The East Anglia THREE Offshore Wind Farm Order 2017
- (5) No part of the authorised scheme may commence until the MMO, in consultation with the MCA, has given written approval of an Emergency Response Co-operation Plan (ERCoP) which includes full details of the plan for emergency, response and co-operation for the construction, operation and decommissioning phases of that part of the authorised scheme in accordance with the MCA recommendations contained within MGN543 “Offshore Renewable Energy Installations (OREIs) – Guidance on UK Navigational Practice, Safety and Emergency Response Issues”, and has confirmed in writing that the undertaker has taken into account and, so far as is applicable to that part of the authorised scheme, adequately addressed all MCA recommendations contained within MGN543 and its annexes.
Reporting of engaged agents, contractors and vessels
8
- (1) The undertaker must provide the following information to the MMO—
- (a) the name and function of any agent or contractor appointed to engage in the licensed activities within seven days of appointment; and
- (b) each week during the construction of the authorised scheme a completed Hydrographic Note H102 listing the vessels currently and to be used in relation to the licensed activities.
- (2) Any changes to the supplied details must be notified to the MMO in writing prior to the agent, contractor or vessel engaging in the licensed activities.
Pre-construction monitoring and surveys
9
- (1) The undertaker must, in discharging condition 6(1)(b), submit details (which accord with the in principle monitoring plan) for written approval by the MMO in consultation with relevant statutory bodies of proposed pre-construction surveys, including methodologies and timings, and a proposed format and content for a pre-construction baseline report; and
- (a) the survey proposals must specify each survey’s objectives and explain how it will assist in either informing a useful and valid comparison with the post-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement; and
- (b) the baseline report proposals must ensure that the outcome of the agreed surveys together with existing data and reports are drawn together to present a valid statement of the pre-construction position, with any limitations, and must make clear what post-construction comparison is intended and the justification for this being required.
- (2) The pre-construction surveys referred to in sub-paragraph (1) must, unless otherwise agreed with the MMO, have due regard to, but not be limited to, the need to undertake—
- (a) appropriate surveys to determine the location and extent of any benthic communities/benthos constituting habitats of principal importance in whole or in part inside the area(s) within the Order limits in which it is proposed to carry out construction works;
- (b) a full sea floor coverage swath-bathymetry survey that meets the requirements of IHO S44ed5 Order 1a, and side scan sonar, of the area(s) within the Order limits in which it is proposed to carry out construction works including a 500 metre buffer area around the site of each work, inclusive of seabed anomalies or sites of historic or archaeological interest that lie within that 500 metre buffer.
- (3) The undertaker must carry out the surveys agreed under sub-paragraph (1) and provide the baseline report to the MMO in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing by the MMO in consultation with the relevant statutory nature conservation bodies.
Construction monitoring
10
- (1) The undertaker must, in discharging condition 6(1)(b), submit details (which accord with the in principle monitoring plan) for approval by the MMO in consultation with the relevant statutory nature conservation bodies of any proposed monitoring, including methodologies and timings, to be carried out during the construction of the authorised scheme. The survey proposals must specify each survey’s objectives.
- (2) The undertaker must carry out the surveys approved under sub-paragraph (1) and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.
Post construction
11
- (1) The undertaker must, in discharging condition 6(1)(b), submit details (which accord with the in principle monitoring plan) for approval by the MMO in consultation with relevant statutory bodies of proposed post-construction surveys, including methodologies and timings, and a proposed format, content and timings for providing reports on the results. The survey proposals must specify each survey’s objectives and explain how it will assist in either informing a useful and valid comparison with the pre-construction position and/or will enable the validation or otherwise of key predictions in the environmental statement.
- (2) The post-construction surveys referred to in sub-paragraph (1) must, unless otherwise agreed with the MMO, have due regard to, but not be limited to, the need to undertake —
- (a) appropriate surveys of any benthic communities/benthos constituting habitats of principal importance in whole or in part inside the area(s) within the Order limits in which construction works were carried out;
- (b) within twelve months of completion of the licensed activities, one full sea floor coverage swath-bathymetry survey that meets the requirements of IHO S44ed5 Order 1a across the area(s) within the Order limits in which construction works were carried out to assess any changes in bedform topography and such further monitoring or assessment as may be agreed to ensure that cables have been buried or protected.
- (3) The undertaker must carry out the surveys agreed under sub-paragraph (1) for up to 3 years post-construction, which could be non-consecutive years, and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.
- (4) Following installation of cables, the cable monitoring plan required under condition 6(1)(f)(iii) must be updated with the results of the post installation surveys. The plan must be implemented during the operational lifetime of the project and reviewed as specified within the plan, following cable burial surveys, or as instructed by the MMO.
Coordination with East Anglia ONE Offshore Wind Farm
12
- (1) Prior to submission of each of the pre-construction plans and documentation required to be submitted under condition 6(1)(a) to (j) above the undertaker must provide a copy of the relevant plans and documentation to the undertaker of the offshore element of the East Anglia ONE Offshore Wind Farm to enable that undertaker to provide any comments on the plans and documentation.
- (2) The undertaker must participate in liaison meetings with the undertaker of the offshore element of the East Anglia ONE Offshore Wind Farm as requested from time to time by the MMO in writing in advance, which meeting will be chaired by the MMO and may consider such matters as are determined by the MMO relating to the efficient operation of the offshore element of the authorised project and the offshore element of the East Anglia ONE Offshore Wind Farm.
Signed
Signed by authority of the Secretary of State for Business, Energy and Industrial Strategy
Giles Scott — Head of Infrastructure Planning and Coal Liabilities — Department for Business, Energy and Industrial Strategy — 7th August 2017
Explanatory note
(This note is not part of the Order)
EXPLANATORY NOTE
This Order grants development consent for, and authorises East Anglia THREE Limited to construct, operate and maintain a generating station located in the North Sea approximately 69 kilometres from the coast at Lowestoft, together with all necessary and associated development. For the purposes of the development that it authorises East Anglia THREE Limited is authorised by the Order compulsorily or by agreement to purchase land and rights in land to use land, as well as to override easements and other rights. The Order also provides a defence in proceedings in respect of statutory nuisance and to discharge water. The Order imposes requirements in connection with the development for which it grants development consent.
The Order also grants deemed marine licences for the marine licensable activities, being the deposit of substances and articles and the carrying out of works, involved in the construction of the generating station and associated development. The deemed marine licences impose conditions in connection with the deposits and works for which they grant consent.
