The Riverside Energy Park Order 2020
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker or, in default of agreement, is not determined by arbitration in accordance with article 42(3) (procedures in relation to certain approvals etc.) to be necessary, then, if such placing involves cost in the construction of works under this Part of this Schedule exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this sub-paragraph would be payable to SGN by virtue of sub-paragraph (1) will be reduced by the amount of that excess save where it is not possible or appropriate in the circumstances (including due to statutory or regulatory changes) to obtain the existing type of apparatus at the same capacity and dimensions or place at the existing depth in which case full costs will be borne by the undertaker.
- (4) For the purposes of sub-paragraph (3)—
- (a) an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
- (b) where the provision of a joint in a pipe or cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole must be treated as if it also had been agreed or had been so determined.
Indemnity
114
- (1) Subject to sub-paragraphs (2) and (3), if by reason or in consequence of the construction of any such works authorised by this Part of this Schedule (including without limitation relocation, diversion, decommissioning, construction and maintenance of apparatus or alternative apparatus) or in consequence of the construction, use, maintenance or failure of any of the authorised works by or on behalf of the undertaker or in consequence of any act or default of the undertaker (or any person employed or authorised by him) in the course of carrying out such works, including without limitation works carried out by the undertaker under this Part of this Schedule or any subsidence resulting from any of these works, any damage is caused to any apparatus or alternative apparatus (other than apparatus the repair of which is not reasonably necessary in view of its intended removal for the purposes of the authorised works) or property of SGN, or there is any interruption in any service provided, or in the supply of any goods, by SGN, or SGN becomes liable to pay any amount to any third party, the undertaker must—
- (a) bear and pay on demand the cost reasonably incurred by SGN in making good such damage or restoring the supply; and
- (b) indemnify SGN for any other expenses, loss, demands, proceedings, damages, claims, penalty or costs incurred by or recovered from SGN, by reason or in consequence of any such damage or interruption or SGN becoming liable to any third party as aforesaid other than arising from any default of SGN.
- (2) The fact that any act or thing may have been done by SGN on behalf of the undertaker or in accordance with a plan approved by SGN or in accordance with any requirement of SGN or under its supervision including under any watching brief will not (unless sub-paragraph (3) applies) excuse the undertaker from liability under the provisions of this sub-paragraph (1) unless SGN fails to carry out and execute the works properly with due care and attention and in a skilful and workman like manner or in a manner that does not accord with the approved plan or as otherwise agreed between the undertaker and SGN.
- (3) Nothing in sub-paragraph (1) imposes any liability on the undertaker in respect of—
- (a) any damage or interruption to the extent that it is attributable to the neglect or default of SGN, its officers, servants, contractors or agents; and
- (b) any authorised works and/or any other works authorised by this Part of this Schedule carried out by SGN as an assignee, transferee or lessee of the undertaker with the benefit of the Order pursuant to section 156 (benefit of order granting development consent) of the Planning Act 2008 or article 9 (consent to transfer benefit of order) subject to the proviso that once such works become apparatus (“new apparatus”), any authorised works yet to be executed and not falling within this sub-section 3(b) will be subject to the full terms of this Part of this Schedule including this paragraph 114.
- (4) SGN must give the undertaker reasonable notice of any such third party claim or demand and no settlement or compromise must, unless payment is required in connection with a statutory compensation scheme, be made without first consulting the undertaker and considering their representations.
- (5) SGN must use its reasonable endeavours to mitigate in whole or in part and to minimise any costs, expenses, loss, demands, and penalties to which the indemnity under this paragraph 114 applies. If requested to do so by the undertaker, SGN must provide an explanation of how the claim has been minimised. The undertaker shall only be liable under this paragraph 114 for claims reasonably incurred by SGN.
Enactments and agreements
115
Save to the extent provided for to the contrary elsewhere in this Part of this Schedule or by agreement in writing between SGN and the undertaker, nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and SGN in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.
Co-operation
116
- (1) Where in consequence of the proposed construction of any of the authorised works, the undertaker or SGN requires the removal of apparatus under sub-paragraph 110(2) or SGN makes requirements for the protection or alteration of apparatus under paragraph 112, the undertaker must use its best endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of SGN's undertaking and SGN must use its best endeavours to co-operate with the undertaker for that purpose.
- (2) For the avoidance of doubt whenever SGN's consent, agreement or approval is required in relation to plans, documents or other information submitted by SGN or the taking of action by SGN, it must not be unreasonably withheld or delayed.
Access
117
If in consequence of the agreement reached in accordance with sub-paragraph 109(1) or the powers granted under this Order the access to any apparatus (including appropriate working areas required to reasonably and safely undertake necessary works by SGN in respect of the apparatus) is materially obstructed, the undertaker must provide such alternative rights and means of access to such apparatus as will enable SGN to maintain or use the apparatus no less effectively than was possible before such obstruction.
Arbitration
118
Save for differences or disputes arising under sub-paragraphs 110(2), 110(4) and 111(1) and paragraph 109 any difference or dispute arising between the undertaker and SGN under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and SGN, be determined by arbitration in accordance with article 42 (procedures in relation to certain approvals etc.).
Notices
119
The plans submitted to SGN by the undertaker pursuant to sub-paragraph 112(1) must be sent to SGN at 1 Forbury Place, 43 Forbury Road, Reading, Berkshire RG1 3JH or such other address as SGN may from time to time appoint instead for that purpose and notify to the undertaker.
SCHEDULE 11 — DOCUMENTS AND PLANS TO BE CERTIFIED
| (1) Document name | (2) Document reference | (3) Revision number | (4) Date |
|---|---|---|---|
| access and public rights of way plans | 2.3 (key plan and sheets 1 to 16) | Rev. 1 | May 2019 |
| book of reference | 4.3 | Rev. 3 | September 2019 |
| CHP statement | 5.4 | Rev. 0 | November 2018 |
| 5.4.1 (CHP supplementary report) | Rev. 0 | May 2019 | |
| design principles | 7.4 | Rev. 0 | November 2018 |
| environmental statement | environmental statement 6.1 (excluding chapters 3, 5, 6, 7, 9, 11, 12, 13, 14 and 18) | Rev. 0 | November 2018 |
| environmental statement 6.1 (chapters 3, 5, 6, 7, 9, 11, 12, 13, 14 and 18) | Rev. 1 | May 2019 | |
| environmental statement 6.2 (excluding Figure 7.5, 7.8, 7.9 and 7.10) | Rev. 0 | November 2018 | |
| environmental statement 6.2 (Figure 7.5) | Rev. 2 | June 2019 | |
| environmental statement 6.2 (Figure 7.8) | Rev. 2 | September 2019 | |
| environmental statement 6.2 (Figure 7.9) | Rev. 2 | September 2019 | |
| environmental statement (Figure 7.10) | Rev. 2 | September 2019 | |
| environmental statement 6.3 (excluding appendix J (network traffic flows and distribution) to appendix B.1, appendix L (outline construction traffic management plan) to appendix B1, appendix C.1 (traffic modelling), C.2 (stack modelling), appendix C.3 (human health risk assessment) | Rev. 0 | November 2018 | |
| environmental statement 6.3 (appendix J (network traffic flows and distribution) to appendix B.1, appendix C.1 (traffic modelling), C.2 (stack modelling), appendix C.3 (human health risk assessment)) | Rev. 1 | May 2019 | |
| environmental statement 6.3 (appendix L (outline construction traffic management plan) to appendix B.1 | Rev. 6 | September 2019 | |
| environmental statement 6.4 | Rev. 0 | November 2018 | |
| environmental statement 6.5 | Rev. 1 | May 2019 | |
| environmental statement supplemental report 6.6 | Rev. 0 | May 2019 | |
| flood risk assessment | 5.2 | Rev. 0 | November 2018 |
| FRAPA drawings | appendix B of 8.01.03 | Rev. 0 | 13 May 2019 |
| land plans | 2.1 | Rev. 2 | July 2019 |
| MOL plan | 8.02.58 | Rev. 0 | 9 August 2019 |
| outline biodiversity and landscape mitigation strategy | 7.6 | Rev. 4 | September 2019 |
| outline code of construction practice | 7.5 | Rev. 5 | September 2019 |
| outline lighting strategy | appendix K.3 of 6.3 | Rev. 0 | November 2018 |
| pre–commencement plan | 8.02.55 | Rev. 0 | August 2019 |
| REP and RRRF Application Boundaries Plan | 8.02.56 | Rev. 1 | September 2019 |
| transport assessment | appendix B.1 of 6.3 (excluding appendix J and appendix L) | Rev. 0 | November 2018 |
| appendix J to appendix B.1 of 6.3 | Rev. 1 | May 2019 | |
| appendix L to appendix B.1 of 6.3 | Rev. 6 | September 2019 | |
| jetty outage review | Rev. 0 | June 2019 | |
| supplementary note to the temporary jetty outage review | Rev. 0 | September 2019 | |
| works plans | 2.2 | Rev. 1 | May 2019 |
SCHEDULE 12 — PROCEDURE IN RELATION TO CERTAIN APPROVALS ETC.
