The Millbrook Gas Fired Generating Station Order 2019
- (1) Not less than 28 days before starting the execution of any works in, on or under any land purchased, held, appropriated or used under this Order that are near to, or will or may affect, any apparatus the removal of which has not been required by the undertaker under paragraph 37(2), the undertaker must submit to EPN a plan, section and description of the works to be executed.
- (2) Those works must be executed only in accordance with the plan, section and description submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made in accordance with sub-paragraph (3) by EPN for the alteration or otherwise for the protection of the apparatus, or for securing access to it, and EPN is entitled to watch and inspect the execution of those works.
- (3) Any requirements made by EPN under sub-paragraph (2) must be made within a period of 21 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.
- (4) If EPN in accordance with sub-paragraph (3) and in consequence of the works proposed by the undertaker, reasonably requires the removal of any apparatus and gives written notice to the undertaker of that requirement, paragraphs (32) to (38) apply as if the removal of the apparatus had been required by the undertaker under paragraph 37(2).
- (5) Nothing in this paragraph precludes the undertaker from submitting at any time or from time to time, but in no case less than 28 days before commencing the execution of any works, a new plan, section and description instead of the plan, section and description previously submitted, and having done so the provisions of this paragraph apply to and in respect of the new plan, section and description.
- (6) The undertaker is not required to comply with sub-paragraph (1) in a case of emergency but in that case it must give to EPN notice as soon as is reasonably practicable and a plan, section and description of those works as soon as reasonably practicable subsequently and must comply with sub-paragraph (2) in so far as is reasonably practicable in the circumstances.
40
- (1) Subject to the following provisions of this paragraph, the undertaker must repay to EPN the reasonable expenses incurred by EPN in, or in connection with, the inspection, removal, alteration or protection of any apparatus or the construction of any new apparatus which may be required in consequence of the execution of any such works as are referred to in paragraph 37(2).
- (2) There is to be deducted from any sum payable under sub-paragraph (1) the value of any apparatus removed under the provisions of this part of this Schedule, that value being calculated after removal.
- (3) If in accordance with the provisions of this part of this Schedule—
- (a) apparatus of better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus of worse type, of smaller capacity or of smaller dimensions; or
- (b) apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 41 (arbitration) to be necessary, then, if such placing involves cost in the construction of works under this part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to EPN by virtue of sub-paragraph (1) is to be reduced by the amount of that excess.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus where such extension is required in consequence of the execution of any such works as are referred to in paragraph 37(2); and
- (b) where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
- (5) An amount which apart from this sub-paragraph would be payable to EPN in respect of works by virtue of sub-paragraph (1), if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on EPN any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, is to be reduced by the amount which represents that benefit.
41
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any of the works referred to in paragraph 37(2), any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of EPN, or there is any interruption in any service provided, or in the supply of any goods, by EPN, the undertaker must—
- (a) bear and pay the cost reasonably incurred by EPN in making good such damage or restoring the supply; and
- (b) indemnify EPN for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from EPN,
by reason or in consequence of any such damage or interruption.
- (2) Nothing in sub-paragraph (1) imposes any liability on the undertaker with respect to any damage or interruption to the extent that it is attributable to the act, neglect or default of EPN, its officers, servants, contractors or agents.
- (3) EPN must give the undertaker reasonable notice of any such claim or demand and no settlement or compromise is to be made without the consent of the undertaker which, if it withholds such consent, has the sole conduct of any settlement or compromise or of any proceedings necessary to resist the claim or demand.
42
Nothing in this part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and EPN in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
PART 5 — FOR THE PROTECTION OF ANGLIAN WATER
43
For the protection of Anglian Water, the following provisions shall, unless otherwise agreed in writing between the undertaker and Anglian Water, have effect.
44
In this Part of this schedule—
- “alternative apparatus” means alternative apparatus adequate to enable Anglian Water to fulfil its statutory functions in not less efficient a manner than previously;
- “Anglian Water” means Anglian Water Services Limited;
- “apparatus” means—any works, mains, pipes or other apparatus belonging to or maintained by Anglian Water for the purposes of water supply and sewerage;any drain or works vested in Anglian Water under the Water Industry Act 1991; andany sewer which is so vested or is the subject of a notice of intention to adopt given under section 102(4) (adoption of sewers and disposal works) of the Water Industry Act 1991 or an agreement to adopt made under section 104 (agreements to adopt a sewer, drain or sewage disposal works, at future date) of that Act ,and includes a sludge main, disposal main or sewer outfall and any manholes, ventilating shafts, pumps or other accessories forming part of any sewer, drain, or works (within the meaning of section 219 (general interpretation) of that Act) and any structure in which apparatus is or is to be lodged or which gives or will give access to apparatus.
- “functions” includes powers and duties;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over or upon land; and
- “plan” includes sections, drawings, specifications and method statements.
45
This Part of this Schedule does not apply to apparatus to the extent that the relations between the undertaker and Anglian Water are regulated by the provisions of Part 3 (water supply) of the 1991 Act.
46
The undertaker must not interfere with, build over or near to any apparatus within the Order land or execute the placing, installation, bedding, packing, removal, connection or disconnection of any apparatus, or execute any filling around the apparatus (where the apparatus is laid in a trench) within the standard protection strips which are the strips of land falling the following distances to either side of the medial line of any relevant pipe or apparatus: 2.25 metres where the diameter of the pipe is less than 150 millimetres; 3 metres where the diameter of the pipe is between 150 and 450 millimetres; 4.5 metres where the diameter of the pipe is between 450 and 750 millimetres; and 6 metres where the diameter of the pipe exceeds 750 millimetres, unless otherwise agreed in writing with Anglian Water, such agreement not to be unreasonably withheld or delayed, and such provision being brought to the attention of any agent or contractor responsible for carrying out the authorised development on behalf of the undertaker.