A copy of the plans and book of reference referred to in this Order and certified in accordance with article 32 (certification of plans, etc.) of this Order may be inspected free of charge at the offices of Suffolk Coastal District Council at Melton Hill, Woodbridge, Suffolk, IP12 1AU and Mid Suffolk District Council at 131 High Street, Needham Market, Ipswich, Suffolk, IP6 8DL.
Footnotes
[^f00001]: 2008 c.29. Section 37 was amended by section 137(5) of, and paragraph 5 of Schedule 13 to, the Localism Act 2011 (c.20). Section 74(2) was amended by paragraph 29(3) of that Schedule. Section 104(2) was amended by paragraph 49 of that Schedule and section 58 of the Marine and Coastal Access Act 2009 (c.23). Section 114 was amended by paragraph 55 of Schedule 13 to the Localism Act 2011. Section 120 was amended by section 140 of, and paragraph 60 of Schedule 13 to, that Act.
[^f00002]: S.I. 2009/2263. Regulation 3 was amended by S.I. 2012/635 and S.I. 2012/787. S.I. 2009/2263 was revoked by S.I. 2017/572, but continues to apply to this application for development consent by virtue of transitional provisions contained in Regulation 37(2) of that instrument.
[^f00003]: 1961 c.33.
[^f00004]: 1965 c.56.
[^f00005]: 1980 c.66.
[^f00006]: 1981 c.66.
[^f00007]: 1989 c.29.
[^f00008]: 1990 c.8.
[^f00009]: 1991 c.22.
[^f00010]: 2003 c.21.
[^f00011]: 2004 c.20.
[^f00012]: 2008 c.29.
[^f00013]: 2009 c.23.
[^f00014]: S.I. 2014/1599.
[^f00015]: S.I. 2016/447.
[^f00016]: “Highway” is defined in section 328(1). For “highway authority”, see section 1.
[^f00017]: 1981 c.67. Section 7 was amended by section 70 of, and paragraph 9 of Schedule 15 to, the Planning and Compensation Act 1991 (c.34). There are other amendments to the Act which are not relevant to this Order.
[^f00018]: Section 48 was amended by section 124(2) of the Local Transport Act 2008 (c.26).
[^f00019]: “street authority” is defined in section 49, which was amended by paragraph 117 of Schedule 1 to the Infrastructure Act 2015 (c.7).
[^f00020]: S.I. 1997/1160.
[^f00021]: 1990 c.43. There are amendments to this Act which are not relevant to the Order.
[^f00022]: 1974 c.40. Sections 61(9) and 65(8) were amended by section 162 of, and paragraph 15 of Schedule 3 to, the Environmental Protection Act 1990, c.25. There are other amendments to the 1974 Act which are not relevant to the Order.
[^f00023]: 1991 c.56. Section 106 was amended by section 35(8)(a) of the Competition and Service (Utilities) Act 1992 (c.43) and sections 36(2) and 99 of the Water Act 2003 (c.37). There are other amendments to this section which are not relevant to this Order.
[^f00024]: S.I. 2016/1154.
[^f00025]: As defined in Part 3 of Schedule 8 (Protection for Network Rail Infrastructure Limited).
[^f00026]: Section 4 was amended by sections 184 and 185 of, and paragraph 2 of Schedule 18 to, the Housing and Planning Act 2016 (c.22) subject to transitional provisions specified in S.I. 2017/75.
[^f00027]: Section 5A to the 1981 Act was inserted by section 182(2) of the Housing and Planning Act 2016 (c.22).
[^f00028]: S.I. 1997/1160.
[^f00029]: S.I. 2010/490
[^f00030]: S.I 2009/3015
[^f00031]: 1973 c.26.
[^f00032]: S.I. 2017/826
[^f00033]: 1986 c. 44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c.45), and was further amended by section 76 of the Utilities Act 2000 (c.27).
[^f00034]: 1991 c. 56.
[^f00035]: See section 106.
[^f00036]: 1984 c.12.
[^f00037]: 1993 c.43.
[^f00038]: 2006 c.46.
[^f00039]: 2004 c.20.
[^f00040]: S.I. 2007/1842.
[^f00041]: 2009 c.23.
[^f00042]: 2006 c.16.
[^f00043]: 2004 c.20.
[^f00044]: S.I. 2007/1842.
[^f00045]: 2009 c.23.
[^f00046]: 2006 c.16.
[^f00047]: 2004 c.20.
[^f00048]: S.I. 2007/1842.
[^f00049]: 2009 c.23.
[^f00050]: 2006 c.16.
[^f00051]: 2004 c.20.
[^f00052]: S.I. 2007/1842.
[^f00053]: 2009 c.23.
[^f00054]: 2006 c.16.
[^f00055]: 2004 c.20.
[^f00056]: 2009 c.23.
[^f00057]: S.I. 2014/1599.
[^f00058]: S.I. 2016/447.
[^f00059]: 2006 c.16.
[^f00060]: 2004 c.20.
[^f00061]: 2009 c.23.
[^f00062]: S.I. 2014/1599.
[^f00063]: S.I. 2016/447.
[^f00064]: 2006 c.16.
