1 to, and Schedule 5 to, the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307). Section 7 was amended by article 8 of, and paragraph 23 of part 1 of Schedule 3 to, S.I. 1990/776, sections 70 and subsections (1), (3) and (8) of, and paragraph 9 of part 1 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34); section 328 of, and paragraphs 34(1) and (2) of part 1 of Schedule 29 to, the Greater London Authority Act 1999 (c.29), article 3(1), and sub-paragraphs (1) and (2) of paragraph 54 of Schedule 1 to, the Local Government Finance (Repeals, Savings and Consequential Amendments) Order 1990 (S.I. 2001/1149); section 53(1) of, and paragraph 53 of Schedule 1 to, the Fire and Rescue Services Act 2004 (c.21); and section 91 of, and paragraph 110 of part 3 of Schedule 12 to, the Postal Services Act 2011 (c.5). There are other amendments to this Act which are not relevant to this Order.
[^f00011]: A joint statutory waste disposal authority.
[^f00012]: 1990 c.43. Subsection (1) of section 79 was amended by section 24 of the London Local Authorities Act 1996 (c.i), section 120 of, paragraphs 1 and 2(a) of Schedule 17 to, paragraph 89 of Schedule 22 to, and Schedule 24 to the Environment Act 2005 (c.25), section 101 of the Clean Neighbourhoods and Environment Act 2005 (c.16) and section 2 of the Noise and Statutory Nuisance Act 1993 (c.40). Section 82 was amended by section 107 of and paragraphs 1 and 6 of Schedule 17 to, the Environment Act 1995 (c.25), section 5 of the Noise and Statutory Nuisance Act 1993 (c.40), and section 103 of the Clean Neighbourhoods and Environment Act 2005 (c.16). There are other amendments to this Act which are not relevant to this Order.
[^f00013]: 1974 c.40. Section 61(9) was amended by section 162 of, and paragraph 15 of Schedule 3 to, the Environmental Protection Act 1990 (c.25). There are other amendments to this Act which are not relevant to this Order.
[^f00014]: S.I. 2014/1052.
[^f00015]: 1991 c.56. Section 106 has been amended by sections 35, 43 and 56 of the Competition and Service (Utilities) Act 1992 (c.43), sections 36 and 99 of the Water Act 2003 (c.37) and section 32 of, and paragraph 16(1) of Schedule 3 to, the Flood and Water Management Act 2010 (c.29). There are other amendments to this Act that are not relevant to this Order.
[^f00016]: 1991 c.57. There are other amendments to this Act that are not relevant to this Order.
[^f00017]: 1981 c.66, Sections 2 and 6 and subsection (6) of section 11 have been amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11). Section 3 has been amended by section 34 of, and paragraph 37 of part 3 of Schedule 5 to, the Infrastructure Act 2015 (c.7). Section 10, subsection (4) of section 11 and paragraphs 4, 8 and 9 of Schedule 1 have been amended by article 5 of, paragraphs 145 – 148 of Schedule 1 to, and Schedule 5 to, the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307). Section 15 and Schedule 2 have been amended by section 161 of, and paragraphs 6 and 7 of Schedule 19 to, the Leasehold Reform, Housing and Urban Development Act 1993 (c.28) and sections 56 and 321 of, paragraph 33 of Schedule 8 to, and Schedule 16 to the Housing Regeneration Act 2008 (c.17). Paragraphs 1 and 3 have also been amended by section 76 of, and paragraph 12 of part II of Schedule 9 to, the Housing Act 1988 (c.50). Schedule 3 was amended by section 277 of, and Schedule 9 to, the Inheritance Tax Act 1984 (c.51). There are other amendments to this Act that are not relevant to this Order.