47
The alteration, extension, removal or re-location of any apparatus shall not be implemented until—
- (a) any requirement for any permits under the Environmental Permitting (England and Wales) Regulations 2010 or other legislation and any other associated consents are obtained, and any approval or agreement required from Anglian Water on alternative outfall locations as a result of such re-location are approved, such approvals from Anglian Water not to be unreasonably withheld or delayed; and
- (b) the undertaker has made the appropriate application required under the Water Industry Act 1991 together with a plan and section of the works proposed and Anglian Water has agreed all of the contractual documentation required under the Water Industry Act 1991, such agreement not to be unreasonably withheld or delayed; and such works to be executed only in accordance with the plan, section and description submitted and in accordance with such reasonable requirements as may be made by Anglian Water for the alteration or otherwise for the protection of the apparatus, or for securing access to it.
48
In the situation, where in exercise of the powers conferred by the Order, the undertaker acquires any interest in any land in which Apparatus is placed and such apparatus is to be relocated, extended, removed or altered in any way, no alteration or extension shall take place until Anglian Water has established to its reasonable satisfaction in a timely manner, contingency arrangements in order to conduct its functions for the duration of the works to relocate, extend, remove or alter the apparatus or provide alternative apparatus.
49
Regardless of any provision in this Order or anything shown on any plan, the undertaker must not acquire any apparatus otherwise than by agreement, and before extinguishing any existing rights for Anglian Water to use, keep, inspect, renew and maintain its apparatus in the Order land, the undertaker shall, with the agreement of Anglian Water, create a new right to use, keep, inspect, renew and maintain the apparatus that is reasonably convenient for Anglian Water such agreement not to be unreasonably withheld or delayed, and to be subject to arbitration under article 41 (arbitration).
50
If the undertaker is unable to create the new rights referred to in paragraph (49), Anglian Water must, on receipt of a written notice to that effect from the undertaker, as soon as reasonably possible, use its reasonable endeavours to obtain the necessary rights.
51
If in consequence of the exercise of the powers conferred by the Order the access to any apparatus is materially obstructed the undertaker shall provide such alternative means of access to such apparatus as will enable Anglian Water to maintain or use the apparatus no less effectively than was possible before such obstruction.
52
In consequence of the exercise of the powers conferred by the Order, previously unmapped sewers, lateral drains or other apparatus are identified by the undertaker, notification of the location of such assets will immediately be given to Anglian Water and afforded the same protection of other Anglian Water assets.
53
If for any reason or in consequence of the construction of any of the works referred to in paragraphs 46, 47 and 48 and 52 above any damage is caused to any apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of those works) or property of Anglian Water, or there is any interruption in any service provided, or in the supply of any goods, by Anglian Water, the undertaker shall—
- (a) bear and pay the cost reasonably incurred by Anglian Water in making good any damage or restoring the supply; and
- (b) make reasonable compensation to Anglian Water for any other expenses, loss, damages, penalty or costs incurred by Anglian Water,
by reason or in consequence of any such damage or interruption.
54
- (1) Nothing in paragraph 53 imposes any liability on the undertaker in respect of any damage or interruption to the extent that it is attributable to the neglect or default of Anglian Water, its officers' servants, contractors or agents.
- (2) Anglian Water must give the undertaker reasonable notice of any claim or demand pursuant to paragraph 53 and must consider its representations before proceeding further in respect of the claim or demand.
- (3) Anglian Water must use its reasonable endeavours to mitigate in whole or in part and to minimise any claim, costs, expenses, loss, demands and penalties pursuant to paragraph 53. If requested to do so by the undertaker, Anglian Water shall provide an explanation of how the claim has been minimised
55
Any difference or dispute arising between the undertaker and Anglian Water under this schedule must, unless otherwise agreed in writing between the undertaker and Anglian Water, be determined by arbitration in accordance with article 41 (arbitration).
PART 6 — FOR THE PROTECTION OF COVANTA ROOKERY SOUTH LIMITED
56
For the protection of Covanta Rookery South Limited (Company No. 07094843) as referred to in this part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and Covanta.
57
In this part of this Schedule—
- “Covanta” means Covanta Rookery South Limited (Company No. 07094843) whose registered office is at 20-22 Bedford Row London WC1R 4JS;
- “the Millbrook authorised development” means the development authorised by this Order;
- “the respective authorised developments” means the Rookery authorised development and the Millbrook authorised development”
- “the Rookery Order” means the Rookery South (Resource Recovery Facility) Order 2011;
- “Rookery limits of deviation” means the areas of the Rookery Order land in respect of which the Rookery authorised development may be constructed, in accordance with Article 3(2) of the Rookery Order;
- “the Rookery Order land” means the land or any part of it shown as falling within the Rookery Order limits; and
- “the Rookery authorised development” means the development authorised by the Rookery Order.
Co-operation during construction
58
The undertaker shall not submit written details for numbered work 2A for approval to the relevant planning authorities in accordance with requirement 5(2) (highway access) without first obtaining the written consent of Covanta in respect of the route, siting and location of numbered work 2A.
59
The undertaker shall not exercise powers pursuant to articles 9 (street works), 10 (construction and maintenance of new or altered means of access) or 11 (temporary prohibition or restriction of use of streets) over land within the Rookery limits of deviation without first obtaining the written consent of Covanta.
60
- (1) Wherever in this Part of this Schedule provision is made with respect to the approval or consent of Covanta, that approval or consent shall be in writing (and subject to such reasonable terms and conditions as Covanta may require), but shall not be unreasonably withheld.
- (2) In the event that Covanta does not respond in writing to a request for approval or consent within 28 days of receipt of such a request, Covanta is deemed to have given its consent (without any terms or conditions).
61
Insofar as the construction of the Millbrook authorised development is or may be undertaken concurrently with the Rookery authorised development, the undertaker shall—
- (a) co-operate with Covanta with a view to ensuring—
- (i) the co-ordination of construction programming and the carrying out of works; and
- (ii) that access for the purposes of constructing the respective authorised developments is maintained for the undertaker and Covanta and their respective contractors.
- (b) use reasonable endeavours to avoid any conflict arising between the carrying out of the respective authorised developments.
62
Insofar as the construction of the Millbrook authorised development gives rise to the need to modify any scheme secured by a requirement contained in Part 2 of Schedule 1 to the Rookery Order, the undertaker shall provide such assistance as is reasonably necessary to support Covanta in pursuing any such modification.
