The Immingham Open Cycle Gas Turbine Order 2020
- (7) The undertaker must compensate the owners and occupiers of any building or land in relation to which rights under this article have been exercised for any loss or damage arising to them by the reason of the exercise of those rights.
- (8) Where—
- (a) protective works are carried out under this article to a building; and
- (b) within a period of five years beginning with the date of final commissioning it appears that the protective works are inadequate to protect the building against damage caused by construction, operation or maintenance of that part of the authorised development,
the undertaker must compensate the owners and occupiers of the building for any loss or damage sustained by them.
- (9) Nothing in this article relieves the undertaker from any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the Planning Act 2008.
- (10) Any compensation payable under paragraph (7) or (8) is to be determined, in the case of dispute, under Part 1 (determination of questions of disputed compensation) of the 1961 Act.
- (11) In this article “protective works” in relation to a building means—
- (a) underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the construction, operation and maintenance or use of the authorised development;
- (b) any works the purpose of which is to remedy any damage which has been caused to the building by the construction, operation and maintenance or use of the authorised development; and
- (c) any works the purpose of which is to secure the safe operation of the authorised development or to prevent or minimise the risk of such operation being disrupted.
- (12) Section 13 (refusal to give possession to acquiring authority) of the 1965 Act applies to the entry onto, or possession of land under this article, to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
PART 7 — MISCELLANEOUS AND GENERAL
Application of landlord and tenant law
34
- (1) This article applies to—
- (a) any agreement for leasing to any person the whole or any part of the authorised development or the right to operate the same; and
- (b) any agreement entered into by the undertaker with any person for the construction, maintenance, use or operation of the authorised development, or any part of it,
so far as any such agreement relates to the terms on which any land which is the subject of a lease granted by or under that agreement is to be provided for that person's use.
- (2) No enactment or rule of law regulating the rights and obligations of landlords and tenants prejudices the operation of any agreement to which this article applies.
- (3) No enactment or rule of law to which paragraph (2) applies is to apply in relation to the rights and obligations of the parties to any lease granted by or under any such agreement so as to—
- (a) exclude or in any respect modify any of the rights and obligations of those parties under the terms of the lease, whether with respect to the termination of the tenancy or any other matter;
- (b) confer or impose on any such party any right or obligation arising out of or connected with anything done or omitted on or in relation to land which is the subject of the lease, in addition to any such right or obligation provided for by the terms of the lease; or
- (c) restrict the enforcement (whether by action for damages or otherwise) by any party to the lease of any obligation of any other party under the lease.
Operational land for purposes of the 1990 Act
35
Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) (cases in which land is to be treated as not being operational land) of the 1990 Act.
Defence to proceedings in respect of statutory nuisance
36
- (1) Where proceedings are brought under section 82(1) (summary proceedings by persons aggrieved by statutory nuisances) of the Environmental Protection Act 1990 in relation to a nuisance falling within paragraph (g) of section 79(1) (noise emitted from premises so as to be prejudicial to health) of that Act no order is to be made, and no fine may be imposed, under section 82(2) of that Act if—
- (a) the defendant shows that the nuisance—
- (i) relates to premises used by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development and that the nuisance is attributable to the carrying out of the authorised development in accordance with a notice served under section 60 (control of noise on construction sites), or a consent given under section 61 (prior consent for work on construction sites) of the Control of Pollution Act 1974 ; or
- (ii) is a consequence of the construction or maintenance of the authorised development and that it cannot reasonably be avoided; or
- (b) the defendant shows that the nuisance is a consequence of the use of the authorised development and that it cannot reasonably be avoided.
- (2) Section 61(9) of the Control of Pollution Act 1974 does not apply where the consent relates to the use of premises by the undertaker for the purposes of or in connection with the construction or maintenance of the authorised development.
Protective provisions
37
Schedule 9 (protective provisions) has effect.
Procedure in relation to certain approvals
38
- (1) Where an application is made to, or a request is made of, the relevant planning authority, highway authority, traffic authority, street authority, or the owner of a watercourse, sewer or drain or the beneficiary of any of the protective provisions contained in Schedule 9 (protective provisions) for any consent, agreement or approval required or contemplated by any of the provisions of the Order (not including the requirements), such consent, agreement or approval to be validly given, must be given in writing.
- (2) Where paragraph (1) applies to any consent, agreement or approval, such consent, agreement or approval must not be unreasonably withheld or delayed.
- (3) Schedule 10 (procedure for discharge of requirements) has effect in relation to all consents, agreements or approvals granted, refused or withheld in relation to the requirements.
- (4) Save for applications made pursuant to Schedule 10 and where stated to the contrary if, within eight weeks (or such longer period as may be agreed with the undertaker in writing) after the application or request has been submitted to an authority, beneficiary of protective provisions or an owner as referred to in paragraph (1) of this article it has not notified the undertaker of its disapproval and the grounds of disapproval, it is deemed to have approved the application or request.
- (5) The procedure set out in paragraph 1(3) of Schedule 10 has effect in relation to any refusal by an authority, beneficiary of protective provisions, or an owner as referred to in paragraph (1) of this article to any consent, agreement or approval required under this Order, including such as may be required pursuant to the protective provisions contained within Schedule 9 (protective provisions).
- (6) Where any application is made as described in paragraph (1), the undertaker must include a statement in such application that refers to the timeframe for consideration of the application and the consequences of failure to meet that timeframe as prescribed by paragraph (4).
Certification of plans etc.
39
- (1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of all documents and plans listed in Table 8 of Schedule 11 (documents and plans to be certified) to this Order for certification that they are true copies of the documents referred to in this Order.
- (2) A plan or document so certified is to be admissible in any proceedings as evidence of the contents of the document of which it is a copy.
Service of notices
40
- (1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
- (a) by post;
- (b) by delivering it to the person on whom it is to be served or to whom it is to be given or supplied; or
- (c) with the consent of the recipient and subject to paragraphs (6) to (8), by electronic transmission.