Interpretation
1
In this Schedule—
- “the appeal parties” means the relevant authority, the undertaker and any requirement consultees;
- “business day” means a day other than a Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 of the Banking and Financial Dealings Act 1971 ;
- “relevant authority” means the relevant planning authority, relevant highway authority, relevant traffic authority, relevant street authority, or the owner of a watercourse, sewer or drain as may be appropriate to the consent, agreement or approval sought; and
- “requirement consultee” means any body named in a requirement as a body to be consulted by the relevant planning authority in discharging that requirement.
Applications made under requirements
2
- (1) Subject to article 42(2) (procedures in relation to certain approvals etc), where an application has been made to the relevant authority for any consent, agreement or approval required or contemplated by any provisions of this Order (including consent, agreement or approval in respect of part of a requirement) the relevant authority must give notice to the undertaker of its decision on the application within a period of nine weeks beginning with—
- (a) the day immediately following that on which the application is received by the relevant authority;
- (b) the day immediately following that on which further information has been supplied by the undertaker under sub-paragraph (2); or
- (c) such longer period as may be agreed in writing by the undertaker and the relevant authority.
- (2) Subject to sub-paragraph (4), in the event that the relevant authority does not determine an application within the period set out in sub-paragraph (1), the relevant authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) Where an application is made to the relevant authority for any consent, agreement or approval required by a requirement included in this Order, it must be accompanied by a report which states whether the subject matter of the application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement.
- (4) Where an application has been made to the relevant authority for any consent, agreement or approval required by a requirement included in this Order, and—
- (a) the relevant authority does not determine the application within the period set out in sub-paragraph (1) and such application is accompanied by a report which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects compared to those in the environmental statement; or
- (b) the relevant authority determines during the period set out in sub-paragraph (1) that it considers that the subject matter of such application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement,
the application is to be taken to have been refused by the relevant authority at the end of that period.
Further information and consultation
3
- (1) In relation to any application to which this Schedule applies, the relevant authority has the right to request such reasonable further information from the undertaker as is necessary to enable it to consider the application.
- (2) In the event that the relevant authority considers such further information to be necessary and the provision of the Order governing or requiring the application does not specify that consultation with a requirement consultee is required, the relevant authority must, within ten business days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the provision of the Order governing or requiring the application specifies that consultation with a requirement consultee is required, the relevant authority must issue the consultation to the requirement consultee within five business days of receipt of the application, and must notify the undertaker in writing specifying any further information requested by the requirement consultee within five business days of receipt of such a request and in any event within ten business days of receipt of the application.
- (4) In the event that the relevant authority does not give notification as specified in sub-paragraph (2) or (3) it is to be deemed to have sufficient information to consider the application and is not subsequently entitled to request further information without the prior agreement of the undertaker.
Appeals
4
- (1) The undertaker may appeal in the event that—
- (a) the relevant authority refuses (including a deemed refusal pursuant to paragraph 2(3)) an application for any consent, agreement or approval required or contemplated by any of the provisions of this Order or grants it subject to conditions;
- (b) on receipt of a request for further information pursuant to paragraph 3 the undertaker considers that either the whole or part of the specified information requested by the relevant authority is not necessary for consideration of the application; or
- (c) on receipt of any further information requested, the relevant authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The appeal process is to be as follows—
- (a) any appeal by the undertaker must be made within 42 days of the date of the notice of the decision or determination, or (where paragraph 2(3) applies) expiry of the decision period as determined under paragraph 2(1);
- (b) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the appeal parties;
- (c) as soon as is practicable following receipt of the appeal documentation, the Secretary of State is to appoint a person to determine the appeal (“the appointed person”) and must notify the appeal parties of the identity of the appointed person and the address to which all correspondence for that person's attention must be sent, the date of such notification being the “start date” for the purposes of this sub-paragraph (2);
- (d) the relevant authority and any requirement consultee must submit written representations to the appointed person in respect of the appeal within ten business days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (e) the appeal parties must make any counter-submissions to the appointed person within ten business days of receipt of written representations pursuant to sub-paragraph (d); and
- (f) the appointed person must decide the appeal and notify the appeal parties of the decision, with reasons, as soon as reasonably practicable and in any event within 30 business days of the deadline for the receipt of counter-submissions pursuant to sub-paragraph (e).
- (3) The appointment of the person pursuant to sub-paragraph (2)(c) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (4) If the appointed person considers that further information is necessary to enable consideration of the appeal the appointed person must, within five business days of his appointment, notify the appeal parties in writing specifying the further information required, the appeal part from whom the information is sought, and the date by which the information is to be submitted.
- (5) Any further information required pursuant to sub-paragraph (4) is to be provided by the party from whom the information is sought to the appointed person and to the other appeal parties by the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within ten business days of the specified date but otherwise is to be in accordance with the process and time limits set out in sub-paragraphs (2)(d) to (2)(f).
- (6) On an appeal under this paragraph, the appointed person may—
- (a) allow or dismiss the appeal, or
- (b) reverse or vary any part of the decision of the relevant authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to the appointed person in the first instance.
- (7) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the prescribed time limits, or set by the appointed person, under this paragraph.
- (8) The appointed person may proceed to a decision even though no written representations have been made within the prescribed time limits, if it appears to him that there is sufficient material to enable a decision to be made on the merits of the case.
- (9) The decision of the appointed person on an appeal is to be final and binding on the appeal parties, and a court may entertain proceedings for questioning the decision only if the proceedings are brought by a claim for judicial review.
- (10) If an approval is given by the appointed person pursuant to this Schedule, it is deemed to be an approval for the purpose of any consent, agreement or approval required under the Order or for the purpose of Schedule 2 as if it had been given by the relevant authority. The relevant authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) is not to be taken to affect or invalidate the effect of the appointed person's determination.
- (11) The appointed person may or may not be a member of the Planning Inspectorate but must be a qualified town planner of at least ten years' experience.
- (12) Save where a direction is given pursuant to sub-paragraph (13) requiring the costs of the appointed person to be paid by the relevant authority, the reasonable costs of the appointed person must be met by the undertaker.
- (13) On application by the relevant authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to Planning Practice Guidance: Appeals (March 2014), published by the Ministry of Housing, Communities & Local Government, or any circular or guidance which may from time to time replace it.
Application to protective provisions
5
Nothing in this Schedule applies to any consent, agreement or approval required or contemplated by Schedule 10 or article 20(6) (protective work to buildings).
SCHEDULE 13 — MODIFICATIONS TO THE SECTION 36 CONSENT AND RRRF PLANNING PERMISSION
PART 1 — SECTION 36 CONSENT
1
Delete the words “associated open storage areas for ash container storage,” in paragraph 2(f).
