The Thames Water Utilities Limited (Thames Tideway Tunnel) (Amendment) Order 2020

Type Statutory-Instrument
Publication 2020-03-10
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: 10th March 2020

Coming into force in accordance with article 1(1)

In accordance with paragraph 2 of Schedule 6 to the 2008 Act, the Secretary of State has had regard to the effect of the change, together with the previous changes made under that paragraph, on the 2014 Order as originally made, and is satisfied that the change to the 2014 Order is not material.

Citation, commencement and interpretation

1

Amendment of the 2014 Order

2

  • the book of reference” means— the book of reference certified by the Secretary of State as the book of reference for the purposes of this Order, and the addendum to that book dated January 2020 certified by the Secretary of State for the purposes of this Order;
  • *Work No.24aa: North East Storm Relief connection tunnel – A tunnel between the King Edward Memorial Park CSO drop shaft (Work No.24a) and the main tunnel (east) (Work No.1d).

Certification of substituted plans, etc.

3

to the Secretary of State for certification in accordance with paragraph (2).

SCHEDULE — Amendments to Schedule 2 to the 2014 Order

Provision to be amended Current text Text to be substituted for the current text
Schedule 2, Part 1 (Works Plans) Table 1, column 3 “DCO-WP-000-ZZZZZ-010050” “DCO-WP-000-ZZZZZ-010050-rev 1”
Schedule 2, Part 1 (Works Plans) Table 1, column 3 “DCO-WP-000-ZZZZZ-010051” “DCO-WP-000-ZZZZZ-010051-rev 1”
Schedule 2, Part 2 (Land Plans) Table 1, column 3 “DCO-LP-000-ZZZZZ-030040-rev 2” “DCO-LP-000-ZZZZZ-030040-rev 4”[^f00007]

Signed

For and on behalf of the Secretary of State

Kirstin Green — Deputy Director, Water Quality — Department for Environment, Food and Rural Affairs — 10th March 2020

For and on behalf of the Secretary of State

Steve Quartermain — Chief Planner (Director) — Ministry of Housing, Communities and Local Government — 10th March 2020

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I 2014/2384 (“the 2014 Order”) granted development consent within the meaning of the Planning Act 2008 (c. 29).

Following an application made under paragraph 2 of Schedule 6 to the Planning Act 2008, this Order makes the following non-material changes to the 2014 Order—

A copy of the substituted plans and of the addendum to the book of reference dated January 2020 mentioned in this Order and certified in accordance with article 3 of this Order (certification of plans, etc.) may be inspected free of charge during working hours at the offices of Tower Hamlets Council, Mulberry Place, 5 Clove Crescent, London, E14 2BG.

A full impact assessment has not been produced for this instrument as no, or no significant, impact on the private, voluntary or public sector is foreseen.

Footnotes

[^f00001]: 2008 c. 29; paragraph 2 of Schedule 6 was amended by paragraph 4(6)(a) of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraph 72(3) to (7) of Schedule 13, and by Part 20 of Schedule 25, to the Localism Act 2011 (c. 20), and by section 28(2) of the Infrastructure Act 2015 (c. 7).

[^f00002]: S.I. 2018/378 makes provision for, and in connection with, the transfer of functions from the Secretary of State for Communities and Local Government to the Secretary of State for Housing, Communities and Local Government.

[^f00003]: Article 62 of the Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (“the 2014 Order”) provides insofar as relevant to this Order that “the Secretary of State shall mean the Secretary of State for Communities and Local Government and the Secretary of State for Environment, Food and Rural Affairs”.

[^f00004]: S.I. 2011/2055; relevant amending instruments are S.I. 2012/635 and 2015/760.

[^f00005]: S.I. 2014/2384, amended by S.I. 2015/723, 2017/659 and 2018/1262.

[^f00006]: Article 2(1) defines “undertaker” as the person who has the benefit of the 2014 Order in accordance with articles 8 and 9 of that Order.

[^f00007]: This plan and those referred to above may be inspected free of charge during working hours at the offices of Tower Hamlets Council, Mulberry Place, 5 Clove Crescent, London, E14 2BG.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.