- (2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
- (3) For the purposes of section 7 (references to service by post) of the Interpretation Act 1978 as it applies for the purposes of this article, the proper address of any person in relation to the service on that person of a notice or document under paragraph (1) is, if that person has given an address for service, that address and otherwise—
- (a) in the case of the secretary or clerk of that body corporate, the registered or principal office of that body; and
- (b) in any other case, the last known address of that person at that time of service.
- (4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having an interest in, or as the occupier of, land and the name or address of that person cannot be ascertained after reasonable enquiry, the notice may be served by—
- (a) addressing it to that person by the description of “owner”, or as the case may be, “occupier” of the land (describing it); and
- (b) either leaving it in the hands of the person who is or appears to be resident or employed on the land or leaving it conspicuously affixed to some building or object on or near the land.
- (5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement is to be taken to be fulfilled only where—
- (a) the recipient of the notice or other document to be transmitted has given consent to the use of electronic transmission in writing or by electronic transmission;
- (b) the notice or document is capable of being accessed by the recipient;
- (c) the notice or document is legible in all material respects; and
- (d) in a form sufficiently permanent to be used for subsequent reference.
- (6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within seven days of receipt that the recipient requires a paper copy of all or any part of that notice or other document the sender must provide such a copy as soon as reasonably practicable.
- (7) Any consent to the use of an electronic transmission by a person may be revoked by that person in accordance with paragraph (8).
- (8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order—
- (a) that person must give notice in writing or by electronic transmission revoking any consent given by that person for that purpose; and
- (b) such revocation is final and takes effect on a date specified by the person in the notice but that date must not be less than seven days after the date on which the notice is given.
- (9) This article does not exclude the employment of any method of service not expressly provided for by it.
- (10) In this article “legible in all material respects” means that the information contained in the notice or document is available to that person to no lesser extent than it would be if served, given or supplied by means of notice or document in printed form.
Amendment and modification of statutory provisions
41
The Able Marine Energy Park Development Consent Order 2014 is amended for the purposes of this Order only as set out in Schedule 13 (modifications to the Able Marine Energy Park Development Consent Order 2014).
Arbitration
42
Any difference under any provision of this Order, unless otherwise provided for, is to be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.
Funding
43
- (1) The undertaker must not exercise the powers conferred by the provisions referred to in paragraph (2) in relation to any Order land unless it has first put in place, following approval by the Secretary of State, either—
- (a) a guarantee (and the amount of that guarantee) in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph (2) in respect of the exercise of the relevant power in relation to that land; or
- (b) an alternative form of security (and the amount of that security) in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph (2) .
- (2) The provisions are—
- (a) article 18 (compulsory acquisition of land);
- (b) article 21 (compulsory acquisition of rights etc.);
- (c) article 22 (private rights);
- (d) article 24 (acquisition of subsoil only);
- (e) article 26 (rights under or over streets);
- (f) article 27 (temporary use of land for carrying out the authorised development);
- (g) article 28 (temporary use of land for maintaining the authorised development); and
- (h) article 29 (statutory undertakers).
- (3) A guarantee or alternative form of security given in respect of the liabilities of the undertaker to pay compensation pursuant to the provisions referred to in paragraph (2) is to be treated as enforceable against the guarantor or person providing the alternative form of security by any person to whom such compensation is payable and must be in such a form as to be capable of enforcement by such a person.
- (4) Nothing in this article requires a guarantee or alternative form of security to be in place for more than 15 years after the date on which the relevant power is exercised.
SCHEDULE 1 — AUTHORISED DEVELOPMENT
In North Lincolnshire—
A nationally significant infrastructure project as defined in sections 14(1)(a) and 15 of the 2008 Act, and associated development under section 115(1)(b) of that Act, consisting of a generating station with a gross rated electrical output of up to 299MWe—
Work No. 1 – OCGT power station, being an open cycle gas turbine generating station with a gross capacity of up to 299 megawatts, comprising—
- (a) gas turbine and turbine hall buildings;
- (b) electrical generator;
- (c) stack;
- (d) auxiliary cooling equipment or system;
- (e) gas turbine air intake filters;
- (f) banks of finfan coolers;
- (g) nitrogen oxide emissions control equipment;
- (h) transformers;
- (i) a switchyard, associated switch gear and ancillary equipment;
- (j) a gas receiving area, gas control facilities and gas reception building;
- (k) lubricating oil, hydraulic oil and chemical storage tanks and equipment;
- (l) continuous emissions monitoring system;
- (m) raw water and fire water storage tanks;
- (n) water treatment facilities, demineralised water treatment works, including storage tanks;
- (o) oily water and waste water treatment plant building and basin;
- (p) fire fighting equipment, buildings and distribution pipework;
- (q) permanent plant laydown area;
- (r) auxiliary plant, buildings, enclosures and structures;
- (s) mechanical, electrical, gas, telecommunications and water networks, pipework, cables, racks, infrastructure, instrumentation and utilities, including connections between parts of this Work No. 1 and Work Nos 4, 5 and 6;
- (t) workshop buildings and stores;
- (u) electrical, control, administration and welfare buildings; and
- (v) storm water attenuation system.
Work No. 2 – access, comprising access from Rosper Road to each of Work Numbers 1, 3, 4, 5 and 6.
Work No. 3 – temporary construction and laydown comprising hard standing, laydown and open storage areas, contractor compounds and staff welfare facilities, vehicle parking, roadways and haul routes, security fencing and gates, gatehouses, external lighting and lighting columns.
Work No. 4 – gas connection, being works for the transport of natural gas to Work No. 1, comprising—
- (a) an underground and overground gas pipeline up to 600 millimetres (nominal internal diameter);
- (b) cathodic protection system and posts;
- (c) marker posts; and
- (d) control systems and cables.
Work No. 5 – overground electrical connection up to 400 kilovolts and controls systems.