2
Delete “and” at the end of paragraph 3(1)(i).
3
For the words “25 September 2014.” at the end of paragraph 3(1)(ii) substitute “ 25 September 2014; and ”.
4
After paragraph 3(1)(ii) insert new paragraph 3(1)(iii) as follows, “ (iii) the Riverside Energy Park Order 2020 ”.
PART 2 — RRRF PLANNING PERMISSION
5
After RRRF condition 1(iii), insert new condition 1(iv) as follows, “ (iv) the Riverside Energy Park Order 2020 ”.
6
In RRRF condition 7, insert the words “ (except for the development authorised by the Riverside Energy Park Order 202 ”)” after “ and for no other purpose ”.
7
For RRRF condition 23, substitute new condition 23 as follows “ 23. Bottom ash shall only be stored in the bunkers to the development hereby approved ”.
Signed
Signed by the authority of the Secretary of State for Business, Energy and Industrial Strategy
Gareth Leigh — Head of Energy Infrastructure Planning — 2020-04-09
Explanatory note
(This note is not part of the Order)
Footnotes
[^f00001]: 2008 c.29. The relevant provisions of the 2008 Act are amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c.20).
[^f00002]: S.I. 2009/2264, amended by S.I 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, 2014/469, 2014/2381, 2015/377, 2015/1682, 2017/524, 2017/572 and S.I. 2018/378.
[^f00003]: S.I. 2010/103, amended by S.I. 2012/635.
[^f00004]: 2008 c.29. Section 83 was amended by paragraphs 35(2) and 35(3) of schedule 13(1) and paragraph 1 of Schedule 25(20) to the Localism Act 2011 (c.20).
[^f00005]: S.I. 2017/572.
[^f00006]: 2008 c.29. Section 127 was amended by section 23,(2)(a), 23(2)(b) and 23(2)(c) of the Growth and Infrastructure Act 2013 (c.27) and by paragraphs 64 (2) of Schedule 13(1) to the Localism Act 2011 (c.20).
[^f00007]: 1961 c.33.
[^f00008]: 1965 c.56.
[^f00009]: 1980 c.66.
[^f00010]: 1981 c.66.
[^f00011]: 1984 c.27.
[^f00012]: 1990 c.8.
[^f00013]: 1991 c.22.
[^f00014]: 2008 c.29.
[^f00015]: S.I. 2016/1154.
[^f00016]: 1981. c.67. Section 7 was amended by paragraph 9 of Schedule 15 to the Planning and Compensation Act 1991 (c.34). There are other amendments to this section which are not relevant to this Order.
[^f00017]: 1989 c.29
[^f00018]: 2003 c.21
[^f00019]: 1991 c.57
[^f00020]: 2017 c.20
[^f00021]: 1968 (c.xxxii).
[^f00022]: 2004 c.18. There are amendments to this Act not relevant to this Order.
[^f00023]: 1991 c.56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c.43) and sections 99(2), (4), (5)(a), (5)(b),(5)(c) and 36(2) of the Water Act 2003 (c.37) and section 32, Schedule 3, paragraph 16(1) of the Flood and Water Management Act 2010 c.29.
[^f00024]: 1964 c.40.
[^f00025]: 1991 c.57.
[^f00026]: The functions of the Lands Tribunal under the 1961 Act are transferred to the Upper Tribunal under the Tribunals, Courts and Enforcement Act 2007 (c.15).
[^f00027]: Inserted by section 182(2) of The Housing and Planning Act 2016 (c.22).
[^f00028]: Inserted by section 202(2) of The Housing and Planning Act 2016 (c.22).
[^f00029]: Inserted by paragraph 6 of Schedule 18 to The Housing and Planning Act 2016 (c.22).
[^f00030]: Inserted by section 202(1) of the Housing and Planning Act 2016 (c.22).
[^f00031]: Inserted by section 186(3) of the Housing and Planning Act 2016 (c.22).
[^f00032]: Inserted by schedule 17(1) paragraph 3 to the Housing and Planning Act 2016 (c.22).
[^f00033]: 2003 c.21.
[^f00034]: 1990 c.43. Section 82 was amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c.16); section 79 was amended by sections 101 and 102 of the same Act. There are other amendments not relevant to this Order.
[^f00035]: 1974 c.40.
[^f00036]: 1978 c.30.
[^f00037]: 1984 c.27, amended by the Road Traffic (Consequential Provisions) act 1988 (c.54), section 4, Schedule 3, paragraph 25(8).
[^f00038]: 1973 c.26.
[^f00039]: 1989 c.29.
[^f00040]: 1991 c.56.
[^f00041]: 1991 c.56. Section 102 was amended by sections 96(1)(a), 96(1)(b), 96(1)(c), 96(1)(d) and 96(1)(e) of the Water Act 2003 c.37 and paragraph 90 of Schedule 7 to the Water Act 2014 c.21.
[^f00042]: 1986 c.44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c.45), and was further amended by section 76 of the Utilities Act 2000 (c.27).
[^f00043]: 2003 c.21.
[^f00044]: 1991 c.29.
[^f00045]: 1993 c.43.
[^f00046]: 2006 c.46
[^f00047]: 1971 c.80
A nationally significant infrastructure project as defined in section 14(1)(a) (nationally significant infrastructure projects: general) and section 15 (generating stations) of the 2008 Act being a generating station with a capacity of over 50 megawatts but below 300 megawatts and associated development under sections 115(1) and (2) (development for which development consent may be granted) of the 2008 Act comprising all or part of—
In the London Borough of Bexley
Work No. 1 — Works to construct an integrated energy park—
- (a) Work No. 1A — an energy recovery facility with a capacity to process up to 805,920 tonnes of waste per calendar year including—
- (i) fuel reception and storage facilities consisting of a tipping hall and vehicle ramp(s), shredder, solid fuel storage bunker, cranes and handling equipment;
- (ii) waste processing lines, each line including a feed hopper, ram feed, air cooled moving grates, a boiler and steam systems, combustion air systems and flue gas treatment facilities including residue and reagent storage silos and tanks;
- (iii) associated induced fans and emissions control monitoring systems;
- (iv) up to two emission stacks;
- (v) a steam turbine incorporating at least 30 megawatts heat off–take for district heating and electrical generator (if not constructed and installed as part of Work No. 2);
- (vi) an integrated protection system and uninterruptable power supplies; and
- (vii) bottom ash conveyors, including storage bunker, crane and ash collection bay.
- (b) Work No. 1B— an anaerobic digestion system with a capacity to process up to 40,000 tonnes of waste per calendar year including—
- (i) fuel reception and storage facilities as constructed for Work No. 1A;
- (ii) conveyor and feed system;
- (iii) anaerobic digestor, dryers and integrated heating system;
- (iv) solid digestate treatment equipment, handling and storage;
- (v) ventilation and air collection system;
- (vi) emission stack;
- (vii) gas flare;
- (viii) combined heat and power plant, including combined heat and power engine;
- (ix) an electrical switchyard, including switchgear and transformer;
- (x) gas storage and upgrading equipment; and
- (xi) associated gas and process heat pipes.
- (c) Work No. 1C — solar photovoltaic panels on all or part of Work No. 1E and, should a steam turbine building be constructed as part of Work No. 2, on all or part of the steam turbine building forming part of Work No. 2, switchgear, inverters, transformers and permanent equipment for maintenance.
- (d) Work No. 1D — a battery storage facility including—
- (i) battery energy storage cells;
- (ii) transformers;
- (iii) protection cabinets; and
- (iv) switch gear and ancillary equipment.
- (e) Work No. 1E — a building with roof enclosing and/or supporting all or part of Work Nos. 1A, 1B, 1C and 1D.
Work No. 2 — Works to construct—
- (a) a cooling system comprising air-cooled condensers; and
- (b) if not constructed and installed as part of Work No. 1A, a steam turbine incorporating at least 30 megawatts heat off–take for district heating and electrical generator and a steam turbine building to house all or part of the same.