1
A nationally significant infrastructure project as defined in sections 14 and 15 of the 2008 Act which is located in the North Sea approximately 69 kilometres from the Suffolk coast, comprising—
In the county of Suffolk, district of Suffolk Coastal
Work No. 5B – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from mean low water springs at Bawdsey Cliffs to Work No. 7 together with a temporary transition bay compound;
Work No. 6– A new temporary vehicular access track running in an easterly direction from the eastern side of Ferry Road to Work No. 7 and Work No. 5B, together with modifications to the junction of the new vehicular access track and Ferry Road and a new temporary vehicular access ramp to the beach at Bawdsey Cliffs;
Work No. 7 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 5B to Work No. 8, together with up to four transition bays and a temporary transition bay compound, and a new temporary vehicular access track from Ferry Road;
Work No. 8 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 7 to Work No. 12 crossing under Ferry Road and running in a westerly then north-westerly direction;
Work No. 9 – Temporary widening and upgrade of an existing access track running in a north-westerly direction from the western side of Ferry Road to Work No. 8;
Work No. 10– Temporary widening and upgrade of an existing access track running in a north-westerly then westerly direction from Work No. 8 and a new temporary vehicular access track running from the existing access track in a south-westerly direction to Work No. 8;
Work No. 11 – Temporary widening and upgrade of an existing access track running in a south-easterly direction from the southern side of Dock Road to Duke’s Lane, then temporary widening and upgrade of Duke’s Lane running in a south-westerly then south-easterly direction to Work No. 8 and a new temporary vehicular access track from Duke’s Lane to Work No. 8, together with modifications to the junction of the new temporary vehicular access track and Duke’s Lane;
Work No. 12– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 8 to Work No. 13 running in a south-westerly direction and passing under the River Deben;
Work No. 13 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 12 to Work No. 17 running in a westerly direction then north-westerly direction;
Work No. 14 –A new temporary vehicular access track running in a north-westerly direction from Work No. 13 and temporary widening and upgrade of an existing access track running in a south-westerly direction to Work No. 13;
Work No. 15 – Temporary widening and upgrade of an existing access track running in a northerly direction from the northern side of Lower Falkenham Road and with two upper branches, one running in a north-westerly direction and the other in a north-easterly direction, to Work No. 13;
Work No. 16 – Temporary widening and upgrade of two existing access tracks, the first running in a south-easterly direction from the southern side of Park Lane to Work No. 13, and the second running in a north-westerly direction from the northern side of Park Lane with two upper branches, the first running in a westerly direction to Work No. 19, and the second continuing in an easterly then northerly direction past Sluice Farm and then in a north westerly direction to the east side of The Thicket, together with a new temporary vehicular access track running from the existing access track on the east side of The Thicket in a westerly direction to Work No. 20;
Work No. 17 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 13 to Work No. 19 running in a north-westerly direction;
Work No. 18 – A new temporary secondary construction consolidation site;
Work No. 19– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 17 to Work No. 20 crossing under Park Lane and running in a northerly direction;
Work No. 20 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 19 to Work No. 21 running in a northerly direction;
Work No. 21 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 20 to Work No. 25 running in a northerly direction and crossing under The Street and Ipswich Road;
Work No. 22 – A new temporary secondary construction consolidation site;
Work No. 23 – Temporary widening and upgrade of an existing access track running in an easterly direction from the eastern side of Woodbridge Road to Work No. 22;
Work No. 24 – A new temporary access track running in an easterly direction from the eastern side of Newbourne Road to Work No. 21;
Work No. 25 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 21 to Work No. 28 crossing under Woodbridge Road and running in an easterly then north-westerly direction and crossing under Waldringfield Road, then running in a north-easterly direction and crossing under Waldringfield Road;
Work No. 26 – Temporary widening and upgrade of an existing access track running in an easterly direction from the eastern side of Waldringfield Road to Work No. 25;
Work No. 27 – Temporary widening and upgrade of an existing access track running in a northerly then easterly direction from the northern side of Waldringfield Road to Work No. 25;
Work No. 28 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 25 to Work No. 29 running in a northerly direction and crossing under Martlesham Creek and the East Suffolk Railway line;
Work No. 29 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 28 to Work No. 30 running in a westerly direction and crossing under Sandy Lane;
Work No. 30 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 29 to Work No. 32 crossing under Top Street and running in a westerly direction;
Work No. 31 – A new temporary primary construction consolidation site;
Work No. 32 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 30 to Work No. 34 and running in a westerly direction;
Work No. 33 – Temporary widening and upgrade of an existing access track known as Brock Lane running in a westerly direction from the western side of Top Street to Work No. 31 and continuing to Work No. 34;
Work No. 34 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 32 to Work No. 35 running in a north-westerly direction and crossing under the A12 highway;
Work No. 35 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 34 to Work No. 38 running in a north-easterly then westerly direction;
Work No. 36 – Temporary widening and upgrade of an existing access track running in a southerly direction to Work No. 35;
Work No. 37 – A new temporary access track from the southern side of Lodge Road to Work No. 35;
Work No. 38 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 35 to Work No. 39 running in a westerly direction and crossing under Lodge Road;
Work No. 39– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 38 to Work No. 41 running in a north-westerly direction and crossing under Holly Lane then running in a westerly direction and crossing under Church Road;
Work No. 40 – A new temporary secondary construction consolidation site;
Work No. 41 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 39 to Work No. 45 crossing under Butts Road then running in a westerly direction then a north-westerly direction and crossing under Grundisburgh Road and Clopton Road then running in a south-westerly direction;
Work No. 42 – A new temporary vehicular access track running in a southerly direction from the southern side of the existing access road to Work No. 41;
Work No. 43 – Temporary widening and upgrade of an existing access track running in a southerly direction from the southern side of Grundisburgh Road to Work No. 41;
Work No. 44 – Temporary widening and upgrade of an existing access track running in a northerly then westerly direction from the northern side of Grundisburgh Road to Work No. 41;
Work No. 45 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 41 to Work No. 47 crossing under Witnesham Road and running in a north-westerly direction;
Work No. 46 – A new temporary secondary construction consolidation site;
Work No. 47– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 45 to Work No. 48 crossing under Cockfield Hall Lane then running in a north-westerly then south-westerly direction;
In the county of Suffolk, district of Mid Suffolk
Work No. 48– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 47 to Work No. 49 running in a westerly direction and crossing under Henley Road and an unnamed road;
Work No. 49– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 48 to Work No. 50 running in a south-westerly direction and crossing under Old Ipswich Road and the A14 highway;
Work No. 50 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 49 to Work No. 52 running in a westerly direction and crossing under Paper Mill Lane;
Work No. 51 – A new temporary primary construction consolidation site;
Work No. 52 – Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 50 to Work No. 55 running in a westerly and crossing under the River Gipping, the Great Eastern Mainline Railway and Bramford Road;
Work No. 53 – A new temporary vehicular access track running in a westerly direction from the western side of Paper Mill Lane to Work No. 52;
Work No. 54– A new temporary vehicular access track running in an easterly direction from the eastern side of Bramford Road to Work No. 52;
Work No. 55– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 52 to Work No. 58 running in a south-westerly direction and crossing under Pound Lane, Somersham Road and Tye Lane;
Work No. 56 – Temporary widening and upgrade of an existing access track running in an easterly direction from the eastern side of Somersham Road to Work No. 55;
Work No. 57– Temporary widening and upgrade of an existing access track running in a southerly then westerly direction from and to Work No. 55;
Work No. 58– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 55 to Work No. 62 running in a south westerly direction and passing under Miller’s Wood;
Work No. 59 – A new temporary vehicular access track running in a south-westerly then south-easterly direction from and to Work No. 58;
Work No. 60– A new temporary vehicular access track running in a northerly direction from Work No. 61A to Work No. 58, together with modifications to the junction of the new temporary access track and Bullen Lane;
Work No. 61 – A new temporary secondary construction consolidation site;
Work No. 61A – Temporary widening and upgrade of Bullen Lane;
Work No. 62– Onshore connection works consisting of up to four circuits pulled through existing ducts laid underground from Work No. 58 to Work No. 63 and/or Work. No 64;
Work No. 63– Onshore connection works consisting of up to four circuits pulled through existing ducts or laid directly underground from Work No. 62 and/or Work No. 64 to Work No. 67, and continuing from Work No. 67 to Work No. 66;
Work No. 64 – Onshore connection works consisting of up to four circuits pulled through existing ducts or laid directly underground from Work No. 62 to Work No. 63, and landscaping works including bunding and planting;
Work No. 65 – A new temporary lay down area and landscaping works including planting;
Work No. 66 –Onshore connection works consisting of up to four circuits pulled through existing ducts or laid directly underground from Work No. 63 running in a southerly direction to a connection point at the existing National Grid Bramford substation;
Work No. 67 – Works comprising onshore substations;
Work No. 68 – Landscaping works including bunding and planting;
Work No. 69 – Landscaping works including bunding and planting;
and in connection with Work Nos. 1 to 5A and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project and which fall within the scope of the work assessed by the environmental statement and the deemed marine licences;
and in connection with such Work Nos. 5B to 69 and to the extent that they do not otherwise form part of any such work—
- (a) haul roads, ramps, and other vehicular and/or pedestrian means of access, including creation of new tracks and footpaths, and/or widening, upgrades and improvements of existing tracks and footpaths;
- (b) bunds, embankments, swales, landscaping and boundary treatments;
- (c) spoil storage;
- (d) jointing bays, manholes, kiosks, marker posts and other works associated with laying cables and/or pulling cables through cable ducts;
- (e) water supply works, foul drainage provision, surface water management systems, temporary drainage during installations of cables and culverting;
- (f) works of restoration;
- (g) fencing or other means of enclosure; and
- (h) such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised project;
which fall within the scope of the works assessed by the environmental statement.