[^f00018]: 1981 c.66, Sections 2 and 6 and subsection (6) of section 11 have been amended by section 4 of, and paragraph 52 of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c.11). Section 3 has been amended by section 34 of, and paragraph 37 of part 3 of Schedule 5 to, the Infrastructure Act 2015 (c.7). Section 10, subsection (4) of section 11 and paragraphs 4, 8 and 9 of Schedule 1 have been amended by article 5 of, paragraphs 145 – 148 of Schedule 1 to, and Schedule 5 to, the Transfer of Tribunal Functions (Lands Tribunal and Miscellaneous Amendments) Order 2009 (S.I. 2009/1307). Section 15 and Schedule 2 have been amended by section 161 of, and paragraphs 6 and 7 of Schedule 19 to, the Leasehold Reform, Housing and Urban Development Act 1993 (c.28) and sections 56 and 321 of, paragraph 33 of Schedule 8 to, and Schedule 16 to the Housing Regeneration Act 2008 (c.17). Paragraphs 1 and 3 have also been amended by section 76 of, and paragraph 12 of part II of Schedule 9 to, the Housing Act 1988 (c.50). Schedule 3 was amended by section 277 of, and Schedule 9 to, the Inheritance Tax Act 1984 (c.51). There are other amendments to this Act that are not relevant to this Order.
[^f00019]: 2003 c.21. There are other amendments to this Act that are not relevant to this Order.
[^f00020]: 1974 c.40 Section 61 has been amended by the Building (Scotland) Act 2008; section 58 of the Building Act 1984 (c.55); Schedule 24 of the Environmental Act 1995 (c.25); section 162(i) of, and paragraph 15 of Schedule 15 to, the Environmental Protection Act 1990 (c.43).
[^f00021]: 1990 c.43.
[^f00022]: 1974 c.40. Section 61 has been amended by the Building (Scotland) Act 2008; section 58 of the Building Act 1984 (c.55); Schedule 24 of the Environment Act 1995 (c.25); and section 162(1) of, and paragraph 15 of Schedule 15 to, the Environmental Protection Act 1990 (c.25).
[^f00023]: 1973 c. 26. Section 44 was amended by paragraph 13(b) of Schedule 24 to the Highways Act 1980, paragraph 14(d) of Schedule 7 to the Gas Act 1986 (c.44) and paragraph 23 of Schedule 1 to the Water Consolidation (Consequential Provisions) Act 1991 (c.60).
[^f00024]: 1989 c.29. Section 6(1) has been amended by section 30 of the Utilities Act 2000 (c.27) and sections 136 and 197 of, and part 1 of Schedule 23 to, the Energy Act 2004 (c.20). Section 64 has been amended by article 24(c) of the Competition Act 1998 (Competition Commission) Transitional, Consequential and Supplemental Provisions Order 1999 (S.I. 1999/506), section 108 of, paragraphs 24 and 38 of part 2 of Schedule 6 to, and Schedule 8 to the Utilities Act 2000 (c.27), sections 44, 89, 102, 143, 147, 180 and 197 of, paragraphs 3 and 15 of Schedule 19 to, and Part 1 of Schedule 23 to, the Energy Act 2000 (c.20), section 79 of, and paragraph 5 of Schedule 8 to, the Climate Change Act 2008 (c.27), section 72 of, and paragraph 5 of Schedule 8 to, the Energy Act 2011 (c.16), regulation 48 of the Electricity and Gas (Internal Markets) Regulations 2011 (S.I. 2011/2704), articles 2 and 13 of the Electricity and Gas (Smart Meters Licensable Activity) Order 2012 (S.I. 2012/2400), section 26 of, and paragraphs 30 and 43 of part 1 of Schedule 6 to, the Enterprise and Regulatory Reform Act 2013 (c.24), and regulation 5 of the Electricity and Gas (Internal Markets) Regulations (S.I. 2014/3332).
[^f00025]: 1986 c.44. Section 7 (1) was amended by section 76 of the Utilities Act 2000 (c.27) and section 197 of, and part 1 of Schedule 23 to, the Energy Act 2004 (c.20).