Work No. 3 — Works to construct and install combined heat and power equipment including heat exchangers, pipework (including flow/return pipework, valving, pumps, pressurisation and water treatment systems).
Work No.4 — Works to construct an electrical substation including switchgear, and transformer, busbar sections, integrated protection scheme and uninterruptable power supplies.
Work No. 5 — Works to construct or install supporting buildings and facilities, including—
- (a) diesel storage tanks;
- (b) a process effluent storage tank;
- (c) a demineralised water treatment plant;
- (d) fire water tank, pump room(s) and fire protection facilities;
- (e) a control room;
- (f) administration block(s);
- (g) a fully integrated distributed control system;
- (h) workshop(s) and associated stores;
- (i) spare parts storage facilities;
- (j) security gatehouses and barriers;
- (k) weighbridges;
- (l) a heavy goods vehicle holding area;
- (m) an external fuel container storage area;
- (n) emergency stand-by generator(s);
- (o) infrastructure for the transmission and/or storage of compressed natural gas;
- (p) an outage contractor compound; and
- (q) a permanent contractor laydown area.
Work No. 6 — Works to construct and install supporting infrastructure, including—
- (a) pipework (including flow/return pipework), cables, telecommunications, other services and associated infrastructure;
- (b) site drainage, waste management, water, wastewater, other services and associated infrastructure;
- (c) new or alteration to accesses, a vehicular access road and internal vehicular access road, vehicle turning, waiting and parking areas; and
- (d) vehicle parking.
Work No. 7 — Works to construct and install from Work No. 6 pipes and cables.
Work No. 8 — Works to construct temporary construction compounds including—
- (a) hard standing;
- (b) vehicle parking;
- (c) accommodation block(s);
- (d) new or alteration to accesses; and
- (e) construction fabrication areas.
In the London Borough of Bexley and the Borough of Dartford
Work No. 9 — Works to construct and install an electrical connection including—
- (a) 132kV electrical underground and overground cables and associated telemetry and electrical cabling;
- (b) cable trenches, ducting and jointing pits;
- (c) above ground cable trough structures which are either freestanding or attached to highway structures;
- (d) temporary construction compounds; and
- (e) new or alteration to accesses.
In the Borough of Dartford
Work No. 10 — Works to connect the electrical connection (Work No. 9) to the Littlebrook substation and associated improvements.
In connection with and in addition to Work Nos. 1, 2, 3, 4, 5, 6, 7, 8, 9 and 10 and, to the extent that it does not otherwise form part of those Work Nos., further associated development within the Order limits including—
- (a) external lighting infrastructure, including perimeter lighting columns;
- (b) fencing, boundary treatment and other means of enclosure;
- (c) demolition of existing buildings and structures;
- (d) signage;
- (e) CCTV and other security measures;
- (f) surface and foul water drainage facilities;
- (g) potable water supply;
- (h) new telecommunications and utilities apparatus and connections;
- (i) hard and soft landscaping;
- (j) biodiversity enhancement measures and environmental mitigation measures;
- (k) works permanently to alter the position of existing telecommunications and utilities apparatus and connections;
- (l) works for the protection of buildings and land; and
- (m) site establishment and preparation works, including site clearance (including temporary fencing and vegetation removal), earthworks (including soil stripping and storage and site levelling) and excavations, the creation of temporary construction access points and the temporary alteration of the position of services and utilities apparatus and connections,
and such other buildings, structures, works or operations and modifications to, or demolition of, any existing buildings, structures or works as may be necessary or expedient for the purposes of or in connection with the construction, operation and maintenance of the works in this Schedule 1, but only within the Order limits and insofar as they are unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
Editorial notes
[^c24052381]: 2008 c.29. The relevant provisions of the 2008 Act are amended by Chapter 6 of Part 6 of, and Schedule 13 to, the Localism Act 2011 (c.20).
[^c24052391]: S.I. 2009/2264, amended by S.I 2010/439, S.I. 2010/602, S.I. 2012/635, S.I. 2012/2654, S.I. 2012/2732, S.I. 2013/522, S.I. 2013/755, 2014/469, 2014/2381, 2015/377, 2015/1682, 2017/524, 2017/572 and S.I. 2018/378.
[^c24052401]: S.I. 2010/103, amended by S.I. 2012/635.
[^c24052411]: 2008 c.29. Section 83 was amended by paragraphs 35(2) and 35(3) of schedule 13(1) and paragraph 1 of Schedule 25(20) to the Localism Act 2011 (c.20).
[^c24052421]: S.I. 2017/572.
[^c24052431]: 2008 c.29. Section 127 was amended by section 23,(2)(a), 23(2)(b) and 23(2)(c) of the Growth and Infrastructure Act 2013 (c.27) and by paragraphs 64 (2) of Schedule 13(1) to the Localism Act 2011 (c.20).
[^c24052441]: 1961 c.33.
[^c24052451]: 1965 c.56.
[^c24052461]: 1980 c.66.
[^c24052471]: 1981 c.66.
[^c24052481]: 1984 c.27.
[^c24052491]: 1990 c.8.
[^c24052501]: 1991 c.22.
[^c24052511]: 2008 c.29.
[^c24052521]: S.I. 2016/1154.
[^c24052531]: 1981. c.67. Section 7 was amended by paragraph 9 of Schedule 15 to the Planning and Compensation Act 1991 (c.34). There are other amendments to this section which are not relevant to this Order.
[^c24052541]: 1989 c.29
[^c24052551]: 2003 c.21
[^c24052561]: 1991 c. 57
[^c24052571]: 2017 c. 20
[^c24052581]: 1968 (c.xxxii).
[^c24052591]: 2004 c.18. There are amendments to this Act not relevant to this Order.
[^c24052601]: 1991 c.56. Section 106 was amended by sections 43(2) and 35(8)(a) and paragraph 1 of Schedule 2 to the Competition and Service (Utilities) Act 1992 (c.43) and sections 99(2), (4), (5)(a), (5)(b),(5)(c) and 36(2) of the Water Act 2003 (c.37) and section 32, Schedule 3, paragraph 16(1) of the Flood and Water Management Act 2010 c.29.
[^c24052611]: 1964 c.40.
[^c24052621]: 1991 c.57.
[^c24052631]: The functions of the Lands Tribunal under the 1961 Act are transferred to the Upper Tribunal under the Tribunals, Courts and Enforcement Act 2007 (c.15).
[^c24052641]: Inserted by section 182(2) of The Housing and Planning Act 2016 (c.22).
[^c24052651]: Inserted by section 202(2) of The Housing and Planning Act 2016 (c.22).
[^c24052661]: Inserted by paragraph 6 of Schedule 18 to The Housing and Planning Act 2016 (c.22).
[^c24052671]: Inserted by section 202(1) of the Housing and Planning Act 2016 (c.22).
[^c24052681]: Inserted by section 186(3) of the Housing and Planning Act 2016 (c.22).
[^c24052691]: Inserted by schedule 17(1) paragraph 3 to the Housing and Planning Act 2016 (c.22).
[^c24052701]: 2003 c.21.
[^c24052711]: 1990 c.43. Section 82 was amended by section 103 of the Clean Neighbourhoods and Environment Act 2005 (c.16); section 79 was amended by sections 101 and 102 of the same Act. There are other amendments not relevant to this Order.
[^c24052721]: 1974 c.40.
[^c24052731]: 1978 c.30.
[^c24052741]: 1984 c.27, amended by the Road Traffic (Consequential Provisions) act 1988 (c.54), section 4, Schedule 3, paragraph 25(8).
[^c24052751]: 1973 c.26.
[^c24052761]: 1989 c.29.
[^c24052771]: 1991 c.56.