Editorial notes
[^key-017294b96dd86069a4ff5fb2d382b7a3]: Words in Sch. 1 Pt. 3 para. 7(2)(b) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(k)
[^key-0308e8c087332b41064851f80a72a35d]: Sch. 6 para. 4 in force at 29.8.2017, see art. 1
[^key-04220208d3d3c687b67df0f8fd42c1fc]: Sch. 8 para. 4 in force at 29.8.2017, see art. 1
[^key-04ab46e90b35b307818fea9cd9b522c9]: Sch. 6 para. 1 in force at 29.8.2017, see art. 1
[^key-04cd6a17a40c3852fe86ab51b8e03874]: Sch. 8 para. 44 in force at 29.8.2017, see art. 1
[^key-055ac747cfae60fa240ebafe8b99635b]: Sch. 1 Pt. 3 para. 38 inserted (17.11.2022) by The East Anglia THREE Offshore Wind Farm (Amendment) (No. 2) Order 2022 (S.I. 2022/1195), arts. 1, 2
[^key-06390b9c1320ce34baae93eaf0602ea9]: Sch. 12 Pt. 2 para. 7 in force at 29.8.2017, see art. 1
[^key-070968a03ed1b4313ff4b726fe2402ca]: Sch. 8 para. 19 in force at 29.8.2017, see art. 1
[^key-071960e827906357fdd9fca894363fae]: Sch. 11 Pt. 1 para. 9 in force at 29.8.2017, see art. 1
[^key-072664b13a3e636b72c940425184a678]: Words in Sch. 1 Pt. 1 substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 5(b)
[^key-075c764e97660b9d131a090b8740cefe]: Sch. 10 Pt. 2 para. 19 in force at 29.8.2017, see art. 1
[^key-08245725919707c25e05764c88645a64]: Sch. 11 Pt. 1 para. 1 in force at 29.8.2017, see art. 1
[^key-0826dbe6e6070443fc47e404054f2404]: Sch. 8 para. 37 in force at 29.8.2017, see art. 1
[^key-084508c938d325d23a54c0d95eedbfaf]: Sch. 8 para. 85 in force at 29.8.2017, see art. 1
[^key-08ced04732ae22b6d871264bd5eba5f9]: Sch. 14 Pt. 2 para. 1 in force at 29.8.2017, see art. 1
[^key-0925733ddf50fc52807fd9375f454777]: Words in Sch. 1 Pt. 1 substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 5(a)
[^key-0a4b4236ef07bb23f2c2f8aa659c17a7]: Sch. 15 para. 11 in force at 29.8.2017, see art. 1
[^key-0a62c4247f9415f268876d83913ce898]: Sch. 8 para. 24 in force at 29.8.2017, see art. 1
[^key-0a811bbeb61c7c19c2ed60611ba99478]: Art. 33 in force at 29.8.2017, see art. 1
[^key-0aad8082b55a3f04065b68456f225b72]: Sch. 12 Pt. 2 para. 8 in force at 29.8.2017, see art. 1
[^key-0d0e3aa13d807d49e6eaa1280c8b7238]: Sch. 11 Pt. 1 para. 6 in force at 29.8.2017, see art. 1
[^key-0e798e1a5c9f87ad73e4b87707570eda]: Art. 2 in force at 29.8.2017, see art. 1
[^key-1025e176400237d9b136165f3dd1baa2]: Sch. 10 Pt. 1 para. 7 in force at 29.8.2017, see art. 1
[^key-102a9212093314e006628016d3293258]: Sch. 8 para. 73 in force at 29.8.2017, see art. 1
[^key-1078f8842f738bcf77068d194cef8c23]: Sch. 14 Pt. 1 para. 9 in force at 29.8.2017, see art. 1
[^key-10bd38f117bd3159cb311f894b92c2a6]: Sch. 8 para. 11 in force at 29.8.2017, see art. 1
[^key-121bd56f5d59c494f18231930eea761a]: Sch. 8 para. 17 in force at 29.8.2017, see art. 1
[^key-12b1fce4fe6eb99b63522f355dbd4203]: Words in Sch. 8 para. 26(9) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-1330b07fd6b02378b6045b98c9142e83]: Sch. 1 Pt. 3 para. 20 in force at 29.8.2017, see art. 1
[^key-13b04f4a816b12f53e71e48e059d19cc]: Art. 18 in force at 29.8.2017, see art. 1
[^key-13d02c94bdd28171c302a9f047b99e63]: Sch. 1 Pt. 3 para. 6 in force at 29.8.2017, see art. 1
[^key-145e9c767a29c1a3b0cd643571077976]: Sch. 8 para. 63 in force at 29.8.2017, see art. 1
[^key-146785af8cc1dfc0fd6e9d2ab2c75dad]: Words in Sch. 8 para. 84(ix) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-14a787070b4691ceee5689010316df73]: Sch. 13 Pt. 2 para. 5 in force at 29.8.2017, see art. 1
[^key-14a80cf2cf4d66275d7fc079218af798]: Art. 30 in force at 29.8.2017, see art. 1
[^key-1558f33d240cc1aa31250b06f9ce46ba]: Sch. 8 para. 16 in force at 29.8.2017, see art. 1
[^key-1564756ffc653b84c285f02e539118fe]: Sch. 8 para. 80 in force at 29.8.2017, see art. 1
[^key-15b600394c5c15578e584d629a5b53db]: Sch. 15 Pt. 1 para. 8 in force at 29.8.2017, see art. 1
[^key-166b7eb818f37c090c18691b4e8c71cd]: Sch. 13 Pt. 2 para. 7 in force at 29.8.2017, see art. 1
[^key-166d3a0230bf80464ad43392f9e2dfd6]: Sch. 8 para. 65 in force at 29.8.2017, see art. 1
[^key-1868759b76ad3e7f084b9fae1332a914]: Sch. 15 Pt. 1 para. 7 in force at 29.8.2017, see art. 1
[^key-1954c2b584a6a9867087553cd1ccbd07]: Word in Sch. 1 Pt. 3 para. 7(2)(a) omitted (16.4.2021) by virtue of The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(j)
[^key-19812826f1c6373091d3b637c7de416c]: Sch. 8 para. 39 in force at 29.8.2017, see art. 1