Editorial notes
[^key-078f5c9a401e23b9b8602e50d18a4c19]: Art. 1 in force at 18.3.2017, see art. 1
[^key-d302815e7321e9709182918ceefaba62]: Art. 2 in force at 18.3.2017, see art. 1
[^key-5836136c6f36c097fde23d56dc1c9af7]: Art. 3 in force at 18.3.2017, see art. 1
[^key-5fb5cccafd06f7d67f123c72a29463d5]: Art. 4 in force at 18.3.2017, see art. 1
[^key-cddf878abbcefb11c9cc50e2819f62af]: Art. 5 in force at 18.3.2017, see art. 1
[^key-2b834c234e78cb5702a158fa75667d07]: Art. 6 in force at 18.3.2017, see art. 1
[^key-975174126a2b590556701086520fc9bf]: Art. 7 in force at 18.3.2017, see art. 1
[^key-e4b612b3d6a7a2cdc0701431efce9335]: Art. 8 in force at 18.3.2017, see art. 1
[^key-7a80892a18271c83f7d490dd20c98741]: Art. 9 in force at 18.3.2017, see art. 1
[^key-bec95dfe5f61ddc28730f9e6036fd998]: Art. 10 in force at 18.3.2017, see art. 1
[^key-b26acd6f88de83f509f81f5a432ded90]: Art. 11 in force at 18.3.2017, see art. 1
[^key-2222b455ed70fd7a78517d828ae31ce9]: Art. 12 in force at 18.3.2017, see art. 1
[^key-6c0997224b71969cd7a420a46dc00929]: Art. 13 in force at 18.3.2017, see art. 1
[^key-b72777740685325be702a648f8971d4d]: Art. 14 in force at 18.3.2017, see art. 1
[^key-19a73cfb98540f3f6183c5d8aee2c282]: Art. 15 in force at 18.3.2017, see art. 1
[^key-50248170728eb6f57ae618f8962fbcb5]: Art. 16 in force at 18.3.2017, see art. 1
[^key-ae2a2161e366fac692288e2a5526a1bb]: Art. 17 in force at 18.3.2017, see art. 1
[^key-a47f21b9770dc041c94099d2ec026fb7]: Art. 18 in force at 18.3.2017, see art. 1
[^key-3fa0f394c7eeb38e8254496a40606c59]: Art. 19 in force at 18.3.2017, see art. 1
[^key-ae5637057c7df170df401c7be9381a2a]: Art. 20 in force at 18.3.2017, see art. 1
[^key-9f403fb292a101e379e7f495f7bd237f]: Art. 21 in force at 18.3.2017, see art. 1
[^key-5dfdeacc0df40b0d8f487f7820293978]: Art. 22 in force at 18.3.2017, see art. 1
[^key-e7f1293b85db147aec76f4540f8c582f]: Art. 23 in force at 18.3.2017, see art. 1
[^key-7987917322ef44e784448dd1d7f747b0]: Art. 24 in force at 18.3.2017, see art. 1
[^key-95cb909433d74d45695c7ce268c94922]: Art. 25 in force at 18.3.2017, see art. 1
[^key-87494d1dda5439457b1a136ed2c9c0f6]: Art. 26 in force at 18.3.2017, see art. 1
[^key-be0eca404ca681f7a1f61e148eeb08d8]: Art. 27 in force at 18.3.2017, see art. 1
[^key-11b86bb6421c0064c7f64ee25cedcef9]: Art. 28 in force at 18.3.2017, see art. 1
[^key-8cf136cb75340822dd2a6f511c8ea5cd]: Art. 29 in force at 18.3.2017, see art. 1
[^key-2b3c3d93deec99d020ed732b3ecdc700]: Art. 30 in force at 18.3.2017, see art. 1
[^key-9cde9588881637655298524c38eb447c]: Art. 31 in force at 18.3.2017, see art. 1
[^key-924d24aea769fd98e43fe48b8a2d5e4d]: Art. 32 in force at 18.3.2017, see art. 1