Work No 6 – utilities and services connections comprising—
- (a) water pipes, connections, structures and ancillary equipment;
- (b) telecommunications cables and equipment;
- (c) compressed air connections and ancillary equipment;
- (d) electrical cables, connections and ancillary equipment;
- (e) control systems and cables; and
- (f) closed circuit television and security system connections.
In connection with and in addition to Work Nos. 1 to 6, further development including—
- (a) buildings and structures;
- (b) surface water drainage systems, storm water attenuation systems including storage basins, oil water separators, including channelling and culverting and works to existing drainage systems;
- (c) electrical, gas, water, foul drainage and telecommunications infrastructure, connections and works, and works to install, remove, alter and connect into such services;
- (d) hard standing and hard landscaping, soft landscaping, embankments, planting and biodiversity enhancement measures;
- (e) security fencing, gates, boundary treatment and other means of enclosure;
- (f) lighting, including lighting columns;
- (g) gatehouses and weighbridges;
- (h) closed circuit television cameras, columns and other security works;
- (i) site establishment and preparation works, including site clearance, demolition, earthworks, excavations, vehicular access points, the alteration and protection of services and utilities, and works for the protection of buildings and land;
- (j) temporary construction laydown areas, contractor facilities, materials and plant storage, generators, concrete batching facilities, vehicle and cycle parking, roadways and haul routes, offices and welfare facilities, wheel wash facilities, and signage;
- (k) vehicle parking and cycle storage;
- (l) accesses, roads, pedestrian and cycle routes; and
- (m) tunnelling, boring and drilling works,
and to the extent that it does not form part of such works, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised development and which fall within the scope of the works assessed in the environmental statement.
SCHEDULE 2 — REQUIREMENTS
Interpretation
1
In this Schedule—
- “Environment Agency” means the non-departmental public body of that name created by section 1 (the Environment Agency) of the Environment Act 1995 ;
- “Highways England” means Highways England Company Limited or such other person who is appointed as the strategic highways company in respect of the A160 Humber Road and the A160/A180 interchange pursuant to section 1 (appointment of strategic highways companies) of the Infrastructure Act 2015 ;
- “Historic England” means the Historic Buildings and Monuments Commission for England established by section 32 (establishment of commission) of the National Heritage Act 1983 ;
- “lead local flood authority” means the body designated as such, for the area in which the authorised development is located, pursuant to section 6(7) (other definitions) of the Flood and Water Management Act 2010 ;
- “Lincolnshire Wildlife Trust” means Lincolnshire Wildlife Trust (registered charity number 218895) of Banovallum House, Lincolnshire, LN9 5HF;
- “North East Lindsey Internal Drainage Board” means the internal drainage board for the area in which the authorised development is located pursuant to section 1 (internal drainage districts and boards) of the Land Drainage Act 1991 ;
- “North Lincolnshire Police” means the police force for the area in which the authorised development is located pursuant to section 1 (police areas) of the Police Act 1996 ;
- “part of the authorised development” means any part of Works Nos. 1 to 6; and
- “permitted preliminary works” means operations consisting of environmental surveys and monitoring, investigations for the purpose of assessing ground conditions, archaeological investigations, receipt and erection of construction plant and equipment, erection of any temporary means of enclosure, the temporary display of site notices or advertisements.
Commencement of the authorised development
2
- (1) The authorised development must not be commenced after the expiration of five years from the date this Order comes into force.
- (2) The authorised development must not commence unless the undertaker has given the relevant planning authority fourteen days' notice of its intention to commence the authorised development.
Notice of commencement
3
Notice of the intended start of commissioning of the authorised development must be given to the relevant planning authority where practicable prior to such start and in any event within seven days from the date that commissioning is started.
Notice of date of final commissioning
4
Notice of the intended date of final commissioning of the authorised development must be given to the relevant planning authority where practicable prior to such date of final commissioning and in any event within seven days from the date of final commissioning.
Detailed design
5
- (1) In relation to any part of the authorised development comprised in Work No. 1 no development of that part may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, in respect of sub-paragraph (d) after consultation with the highway authority, approved by the relevant planning authority—
- (a) the siting, layout, scale and external appearance, including the colour, materials and surface finishes of all new permanent buildings and structures;
- (b) finished floor levels;
- (c) hard standings;
- (d) the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian facilities and routes; and
- (e) landscaping
- (2) The details submitted pursuant to sub-paragraph (1) must be in accordance with the parameters set out in Schedule 12 (design parameters) .
- (3) No part of the authorised development comprised in Work No. 2 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority—
- (a) construction access;
- (b) operational access;
- (c) vehicle parking; and
- (d) haul routes.
- (4) No part of the authorised development comprised in Work No. 3 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, in respect of sub-paragraphs (a), (d) and (e) after consultation with the highway authority, approved by the relevant planning authority—
- (a) hard standings, laydown and open storage areas;
- (b) contractor compounds and construction staff welfare facilities;
- (c) gatehouse;
- (d) vehicle parking and cycle storage facilities; and
- (e) the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian facilities and routes.
- (5) No part of the authorised development comprised in Work Nos. 4 and 5, save for the permitted preliminary works, may commence until details of the following for that part have been submitted to and, after consultation with National Grid, approved by the relevant planning authority—
- (a) the route and method of installation of the gas pipeline; and
- (b) the route and method of electrical connection works comprising overground electrical cables, and control systems and cables.
- (6) No part of the authorised development comprised in Work No. 6 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and, after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority—
- (a) the route and method of construction of any utilities and services connections including water pipes, connections, pumps, tanks, structures and ancillary equipment; telecommunications cables and equipment; electrical cables, connections and ancillary equipment; and control systems and cables; and
- (b) water connection works, comprising underground and overground pipes, plant apparatus, enclosures and structures, and supply cables, transformers and control system cables.
- (7) Work Nos. 1, 2, 3, 4, 5 and 6 must be carried out in accordance with the approved details unless otherwise agreed with the relevant planning authority.