[^key-19864b37b040e3f6427bb25f39784f86]: Sch. 8 para. 78 in force at 29.8.2017, see art. 1
[^key-19a4b429b5d7521d4e5125a6fae591cc]: Art. 12 in force at 29.8.2017, see art. 1
[^key-19b2f24c8e2be7cad95a7ac77e6325d7]: Sch. 8 para. 15 in force at 29.8.2017, see art. 1
[^key-1a2eed890e22f15500caabaa3b68c046]: Sch. 8 para. 54 in force at 29.8.2017, see art. 1
[^key-1bcb60b3464363388d1f68dc99032fb0]: Sch. 8 para. 71 in force at 29.8.2017, see art. 1
[^key-1dc073a653482170001e6cb6fad776c9]: Sch. 8 para. 52 in force at 29.8.2017, see art. 1
[^key-1e60136310570fed3668c7b07fa1fec4]: Sch. 13 Pt. 1 para. 6 in force at 29.8.2017, see art. 1
[^key-1e746673c19f08a03c553d55e23f17fb]: Sch. 10 Pt. 2 para. 4 in force at 29.8.2017, see art. 1
[^key-1eddecfda9b4c83d1894a50cb7e1ab0e]: Sch. 8 para. 48 in force at 29.8.2017, see art. 1
[^key-1f882815d7856af42f826413ae4154eb]: Sch. 14 Pt. 1 para. 7 in force at 29.8.2017, see art. 1
[^key-2039f68a627a83db4f095fbee43bbfdd]: Sch. 1 Pt. 3 para. 34 in force at 29.8.2017, see art. 1
[^key-203a2a93c9cf95a6db50b32948a17155]: Art. 21 in force at 29.8.2017, see art. 1
[^key-20dd10737028e5d10521d7b9ff0c3491]: Sch. 12 Pt. 1 para. 3 in force at 29.8.2017, see art. 1
[^key-20e633374d27b95c48ca4b6b7fd8b6d8]: Sch. 13 Pt. 1 para. 7 in force at 29.8.2017, see art. 1
[^key-20ea8820283d3d8ccc33ba4ede62c6e1]: Words in art. 2(1) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-20f4a46ef89ec99a204c8801c60e6c86]: Words in art. 23(5) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-2142427aef7b7b27a5af3a304e42e80b]: Sch. 13 Pt. 1 para. 9 in force at 29.8.2017, see art. 1
[^key-21536329589dbb9df6ae179df5f32c69]: Sch. 3 in force at 29.8.2017, see art. 1
[^key-21991e616683ed0bdc3e1b49cfb5d982]: Art. 10 in force at 29.8.2017, see art. 1
[^key-21c01c4255b58eca2495f5e397674c9c]: Sch. 1 Pt. 3 para. 8 in force at 29.8.2017, see art. 1
[^key-22977106527747e82006efd67e48466b]: Sch. 12 para. 17 in force at 29.8.2017, see art. 1
[^key-22d870fc739312872982a7fa5b14df48]: Sch. 15 Pt. 1 para. 3 in force at 29.8.2017, see art. 1
[^key-24dca01d1055c0d19b3eda0cf5f7cb4b]: Sch. 1 Pt. 3 para. 25 in force at 29.8.2017, see art. 1
[^key-26a401d0f32c7f10dccb016509bb01a9]: Sch. 8 para. 26 in force at 29.8.2017, see art. 1
[^key-26ab40ab940007d3f463693b6dc466a0]: Sch. 12 Pt. 1 para. 8 in force at 29.8.2017, see art. 1
[^key-2a44e80854a29cf148919dc36e16a705]: Sch. 15 Pt. 2 para. 4 in force at 29.8.2017, see art. 1
[^key-2ba5978669cefdc9035e383c7402731f]: Sch. 15 Pt. 1 para. 2 in force at 29.8.2017, see art. 1
[^key-2c272a4a6a561bba3760930071c272b2]: Words in Sch. 1 Pt. 3 para. 27(1) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-2e337423b225b606022c4b12341e08a7]: Sch. 8 para. 51 in force at 29.8.2017, see art. 1
[^key-2fc95f8308ed7cf092daba89a5a1196e]: Sch. 11 para. 18 in force at 29.8.2017, see art. 1
[^key-315dd53c601e4e5942433dc628f4eb2c]: Sch. 1 Pt. 3 para. 31 in force at 29.8.2017, see art. 1
[^key-32692f7b658d6bd8839a54a0c95d8402]: Sch. 11 para. 16 in force at 29.8.2017, see art. 1
[^key-33497b1beb355bcfc548d96235d175d7]: Words in Sch. 1 Pt. 3 para. 3(2) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(g)
[^key-334ee70f8fd424e5b8da5e01be420a6f]: Sch. 11 Pt. 1 para. 4 in force at 29.8.2017, see art. 1
[^key-3494e53e9ceb3daf37c00a4ef9b85727]: Sch. 8 para. 77 in force at 29.8.2017, see art. 1
[^key-34f695c36a1359407342310db7500082]: Sch. 12 para. 10 in force at 29.8.2017, see art. 1
[^key-36e9aa3123d425df1d5bec75e1e350c7]: Words in Sch. 1 Pt. 1 omitted (1.10.2022) by virtue of The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 (S.I. 2022/1015), arts. 1, 3(a)
[^key-374ef74148a48a1d346608681fa1816d]: Sch. 1 Pt. 3 para. 37 in force at 29.8.2017, see art. 1
[^key-3755a43d4d29750def33e3980d0c525d]: Sch. 15 para. 10 in force at 29.8.2017, see art. 1
[^key-377434e6848f913ddd269a5cddc3cff9]: Sch. 1 Pt. 3 para. 3(9) inserted (7.6.2019) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019 (S.I. 2019/997), arts. 1, 4(2)
[^key-37e2e936359374f3209c8a279130c95a]: Sch. 11 para. 19 in force at 29.8.2017, see art. 1
[^key-382b5f21bda3fde9a16d1eba27600f5b]: Sch. 14 para. 11 in force at 29.8.2017, see art. 1
[^key-38c6eef2a0e96a2484eb45222621a744]: Sch. 8 para. 46 in force at 29.8.2017, see art. 1