Arbitration
63
- (1) Any difference or dispute arising between the undertaker and Covanta under this Part of this Schedule shall, unless otherwise agreed in writing between the undertaker and Covanta, be referred to and settled in arbitration in accordance with the Rules at Schedule 13 of this Order, by a single arbitrator to be agreed upon by the parties within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
- (2) Article 41 (arbitration) shall not apply to any difference or dispute under any provisions of the Part of this Schedule.
PART 7 — FOR THE PROTECTION OF NETWORK RAIL
64
For the protection of Network Rail as referred to in this part of this Schedule the following provisions shall, unless otherwise agreed in writing between the undertaker and Network Rail, have effect.
65
In this part of this Schedule—
- “Network Rail” means Network Rail Infrastructure Limited (Company registration number 02904587) whose registered office is at 1 Eversholt Street, London, NW1 2DN and any associated company of Network Rail which holds property for railway purposes, and for the purpose of this definition “associated company” means any company which is (within the meaning of section 1159 (meaning of “subsidiary” etc.) of the Companies Act 2006) the holding company of Network Rail Infrastructure Limited, a subsidiary of Network Rail Infrastructure Limited or another subsidiary of the holding company of Network Rail Infrastructure Limited;
- “railway operational procedures” means procedures specified under any access agreement (as defined in the Railways Act 1993) or station lease;
66
- (1) Where under this Part Network Rail is required to give its consent, agreement or approval in respect of any matter, that consent, agreement or approval is subject to the condition that Network Rail complies with any relevant railway operational procedures and any obligations under its network licence or under statute.
- (2) Subject to subparagraph (1) where Network Rail is asked to give its consent, agreement or approval pursuant to this Part, such consent, agreement or approval must not be unreasonably withheld but may be given subject to reasonable conditions.
67
The undertaker shall include provisions relating to anti-dazzle fencing in the written details of any proposed permanent fence or other means of enclosure for numbered work 2A submitted pursuant to requirement 6 of Schedule 2 such provisions to be substantially in accordance with the equivalent provisions in the approved details submitted pursuant to paragraph 11 of Schedule 2 of The Rookery South (Resource Recovery Facility) Order 2011 unless otherwise agreed by Network Rail.
68
- (1) The undertaker shall not submit the written details of any proposed permanent fence or other means of enclosure for numbered work 2A to Central Bedfordshire Council in accordance with requirement 6 of Schedule 2 (Fencing and other means of site perimeter enclosure) without having first obtained the written approval of Network Rail in accordance with subparagraph (2).
- (2) The undertaker shall provide Network Rail with a draft of the written details of any proposed permanent fence or other means of enclosure for numbered work 2A (including the proposed anti-dazzle fencing) for approval and Network Rail shall within a period of 28 days beginning with the date on which the written details are received by Network Rail serve written notice on the undertaker confirming that:
- (a) the written details are approved; or
- (b) the written details are approved subject to reasonable amendments as required by Network Rail; or
- (c) the written details are not approved and the reason for the non-approval; or
- (d) that further information is required in order for Network Rail to make its determination (in which case this paragraph 68(2) shall apply to such further information from the date of its receipt by Network Rail).
- (3) In the event that Network Rail fails to serve written notice in accordance with paragraph 68(2) within 28 days of receipt Network Rail shall be deemed to have served a notice pursuant to paragraph 68(2)(a).
- (4) The undertaker must include any amendments which are required by Network Rail and notified to the undertaker by Network Rail in the notice given pursuant to paragraph 68(2)(b) in the written details of any proposed permanent fence or other means of enclosure for numbered work 2A it submits to Central Bedfordshire Council in accordance with requirement 6 of Schedule 2 (Fencing and other means of site perimeter enclosure) and the undertaker shall not submit any such written details to Central Bedfordshire Council which have not been approved by Network Rail in accordance with paragraphs 68(2) or (3).
- (5) In deciding whether to approve the written details or request any amendments Network Rail shall take into account any fencing approved or constructed pursuant to The Rookery South (Resource Recovery Facility) Order 2011.
- (6) Each notice and all other information required to be sent to Network Rail under the terms of this paragraph 68 shall:
- (a) be sent to the Company Secretary and General Counsel at Network Rail Infrastructure Limited, 1 Eversholt Street, London, NW1 2DN via Royal Mail plc's special delivery service (or if this service is no longer being provided an appropriate recorded delivery postal service) and marked for the attention of the London North Western Route Asset Manager; and
- (b) contain a clear statement on its front page that Network Rail must respond within 28 days of receipt.
69
The undertaker shall not be obliged to construct the anti-dazzle fencing approved pursuant to requirement 6 of Schedule 2 in the event that anti-dazzle fencing has been constructed pursuant to The Rookery South (Resource Recovery Facility) Order 2011.
70
- (1) The undertaker shall not submit the construction traffic management plan to the relevant planning authorities in accordance with requirement 11 of Schedule 2 (construction traffic management plan) without having first obtained the written approval of Network Rail in accordance with subparagraph (2).
- (2) The undertaker shall provide Network Rail with a draft of the construction traffic management plan for approval and Network Rail shall within a period of 28 days beginning with the date on which the draft construction traffic management plan is received by Network Rail serve written notice on the undertaker confirming that:
- (a) the draft construction traffic management plan is approved; or
- (b) the draft construction traffic management plan is approved subject to reasonable amendments as required by Network Rail; or
- (c) the draft construction traffic management plan is not approved and the reason for the non-approval; or
- (d) that further information is required in order for Network Rail to make its determination (in which case this paragraph 70(2) shall apply to such further information from the date of its receipt by Network Rail).
- (3) In the event that Network Rail fails to serve written notice in accordance with paragraph 70(2) within 28 days of receipt Network Rail shall be deemed to have served a notice pursuant to paragraph 70(2)(a).
- (4) The undertaker must include any amendments which are required by Network Rail and notified to the undertaker by Network Rail in the notice given pursuant to paragraph 70(2)(b) in the draft construction traffic management plan it submits to the relevant planning authorities in accordance with requirement 11 of Schedule 2 (construction traffic management plan) and the undertaker shall not submit any such written details to the relevant planning authorities which have not been approved by Network Rail in accordance with paragraphs 70(2) or (3).
