The Network Rail (Felixstowe Branch Line Land Acquisition) (Agreements for Transfer) Order 2017

Type Statutory-Instrument
Publication 2017-08-31
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: 31st August 2017

Coming into force: 21st September 2017

The Secretary of State, in exercise of the powers conferred by sections 1 and 5 of, and paragraph 15 of Schedule 1 to, the 1992 Act makes the following Order—

Citation and commencement

1

This Order may be cited as the Network Rail (Felixstowe Branch Line Land Acquisition) (Agreements for Transfer) Order 2017 and comes into force on 21st September 2017.

Interpretation

2

In this Order—

Agreements between the undertaker and Network Rail

3

Signed

Signed by authority of the Secretary of State for Transport

Natasha Kopala — Head of the Transport and Works Act Orders Unit — Department for Transport — 31st August 2017

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order extends the powers conferred under article 39 of the Felixstowe Branch Line and Ipswich Yard Improvement Order 2008 (“the 2008 Order”) to provide that Network Rail Infrastructure Limited (“Network Rail”) may enter into agreements with the Felixstowe Dock and Railway Company (“the undertaker”) for the exercise of the powers which are conferred on the undertaker by the Felixstowe Branch Line (Land Acquisition) Order 2014 (“the 2014 Order”).

The 2008 Order authorises the undertaker to construct railway works in the County of Suffolk and Borough of Ipswich and to compulsorily acquire land required for the purposes of those works. Article 39 of the 2008 Order provides that the undertaker and Network Rail may enter into and carry into effect agreements for the construction, maintenance and use of the authorised works by Network Rail or by the undertaker or by both of them jointly.

The powers conferred under the 2008 Order to construct the works (which have not been constructed) are not time limited. However, the Order provides for the powers to compulsorily acquire land to expire after the end of the period of 5 years from the coming into force of the Order and those powers therefore expired on 14th October 2013. The 2014 Order confers further powers of compulsory acquisition on the undertaker for the purposes of constructing the works authorised by the 2008 Order.

This Order extends article 39 of the 2008 Order to provide that Network Rail and the undertaker may enter into agreements for the compulsory acquisition and temporary possession of the lands authorised by the 2014 Order, as well as for the construction of the works authorised by the 2008 Order for which that land is required.

Footnotes

[^f00001]: S.I 2006/1466, amended by S.I. 2010/439, S.I. 2011/556, S.I. 2011/2085, S.I. 2012/147, S.I. 2012/1658, S.I. 2012/2590 and S.I. 2013/755.

[^f00002]: 1992 c. 42. section 1 was amended by the Planning Act 2008 (c. 29), Schedule 2, paragraphs 51 and 52; section 5 was amended by S.I. 2012/1659.

[^f00003]: S.I. 2008/2512.

[^f00004]: S.I. 2014/1821.

[^f00005]: 1875 c.cxlv.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.