[^key-a9a2276c7bea834d98381454998d1874]: Art. 33 in force at 18.3.2017, see art. 1
[^key-cf93d2e33dcb0563849e366200aad449]: Art. 34 in force at 18.3.2017, see art. 1
[^key-fa42137220164066090e5983bff29147]: Art. 35 in force at 18.3.2017, see art. 1
[^key-655e3628004cf66a76be7616c1e1dc84]: Art. 36 in force at 18.3.2017, see art. 1
[^key-b97a15fc15b8f7851fb4544aacc711b6]: Art. 37 in force at 18.3.2017, see art. 1
[^key-464e7df0352a646d448f573fa492e053]: Sch. 1 para. 1 in force at 18.3.2017, see art. 1
[^key-57efd3173112107ed1f06ce114762ce8]: Sch. 1 para. 2 in force at 18.3.2017, see art. 1
[^key-cb94726ff7f69b6667d09e2ba7025ef5]: Sch. 1 para. 3 in force at 18.3.2017, see art. 1
[^key-71bea02124744f79fbc6c3d53b69b9fa]: Sch. 2 para. 1 in force at 18.3.2017, see art. 1
[^key-3fb18b42c5cf00bc10fa923794cf69ec]: Sch. 2 para. 2 in force at 18.3.2017, see art. 1
[^key-4868952e04a9791c3a8f93429fd2fc79]: Sch. 2 para. 3 in force at 18.3.2017, see art. 1
[^key-a8fba7d5822adc5f46c1fb07d8db8c3e]: Sch. 2 para. 4 in force at 18.3.2017, see art. 1
[^key-9a706c4a43a6e282a23eca39b769be31]: Sch. 2 para. 5 in force at 18.3.2017, see art. 1
[^key-667fd0977f8f23918d8420ed3a6f4a4b]: Sch. 2 para. 6 in force at 18.3.2017, see art. 1
[^key-06b7691fc67c88b92ad73cd0b0c59dde]: Sch. 2 para. 7 in force at 18.3.2017, see art. 1
[^key-512072ee6b2763a926513eb456af801b]: Sch. 2 para. 8 in force at 18.3.2017, see art. 1
[^key-227ff1b8a4a7a8636580baaf5aaa4ff2]: Sch. 2 para. 9 in force at 18.3.2017, see art. 1
[^key-0868a9b8ce8cbff49c46ee96192304c9]: Sch. 2 para. 10 in force at 18.3.2017, see art. 1
[^key-3fa6e27cdec65ef8e012559492f34ba3]: Sch. 2 para. 11 in force at 18.3.2017, see art. 1
[^key-75d95915ed104e88debc6c2423292d0a]: Sch. 2 para. 12 in force at 18.3.2017, see art. 1
[^key-da14557f88340dd1d5afbe8a15d4014f]: Sch. 2 para. 13 in force at 18.3.2017, see art. 1
[^key-e4ce5b6ca2bffe187165ce36895f4e0d]: Sch. 2 para. 14 in force at 18.3.2017, see art. 1
[^key-b3a25dfebfc7c4ef2f59f2e81fc4f479]: Sch. 2 para. 15 in force at 18.3.2017, see art. 1
[^key-d1a8f9e17b530ca273eca59d2ef24071]: Sch. 2 para. 16 in force at 18.3.2017, see art. 1
[^key-2b1444cd5fc7217d205fba91fee52bf1]: Sch. 2 para. 17 in force at 18.3.2017, see art. 1
[^key-21eafa7963eacfbda8ed43cc73b8eb15]: Sch. 2 para. 18 in force at 18.3.2017, see art. 1
[^key-54c89b227709595aea4b097f6dc2da1c]: Sch. 2 para. 19 in force at 18.3.2017, see art. 1
[^key-fce84145d915abd5f5a4edd9f937ef56]: Sch. 2 para. 20 in force at 18.3.2017, see art. 1
[^key-070dcf0a8f0d528ca8a8bfd58707bf89]: Sch. 2 para. 21 in force at 18.3.2017, see art. 1
[^key-13abbeef5f27b227ebfd66999fa923f5]: Sch. 3 para. 1 in force at 18.3.2017, see art. 1