- (5) In deciding whether to approve the draft construction traffic management plan or request any amendments Network Rail shall take into account any funding received from any other third party in respect of upgrade works to the Green Lane level crossing (even if such upgrade works have not yet been completed by Network Rail) and any approval must not be conditional on the undertaker contributing funding towards a full barrier at Green Lane level crossing.
- (6) Each notice and all other information required to be sent to Network Rail under the terms of this paragraph 70 shall:
- (a) be sent to the Company Secretary and General Counsel at Network Rail Infrastructure Limited, 1 Eversholt Street, London, NW1 2DN via Royal Mail plc's special delivery service (or if this service is no longer being provided an appropriate recorded delivery postal service) and marked for the attention of the London North Western Route Level Crossing Manager; and
- (b) contain a clear statement on its front page that Network Rail must respond within 28 days of receipt.
71
- (1) Any difference or dispute arising between the undertaker and Network Rail under this Part of this Schedule shall, unless otherwise agreed in writing between the undertaker and Network Rail, be referred to and settled in arbitration in accordance with the Rules at Schedule 13 of this Order, by a single arbitrator to be agreed upon by the parties within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State.
- (2) Article 41 (arbitration) shall not apply to any difference or dispute under any provisions of the Part of this Schedule.
72
Nothing in this Order, or in any enactment incorporated with or applied by this Order, prejudices or affects the operation of Part I of the Railways Act 1993.
SCHEDULE 11 — MODIFICATIONS TO AND AMENDMENTS OF THE ROOKERY SOUTH (RESOURCE RECOVERY FACILITY) ORDER 2011
Article 33 to the Rookery South (Resource Recovery Facility) Order 2011
1
In the title to Article 33, after the words “Protection of Network Rail Infrastructure Limited” insert the words “ and Millbrook Power Limited ”.
2
After the words “Schedule 7” and before the words “Protection of Network Rail Infrastructure Limited” insert the words “ Part 1 ”.
Schedule 7 to the Rookery South (Resource Recovery Facility) Order 2011
3
After paragraph 21 of Schedule 7 insert new Part 2—
(22) The following provisions of this Part of this Schedule shall have effect unless otherwise agreed in writing between the undertaker and Millbrook Power. (23) In this part of this Schedule— - “the Millbrook access road land” means the land shown as plots 4_PGP, 5_PGP, 5A_PGP, 6 _PGP and 7_PGP on the land plans and described in the book of reference as certified by the Secretary of State pursuant to the Millbrook Order; - “the Millbrook Order” means the Millbrook Gas Fired Generating Station Order 2019; - “the Millbrook Order land” has the same meaning as the term “Order land” in Article 2(1) of the Millbrook Order but excluding the Millbrook access road land; - “Millbrook Power” means Millbrook Power Limited, (Company No. 08920458) whose registered office is at Drax Power Station, Drax, Selby, North Yorkshire YO58 8PH or any person having the benefit of the Millbrook Order pursuant to Article 6 and/or 7 thereof; - “the Order” means this Order; and - “the respective authorised developments” means the developments authorised by the Order and the Millbrook Order respectively. (24) (1) If as a consequence of the powers granted under this Order access (with or without vehicles plant and machinery) to the Millbrook Order land is obstructed the undertaker shall provide such alternative means of access to the Millbrook Order land as will enable Millbrook Power to construct, use and maintain the development authorised by the Millbrook Order no less effectively than was possible before such obstruction. (2) Subject to Millbrook Power complying with paragraph 58 of Part 6 of Schedule 10 to the Millbrook Order the undertaker shall not exercise the powers granted under this Order so as to hinder or prevent the construction, use or maintenance of numbered work 2 as authorised by the Millbrook Order without the prior written consent of Millbrook Power. (3) Wherever in this Part of this Schedule provision is made with respect to the approval or consent of Millbrook Power, that approval or consent shall be in writing (and subject to such reasonable terms and conditions as Millbrook Power may require), but shall not be unreasonably withheld. (4) In the event that Millbrook Power does not respond in writing to a request for approval or consent within 28 days of receipt of such a request, Millbrook Power is deemed to have given its consent (without any terms or conditions). (25) (1) The undertaker shall not exercise the powers under any of the articles of the Order specified in sub-paragraph (2) over or in respect of the Millbrook Order land otherwise than with the prior written consent of Millbrook Power. (2) The articles referred to in sub-paragraph (1) are— (a) Article 10 (street works); (b) Article 11 (public rights of way); (c) Article 12 (temporary stopping up of streets); (d) Article 13 (access to works); (e) Article 15 (discharge of water); (f) Article 16 (authority to survey and investigate land); (g) Article 17 (compulsory acquisition of land); (h) Article 18 (power to override easements and other rights); (i) Article 26 (temporary use of land for maintaining authorised development); (n) Article 27 (statutory undertakers); and (o) Article 31 (felling or lopping of trees). (3) In the event that Millbrook Power withholds its consent pursuant to sub-paragraph (1) it shall notify the undertaker in writing of the reasons for withholding such consent and (if applicable) the time period during which such consent will be withheld. (26) Insofar as the construction of the respective authorised developments is or may be undertaken concurrently, the undertaker shall— (a) co-operate with Millbrook Power with a view to ensuring— (i) the co-ordination of construction programming and the carrying out of works; and (ii) that access for the purposes of constructing the respective authorised developments is maintained for the undertaker and Millbrook Power and their respective contractors. (b) use reasonable endeavours to avoid any conflict arising between the carrying out of the respective authorised developments. (27) Insofar as the construction of the authorised development gives rise to the need to modify any scheme secured by a requirement contained in Schedule 2 to the Millbrook Order, the undertaker shall provide such assistance as is reasonably necessary to support Millbrook Power in pursuing any such modification. (28) Insofar as compliance with paragraph 25(1) of this Part prevents the undertaker from complying with any requirement contained in Part 2 of Schedule 1 to the Order, the undertaker shall not be in breach of such requirement for the time period specified in paragraph 25(3). (29) In the event that paragraph 28 applies, the undertaker shall provide the relevant planning authority with a copy of the reasons given by Millbrook Power for refusing consent and the time period pursuant to paragraph 25(3). (30) It shall be a defence for any person charged with an offence pursuant to section 161 of the Planning Act 2008 (breach of terms of order granting development consent) to prove that they were not able to comply with a requirement contained in Part 2 of Schedule 1 to the Order due to the effect of paragraph 25 of this Part. (31) (1) Any difference or dispute arising between the undertaker and Millbrook Power under this Part of this Schedule shall, unless otherwise agreed in writing between the undertaker and Millbrook Power, be referred to and settled in arbitration, by a single arbitrator to be agreed upon by the parties within 14 days of receipt of the notice of arbitration, or if the parties fail to agree within the time period stipulated, to be appointed on application of either party (after giving written notice to the other) by the Secretary of State. (2) Article 34 (arbitration) shall not apply to any difference or dispute under any provision of this Part of this Schedule.