[^key-39675e4e5958b1f12d97fc4ee2276cb1]: Sch. 10 Pt. 2 para. 8 in force at 29.8.2017, see art. 1
[^key-3a233f56bd6b63ed80aba7773117e782]: Sch. 10 Pt. 1 para. 9 in force at 29.8.2017, see art. 1
[^key-3aade2c4815545dd14631024cee56224]: Sch. 10 Pt. 2 para. 14 in force at 29.8.2017, see art. 1
[^key-3ad6989c7356abab2893ef493788a936]: Sch. 8 para. 62 in force at 29.8.2017, see art. 1
[^key-3b899a11f9caaaccb2dcec0510f74702]: Sch. 15 Pt. 2 para. 9 in force at 29.8.2017, see art. 1
[^key-3f1458cba5f5a84b75cfd76d6db50782]: Sch. 12 Pt. 1 para. 7 in force at 29.8.2017, see art. 1
[^key-3f2e6c66ea421a2030852a0b1d4fd7d9]: Sch. 8 para. 28 in force at 29.8.2017, see art. 1
[^key-3fabd642c29e548309453f5e902ebab0]: Sch. 11 para. 10 in force at 29.8.2017, see art. 1
[^key-3fad99ddee1830940ab5447853ecb57f]: Sch. 8 para. 35 in force at 29.8.2017, see art. 1
[^key-3fc7f911bf48f6f17f755674189b8510]: Sch. 13 Pt. 2 para. 9 in force at 29.8.2017, see art. 1
[^key-3ff6f5f8f33107e66390560431dd58cc]: Sch. 4 in force at 29.8.2017, see art. 1
[^key-419ea7346d8cf456eb2b41f109c01fdf]: Sch. 14 Pt. 1 para. 1 in force at 29.8.2017, see art. 1
[^key-41c1101da28228b5940d7c214842e0c0]: Sch. 1 Pt. 3 para. 16 in force at 29.8.2017, see art. 1
[^key-420aae20b21f397676f25b6aff96bdf4]: Sch. 10 Pt. 1 para. 4 in force at 29.8.2017, see art. 1
[^key-436675499ff3c6f4aba14eba66651132]: Words in Sch. 8 para. 61 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-441311b9e61f4b342d1cfd9f5b8f13a3]: Words in Sch. 8 para. 49(2) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-4485e8d19ef1f92c2d2f91e7c8c70d2a]: Sch. 8 para. 34 in force at 29.8.2017, see art. 1
[^key-44932ef208fc8ebc7cd1e75aec42f41e]: Sch. 2 in force at 29.8.2017, see art. 1
[^key-45f89f799e5ec73d2670e57bd317eea7]: Art. 26 in force at 29.8.2017, see art. 1
[^key-465810bcdbea63f23008087ef4157a2c]: Sch. 15 Pt. 2 para. 8 in force at 29.8.2017, see art. 1
[^key-4694bc7f5c8404609af230064315aa0f]: Sch. 14 Pt. 1 para. 6 in force at 29.8.2017, see art. 1
[^key-469d743a4bf50b64d0ef4572b6430f1e]: Art. 5 in force at 29.8.2017, see art. 1
[^key-46ac16fcfc131d87ef075260ba383f30]: Words in Sch. 1 Pt. 3 para. 3(8)(a) omitted (1.10.2022) by virtue of The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 (S.I. 2022/1015), arts. 1, 4(c)
[^key-46bf046c97668a2ace3b664451ec6942]: Art. 17 in force at 29.8.2017, see art. 1
[^key-4736b453822c8f8476f0f0729c84e231]: Sch. 14 para. 10 in force at 29.8.2017, see art. 1
[^key-47e7d0d072514f558a1352b575d9acdd]: Sch. 8 para. 75 in force at 29.8.2017, see art. 1
[^key-488fc28749f700fdec8c5018a77972d3]: Sch. 11 Pt. 2 para. 1 in force at 29.8.2017, see art. 1
[^key-48d2f4b366b2e274651f2768e017493f]: Sch. 13 Pt. 1 para. 1 in force at 29.8.2017, see art. 1
[^key-49a19e512da302aeaed45768f094f0d3]: Sch. 12 Pt. 2 para. 4 in force at 29.8.2017, see art. 1
[^key-49cdd3baa99bcef29c988ad860f87036]: Words in Sch. 1 Pt. 3 para. 30 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-4a3019e3e074011ed22530830feee9e3]: Sch. 1 Pt. 3 para. 26 in force at 29.8.2017, see art. 1
[^key-4a417830c29a75c25bf5812440872752]: Sch. 8 para. 9 in force at 29.8.2017, see art. 1
[^key-4a580c6f32d066f850c5b0ba084abed8]: Sch. 6 para. 5 in force at 29.8.2017, see art. 1
[^key-4b26cbfa9dbc1a2929e190d6dbddc8fa]: Sch. 12 para. 15 in force at 29.8.2017, see art. 1
[^key-4c216b21830307ae1378c144cbf133e8]: Sch. 11 Pt. 2 para. 4 in force at 29.8.2017, see art. 1
[^key-4db03de0ba1773dfe745f917d4476d40]: Sch. 15 Pt. 2 para. 7 in force at 29.8.2017, see art. 1
[^key-4ea141ef80ef4f43180b454ed054c792]: Sch. 8 para. 57 in force at 29.8.2017, see art. 1
[^key-4eb2b4d2b18c4989b75c86ef73957ca5]: Sch. 14 Pt. 2 para. 4 in force at 29.8.2017, see art. 1
[^key-4ecea2314ae3b33fedfd384c7c3fde46]: Sch. 10 Pt. 2 para. 6 in force at 29.8.2017, see art. 1
[^key-4eec2284c6586377571ef6b88dc475c1]: Sch. 10 Pt. 2 para. 13 in force at 29.8.2017, see art. 1
[^key-50e354a05c94b52335bdcdb4db75111b]: Sch. 1 Pt. 3 para. 3 in force at 29.8.2017, see art. 1
[^key-5120cccd28259d1bad9c41b5d7e7db88]: Sch. 12 para. 11 in force at 29.8.2017, see art. 1
[^key-517bc6a2b6f87141a2f538ccdeab9423]: Sch. 13 para. 14 in force at 29.8.2017, see art. 1
[^key-51a63db7c7f6345aa730f7037519156e]: Sch. 8 para. 86 in force at 29.8.2017, see art. 1