[^key-46faf6e7325b4e44338aee7b096a5269]: Sch. 3 para. 2 in force at 18.3.2017, see art. 1
[^key-7f4cc1fdaeb8179531ee0369c9be00a0]: Sch. 3 para. 3 in force at 18.3.2017, see art. 1
[^key-ef3221657674b8cccbb16439d668c748]: Sch. 3 para. 4 in force at 18.3.2017, see art. 1
[^key-c90ddf5222de682c6d67c7574b372631]: Sch. 11 para. 1 in force at 18.3.2017, see art. 1
[^key-9fcce4a13f0ad551e74b97cd15072bd5]: Sch. 11 para. 2 in force at 18.3.2017, see art. 1
[^key-87a8248043f531d206f5db71a1a74b52]: Sch. 11 para. 3 in force at 18.3.2017, see art. 1
[^key-f5f0445e5398bd82d75f0702d7287bf5]: Sch. 11 para. 4 in force at 18.3.2017, see art. 1
[^key-dc30dadfd51fe0e02e37156855570588]: Sch. 11 para. 5 in force at 18.3.2017, see art. 1
[^key-3247c777d1282c5f8c348d178c7dabcf]: Sch. 13 Pt. 1 para. 1 in force at 18.3.2017, see art. 1
[^key-f600f5408798e521c086eb688c760843]: Sch. 13 Pt. 1 para. 2 in force at 18.3.2017, see art. 1
[^key-c34a27fc039f93b617430dbb8e17dbf8]: Sch. 13 Pt. 1 para. 3 in force at 18.3.2017, see art. 1
[^key-18aa55c4045ba2409781c8b81429245c]: Sch. 13 Pt. 1 para. 4 in force at 18.3.2017, see art. 1
[^key-259617a51b43325e73d307257e7508fa]: Sch. 13 Pt. 1 para. 5 in force at 18.3.2017, see art. 1
[^key-fb06be244d79f06fc1fef04130404e4a]: Sch. 13 Pt. 1 para. 6 in force at 18.3.2017, see art. 1
[^key-e36cc85a3b2407f05d6da5e73cadef12]: Sch. 13 Pt. 1 para. 7 in force at 18.3.2017, see art. 1
[^key-5fa1f2247e0c09d657ad96076efb2107]: Sch. 13 Pt. 2 para. 1 in force at 18.3.2017, see art. 1
[^key-afaa250add4362a369e7be413ef469e5]: Sch. 13 Pt. 2 para. 2 in force at 18.3.2017, see art. 1
[^key-5458a5ba99705469f7a0ff2ca144b2c3]: Sch. 13 Pt. 2 para. 3 in force at 18.3.2017, see art. 1
[^key-a8571e7a814d6107c57bde0f03af90b2]: Sch. 13 Pt. 2 para. 4 in force at 18.3.2017, see art. 1
[^key-b66b0ec96ecaf4c1cf3d54a0775e776f]: Sch. 13 Pt. 2 para. 5 in force at 18.3.2017, see art. 1
[^key-e03d33c1f18eee37a22d8c893f4cd174]: Sch. 13 Pt. 2 para. 6 in force at 18.3.2017, see art. 1
[^key-d7dfc4fbfa89d34d2c534ab76603e316]: Sch. 13 Pt. 2 para. 7 in force at 18.3.2017, see art. 1
[^key-1fb3cbd029d2bfebb99151d5ebadbbeb]: Sch. 13 Pt. 2 para. 8 in force at 18.3.2017, see art. 1
[^key-b56c2c36af7fe5e6034987536e64185c]: Sch. 13 Pt. 2 para. 9 in force at 18.3.2017, see art. 1
[^key-7900c2a84aacdea2ee8e7f9621413c8c]: Sch. 13 Pt. 2 para. 10 in force at 18.3.2017, see art. 1
[^key-27794061586357c882e8ddc9a034ad73]: Sch. 13 Pt. 3 para. 1 in force at 18.3.2017, see art. 1
[^key-c3c53591a37ea980c7a9b841b0aea5ad]: Sch. 13 Pt. 3 para. 2 in force at 18.3.2017, see art. 1
[^key-fbbfb1ac5942157b4b491314f50c2e5a]: Sch. 13 Pt. 3 para. 3 in force at 18.3.2017, see art. 1