Biodiversity enhancement and management plan
6
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a biodiversity protection plan for that part has been submitted to and, after consultation with Natural England, approved by the relevant planning authority.
- (2) The plan submitted and approved pursuant to sub-paragraph (1) must include details of—
- (a) measures to protect existing shrub and tree planting that is to be retained; and
- (b) biodiversity and habitat impact avoidance.
- (3) The plan submitted and approved pursuant to sub-paragraph (1) must be implemented as approved throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
- (4) Prior to the date of final commissioning a biodiversity enhancement and management plan must be submitted to and approved by the relevant planning authority.
- (5) The plan submitted and approved pursuant to sub-paragraph (4) must include details of—
- (a) measures to protect existing shrub and tree planting that is to be retained;
- (b) measures to enhance biodiversity and habitats;
- (c) an implementation timetable; and
- (d) biodiversity management and maintenance.
- (6) Any shrub or tree planted as part of the approved plan that, within a period of five years after planting, is removed, dies or becomes, in the opinion of the relevant planning authority, seriously damaged or diseased, must be replaced in the first available planting season with a specimen of the same species and size as that originally planted unless otherwise agreed with the relevant planning authority.
- (7) The plan submitted and approved pursuant to sub-paragraph (4) must be in accordance with the principles of the framework biodiversity enhancement and management plan.
- (8) The plan must be implemented as approved during the operation of the authorised development unless otherwise agreed with the relevant planning authority.
External lighting
7
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for all external lighting to be installed during construction for that part has been submitted to and approved by the relevant planning authority.
- (2) No part of the authorised development may be commissioned until a scheme for all permanent external lighting to be installed has been submitted to and approved by the relevant planning authority.
- (3) The schemes submitted and approved pursuant to sub-paragraphs (1) and (2) of this requirement must be in accordance with the indicative lighting strategy and include measures to minimise and otherwise mitigate any artificial light emissions during the construction and operation of the authorised development.
- (4) The schemes must be implemented as approved unless otherwise agreed with the relevant planning authority.
Highway accesses
8
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until details of the siting, design and layout (including visibility splays and construction specification) of any new or modified means of access between any part of the Order limits and the public highway to be used by vehicular traffic during construction, and the means of reinstating any such means of access after construction has, for that part, been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
- (2) The highway accesses approved pursuant to sub-paragraph (1) must be constructed in accordance with the approved details prior to the start of construction of the relevant part of the authorised development (other than the accesses), and where temporary, reinstated prior to the date of final commissioning, unless otherwise agreed with the relevant planning authority.
- (3) Prior to the date of final commissioning details of the siting, design and layout (including visibility splays and construction specification) of any new or modified permanent means of access to a highway to be used by vehicular traffic, must be submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
- (4) The highway accesses approved pursuant to sub-paragraph (3) must be constructed in accordance with the details approved unless otherwise agreed with the relevant planning authority.
Means of enclosure
9
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a programme for the removal of all temporary means of enclosure for any construction areas or sites associated with the authorised development has, for that part, been submitted to and approved by the relevant planning authority.
- (2) Any construction areas or sites associated with the authorised development must remain securely fenced at all times during construction and commissioning of the authorised development.
- (3) Any temporary fencing must be removed by the end of three months beginning with the date of completion of construction of the authorised development (or such other period as the relevant planning authority may approve).
- (4) Prior to the date of final commissioning details of any proposed permanent means of enclosure must be submitted to and approved by the relevant planning authority.
- (5) Any permanent means of enclosure approved pursuant to sub-paragraph (4) must be completed prior to the date of final commissioning.
- (6) The authorised development must be carried out in accordance with the approved details unless otherwise agreed with the relevant planning authority.
- (7) In this requirement, “means of enclosure” means fencing, walls or other means of boundary treatment and enclosure.
Surface water drainage
10
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until details of the temporary surface water drainage systems, including means of pollution control in accordance with the construction environmental management plan submitted pursuant to requirement 14 and a management and maintenance plan to ensure that the systems remain fully operational throughout the construction of the relevant part of the authorised development have, for that part, been submitted to, and after consultation with the lead local flood authority and North East Lindsey Internal Drainage Board, approved by the relevant planning authority.
- (2) The scheme approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
- (3) Details of the permanent surface water drainage systems, including a programme for their implementation, must be submitted to, and after consultation with the Environment Agency, the lead local flood authority, Anglian Water and North East Lindsey Internal Drainage Board, approved by the relevant planning authority prior to the start of construction of any part of those systems.
- (4) The details submitted and approved pursuant to sub-paragraphs (1) and (3) of this requirement must be in accordance with the principles set out in chapter 12 (surface water, flood risk and drainage) of the environmental statement and the flood risk assessment.
- (5) The scheme approved pursuant to sub-paragraph (3) must be implemented as approved and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.
Flood risk mitigation
11
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for the mitigation of flood risk during construction, has, for that part, been submitted to and approved by the relevant planning authority.
- (2) The scheme approved pursuant to sub-paragraph (1) must be implemented as approved and maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
- (3) No part of the authorised development may commence save for the permitted preliminary works until a scheme for the mitigation of flood risk during operation has, for that part, been submitted to and, after consultation with the Environment Agency and North East Lindsey Internal Drainage Board, approved by the relevant planning authority.
- (4) The schemes submitted and approved pursuant to sub-paragraphs (1) and (3) of this requirement must be in accordance with the principles set out in chapter 12 (surface water, flood risk and drainage) of the environmental statement and the flood risk assessment.
- (5) The scheme approved pursuant to sub-paragraph (3) must be implemented as approved and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.
- (6) The authorised development must not be commissioned until the flood risk mitigation has been implemented and a flood emergency response and contingency plan has been submitted to, and after consultation with North East Lindsey Internal Drainage Board, approved by the relevant planning authority.
- (7) The plan approved pursuant to sub-paragraph (6) must be implemented throughout the commissioning and operation of the authorised development unless otherwise agreed with the relevant planning authority.