[^c24052781]: 1991 c.56. Section 102 was amended by sections 96(1)(a), 96(1)(b), 96(1)(c), 96(1)(d) and 96(1)(e) of the Water Act 2003 c.37 and paragraph 90 of Schedule 7 to the Water Act 2014 c.21.
[^c24052791]: 1986 c.44. A new section 7 was substituted by section 5 of the Gas Act 1995 (c.45), and was further amended by section 76 of the Utilities Act 2000 (c.27).
[^c24052801]: 2003 c.21.
[^c24052811]: 1991 c.29.
[^c24052821]: 1993 c.43.
[^c24052831]: 2006 c.46
[^c24052841]: 1971 c.80
[^key-caa1207b19eb98428bce6d70c291d59c]: Art. 1 in force at 1.5.2020, see art. 1
[^key-672faca9f51fdd655cfe35c4b530ada2]: Art. 2 in force at 1.5.2020, see art. 1
[^key-2705033058797caac870ca8693ffcaab]: Art. 3 in force at 1.5.2020, see art. 1
[^key-b3b9b46a6c174da79cf71e37b6f8b662]: Art. 4 in force at 1.5.2020, see art. 1
[^key-662468cf80c755bc4d0c83a14cd481cf]: Art. 5 in force at 1.5.2020, see art. 1
[^key-594a05f0459863282e60bc54ede4c70a]: Art. 6 in force at 1.5.2020, see art. 1
[^key-c1cfd3ea40d71c53cb7ddbd5af429de7]: Art. 7 in force at 1.5.2020, see art. 1
[^key-e3feb863f9e426af7ceaf9170dfa7035]: Art. 8 in force at 1.5.2020, see art. 1
[^key-91915e3ee810dc2b70d1d571848e447f]: Art. 9 in force at 1.5.2020, see art. 1
[^key-970324f9dcfccd55f9687cd4fde80a00]: Art. 10 in force at 1.5.2020, see art. 1
[^key-54741fc3970ddc692f7b2bec209c9b52]: Art. 11 in force at 1.5.2020, see art. 1
[^key-82268a385ec7e275e827aa8de33437ef]: Art. 12 in force at 1.5.2020, see art. 1
[^key-aee4afb18b7272be2a3a772a6cf5f12a]: Art. 13 in force at 1.5.2020, see art. 1
[^key-508a33330fa4aaf4de91343f1c42fc0c]: Art. 14 in force at 1.5.2020, see art. 1
[^key-dbfa67919f18329a502a4e7de0b90947]: Art. 15 in force at 1.5.2020, see art. 1
[^key-072a23cfb80aa6d62f9e636887956aa9]: Art. 16 in force at 1.5.2020, see art. 1
[^key-81d0ffc4b52e8bca915069f937ec705a]: Art. 17 in force at 1.5.2020, see art. 1
[^key-4d631c136462ebaab66a6eb920ce7791]: Art. 18 in force at 1.5.2020, see art. 1
[^key-8d7f7b5cc728119f84348490e4a5287f]: Art. 19 in force at 1.5.2020, see art. 1
[^key-2fdf7f9ed1cdbde1d89a54125af1e05e]: Art. 20 in force at 1.5.2020, see art. 1
[^key-425a28bb58d1be656dbee9dbe830b699]: Art. 21 in force at 1.5.2020, see art. 1
[^key-ac6641aaee8a4fdc0c91d6eba37b7bdd]: Art. 22 in force at 1.5.2020, see art. 1
[^key-025d2644bc333e029111ad20a3b1a43a]: Art. 23 in force at 1.5.2020, see art. 1
[^key-27802dfdc66a9dc4b391fa5fe442d530]: Art. 24 in force at 1.5.2020, see art. 1
[^key-1372e7df11669e46258f0022bb0c9879]: Art. 25 in force at 1.5.2020, see art. 1
[^key-e10cd36f9858175c1a97058fe0bf9696]: Art. 26 in force at 1.5.2020, see art. 1
[^key-605ae70aeb7f75801a4c1a45371aeb5b]: Art. 27 in force at 1.5.2020, see art. 1
[^key-e90cfccb4c7eb257fe3b4bd38ce9d997]: Art. 28 in force at 1.5.2020, see art. 1
[^key-c5f0ea77708b59696f7f381e0212f29a]: Art. 29 in force at 1.5.2020, see art. 1
[^key-aa715e1ca08d0e4ec3e787d79a6e3699]: Art. 30 in force at 1.5.2020, see art. 1
[^key-e225c0a25659ff96ec1ac7361787747f]: Art. 31 in force at 1.5.2020, see art. 1
[^key-940fc327c545abccbcb4f227452c527f]: Art. 32 in force at 1.5.2020, see art. 1
[^key-cbdf9c8620bbf8e2ce17d3dd1fcc8e84]: Art. 33 in force at 1.5.2020, see art. 1
[^key-958f711cd0f7897e80c20a891a972dcc]: Art. 34 in force at 1.5.2020, see art. 1
[^key-b80a9f073e596fe6f22c126d6c5a8215]: Art. 35 in force at 1.5.2020, see art. 1
[^key-6ad076af5fe70c7855c51e26f710de97]: Art. 36 in force at 1.5.2020, see art. 1
[^key-1fe12a6d5ed5c05adcb099388fbbdb9d]: Art. 37 in force at 1.5.2020, see art. 1
[^key-adcf807d14f387b701858e09ece16efe]: Art. 38 in force at 1.5.2020, see art. 1
[^key-572c4d938cf7334e6d286742916c34a5]: Art. 39 in force at 1.5.2020, see art. 1
[^key-855769479929aa48b9ff3b04e88723b7]: Art. 40 in force at 1.5.2020, see art. 1
[^key-fdb1bcebbbd10f4468c0d0b63606a721]: Art. 41 in force at 1.5.2020, see art. 1
[^key-b670f12a5e3c22ad953ff078fed3a4c8]: Art. 42 in force at 1.5.2020, see art. 1
[^key-b9a82e123fedcd547031a4281bda43fa]: Art. 43 in force at 1.5.2020, see art. 1
[^key-14efabccb6d308e573093f3a3be7cdac]: Sch. 2 para. 1 in force at 1.5.2020, see art. 1
[^key-33b30f39969b6b29ec86fad574ddd92e]: Sch. 2 para. 2 in force at 1.5.2020, see art. 1
[^key-1b3377b929f69178c297c627618d5776]: Sch. 2 para. 3 in force at 1.5.2020, see art. 1
[^key-7d4dd3d3fc3d11aba22fcf6020b46bbd]: Sch. 2 para. 4 in force at 1.5.2020, see art. 1
[^key-84238d64ddcafaed295e754cc6974243]: Sch. 2 para. 5 in force at 1.5.2020, see art. 1
[^key-c83b8b787d741b16bda852ca21e657c3]: Sch. 2 para. 6 in force at 1.5.2020, see art. 1
[^key-04e347644aeb97bf20330cdb48d16981]: Sch. 2 para. 7 in force at 1.5.2020, see art. 1
[^key-43c50dee987d94a6afb6d51ea70f0175]: Sch. 2 para. 8 in force at 1.5.2020, see art. 1
[^key-a4414e2e1df0de3d9faa20e4dd858a82]: Sch. 2 para. 9 in force at 1.5.2020, see art. 1
[^key-42b951d8bb5a69a2a0d5a361c83b831e]: Sch. 2 para. 10 in force at 1.5.2020, see art. 1
[^key-95c83ff8fe9f8891df6e28ad43bd8253]: Sch. 2 para. 11 in force at 1.5.2020, see art. 1
[^key-dc597ff6bc287d6a1155bbc4b1e4a1ca]: Sch. 2 para. 12 in force at 1.5.2020, see art. 1
[^key-b47b15a90ee1b52a748f46ba0341afe2]: Sch. 2 para. 13 in force at 1.5.2020, see art. 1
