The High Speed Rail (West Midlands – Crewe) (Nomination) Regulations 2021
Made: 11th February 2021
Coming into force: 12th February 2021
The Secretary of State makes the following Regulations in exercise of the powers conferred by section 41(1) of the High Speed Rail (West Midlands – Crewe) Act 2021[^f00001]:
Citation and commencement
1
These Regulations may be cited as the High Speed Rail (West Midlands – Crewe) (Nomination) Regulations 2021 and come into force on 12th February 2021.
Appointment of nominated undertaker
2
High Speed Two (HS2) Ltd is the nominated undertaker for—
- (a) all purposes of the scheduled works; and
- (b) the purposes of any other provision of the High Speed Rail (West Midlands – Crewe) Act 2021 so far as connected with or in any way related to those works or otherwise for Phase 2a purposes.
Signed
Signed by authority of the Secretary of State for Transport
Andrew Stephenson — Minister of State — Department for Transport — 11th February 2021
Explanatory note
(This note is not part of the Regulations)
EXPLANATORY NOTE
Regulation 2 of these Regulations appoints High Speed Two (HS2) Ltd as the nominated undertaker for all purposes of the scheduled works of the High Speed Rail (West Midlands – Crewe) Act 2021 and for any other purposes under that Act in so far as those purposes are connected to those works or otherwise for Phase 2a purposes.
Footnotes
[^f00001]: 2021 c. 2.
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.