Contaminated land and groundwater
12
- (1) No part of the authorised development may commence, save for geotechnical surveys and other investigations for the purpose of assessing ground conditions, until a scheme to deal with the contamination of land, including groundwater, which is likely to cause significant harm to persons or pollution of controlled waters or the environment, has, for that part, been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.
- (2) The scheme submitted and approved must be in accordance with the principles set out in chapter 11 (ground conditions and hydrogeology) of the Environmental Statement and with the construction environmental management plan submitted pursuant to requirement 14.
- (3) The scheme must include a risk assessment, supported by site investigation data, to identify the extent of any contamination and the remedial measures to be taken to render the land fit for its intended purpose, together with a materials management plan, which sets out long-term measures with respect to any contaminants remaining on the site.
- (4) The authorised development, including any remediation, must be carried out in accordance with the approved scheme unless otherwise agreed with the relevant planning authority.
- (5) Should any remediation be required a verification report demonstrating the completion of works set out in the approved scheme and the effectiveness of the remediation must be submitted to, and approved, by the relevant planning authority prior to the date of final commissioning. The report must include results of sampling and monitoring carried out in accordance with the approved scheme to demonstrate that the site remediation criteria have been met.
Archaeology
13
- (1) No part of the authorised development may commence until a written scheme of investigation for that part has been submitted to and, after consultation with Historic England, approved by the relevant planning authority.
- (2) The scheme submitted and approved must be in accordance with chapter 13 (cultural heritage) of the environmental statement and the framework written scheme of investigation.
- (3) The scheme must identify whether any further archaeological investigations are required and, if investigations are deemed to be required, the nature and extent of the investigations in order to preserve by knowledge or in-situ any archaeological features that are identified.
- (4) The scheme must provide details of the measures to be taken to protect, record or preserve any significant archaeological features that may be found.
- (5) Any archaeological investigations implemented and measures taken to protect, record or preserve any identified significant archaeological features that may be found must be carried out—
- (a) in accordance with the approved scheme; and
- (b) by a suitably qualified person or organisation approved by the relevant planning authority unless otherwise agreed with the relevant planning authority.
Construction environmental management plan
14
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction environmental management plan has been submitted to and, after consultation with Natural England, approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with the framework construction environmental management plan and incorporate—
- (a) a code of construction practice, specifying measures designed to minimise the impacts of construction works;
- (b) a scheme for the control of emissions of dust;
- (c) a soil management plan;
- (d) a sediment control plan;
- (e) a scheme for environmental monitoring and reporting during the construction of the authorised development, including measures for undertaking any corrective actions;
- (f) a scheme for the notification of any significant construction impacts on local residents and for handling any complaints received from local residents relating to such impacts during the construction of the authorised development; and
- (g) a requirement that the detail of the fencing and protection of asset A6 is in accordance with the strategy set out in the framework written scheme of investigation.
- (3) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan unless otherwise agreed with the relevant planning authority.
- (4) The plan submitted must include information on the proposed piling methods, their approximate duration and timing, the likely sound power levels, and any necessary management measures or mitigation to ensure, taking into account the information in the statement to inform appropriate assessment, that there will be no adverse impact on any qualifying species of the Humber Estuary Special Protection Area and Ramsar Site.
Protection of highway surfaces
15
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until details for undertaking condition surveys of the relevant parts of Rosper Road which are maintainable at the public expense and which are to be used during construction have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
- (2) The condition surveys must be undertaken in accordance with the approved details and a schedule of repairs required due to use by construction traffic for the authorised development, including a programme for undertaking any such repairs and their inspection, must, following the completion of the post-construction condition surveys, be submitted to, and after consultation with the highway authority, approved by the relevant planning authority.
- (3) The schedule of repairs must be carried out as approved unless otherwise agreed with the relevant planning authority.
Construction traffic management plan
16
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction traffic management plan has been submitted to and, after consultation with North East Lincolnshire Council, Highways England and the highway authority, approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with chapter 7 (traffic and transport) of the environmental statement and the framework construction traffic management plan.
- (3) The plan submitted and approved must include—
- (a) details of the routes to be used for the delivery of construction materials and any temporary signage to identify routes and promote their safe use, including details of the access points to the construction site to be used by light goods vehicles and heavy goods vehicles;
- (b) details of the routing strategy and procedures for the notification and conveyance of abnormal invisible loads, including agreed routes, the numbers of abnormal loads to be delivered by road and measures to mitigate traffic impact; ...
- (c) any necessary measures for the temporary protection of carriageway surfaces, the protection of statutory undertakers' plant and equipment, and any temporary removal of street furniture; and
- (d) the construction programme.
- (4) Notices must be erected and maintained throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site.
- (5) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.
Construction workers travel plan
17
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan has been submitted to and, after consultation with North East Lincolnshire Council, Highways England and the highway authority, approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with chapter 7 (traffic and transport) of the environmental statement and the framework construction worker travel plan.
- (3) The plan submitted and approved must include—
- (a) measures to promote the use of sustainable transport to and from the authorised development by construction staff;
- (b) provision as to the responsibility for, and timescales of, the implementation of those measures;
- (c) details of parking for construction personnel within the construction sites; and
- (d) a monitoring and review regime.
- (4) The approved plan must be implemented prior to commencement of the authorised development, save for the permitted preliminary works, and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
Construction hours
18
- (1) Construction work relating to the authorised development must not take place on bank holidays or otherwise outside the hours of—
- (a) 0700 to 1900 hours on Monday to Friday; and
- (b) 0800 to 1800 hours on a Saturday.
- (2) Delivery or removal of materials, plant and machinery must not take place on bank holidays nor outside the hours of 0700 to 1900 hours on Monday to Saturday.
- (3) The restrictions in sub-paragraphs (1) and (2) do not apply to construction work or the delivery or removal of materials, plant and machinery, where these—
- (a) do not exceed a noise limit measured at the Order limits which has been agreed with the relevant planning authority;
- (b) are carried out with the prior approval of the relevant planning authority; or
- (c) are associated with an emergency.