[^key-a6c37fd11e7117e963ea0440827ec844]: Sch. 2 para. 14 in force at 1.5.2020, see art. 1
[^key-9f5cf1c2108bfcb4ba5b8fcb6931e699]: Sch. 2 para. 15 in force at 1.5.2020, see art. 1
[^key-d23d16282cfb309ab7b21e1e7f21270f]: Sch. 2 para. 16 in force at 1.5.2020, see art. 1
[^key-43c6ab78d34fd3da3f167c57d37f8141]: Sch. 2 para. 17 in force at 1.5.2020, see art. 1
[^key-f999e48c5bbc71a389f9eba59a783d1b]: Sch. 2 para. 18 in force at 1.5.2020, see art. 1
[^key-4469d4b77a48536fb932ebe809957023]: Sch. 2 para. 19 in force at 1.5.2020, see art. 1
[^key-dc60c32b3916128b785359aa66f8e3e6]: Sch. 2 para. 20 in force at 1.5.2020, see art. 1
[^key-6e9061058c3437fe0682cbbf4f6b6c13]: Sch. 2 para. 21 in force at 1.5.2020, see art. 1
[^key-454bccf6258a2a76e0e929ba81e463c7]: Sch. 2 para. 22 in force at 1.5.2020, see art. 1
[^key-b754edf8dccd099881d1a328e27e8ccf]: Sch. 2 para. 23 in force at 1.5.2020, see art. 1
[^key-1f1719b09bb4a5f149452b187985737e]: Sch. 2 para. 24 in force at 1.5.2020, see art. 1
[^key-31e3f6eb2332948613966fc36f4d7c75]: Sch. 2 para. 25 in force at 1.5.2020, see art. 1
[^key-d956f65c95bbfde821252002a7e59e31]: Sch. 2 para. 26 in force at 1.5.2020, see art. 1
[^key-de3d773de80db5ec7328f550ef9bad42]: Sch. 2 para. 27 in force at 1.5.2020, see art. 1
[^key-a1dfae69afa6194daac01a71b21a74a5]: Sch. 2 para. 28 in force at 1.5.2020, see art. 1
[^key-5de1c5c55754950564da549abb69b111]: Sch. 2 para. 29 in force at 1.5.2020, see art. 1
[^key-11e3fe4233953ebbed79ba5eb5313bed]: Sch. 2 para. 30 in force at 1.5.2020, see art. 1
[^key-08bfed4753c85ad40a84c0cef727a4cf]: Sch. 2 para. 31 in force at 1.5.2020, see art. 1
[^key-00e1faec3bebb316e6e133840bc0d3a6]: Sch. 2 para. 32 in force at 1.5.2020, see art. 1
[^key-7f50d1dde75908bc5d3ea148b54265ea]: Sch. 2 para. 33 in force at 1.5.2020, see art. 1
[^key-da7bc0ef67cadd94f0b34cd689a4da03]: Sch. 7 para. 1 in force at 1.5.2020, see art. 1
[^key-45b2d1805d13cd6d5f2d7548ba45f608]: Sch. 8 para. 1 in force at 1.5.2020, see art. 1
[^key-726fb42d64220766038d47ad8fe0946c]: Sch. 8 para. 2 in force at 1.5.2020, see art. 1
[^key-8967575c3b9b87d435e81e72f04e4cb0]: Sch. 8 para. 3 in force at 1.5.2020, see art. 1
[^key-e289e349614dfd62116a64e52605e0fc]: Sch. 8 para. 4 in force at 1.5.2020, see art. 1
[^key-227766dd858717635a24741df85f213c]: Sch. 8 para. 5 in force at 1.5.2020, see art. 1
[^key-a6ca112028fa8929e803d49900555700]: Sch. 10 para. 1 in force at 1.5.2020, see art. 1
[^key-ddc29c0abb15c0c518107c06efed900c]: Sch. 10 para. 2 in force at 1.5.2020, see art. 1
[^key-59eeeb575ffa02e7b90593215e0ba52d]: Sch. 10 para. 3 in force at 1.5.2020, see art. 1
[^key-6f8d892f629c5456a7daca6fe3f51162]: Sch. 10 para. 4 in force at 1.5.2020, see art. 1
[^key-7b646dcbc07da8c5face894cd9ff259f]: Sch. 10 para. 5 in force at 1.5.2020, see art. 1
[^key-ad97446e13a5a286fe6e7108c715d8ca]: Sch. 10 para. 6 in force at 1.5.2020, see art. 1
[^key-f88d6c4a68823510ccce0b2d7c316275]: Sch. 10 para. 7 in force at 1.5.2020, see art. 1
[^key-e40bf7ae806b8d8c4ad68c6e03e99bf4]: Sch. 10 para. 8 in force at 1.5.2020, see art. 1
[^key-1c5d85ab7ea369fcebd012923f4c62f9]: Sch. 10 para. 9 in force at 1.5.2020, see art. 1
[^key-d14e9f57d52f03d91c99ba6bbd4e5bfc]: Sch. 10 para. 10 in force at 1.5.2020, see art. 1
[^key-75c3dfb4cae3b1d59ba20cb05ef302a4]: Sch. 10 para. 11 in force at 1.5.2020, see art. 1
[^key-d37aebf2a9164ec2e9919b6cca4e8185]: Sch. 10 para. 12 in force at 1.5.2020, see art. 1
[^key-7265b19d5007f39480e6473d97930538]: Sch. 10 para. 13 in force at 1.5.2020, see art. 1
[^key-1e7b29d5587d3a7e64f7fa7ebaa42c70]: Sch. 10 para. 14 in force at 1.5.2020, see art. 1
[^key-71e46c80af3f76319abf0a34c9a9f44a]: Sch. 10 para. 15 in force at 1.5.2020, see art. 1
[^key-e9267007dcf9870d366b45497e280d2e]: Sch. 10 para. 16 in force at 1.5.2020, see art. 1
[^key-3491de82af7d16e8a308f32d71815dc4]: Sch. 10 para. 17 in force at 1.5.2020, see art. 1
[^key-b4f1d5b66350c4fc8d9419f3d93c944d]: Sch. 10 para. 18 in force at 1.5.2020, see art. 1
[^key-b9b880ca6bad81eabdc0329e70812791]: Sch. 10 para. 19 in force at 1.5.2020, see art. 1
[^key-1e5b2809c4aed80c8db969e660fcac75]: Sch. 10 para. 20 in force at 1.5.2020, see art. 1
[^key-46a33e2a7fbad736a91954b2ce173546]: Sch. 10 para. 21 in force at 1.5.2020, see art. 1
[^key-a8a8110b51bb680f24916dd92d120cc8]: Sch. 10 para. 22 in force at 1.5.2020, see art. 1
[^key-23b539a54582b5c38e51be468097c369]: Sch. 10 para. 23 in force at 1.5.2020, see art. 1
[^key-287356b2f397cc9d025a0876e60134c6]: Sch. 10 para. 24 in force at 1.5.2020, see art. 1
[^key-9afb8a4bb1aa3aaa44fa70bd504995c7]: Sch. 10 para. 25 in force at 1.5.2020, see art. 1
[^key-e0798d7a6d87b814a6bbb8d5463bff81]: Sch. 10 para. 26 in force at 1.5.2020, see art. 1
[^key-b1c94498af11a266a52b18e254b6c82b]: Sch. 10 para. 27 in force at 1.5.2020, see art. 1
[^key-7917e3b1c4c7410b6c2852a04a6c1973]: Sch. 10 para. 28 in force at 1.5.2020, see art. 1
[^key-1ed99f91e6b93e6a8a42e5af30d6f94d]: Sch. 10 para. 29 in force at 1.5.2020, see art. 1
[^key-11eac5a155e9df96e77b4c256e044a70]: Sch. 10 para. 30 in force at 1.5.2020, see art. 1
[^key-47f66ee5b57534fe7577888577ffe548]: Sch. 10 para. 31 in force at 1.5.2020, see art. 1