SCHEDULE 12 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
Applications made under requirements
1
- (1) Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement (including agreement or approval in respect of part of a requirement) included in this Order the relevant authority must give notice to the undertaker of their decision on the application within a period of eight (8) weeks beginning with—
- (a) the day immediately following that on which the application is received by the authority;
- (b) the day immediately following that on which further information has been supplied by the undertaker under paragraph 2; or
- (c) such longer period as may be agreed by the undertaker and the relevant authority in writing.
- (2) Subject to sub-paragraph (3), in the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) Where—
- (a) an application has been made to the relevant planning authorities for any consent, agreement or approval required by a requirement included in this Order; and
- (b) the relevant planning authorities do not determine such application within the period set out in sub-paragraph (1); and
- (c) such application is accompanied by a report that considers it likely that the subject matter of such application will give rise to any materially new or materially different environmental effects in comparison with the authorised development as approved, then the application is to be taken to have been refused by the relevant planning authorities at the end of that period.
Further information
2
- (1) In relation to any part of the application to which this Schedule applies, the relevant authority has the right to request such further information from the undertaker as is necessary to enable it to consider the application.
- (2) In the event that it considers such further information to be necessary the relevant authority must, within twenty eight (28) days of receipt of the application, notify the undertaker in writing specifying the further information required and (if applicable) to which part of the application it relates. In the event that the relevant planning authorities do not give such notification within this twenty eight (28) day period it is deemed to have sufficient information to consider the application and thereafter is not entitled to request further information without the prior agreement of the undertaker.
- (3) Where further information is requested under this paragraph 2 in relation to part only of an application, that part is to be treated as separate from the remainder of the application for the purposes of calculating time periods in paragraph 1(1)(b), paragraph 1(3) and paragraph 2.
Appeals
3
- (1) The undertaker may appeal in the event that—
- (a) the relevant authority refuses (including a deemed refusal pursuant to paragraph 1(3)) an application for any consent, agreement or approval required by an article or requirement included in this Order or grants it subject to conditions;
- (b) on receipt of a request for further information pursuant to paragraph 2 the undertaker considers that either the whole or part of the specified information requested by the relevant authority is not necessary for consideration of the application; or
- (c) on receipt of any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The appeal process is to be as follows—
- (a) The undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the relevant authority and any article or requirement consultee (together with the undertaker, these are the “appeal parties”);
- (b) The Secretary of State must appoint a person within twenty (20) business days of receiving the appeal documentation and must forthwith notify the appeal parties of the identity of the appointed person and the address to which all correspondence for his attention should be sent;
- (c) The relevant authority and any requirement consultee must submit written representations to the appointed person in respect of the appeal within twenty (20) business days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (d) The appeal parties must make any counter-submissions to the appointed person within twenty (20) business days of receipt of written representations pursuant to sub-paragraph (c) above; and
- (e) The appointed person must make his decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable and in any event within thirty (30) business days of the deadline for the receipt of counter-submissions pursuant to sub-paragraph (d).
The appointment of the person pursuant to sub-paragraph (b) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (3) In the event that the appointed person considers that further information is necessary to enable him to consider the appeal he must, within five (5) days of his appointment, notify the appeal parties in writing specifying the further information required.
- (4) Any further information required pursuant to sub-paragraph (3) must be provided by the undertaker to the appointed person, the relevant authority and any requirement consultee on the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within ten (10) days of the specified date but must otherwise be in accordance with the process and time limits set out in sub-paragraph (2)(c)-(e).
- (5) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal, or
- (b) reverse or vary any part of the decision of the relevant authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to him in the first instance.
- (6) The appointed person may take into account written representations that have been sent outside of the relevant time limits but the appointed person must proceed to a decision within the time limits set by this Schedule.
- (7) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears to him that there is sufficient material to enable a decision to be made on the merits of the case.
- (8) The decision of the appointed person on an appeal is to be final and binding on the parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (9) If an approval is given by the appointed person pursuant to this Schedule, it is deemed to be an approval for the purpose of Schedule 2 of this Order as if it had been given by the relevant authority. The relevant authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person's determination.
- (10) The appointed person may or may not be a member of the Planning Inspectorate but must be a qualified town planner of at least ten (10) years' experience.
- (11) Save where a direction is given pursuant to sub-paragraph (12) requiring the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.
- (12) On application by the relevant authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Planning Practice Guidance: Appeals (March 2014) or any circular or guidance which may from time to time replace it.
4
In this Schedule “relevant authority” means the relevant planning authorities, relevant highway authority, traffic authority, street authority, or the owner of a watercourse, sewer or drain as may be appropriate to the consent, agreement or approval sought.
SCHEDULE 13 — ARBITRATION RULES
Primary Objective
1
The primary objective of these Arbitration Rules is to achieve a fair, impartial, final and binding award on the substantive difference between the parties (save as to costs) within 4 months from the date the Arbitrator is appointed pursuant to paragraph 63 or 71 of Schedule 10 of the Order.
2
The Arbitration shall be deemed to have commenced when a party (“the Claimant”) serves a written notice of arbitration on the other party (“the Respondent”).
Time Periods
3
All time periods in these Arbitration Rules will be measured in days and this will include weekends, but not bank or public holidays.
4
Time periods will be calculated from the day after the Arbitrator is appointed which shall be either:
- (a) the date the Arbitrator notifies the parties in writing of his/her acceptance of an appointment by agreement of the parties; or
- (b) the date the Arbitrator is appointed by the Secretary of State.