[^key-eaa74813e633522f060e1b18723cb2e1]: Sch. 13 Pt. 3 para. 4 in force at 18.3.2017, see art. 1
[^key-eac42c6b0b13623b295843dc2bc9589d]: Sch. 13 Pt. 3 para. 5 in force at 18.3.2017, see art. 1
[^key-6945a996920c5f35427bc08046c4818c]: Sch. 13 Pt. 3 para. 6 in force at 18.3.2017, see art. 1
[^key-693de566631487901c8adbda0f2dc31a]: Sch. 13 Pt. 3 para. 7 in force at 18.3.2017, see art. 1
[^key-1af3b4c4eb36a09fa0ef04264d1c019d]: Sch. 13 Pt. 3 para. 8 in force at 18.3.2017, see art. 1
[^key-32bfa431e900b222c4922ddfb279f443]: Sch. 13 Pt. 3 para. 9 in force at 18.3.2017, see art. 1
[^key-c1b6af205de10f73334d6d691d79cc42]: Sch. 13 Pt. 3 para. 10 in force at 18.3.2017, see art. 1
[^key-ed18d062ea88ddac60afe223511b610a]: Sch. 13 Pt. 3 para. 11 in force at 18.3.2017, see art. 1
[^key-afe197e249cf2662707fdb4afb105dd5]: Sch. 13 Pt. 4 para. 1 in force at 18.3.2017, see art. 1
[^key-83d45fd8423b1524cd32076bd954005c]: Sch. 13 Pt. 4 para. 2 in force at 18.3.2017, see art. 1
[^key-83db999b6a498faa3778c3b35963c63f]: Sch. 13 Pt. 4 para. 3 in force at 18.3.2017, see art. 1
[^key-3c82f605184d6fe2410aa15b8175555f]: Sch. 13 Pt. 5 para. 1 in force at 18.3.2017, see art. 1
[^key-ebef353e60c8c5cea8f7ef3ae6c2e479]: Sch. 13 Pt. 5 para. 2 in force at 18.3.2017, see art. 1
[^key-235c062aec053fe714b12addc3a36377]: Sch. 13 Pt. 5 para. 3 in force at 18.3.2017, see art. 1
[^key-47dac48bcdb3f2a92543116d96db0a3b]: Sch. 13 Pt. 5 para. 4 in force at 18.3.2017, see art. 1
[^key-57a0d412c7c0fc83ea4469d1a3d79983]: Sch. 13 Pt. 5 para. 5 in force at 18.3.2017, see art. 1
[^key-8abf1d5a0e4111a635b89d0f6d9c7244]: Sch. 13 Pt. 5 para. 6 in force at 18.3.2017, see art. 1
[^key-6d52531b25eb35bde2491809e5fb0920]: Sch. 13 Pt. 5 para. 7 in force at 18.3.2017, see art. 1
[^key-0da00b1e001e85f9d8e3a32208143a1e]: Sch. 13 Pt. 5 para. 8 in force at 18.3.2017, see art. 1
[^key-6e1bb937ac61ec045cb6328c1244b5c7]: Sch. 13 Pt. 5 para. 9 in force at 18.3.2017, see art. 1
[^key-a38346961c66b7f731cf4e1d17968364]: Sch. 13 Pt. 5 para. 10 in force at 18.3.2017, see art. 1
[^key-a3f369d8c31d5f99116b2caa208fc42e]: Sch. 13 Pt. 5 para. 11 in force at 18.3.2017, see art. 1
[^key-f6b85d3d4e022f3c05ec496dc07dc0bc]: Sch. 13 Pt. 5 para. 12 in force at 18.3.2017, see art. 1
[^key-3827ea08fd2e8d1062bf0d6ec084a517]: Sch. 13 Pt. 5 para. 13 in force at 18.3.2017, see art. 1
[^key-3a3b11d550d5fceee70be37fcc1bc828]: Sch. 13 Pt. 5 para. 14 in force at 18.3.2017, see art. 1
[^key-d1f7c4b0d57996053178c698ceb5d14a]: Sch. 13 Pt. 5 para. 15 in force at 18.3.2017, see art. 1
[^key-877f26be9574666d25d59e5572c47773]: Sch. 13 Pt. 5 para. 16 in force at 18.3.2017, see art. 1