[^key-b80ae1d02d4c40dfed3aec43dfcc013b]: Sch. 10 para. 32 in force at 1.5.2020, see art. 1
[^key-ee07c0cf5c42f75e56ef840b00878b94]: Sch. 10 para. 33 in force at 1.5.2020, see art. 1
[^key-030a173fb6aa67a9c2a8c4abc18e02de]: Sch. 10 para. 34 in force at 1.5.2020, see art. 1
[^key-919ce069f2fd226f64cd725b91c8b20b]: Sch. 10 para. 35 in force at 1.5.2020, see art. 1
[^key-8c42a936b246c1ee362336b67e24b0d4]: Sch. 10 para. 36 in force at 1.5.2020, see art. 1
[^key-d2ef5874508bd190aca626baefa050b4]: Sch. 10 para. 37 in force at 1.5.2020, see art. 1
[^key-cc87f3609733fa8a7f45dd343f9db5a9]: Sch. 10 para. 38 in force at 1.5.2020, see art. 1
[^key-b2a5ce4aabf6573d0a06d114e0f5ddea]: Sch. 10 para. 39 in force at 1.5.2020, see art. 1
[^key-f91aee1e7354af309fec61c4c3a760ca]: Sch. 10 para. 40 in force at 1.5.2020, see art. 1
[^key-1d4d9c531f1da752a59a1b82b73be1c2]: Sch. 10 para. 41 in force at 1.5.2020, see art. 1
[^key-07d7fb2d340c35aef9afc0cb5cbaf542]: Sch. 10 para. 42 in force at 1.5.2020, see art. 1
[^key-d1b3c7ce343e0bc8e64d2d43f1469688]: Sch. 10 para. 43 in force at 1.5.2020, see art. 1
[^key-8525b1fa3dc716b56a471fd60a9f60ba]: Sch. 10 para. 44 in force at 1.5.2020, see art. 1
[^key-6148fda1a2263a1f57f3901ae459eacb]: Sch. 10 para. 45 in force at 1.5.2020, see art. 1
[^key-acaa7575f01979c199a0df4794f89c31]: Sch. 10 para. 46 in force at 1.5.2020, see art. 1
[^key-fe17b22f8edafd3f50070d3414fe2428]: Sch. 10 para. 47 in force at 1.5.2020, see art. 1
[^key-82748cb717c883091917df99a1db7ff2]: Sch. 10 para. 48 in force at 1.5.2020, see art. 1
[^key-148bdff31422aa280f0b21bea38793b7]: Sch. 10 para. 49 in force at 1.5.2020, see art. 1
[^key-f7a24204f47bcbd01671a4b41e260f65]: Sch. 10 para. 50 in force at 1.5.2020, see art. 1
[^key-8644e41fde938261f8ba477f295e65d0]: Sch. 10 para. 51 in force at 1.5.2020, see art. 1
[^key-6bf86f36be2eb90e033d7be8d336f664]: Sch. 10 para. 52 in force at 1.5.2020, see art. 1
[^key-bd7af4f4a5bdab29740e4b349deabbc5]: Sch. 10 para. 53 in force at 1.5.2020, see art. 1
[^key-3210af97e1891317b65b11d4a5253c9c]: Sch. 10 para. 54 in force at 1.5.2020, see art. 1
[^key-941ab3755e0be7e27edf2b4e2aea2367]: Sch. 10 para. 55 in force at 1.5.2020, see art. 1
[^key-d8a1008e8aa9f03270ac70d79c45f19f]: Sch. 10 para. 56 in force at 1.5.2020, see art. 1
[^key-f5c013e5a7a197064d131cbb2b7e2d1d]: Sch. 10 para. 57 in force at 1.5.2020, see art. 1
[^key-765341e6715b59b64180d738e352282b]: Sch. 10 para. 58 in force at 1.5.2020, see art. 1
[^key-996934e3e6c3ab0f607bbb153b973dc2]: Sch. 10 para. 59 in force at 1.5.2020, see art. 1
[^key-38a7e42733e5aaa1b342259a340f382e]: Sch. 10 para. 60 in force at 1.5.2020, see art. 1
[^key-9fef4d4e82d1a03c59f002a8b6938f40]: Sch. 10 para. 61 in force at 1.5.2020, see art. 1
[^key-503f988bc4551848369312e316cac5db]: Sch. 10 para. 62 in force at 1.5.2020, see art. 1
[^key-b813db1ef184a2e0fbcfef51cace9d8b]: Sch. 10 para. 63 in force at 1.5.2020, see art. 1
[^key-29321bd2a591b9f085ebeb54b1840f4a]: Sch. 10 para. 64 in force at 1.5.2020, see art. 1
[^key-079e086bba601e3308dc70f06cc88373]: Sch. 10 para. 65 in force at 1.5.2020, see art. 1
[^key-7cb23d44704ad87b5fd678447f3f5fd6]: Sch. 10 para. 66 in force at 1.5.2020, see art. 1
[^key-5d39cec7f7a59800879640d7b1186c79]: Sch. 10 para. 67 in force at 1.5.2020, see art. 1
[^key-10c70343f21a93e34a94de7a0d3448a5]: Sch. 10 para. 68 in force at 1.5.2020, see art. 1
[^key-87c850b5eeb6e2b91d8e341e138a3909]: Sch. 10 para. 69 in force at 1.5.2020, see art. 1
[^key-84175b47413a4dde845fecddbc434ebc]: Sch. 10 para. 70 in force at 1.5.2020, see art. 1
[^key-058914575b814d4da11f424b2c4327ff]: Sch. 10 para. 71 in force at 1.5.2020, see art. 1
[^key-1857bb45d04ed39c41974eb976ec99ee]: Sch. 10 para. 72 in force at 1.5.2020, see art. 1
[^key-7901f367b286d83dbec46b2f9c590cc7]: Sch. 10 para. 73 in force at 1.5.2020, see art. 1
[^key-3e72745de9ab5b91a89b4c66fe43e1a4]: Sch. 10 para. 74 in force at 1.5.2020, see art. 1
[^key-71cd9049821fc2d9c5c07a06dc1dc89f]: Sch. 10 para. 75 in force at 1.5.2020, see art. 1
[^key-21a183bd002ed8c11f360573bfa5e8ba]: Sch. 10 para. 76 in force at 1.5.2020, see art. 1
[^key-6f093519a730d2c23fc3429c30ba9644]: Sch. 10 para. 77 in force at 1.5.2020, see art. 1
[^key-8ce3a7a38320cbc0b8c52ee2ec9f333a]: Sch. 10 para. 78 in force at 1.5.2020, see art. 1
[^key-8a0da1e6816a380015a32e56f7e3ddeb]: Sch. 10 para. 79 in force at 1.5.2020, see art. 1
[^key-021b7d2b0ad2c2524e1d84c78e10e65b]: Sch. 10 para. 80 in force at 1.5.2020, see art. 1
[^key-88cff505018a40378d6c276b2ba233db]: Sch. 10 para. 81 in force at 1.5.2020, see art. 1
[^key-101738d85c7d1866807620c5aec83886]: Sch. 10 para. 82 in force at 1.5.2020, see art. 1
[^key-5240e830af4dcb22fddc14a4ed985122]: Sch. 10 para. 83 in force at 1.5.2020, see art. 1
[^key-a8e446ae58d884e811e813d65ade2951]: Sch. 10 para. 84 in force at 1.5.2020, see art. 1
[^key-3dbfd692fa46e7a2222f565e7c147fc3]: Sch. 10 para. 85 in force at 1.5.2020, see art. 1
[^key-4dfa0fd01ee10ccccf18443dabfe74f9]: Sch. 10 para. 86 in force at 1.5.2020, see art. 1
[^key-1252c7ba10fb7cb3956019b4c8df2737]: Sch. 10 para. 87 in force at 1.5.2020, see art. 1
[^key-316d6366ec9b1bd97ba4d030a940a016]: Sch. 10 para. 88 in force at 1.5.2020, see art. 1