Timetable
5
The timetable for the Arbitration will be that set out in Rules 6 to 8 below unless amended in accordance with Rule 22.
6
Within 14 days of the Arbitrator being appointed, the Claimant shall provide both the Respondent and the Arbitrator with:
- (a) a written Statement of Claim which describes the nature of the difference between the parties, the legal and factual issues, the Claimant's contentions as to those issues, the amount of its claim and/or the remedy it is seeking;
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports.
7
Within 14 days of receipt of the Claimant's Rule 6 statements by the Arbitrator and Respondent, the Respondent shall provide the Claimant and the Arbitrator with:
- (a) a written Statement of Defence responding to the Claimant's Statement of Claim, its statement in respect of the nature of the difference, the legal and factual issues in the Claimant's claim, its acceptance of any element(s) of the Claimant's claim, its contentions as to those elements of the Claimant's claim it does not accept;
- (b) all statements of evidence and copies of all documents on which it relies, including contractual documentation, correspondence (including electronic documents), legal precedents and expert witness reports;
- (c) any objections it wishes to make to the Claimant's statements, comments on the Claimant's expert report(s) (if submitted by the Claimant) and explanations for the objections.
8
Within 7 days of the Respondent serving its Rule 7 statements, the Claimant may make a Statement of Reply by providing both the Respondent and the Arbitrator with:
- (a) a written statement responding to the Respondent's submissions, including its reply in respect of the nature of the difference, the issues (both factual and legal) and its contentions in relation to the issues;
- (b) all statements of evidence and copies of documents in response to the Respondent's submissions;
- (c) any expert report in response to the Respondent's submissions;
- (d) any objections to the statements of evidence, expert reports or other documents submitted by the Respondent;
- (e) its written submissions in response to the legal and factual issues involved.
Procedure
9
The parties' pleadings, witness statements and expert reports (if any) shall be concise. No single pleading will exceed 30 single-sided A4 pages using 10pt Arial font.
10
The Arbitrator shall make an award on the substantive difference(s) based solely on the written material submitted by the parties unless the Arbitrator decides that a hearing is necessary to explain or resolve any matters.
11
Either party may, within 2 days of delivery of the last submission, request a hearing giving specific reasons why it considers a hearing is required.
12
Within 7 days of receiving the last submission, the Arbitrator will notify the parties whether a hearing is to be held and the length of that hearing.
13
Within 10 days of the Arbitrator advising the parties that he will hold a hearing, the date and venue for the hearing will be fixed by agreement with the parties, save that if there is no agreement the Arbitrator shall direct a date and venue which he considers is fair and reasonable in all the circumstances. The date for the hearing shall not be less than 35 days from the date of the Arbitrator's direction confirming the date and venue of the hearing.
14
A decision will be made by the Arbitrator on whether there is any need for expert evidence to be submitted orally at the hearing. If oral expert evidence is required by the Arbitrator, then any expert(s) attending the hearing may be asked questions by the Arbitrator.
15
There will be no process of examination and cross-examination of experts, but the Arbitrator shall invite the parties to ask questions of the experts by way of clarification of any answers given by the expert(s) in response to the Arbitrator's questions. Prior to the hearing the procedure for the expert(s) will be that:
- (a) At least 28 days before a hearing, the Arbitrator will provide a list of issues to be addressed by the expert(s);
- (b) If more than one expert is called, they will jointly confer and produce a joint report or reports within 14 days of the issues being provided; and
- (c) The form and content of a joint report shall be as directed by the Arbitrator and must be provided at least 7 days before the hearing.
16
Within 14 days of a Hearing or a decision by the Arbitrator that no hearing is to be held the Parties may by way of exchange provide the Arbitrator with a final submission in connection with the matters in dispute and any submissions on costs. The Arbitrator shall take these submissions into account in the Award.
17
The Arbitrator may make other directions or rulings as considered appropriate in order to ensure that the parties comply with the timetable and procedures to achieve an award on the substantive difference within 4 months of the date on which he/she is appointed, unless both parties otherwise agree to an extension to the date for the award.
18
If a party fails to comply with the timetable, procedure or any other direction then the Arbitrator may continue in the absence of a party or submission or document, and may make a decision on the information before him/her attaching the appropriate weight to any evidence submitted beyond any timetable or in breach of any procedure and/or direction.
19
The Arbitrator's award shall include reasons. The parties shall accept that the extent to which reasons are given shall be proportionate to the issues in dispute and the time available to the Arbitrator to deliver the award.
Arbitrator's Powers
20
The Arbitrator has all the powers of the Arbitration Act 1996, including the non-mandatory sections, save where modified by these Rules.
21
There shall be no discovery or disclosure, except that the Arbitrator shall have the power to order the parties to produce such documents as are reasonably requested by another party no later than the Statement of Reply, or by the Arbitrator, where the documents are manifestly relevant, specifically identified and the burden of production is not excessive. Any application and orders should be made by way of a Redfern Schedule without any hearing.
22
Any time limits fixed in accordance with this procedure or by the Arbitrator may be varied by agreement between the parties, subject to any such variation being acceptable to and approved by the Arbitrator. In the absence of agreement, the Arbitrator may vary the timescales and/or procedure:
- (a) if the Arbitrator is satisfied that a variation of any fixed time limit is reasonably necessary to avoid a breach of the rules of natural justice and then;
- (b) only for such a period that is necessary to achieve fairness between the parties.
23
On the date the award is made, the Arbitrator will notify the parties that the award is completed, signed and dated, and that it will be issued to the parties on receipt of cleared funds for the Arbitrator's fees and expenses.
Costs
24
The costs of the Arbitration shall include the fees and expenses of the Arbitrator, the reasonable fees and expenses of any experts and the reasonable legal and other costs incurred by the parties for the Arbitration.
25
Where the difference involves connected/interrelated issues, the Arbitrator will consider the relevant costs collectively.
26
The final award shall fix the costs of the arbitration and decide which of the parties shall bear them or in what proportion they shall be borne by the parties.