[^key-51e8a7a55d7f87c5c88333c149014946]: Sch. 8 para. 61 in force at 29.8.2017, see art. 1
[^key-5201409ca40e250921606403af63084a]: Sch. 14 Pt. 1 para. 5 in force at 29.8.2017, see art. 1
[^key-52729fb3bdb0ba54da94de1dd01ad748]: Sch. 14 Pt. 1 para. 4 in force at 29.8.2017, see art. 1
[^key-539e3424cf68b9121b875121ef64383f]: Art. 4 in force at 29.8.2017, see art. 1
[^key-53a52e75c1a2d9932f57dd7f4b6b7b58]: Sch. 8 para. 69 in force at 29.8.2017, see art. 1
[^key-53b1d8101e0567a5711fcb82542a108c]: Sch. 13 para. 10 in force at 29.8.2017, see art. 1
[^key-53e086bd2edaf83f05d35a9d36b07602]: Sch. 13 Pt. 1 para. 4 in force at 29.8.2017, see art. 1
[^key-54e52b86c06f13866c7913b78fac75e8]: Sch. 6 para. 3 in force at 29.8.2017, see art. 1
[^key-55fa36d7cb2b74106325d33496d7d4ed]: Art. 29 in force at 29.8.2017, see art. 1
[^key-565323c71c720b9e34b313693d6cf122]: Sch. 11 Pt. 2 para. 8 in force at 29.8.2017, see art. 1
[^key-57a1ce478195d6c8aca8412cebe273a0]: Sch. 1 Pt. 1 para. 1 in force at 29.8.2017, see art. 1
[^key-57c6583cfcc3536eb429a704f3beeb0d]: Sch. 12 para. 14 in force at 29.8.2017, see art. 1
[^key-58657c073660dc8e1ff9f21042d5f608]: Words in Sch. 1 Pt. 3 para. 3(8)(e) substituted (16.4.2021) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2021 (S.I. 2021/471), arts. 1, 6(i)
[^key-5a39111cd1e07af06f9d8f107c1b1a6a]: Sch. 1 Pt. 3 para. 30 in force at 29.8.2017, see art. 1
[^key-5aaf408ce40507030dbedfb7210dc33f]: Sch. 10 Pt. 1 para. 3 in force at 29.8.2017, see art. 1
[^key-5ad79cd6cc0f31ad1a537f2ee3c75857]: Sch. 8 para. 41 in force at 29.8.2017, see art. 1
[^key-5cc74bbde0e6f16b06da743686adda11]: Sch. 8 para. 6 in force at 29.8.2017, see art. 1
[^key-5dbf6ae0b4454021b873bc337282d3e6]: Words in art. 34(1) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-5e336d8a2c79d390b4f34d99e4c3bb94]: Sch. 11 para. 15 in force at 29.8.2017, see art. 1
[^key-6020de80ba08c74b22b75ee8a518fbf6]: Sch. 15 Pt. 1 para. 5 in force at 29.8.2017, see art. 1
[^key-609f2d9ef7058756fa6690a38d8878eb]: Sch. 1 Pt. 3 para. 4 in force at 29.8.2017, see art. 1
[^key-62b1f08ba1113f0ae4e370d275c1f2e9]: Word in Sch. 1 Pt. 3 para. 33(2)(a) substituted (1.10.2022) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2022 (S.I. 2022/1015), arts. 1, 4(e)
[^key-62bd89e78ef76240b6d56bec555048a1]: Sch. 13 Pt. 2 para. 6 in force at 29.8.2017, see art. 1
[^key-630c2599e420815fc8892ffab59652b7]: Sch. 10 Pt. 2 para. 9 in force at 29.8.2017, see art. 1
[^key-6346ff6533b7ea354ebddb5080ddd0c5]: Words in Sch. 8 para. 59(2) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-63c9d15a1dbd638e2dc24a3ce49bc173]: Sch. 12 Pt. 2 para. 9 in force at 29.8.2017, see art. 1
[^key-64e233cc29ad3068052c53dcd879d232]: Sch. 1 Pt. 3 para. 7 in force at 29.8.2017, see art. 1
[^key-65924dde23a31a85271f4fc16c5ae093]: Sch. 12 Pt. 1 para. 5 in force at 29.8.2017, see art. 1
[^key-6680269b806aba89bbc4ab09ddc1c176]: Sch. 8 para. 81 in force at 29.8.2017, see art. 1
[^key-6709e6dc662522da6344767329d80b08]: Sch. 8 para. 7 in force at 29.8.2017, see art. 1
[^key-67183e90eba97d6c9d70df51596b86cd]: Art. 38 in force at 29.8.2017, see art. 1
[^key-6730a7964b4384e7a3c6c8743bfaf6a2]: Sch. 1 Pt. 2 para. 1 in force at 29.8.2017, see art. 1
[^key-67ac3ae6665ec150f7a3f37ebf3b9180]: Sch. 8 para. 83 in force at 29.8.2017, see art. 1
[^key-67c44ba2faf6c7ef33e69a65d9c6ad4a]: Sch. 11 para. 13 in force at 29.8.2017, see art. 1
[^key-67da4fbb39d6ca7e48c19e83fb0c2a8e]: Sch. 14 Pt. 2 para. 7 in force at 29.8.2017, see art. 1
[^key-6945131cbca4f15b6dc2d93b471f37a5]: Sch. 15 Pt. 1 para. 6 in force at 29.8.2017, see art. 1
[^key-69f5cbeff74170434c3623bb81f9c3eb]: Sch. 1 Pt. 3 para. 11 in force at 29.8.2017, see art. 1
[^key-6a3d961e4132e6073a4e84a643732a33]: Sch. 1 Pt. 3 para. 28 in force at 29.8.2017, see art. 1
[^key-6b1620125af659bf1cf223866f0f1ec7]: Words in Sch. 8 para. 45 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-6cade85b2e353f90b936a6739f1d8ca0]: Sch. 6 para. 8 in force at 29.8.2017, see art. 1
[^key-6ce7df3647717aeef9590e7ee459e352]: Art. 9 in force at 29.8.2017, see art. 1
[^key-6cf2ea3c232207e130ae255259394144]: Sch. 12 Pt. 1 para. 4 in force at 29.8.2017, see art. 1
[^key-6d81a08dcdb6ac04368dceeae98ff763]: Sch. 11 Pt. 1 para. 3 in force at 29.8.2017, see art. 1