- (4) The restrictions in sub-paragraph (2) do not apply to the delivery of abnormal indivisible loads, which are—
- (a) associated with an emergency; or
- (b) carried out with the prior approval of the relevant planning authority.
- (5) Sub-paragraph (1) does not preclude—
- (a) a start-up period from 0630 to 0700 and a shut-down period from 1900 to 1930 Monday to Friday and a start-up period from 0730 to 0800 and a shut-down period from 1800 to 1830 on a Saturday; or
- (b) maintenance at any time of plant and machinery engaged in the construction of the authorised development.
- (6) In this requirement—
- “shut down period” means the period during which construction workers may return to the site office to return safety and other equipment, attend debrief sessions, change clothing and prepare to leave site; and
- “start-up period” means the period during which construction workers may arrive at site, sign in, don personal protective equipment, attend safety and other briefings and mobilise on site.
Control of noise - operation
19
- (1) Prior to the date of final commissioning a scheme for the management and monitoring of noise during operation of the authorised development must be submitted to and approved by the relevant planning authority.
- (2) The scheme submitted pursuant to sub-paragraph (1) must include the results of daytime and night time baseline noise monitoring that has been carried out by the undertaker for the purposes of this requirement as agreed with the relevant planning authority.
- (3) Noise (in terms of the BS4142:2014 rating level) from the operation of the authorised development must be no greater than 3dB higher than the defined representative background sound level during each of the daytime and the night time, adjacent to the nearest residential properties at locations agreed with the relevant planning authority.
- (4) The scheme must be implemented as approved unless otherwise agreed with the relevant planning authority.
- (5) In this requirement—
- (a) “daytime” means the period from 0700 to 2300 and “night time” means the period from 2300 to 0700; and
- (b) “defined representative background sound level” means the sound level measured during the monitoring secured by sub-paragraph (2).
Piling and penetrative foundation design
20
- (1) No part of the authorised development comprised within Work No. 1 may commence, save for the permitted preliminary works, until a written piling and penetrative foundation design method statement, informed by a risk assessment, for that part, has been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.
- (2) All piling and penetrative foundation works must be carried out in accordance with the approved method statement unless otherwise agreed with the relevant planning authority.
Waste management on site - construction wastes
21
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction site waste management plan for that part has been submitted to and approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with the principles set out in the framework construction environmental management plan.
- (3) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.
Restoration of land used temporarily for construction
22
- (1) Prior to the date of final commissioning a scheme for the restoration of any land within the Order limits which has been used temporarily for construction must be submitted to and approved by the relevant planning authority.
- (2) The land must be restored within three years of the date of final commissioning (or such other period as the relevant planning authority may approve), in accordance with the restoration scheme approved in accordance with sub-paragraph (1).
Employment, skills and training plan
23
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a plan detailing arrangements to promote employment, skills and training development opportunities for local residents during construction and employment opportunities during operation of the authorised development has been submitted to and, after consultation with North East Lincolnshire Council, approved by the relevant planning authority.
- (2) The approved plan must be implemented and maintained during the construction and operation of the authorised development unless otherwise agreed with the relevant planning authority.
Decommissioning
24
- (1) Within 12 months of the date that the undertaker decides to decommission the authorised development, the undertaker must submit to the relevant planning authority for their approval a decommissioning environmental management plan.
- (2) No decommissioning works may be carried out until the relevant planning authority has approved the plan.
- (3) The plan submitted and approved must include details of—
- (a) the buildings to be demolished;
- (b) the means of removal of the materials resulting from the decommissioning works;
- (c) the phasing of the demolition and removal works;
- (d) any restoration works to restore the land to a condition agreed with the relevant planning authority;
- (e) the phasing of any restoration works; and
- (f) a timetable for the implementation of the scheme.
- (4) The plan must be implemented as approved unless otherwise agreed with the relevant planning authority.
Foul water drainage
25
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until full details of a scheme, for the connection, conveyance, treatment and disposal of mains foul water drainage on and off site has been submitted to, and after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority.
- (2) If it is demonstrated as part of the information submitted pursuant to sub-paragraph (1) that it is not practicable or reasonable to connect to a mains system, an alternative strategy for the provision and implementation of wastewater treatment must be submitted to and, after consultation with the Environment Agency and Anglian Water, approved by the relevant planning authority. Any non-mains drainage proposal must include a management and maintenance plan to ensure that it will not cause pollution to the water environment.
- (3) The schemes approved pursuant to sub-paragraph (1) and (where relevant) sub-paragraph (2) must be implemented and maintained throughout the operation of the authorised development unless otherwise agreed with the relevant planning authority.
Requirement for written approval
26
Where under any of the above requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.
Approved details and amendments to them
27
- (1) All details submitted for approval of the relevant planning authority under these requirements must be in accordance with the parameters of the environmental statement and reflect the principles set out in the documents certified under article 39 (certification of plans etc.).
- (2) With respect to any requirement which requires the authorised development to be carried out in accordance with the details approved by the relevant planning authority, the approved details are to be taken to include any amendments that may subsequently be approved by the relevant planning authority.
Amendments agreed by the relevant planning authority
28
- (1) Where the words “unless otherwise agreed with the relevant planning authority” appear in the above requirements, any such approval or agreement may only be given in relation to non-material amendments and where it has been demonstrated to the satisfaction of the relevant planning authority that the subject matter of the approval or agreement sought will not give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
- (2) In cases where the requirement or the relevant sub-paragraph requires consultation with specified persons, any approval or agreement must not be given without the relevant planning authority having first consulted with those persons.