27
The Arbitrator will award recoverable costs on the general principle that costs follow the event, having regard to all material circumstances, including such matters as exaggerated claims and/or defences, the degree of success for different elements of the claims, claims that have incurred substantial costs, the conduct of the parties and the degree of success of a party.
Confidentiality
28
The parties agree that any hearings in this Arbitration shall take place in private.
29
The parties and Arbitrator agree that any matters, materials, documents, awards, expert reports and the like are confidential and shall not be disclosed to any third party without prior written consent of the other party, save for any application to the Courts.
SCHEDULE 14 — DOCUMENTS AND PLANS TO BE CERTIFIED
| (1) Document name | (2) Document reference | (3) Revision number | (4) Date |
|---|---|---|---|
| access road visibility splay plan (contained in appendix 2.1 of appendix 12.1 of the environmental statement) | Drawing reference 31116/2001/008 | B | April 2018 |
| book of reference | 4.3 | 3 | August 2018 |
| design principles statement | 10.2 | 0 | October 2017 |
| environmental statement, Main statement | 6.1 | 0 | October 2017 |
| Appendix Volume A: 1.1 Glossary | 6.2 | 0 | October 2017 |
| Appendix Volume B: 1.2 Scoping Report and Scoping Opinion | 6.2 | 0 | October 2017 |
| Appendix Volume C: 2.6-2.14 Legislation and Policy | 6.2 | 0 | October 2017 |
| Appendix Volume D: 3.1 Mitigation Roadmap | 6.2 | 0 | October 2017 |
| Appendix Volume E: 3.2 Outline CEMP | 6.2 | 2 | July 2018 |
| Appendix Volume F: 5.1 CHP Statement | 6.2 | 0 | October 2017 |
| Appendix Volume G: 6.1-6.3 Air Quality | 6.2 | 0 | October 2017 |
| Appendix Volume H: 7.1 Noise | 6.2 | 0 | October 2017 |
| Appendix Volume H: 7.2 and 7.3 Noise | 6.2 | 1 | April 2018 |
| Appendix Volume I: 8.1-8.5 Ecology | 6.2 | 0 | October 2017 |
| Appendix Volume J: 10.1 Ground Conditions | 6.2 | 0 | October 2017 |
| Appendix Volume K: 11.1 and 11.2 LVIA | 6.2 | 0 | October 2017 |
| Appendix Volume K: 11.3 LVIA | 6.2 | 1 | April 2018 |
| Appendix Volume L: 12.1 TA (save in respect of Appendix 2.1) | 6.2 | 0 | October 2017 |
| Appendix Volume L: Appendix 2.1 of the TA | 6.2 Drawing reference 31116/2001/0008 | B | April 2018 |
| Appendix Volume M: 13.1-13.3 Historic Environment | 6.2 | 0 | October 2017 |
| Appendix Volume N: 15.1 Electric and Magnetic Fields Assessment Report | 6.2 | 0 | October 2017 |
| Figures (save in respect of Figure 11.1) | 6.3 | 0 | October 2017 |
| Figure 11.1 | 6.3 | 1 | April 2018 |
| Non-technical summary | 6.4 | 0 | October 2017 |
| the indicative site layout plans | 2.3 | 1 | July 2018 |
| land plans | 2.5 | 1 | July 2018 |
| the low level restoration scheme baseline works plan | Drawing reference: J0008128-409 | 0 | April 2018 |
| the outline construction environment management plan (contained in appendix 3.2 of the environmental statement) | 6.2 | 2 | July 2018 |
| the outline construction traffic management measures (contained in the outline construction environment management plan and appendices 5.2 to 5.5 of appendix 12.1 of the environmental statement) | 6.2 | 0 | October 2017 |
| the outline landscape and ecological mitigation and management strategy (contained in appendix 11.2 of the environmental statement) | 6.2 | 1 | April 2018 |
| the outline lighting strategy (contained in appendix 11.3 of the environmental statement) | 6.2 | 0 | October 2017 |
| the outline travel plan (contained in appendix 12.1 of the environmental statement) | 6.2 | 0 | October 2017 |
| the rights of way, streets and access plan | 2.7 | 2 | August 2018 |
| works plans | 2.6 | 1 | July 2018 |
Signed
Signed by the authority of the Secretary of State for Business, Energy and Industrial Strategy
Gareth Leigh — Head of Energy Infrastructure Planning — 2019-03-13
Explanatory note
(This note is not part of the Order)
Footnotes
2008 c.29: The relevant provisions of the 2008 Act are amended by Chapter 6 of Part 6 of, and schedule 13 to, the Localism Act 2011 (c. 20) and by sections 22-27 of the Growth and Infrastructure Act 2013 (c. 27). Transitional provisions are contained in S.I. 2013/1124.
S.I. 2010/103, amended by S.I. 2012/635.
2008 c.29. Section 83 was amended by paragraphs 35(2) and 35(3) of schedule 13(1) and paragraph 1 of Part 20 of section 25(20) to the Localism Act 2011 (c.20).
S.I. 2009/2263. Regulation 3 was amended by S.I. 2012/635 and S.I. 2012/787. S.I 2009/2263 was revoked by S.I. 2017/572, but continues to apply to this application for development consent by virtue of transitional provisions contained in Regulation 37(2) of that instrument.
2008( c.29), Section 127 was amended by sections 23, (2)(a), 23(2)(b) and 23(2)(c) of the Growth and Infrastructure Act 2013 (c.27) and by paragraphs 64(1) and (2) of Schedule 13(1) and paragraph 1 of Schedule 25 to the Localism Act 2011 (c.20).
1989 c.29. Section 6 was amended by section 30 of the Utilities Act 2000 (c.27), and section 6(10) amended by section 89(3) of the Energy Act 2004 (c.20). There are other amendments to this section that are not relevant to this Order.
1986 c.44. Section 7 was amended by section 5 of the Gas Act 1995 (c.45) and section 76(2) of the Utilities Act 2000 (c.27). There are other amendments to the section that are not relevant to this Order.
2004 c.18. There are amendments to this Act not relevant to this Order.
1991 c.56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c.43) and sections 99(2), (4), (5)(a), (5)(b),(5)(c) and 36(2) of the Water Act 2003 (c.37).