[^key-6e21269d0b8612e0fef9aa51fa99e4c6]: Sch. 13 Pt. 2 para. 3 in force at 29.8.2017, see art. 1
[^key-6e2eed63a9c9788c3f9868910058ce7a]: Words in Sch. 8 para. 64 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-6e4fce50f9f89eb286177b67e2f63d1f]: Words in Sch. 8 para. 68(6) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-704c441789ebb8909904aa9e0f69db0b]: Sch. 11 Pt. 1 para. 5 in force at 29.8.2017, see art. 1
[^key-708530b53482ddbc8648b031d23eb1d9]: Sch. 10 Pt. 1 para. 8 in force at 29.8.2017, see art. 1
[^key-70de3c2c49de23dfe7fb8aadd09a7c14]: Sch. 11 Pt. 2 para. 6 in force at 29.8.2017, see art. 1
[^key-7130a7a5d3ae499bf40e0837c9cc89f4]: Sch. 11 Pt. 2 para. 2 in force at 29.8.2017, see art. 1
[^key-71a2153e2976265e430c113a4fd3cd8a]: Sch. 8 para. 38 in force at 29.8.2017, see art. 1
[^key-73589dfd35c25ba6302a1ebb81d3309f]: Words in Sch. 8 para. 50(1) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-73e74c64694c91ecc05667c766b40b09]: Sch. 8 para. 82 in force at 29.8.2017, see art. 1
[^key-7448d344c785240b1d85125baf046698]: Sch. 1 Pt. 3 para. 15 in force at 29.8.2017, see art. 1
[^key-74adf23879ad2019fff708eca0b20b80]: Words in Sch. 8 para. 69(3)(b) substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-75544ba3bfb27c780b164ade12dc0891]: Sch. 1 Pt. 3 para. 18 in force at 29.8.2017, see art. 1
[^key-75fd13b48e205804ec88b7395fd3b83d]: Sch. 15 Pt. 2 para. 2 in force at 29.8.2017, see art. 1
[^key-76142f900e671d9e2ad424088c13a165]: Sch. 1 Pt. 3 para. 3(8) substituted (7.6.2019) by The East Anglia THREE Offshore Wind Farm (Amendment) Order 2019 (S.I. 2019/997), arts. 1, 4(1)
[^key-763f4c528dc338e5088db07cb82cef20]: Words in Sch. 1 Pt. 3 para. 19 heading substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-76f74fbfb9d5b313f7d70ea818fd1d7f]: Sch. 8 para. 42 in force at 29.8.2017, see art. 1
[^key-77f95d4e1c0baa2ce736c25dda769c0c]: Sch. 8 para. 70 in force at 29.8.2017, see art. 1
[^key-7844f1e0e60dc600a6776952fc5bd261]: Sch. 8 para. 31 in force at 29.8.2017, see art. 1
[^key-787155c750ef7b820f076285a7cffa63]: Sch. 13 Pt. 1 para. 5 in force at 29.8.2017, see art. 1
[^key-789f9ed27800f0d15635ac5d6d299beb]: Art. 25 in force at 29.8.2017, see art. 1
[^key-78c7020f9350b4670dad3fd3712d7e80]: Sch. 11 Pt. 1 para. 8 in force at 29.8.2017, see art. 1
[^key-79162d2578faa9ead53e5a28fd3a816c]: Sch. 10 Pt. 1 para. 5 in force at 29.8.2017, see art. 1
[^key-79a85352f3372fce11824d7c5ba7a63c]: Sch. 13 para. 19 in force at 29.8.2017, see art. 1
[^key-7a2240216cf99eb6366c343ae3194a76]: Art. 13 in force at 29.8.2017, see art. 1
[^key-7b7c2fa1cacd590cab84a9a5fcd1c985]: Sch. 14 Pt. 2 para. 6 in force at 29.8.2017, see art. 1
[^key-7c4d69f9c25cf4a9e5f93631a107f13a]: Sch. 1 Pt. 3 para. 5 in force at 29.8.2017, see art. 1
[^key-7cd8af5a570b68e52f74d97f5e5ca3f0]: Sch. 10 Pt. 2 para. 12 in force at 29.8.2017, see art. 1
[^key-7e4ee8dbc03b1eac4bdac0f4ba336fff]: Sch. 6 para. 7 in force at 29.8.2017, see art. 1
[^key-7f3b45c238fb399c30336a6a6f9a20f5]: Sch. 13 Pt. 1 para. 2 in force at 29.8.2017, see art. 1
[^key-7fbcaee23b69b0f5de4d0849b2fb5498]: Words in Sch. 8 para. 65 substituted (13.7.2018) by The East Anglia THREE Offshore Wind Farm (Correction) Order 2018 (S.I. 2018/843), art. 1, Sch.
[^key-800bfa3e457365d7e4a3ca73fb403b33]: Art. 37 in force at 29.8.2017, see art. 1
[^key-802bb230fcc6e9cac26b42f08440863e]: Sch. 10 Pt. 2 para. 11 in force at 29.8.2017, see art. 1
[^key-8170a9b9a2bcba550783c08138489cf6]: Sch. 8 para. 72 in force at 29.8.2017, see art. 1
[^key-81a705839549aaa0a9358d7c1125e575]: Sch. 10 Pt. 1 para. 2 in force at 29.8.2017, see art. 1
[^key-825c1aa9e842f0a82232fb9d650841e9]: Sch. 8 para. 43 in force at 29.8.2017, see art. 1
[^key-833d5937172ccd82c7b7adaf1abd2fdf]: Sch. 11 para. 17 in force at 29.8.2017, see art. 1
[^key-83e8bee8245d899d6018d7f9ff982701]: Sch. 11 Pt. 1 para. 2 in force at 29.8.2017, see art. 1
[^key-843b9f273892ad1ef7bbca5c1eb33241]: Sch. 11 Pt. 2 para. 3 in force at 29.8.2017, see art. 1
[^key-844af84d96452a0e088e65588ab2510b]: Sch. 1 Pt. 3 para. 14 in force at 29.8.2017, see art. 1
[^key-845fd2f3b4c815b3b4b9211953780a5d]: Sch. 8 para. 68 in force at 29.8.2017, see art. 1
[^key-84b6161016c21a1e33cda96905640d89]: Sch. 13 para. 11 in force at 29.8.2017, see art. 1
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.