SCHEDULE 3 — STREETS SUBJECT TO STREET WORKS
| (1) Area | (2) Street subject to street works | (3) Description of the street works |
|---|---|---|
| In the District of North Lincolnshire | Rosper Road | Works to repair and resurface the access and to maintain visibility splays in the areas cross hatched in red and blue at the point marked C on sheet 1 of the access and rights of way plans |
| In the District of North Lincolnshire | Rosper Road | Works to repair and resurface the access and to maintain visibility splays in the area cross hatched in red at the point marked A on sheet 1 of the access and rights of way plans |
| In the District of North Lincolnshire | Rosper Road | Works for the installation and maintenance of Work No. 6 in the area cross hatched in blue at the point marked B on sheet 1 of the access and rights of way plans |
SCHEDULE 4 — ACCESS
PART 1 — THOSE PARTS OF THE ACCESSES TO BE MAINTAINED BY THE HIGHWAY AUTHORITY
| (1) Area | (2) Street | (3) Description of relevant part of access |
|---|---|---|
| In the District of North Lincolnshire | Rosper Road | That part of the access in the area cross hatched in blue at the point marked C on sheet 1 of the access and rights of way plans |
PART 2 — THOSE PARTS OF THE ACCESSES TO BE MAINTAINED BY THE STREET AUTHORITY
| (1) Area | (2) Street | (3) Description of relevant part of access |
|---|---|---|
| In the District of North Lincolnshire | Rosper Road | That part of the access cross hatched in red at the point marked A on sheet 1 of the access and rights of way plans |
| In the District of North Lincolnshire | Rosper Road | That part of the access cross hatched in red at the point marked C on sheet 1 of the access and rights of way plans |
SCHEDULE 5 — TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OF STREETS
| (1) Area | (2) Streets subject to temporary prohibition or restriction of use | (3) Extent of temporary prohibition or restriction of use of street |
|---|---|---|
| In the District of North Lincolnshire | Rosper Road | Temporary closure of the part of the street cross hatched in blue at the point marked B on sheet 1 of the access and rights of way plans |
SCHEDULE 6 — LAND IN WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED
| (1)Class of compulsory acquisition and the creation of rights and the imposition of restrictions for the installation and use of the authorised development | (2)Means of all rights and restrictions necessary for the undertaker and/or those authorised by the undertaker |
|---|---|
| (a) | To pass and repass on foot, with or without vehicles, plant and machinery |
| (b) | To construct, maintain, improve and protect access routes |
| (c) | To install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve an underground and overground gas pipeline up to 600 millimetres (nominal internal diameter), control systems and cables and any other ancillary apparatus and any other works as necessary |
| (d) | To install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve an overground electrical connection of up to 400 kilovolt, control systems and any other ancillary apparatus and any other works as necessary |
| (e) | To install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve water pipes, connections, structures and ancillary equipment; telecommunications cables and equipment; compressed air connections and ancillary equipment; electrical cables, connections and ancillary equipment; control systems and cables; closed circuit television and security system connections; and any other ancillary apparatus and any other works as necessary |
| (f) | To retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve an underground gas pipeline, control systems and cables and any other ancillary apparatus and any other works as necessary |
| (g) | To install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve water pipes, connections, structures and ancillary equipment and any other ancillary apparatus and any other works as necessary |
| (h) | To install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve security fencing, gates, boundary treatment and any other ancillary apparatus and any other works as necessary |
| (i) | To install, retain, use, maintain, inspect, alter, remove, refurbish, reconstruct, replace, protect and improve gatehouses and weighbridges and any other ancillary apparatus and any other works as necessary |
| (j) | Restrictions on erecting buildings or structures, altering ground levels, planting trees or carrying out operations or actions which may obstruct, interrupt or interfere with the exercise of rights |
| (1)Plot | (2)Class of rights listed in Table 5 applicable to the plot |
| --- | --- |
| 2 | (a), (b), (h), (i) and (j) |
| 6 | (a) and (g) |
| 7 | (a) and (g) |
| 8 | (a), (b), (h), (i) and (j) |
| 9 | (a), (b), (h), (i) and (j) |
| 10 | (a), (b), (h), (i) and (j) |
| 12 | (a), (e) and (j) |
| 14 | (a), (e), (b), (h), (i) and (j) |
| 15 | (a), (b), (h), (i) and (j) |
| 16 | (a), (c) and (j) |
| 17 | (a), (d), (e), (c) and (j) |
| 17a | (a), (d), (e), (c) and (j) |
| 18 | (a), (e) and (j) |
| 20 | (a), (b), (c), (h), (i) and (j) |
| 21 | (a), (b), (h), (i) and (j) |
| 22 | (a), (b), (e), (h), (i) and (j) |
| 23 | (a), (b), (c), (d), (e), (h), (i) and (j) |
| 23a | (a), (b), (c), (d), (e), (h), (i) and (j) |
| 24 | (a), (d) and (j) |
| 24a | (a), (d) and (j) |
| 25 | (a), (b), (h), (i) and (j) |
| 26 | (a), (b), (h), (i) and (j) |
| 27 | (a), (e) and (j) |
| 28 | (a), (b), (c), (e), (h), (i) and (j) |
| 29 | (a), (b), (c), (e), (h), (i) and (j) |
| 30 | (a), (b), (d), (h), (i) and (j) |
| 30a | (a), (b), (d), (h), (i) and (j) |
| 31 | (a), (b), (h), (i) and (j) |
| 32 | (a), (e), (b), (h), (i) and (j) |
| 34 | (a), (b), (h), (i) and (j) |
| 35 | (a), (b), (c) (h), (i) and (j) |
| 33, 37-111 | (a) and (f) |
SCHEDULE 7 — MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS
Compensation enactments
1
The enactments for the time being in force with respect to compensation for the compulsory purchase of land apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right as they apply as respects compensation on the compulsory purchase of land and interests in land.
2
- (1) Without limitation to the scope of paragraph 1, the Land Compensation Act 1973 has effect subject to the modifications set out in sub-paragraph (2).