1964 c.40. Paragraph 9B was inserted into Schedule 2 paragraph 9 of Schedule 3 of by the Transport and Works Act 1992 (c.42). There are other amendments to the 1964 Act that are not relevant to this Order.
Section 8 was amended by section 199 of and Schedule 17 to the Housing and Planning Act 2016 (c.22). Section 8 is modified by section 9 of and Schedule 3 (as amended by section 108 of the Utilities Act 2000 (c.27) to the Gas Act 1986 (c.44), section 151 of and Schedule 18 to the Water Act 1989 (c.15), section 10 of and Schedule 3 to the Electricity Act 1989 (c.29), Schedules 9 and 11 to the Water Industry Act 1991 (c.56) and Schedules 18 and 19 to the Water Resources Act 1991 (c.57). There were other amendments, and are other modifications, to that section that are not relevant to this Order.
Section 11(1) was amended by section 34 of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67) and sections 186 and 187 of, and paragraph 6 of Schedule 14 and paragraph 3 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22). There are other amendments to the section that are not relevant to this Order.
1990 c.43. There are amendments not relevant to this Order.
1974 c.40. Section 61 was amended by section 162 of and paragraph 15 of Schedule 15 to the Environmental Protection Act 1990 (c.43). There are other amendments not relevant to this Order.
Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
Section 11B was inserted by section 187(2) of the Housing and Planning Act 2016 (c. 22).
Section 12 was amended by section 56(2) of and part 1 of Schedule 9 to, the Courts Act 1971 (c. 23).
Section 13 was amended by sections 62(3), 139(4) to (9) and 146 of, and paragraphs 27 and 28 of Schedule 13 and part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
Section 20 was amended by paragraph 4 of Schedule 15 to the Planning and Compensation Act 1991 and S.I. 2009/1307.
1991 c.56. Section 51A to the 1991 Act was inserted by section 92(1) of the Water Act 2003(c.37) and amended by sections 10(2)(a), 10(2)(b) and 10(2)(c) of the Water Act 2014 (c.21).
1986 c.44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c.45), and was further amended by section 76 of the Utilities Act 2000 (c.27), Section 48 was amended by paragraph 2(1) of Schedule 6 to the Utilities Act 2000(c.27).
2003 c.21.as amended by the Digital Economy Act 2017 (c.30)
added by Schedule 1 of the Digital Economy Act 2017 (c.30)
1991 c.56. Section 102(4) was amended by paragraph 90 of Schedule 7 to the Water Act 2014 (c.21) and section 96(1)(c) of the Water Act 2003 (c.37); Section 104 was amended by section 96(4)(a), (b), (c), (e) and (f), and paragraph 1 of Schedule 9(3) to the Water Act 2003 (c.37), section 42(3) of the Flood and Water Management Act 2010 and by sections 11(2)(a), 11(2)(b) and 11(2)(c) of the Water Act 2014 (c.21).
In Central Bedfordshire—
A nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act, and associated development under section 115(1)(b) of that Act consisting of a generating station with a gross rated electrical output of up to 299MWe comprising all or part of—
Work No. 1A development comprising a generating station including—
- (a) 1 gas turbine generator;
- (b) 1 exhaust gas emission flue stack; and
- (c) external fin fan cooler(s),
Work No. 1B development comprising a generating station and gas and electrical infrastructure including—
- (a) a control room/office/workshop;
- (b) telemetry apparatus;
- (c) a fire water tank;
- (d) a demineralised water storage tank;
- (e) an emergency generator including fuel storage tank;
- (f) gas pipeline and telemetry cabling and cathodic protection test/ transformer rectifier unit;
- (g) a natural gas receiving station and gas treatment compound containing—
- (i) a pipeline inspection gauge (PIG) receiving facility;
- (ii) isolation valves, metering, heating, filtering, compression, pressure regulation equipment;
- (iii) electricity supply kiosks;
- (iv) emergency generator including fuel storage tank;
- (v) Joule-Thomson boiler(s); and
- (vi) control and instrumentation kiosks,
Work No. 1C development comprising a generating station and electrical infrastructure including a transformer compound, generator step up transformer, unit and other transformers, ... overhead conductors and other plant and structures required to manage the transmission of electricity,
Work No. 1D development comprising a generating station including—
- (a) security infrastructure, including cameras, perimeter fencing and a gatehouse;
- (b) site lighting infrastructure, including perimeter lighting columns;
- (c) internal roadways, car parking, pedestrian network, cycle parking, hardstanding and water treatment trailers;
- (d) a maintenance compound including hardstanding and welfare and administration facilities;
- (e) site drainage and waste management infrastructure, including relocation of existing infrastructure as required;
- (f) electricity, water, wastewater and telecommunications and other services including high voltage and low voltage cabling, equipment and controls and associated telemetry and electrical protection auxiliary cabling;
- (g) landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation; and
- (h) other ancillary equipment.
Work No. 2A development comprising the creation of a junction with Green Lane, maintenance of an existing access road between Green Lane and Rookery South Pit, including permanent road surface and kerb stones, fencing, safety barrier(s), signing and road markings works, footway, drainage (including culverts), electricity and telecommunications connections and other services and other incidental works,
Work No. 2Bdevelopment comprising a new means of access, including permanent road surface and kerb stones, safety barrier(s), signing and road markings works, footway, drainage (including culverts), electricity and telecommunications connections and other services and other incidental works,
Work No. 3A development comprising gas infrastructure including—
- (a) an above ground installation (also referred to as a minimum offtake connection compound) containing—
- (i) a minimum offtake connection comprising remotely operable valves, control and instrumentation kiosks and electrical supply kiosks;
- (ii) a pipeline inspection gauge (PIG) facility, comprising a PIG launching facility, emergency control valves, isolation valves, control and instrumentation kiosks, and electricity supply kiosks;
- (b) security infrastructure, including cameras, lighting (including perimeter lighting columns) and perimeter fencing;
- (c) site drainage and waste management infrastructure;
- (d) electricity and telecommunications connections and other services;
- (e) below ground sacrificial anode pit; and
- (f) landscaping including tree planting, temporary and permanent fencing and other boundary treatments and ecological mitigation,
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.