[^key-8e0cb4ffcbcd9414d002c21e7ae0b34c]: Sch. 13 Pt. 5 para. 17 in force at 18.3.2017, see art. 1
[^key-8523566ad4631f962c66943b00e2ca48]: Sch. 4 in force at 18.3.2017, see art. 1
[^key-fef0cfd45ee27310f6b574cb453dc508]: Sch. 5 in force at 18.3.2017, see art. 1
[^key-9aa888a85746aa00a271762d39e55112]: Sch. 6 in force at 18.3.2017, see art. 1
[^key-413b9a26d6285e9e74944c9e5ebb5f45]: Sch. 7 in force at 18.3.2017, see art. 1
[^key-e4a47455677ce98a58b951749d148692]: Sch. 8 in force at 18.3.2017, see art. 1
[^key-374d1bc898b15e2ab04c1bc5740b76eb]: Sch. 9 in force at 18.3.2017, see art. 1
[^key-32bdcbb0848fe6e437d3b6868435915a]: Sch. 10 in force at 18.3.2017, see art. 1
[^key-da3940838036a90f753c0e41757c9d1e]: Sch. 12 in force at 18.3.2017, see art. 1
[^key-68d39b50473f7a9c9d375c0cb5c64da9]: Words in art. 8(4) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-d6b5f5a4d77c0810ec7a4fb85775079c]: Art. 33(3) inserted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-2f67ccb9bb4e57deb741c1f30be7f390]: Sch. 1 para. 2(7) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-ee10e540cb9e7103d5cb56550fea7832]: Sch. 2 para. 1(2) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-18d432c74055ad5a515c5dadd13e0d40]: Words in Sch. 3 para. 4(7) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-16d6040ed95c79f3e0aba126d2f76c41]: Words in Sch. 5 substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-ce2a140ad6a0adbd566fdf7cfe3b71e4]: Words in Sch. 8 substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-ea5cd7537991d5e7d6ab4fd0040704a8]: Words in Sch. 10 substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-754c3b1c10e682c6236e83b68b145ac7]: Words in Sch. 13 Pt. 5 para. 9(4)(a) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-27eccf3a41c19eea72ec06e62cc722b1]: Words in Sch. 13 Pt. 5 para. 9(6) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-5d1856a2c795da75ac20057ece37ead5]: Words in Sch. 13 Pt. 5 para. 10(5)(a) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-557aab2e387280a3d8198e095238e474]: Words in Sch. 13 Pt. 5 para. 10(9) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-bacdf1fc0219341a80cee5ade128df8b]: Words in Sch. 13 Pt. 5 para. 12(2) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-a919926c9207c5be2cf61ba728c3d7cb]: Words in Sch. 13 Pt. 5 para. 14(2) substituted (6.7.2018) by The North London Heat and Power Generating Station (Correction) Order 2018 (S.I. 2018/822), art. 1, Sch.
[^key-72f603e7ebfabe6d9f6f3d9d7ed1d745]: Word in Sch. 1 para. 1(1) substituted (20.7.2018) by The North London Heat and Power Generating Station (Amendment) Order 2018 (S.I. 2018/882), arts. 1, 2(2)
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.