[^key-13939c6234e641f49d8ff5d3a4e5cb06]: Sch. 10 para. 89 in force at 1.5.2020, see art. 1
[^key-fbf3b6d6c175e473f9ebb331d1ea832f]: Sch. 10 para. 90 in force at 1.5.2020, see art. 1
[^key-b1a1c879bda232fc9c94c0de8b277d04]: Sch. 10 para. 91 in force at 1.5.2020, see art. 1
[^key-15eef71308519cf5f13e325e10810071]: Sch. 10 para. 92 in force at 1.5.2020, see art. 1
[^key-ddd0063a47724f0dabad6f72cbb0a501]: Sch. 10 para. 93 in force at 1.5.2020, see art. 1
[^key-0d81ef285940a21b48178ed4f28c25a5]: Sch. 10 para. 94 in force at 1.5.2020, see art. 1
[^key-508d357df067e5ad8bb9fe0003e7faa0]: Sch. 10 para. 95 in force at 1.5.2020, see art. 1
[^key-cf24705d83695452832ab2c13b98dcac]: Sch. 10 para. 96 in force at 1.5.2020, see art. 1
[^key-5bbba6247312d43cc65b0b73724ba65e]: Sch. 10 para. 97 in force at 1.5.2020, see art. 1
[^key-bf47090b38f2689573b5ec81acf86ede]: Sch. 10 para. 98 in force at 1.5.2020, see art. 1
[^key-7e4232f7b83d02497d1492344f10dabb]: Sch. 10 para. 99 in force at 1.5.2020, see art. 1
[^key-88a86322ce1a0ac177b9f98243a06f96]: Sch. 10 para. 100 in force at 1.5.2020, see art. 1
[^key-d71ea77660778b037e4d30b311435053]: Sch. 10 para. 101 in force at 1.5.2020, see art. 1
[^key-eb5ea2265a620aa221b7cc83ec6a591a]: Sch. 10 para. 102 in force at 1.5.2020, see art. 1
[^key-d60f6d22032ac6391a0e910548528303]: Sch. 10 para. 103 in force at 1.5.2020, see art. 1
[^key-dc21ce74a35ed365a21c61fbdd7e6dcc]: Sch. 10 para. 104 in force at 1.5.2020, see art. 1
[^key-6ffbf5ab8df8ed5d89817e9f2c6cb94c]: Sch. 10 para. 105 in force at 1.5.2020, see art. 1
[^key-2ace930f97dd8a06f4d2f258690fadf6]: Sch. 10 para. 106 in force at 1.5.2020, see art. 1
[^key-073207ced079030b2fdebf115333aa60]: Sch. 10 para. 107 in force at 1.5.2020, see art. 1
[^key-c3a593617cc20e0a16c380b5c84095b7]: Sch. 10 para. 108 in force at 1.5.2020, see art. 1
[^key-fddf14401ebc4806583c7eb18d570dd4]: Sch. 10 para. 109 in force at 1.5.2020, see art. 1
[^key-4793ab3a22e24b718d0985e57a0b63d0]: Sch. 10 para. 110 in force at 1.5.2020, see art. 1
[^key-a72515719d3d70bf9dcc51653d4208e7]: Sch. 10 para. 111 in force at 1.5.2020, see art. 1
[^key-3d2bca01fb9bb0f12577d80eb952f94d]: Sch. 10 para. 112 in force at 1.5.2020, see art. 1
[^key-b43613b1a0fb576967b70d0e792fea9e]: Sch. 10 para. 113 in force at 1.5.2020, see art. 1
[^key-49b26cb8dc613a1ec451911180b51a8d]: Sch. 10 para. 114 in force at 1.5.2020, see art. 1
[^key-4cfc3265b3578cf3c5cd2801e9895f9c]: Sch. 10 para. 115 in force at 1.5.2020, see art. 1
[^key-f22345323ae02a81b0b401b64cd83f40]: Sch. 10 para. 116 in force at 1.5.2020, see art. 1
[^key-7fb03070b00e58990003966e256e19bd]: Sch. 10 para. 117 in force at 1.5.2020, see art. 1
[^key-2dabd97e074b491bfb7d4e16fa7e5d16]: Sch. 10 para. 118 in force at 1.5.2020, see art. 1
[^key-9f57cd4c91c72d2e6c554d29f9536dc3]: Sch. 10 para. 119 in force at 1.5.2020, see art. 1
[^key-bd5aab53eea37cf23c7f6cef80fcba66]: Sch. 12 para. 1 in force at 1.5.2020, see art. 1
[^key-c7b2179be67e004f42da3d61340e60f8]: Sch. 12 para. 2 in force at 1.5.2020, see art. 1
[^key-af6014d50b525577eec4637efd4b9a60]: Sch. 12 para. 3 in force at 1.5.2020, see art. 1
[^key-b9c72c68235c8d41f6303b079c79eaf7]: Sch. 12 para. 4 in force at 1.5.2020, see art. 1
[^key-55d97b63a67f0d20afbabc7771dbdec0]: Sch. 12 para. 5 in force at 1.5.2020, see art. 1
[^key-10e1a84be79fbb60f5c04e14c38728f8]: Sch. 13 para. 1 in force at 1.5.2020, see art. 1
[^key-ae39bdc32178143568850fe3d9ac49c7]: Sch. 13 para. 2 in force at 1.5.2020, see art. 1
[^key-c512b5c616dbc8101a1f5b527d8f04eb]: Sch. 13 para. 3 in force at 1.5.2020, see art. 1
[^key-6124a900297ff63c809ed9d7e93f353f]: Sch. 13 para. 4 in force at 1.5.2020, see art. 1
[^key-1e0502e8ab4bbbff8d82cc7649874cfc]: Sch. 13 para. 5 in force at 1.5.2020, see art. 1
[^key-b812c6c9c4f3afe5e8fdf9cfd1469a89]: Sch. 13 para. 6 in force at 1.5.2020, see art. 1
[^key-89dbda69d3323921d29bb204e3335a22]: Sch. 13 para. 7 in force at 1.5.2020, see art. 1
[^key-71f406241b48fdddea4334bc846ec20a]: Sch. 1 in force at 1.5.2020, see art. 1
[^key-662163474c789cc7dd5d93bce4dab53a]: Sch. 3 in force at 1.5.2020, see art. 1
[^key-21d1dfa4075c5a2ecd146a990af1a939]: Sch. 4 Pt. 1 in force at 1.5.2020, see art. 1
[^key-1173ef46d0f6ad56b17b3e8846c5a97d]: Sch. 4 Pt. 2 in force at 1.5.2020, see art. 1
[^key-6b59796b50bc721f982fd28817f712a6]: Sch. 5 in force at 1.5.2020, see art. 1
[^key-c92685208a641400a5c7e4c05af033b7]: Sch. 6 in force at 1.5.2020, see art. 1
[^key-321393c8bc9285cce43c1fc2d9d5943b]: Sch. 9 in force at 1.5.2020, see art. 1
[^key-9a48e47e1c518f06e0fcd52931c427bd]: Sch. 11 in force at 1.5.2020, see art. 1
[^key-d51cc641dbfeb2f5b166de5671a496b8]: Words in Sch. 1 substituted (10.3.2021) by The Riverside Energy Park (Correction) Order 2021 (S.I. 2021/273), art. 1(2), Sch.
[^key-5d4c5a37d7b9060c7957366d756c05cc]: Words in art. 2(1) inserted (10.3.2021) by The Riverside Energy Park (Correction) Order 2021 (S.I. 2021/273), art. 1(2), Sch.
[^key-e13edebfd06c436edcc2457436c19e89]: Words in art. 9(4)(a) substituted (10.3.2021) by The Riverside Energy Park (Correction) Order 2021 (S.I. 2021/273), art. 1(2), Sch.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.