- (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 (measure of compensation in case of severance) of the 1965 Act as substituted by paragraph 5(3)—
- (a) for “land is acquired or taken from” substitute “ a right or restrictive covenant over land is purchased from or imposed on ”; and
- (b) for “acquired or taken from him” substitute “ over which the right is exercisable or the restrictive covenant enforceable ”.
3
- (1) Without limitation on the scope of paragraph 1, the 1961 Act has effect subject to the modification set out in sub-paragraph (2).
- (2) In section 5A(5A) (relevant valuation date) of the 1961 Act, for (a) and (b) substitute—
(a) the acquiring authority enters on land for the purpose of exercising a right in pursuance of a notice of entry under section 11(1) of the 1965 Act (as modified by paragraph 5(5) of Schedule 7 to the Immingham Open Cycle Gas Turbine Order 2020; ... (b) the acquiring authority is subsequently required by a determination under paragraph 12 of Schedule 2A to the 1965 Act (as substituted by paragraph 5(8) of Schedule 7 to the Immingham Open Cycle Gas Turbine Order 2020 to acquire an interest in the land, and (c) the acquiring authority enters on and takes possession of that land, the authority is deemed for the purposes of subsection (3)(a) to have entered on that land where it entered on that land for the purpose of exercising that right.
Application of Part 1 of the 1965 Act
4
Part 1 (compulsory purchase under Acquisition of Land Act 1946) of the 1965 Act, as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and modified by article 25 (modification of Part 1 of the Compulsory Purchase Act 1965)) to the acquisition of land under article 18 (compulsory acquisition of land), applies to the compulsory acquisition of a right by the creation of a new right, or to the imposition of a restrictive covenant under article 21 (compulsory acquisition of rights etc.)—
- (a) with the modification specified in paragraph 5; and
- (b) with such other modifications as may be necessary.
5
- (1) The modifications referred to in paragraph 4(a) are as follows.
- (2) References in the 1965 Act to land are, in the appropriate contexts, to be read (according to the requirements of the particular context) as referring to, or as including references to—
- (a) the right acquired or to be acquired, or the restrictive covenant imposed or to be imposed; or
- (b) the land over which the right is or is to be exercisable, or the restrictive covenant is or is to be enforceable.
- (3) For section 7 of the 1965 Act there is substituted the following section—
(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.
- (4) The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
- (a) section 9(4) (failure by owners to convey);
- (b) paragraph 10(3) of Schedule 1 (persons without powers to sell their interests);
- (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
- (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),
are so modified as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.
- (5) Section 11 (powers of entry) of the 1965 Act is modified as to secure that, where the acquiring authority has served notice to treat in respect of any right or restrictive covenant, as well as the notice of entry required by subsection (1) of that section (as it applies to compulsory acquisition under article 18, it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant; and sections 11A (powers of entry: further notices of entry), 11B (counter-notice requiring possession to be taken on a specified date), 12 (unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are modified correspondingly.
- (6) Section 20 (tenants at will etc.) of the 1965 Act applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.
- (7) Section 22 (interests omitted from purchase) of the 1965 Act as modified by article 25(3) (modification of Part 1 of the Compulsory Purchase Act 1965) is also modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired or enforce the restrictive covenant imposed, subject to compliance with that section as respects compensation.
- (8) For Schedule 2A to the 1965 Act substitute—
SCHEDULE 2A (1) (1) This Schedule applies where an acquiring authority serve a notice to treat in respect of a right over, or restrictive covenant affecting, the whole or part of a house, building or factory and have not executed a general vesting declaration under section 4 of the 1981 Act (execution of declaration) as applied by article 23 of the Immingham Open Cycle Gas Turbine Order 2020 (application of the Compulsory Purchase (Vesting Declarations) Act 1981) in respect of the land to which the notice to treat relates. (2) But see article 24(3) of the Immingham Open Cycle Gas Turbine Order 2020 (acquisition of subsoil only) which excludes the acquisition of subsoil only from this Schedule. (2) In this Schedule, “house” includes any park or garden belonging to a house. (3) A person who is able to sell the house, building or factory (“the owner”) may serve a counter-notice requiring the authority to purchase the owner's interest in the house, building or factory. (4) A counter-notice under paragraph 3 must be served within the period of 28 days beginning with the day on which the notice to treat was served. (5) On receiving a counter-notice, the acquiring authority must decide whether to— (a) withdraw the notice to treat, (b) accept the counter-notice, or (c) refer the counter-notice to the Upper Tribunal. (6) The authority must serve notice of their decision on the owner within the period of three months beginning with the day on which the counter-notice is served (“the decision period”). (7) If the authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period. (8) If the authority do not serve notice of a decision within the decision period they are to be treated as if they had served notice of a decision to withdraw the notice to treat at the end of that period. (9) If the authority serve notice of a decision to accept the counter-notice, the compulsory purchase order and the notice to treat are to have effect as if they included the owner's interest in the house, building or factory. (10) On a referral under paragraph 7, the Upper Tribunal must determine whether the acquisition of the right or the imposition of the restrictive covenant would— (a) in the case of a house, building or factory, cause material detriment to the house, building or factory, or (b) in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs. (11) In making its determination, the Upper Tribunal must take into account— (a) the effect of the acquisition of the right or the imposition of the covenant, (b) the use to be made of the right or covenant proposed to be acquired or imposed, and (c) if the right or covenant is proposed to be acquired or imposed for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land. (12) If the Upper Tribunal determines that the acquisition of the right or the imposition of the covenant would have either of the consequences described in paragraph 10, it must determine how much of the house, building or factory the authority ought to be required to take. (13) If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the compulsory purchase order and the notice to treat are to have effect as if they included the owner's interest in that land. (14) (1) If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the authority may at any time within the period of six weeks beginning with the day on which the Upper Tribunal makes its determination withdraw the notice to treat in relation to that land. (2) If the acquiring authority withdraws the notice to treat under this paragraph they must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawal of the notice. (3) Any dispute as to the compensation is to be determined by the Upper Tribunal.
SCHEDULE 8 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.