Made: 30th March 2021

Coming into force: 31st March 2021

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and (8) of Schedule 4 to, the Act, makes the following Order:

Citation and commencement

1

This Order may be cited as the A303 (Amesbury to Berwick Down) Development Consent (Correction) Order 2021 and comes into force on 31st March 2021.

Corrections

2

The A303 (Amesbury to Berwick Down) Development Consent Order 2020 is corrected as set out in the table in the Schedule to this Order, in which—

SCHEDULE — Corrections

(1) (2) (3)
Where the correction is to be made How the correction is to be made Text to be substituted, inserted or omitted
Article 4(1) After “Subject to the provisions of this Order, including the requirements in Schedule 2 (requirements), the undertaker is granted development consent for the authorised development” omit “to be carried out within the Order limits”
Article 50(4) For “or are proposed to be exercised for the express benefit of accommodation of owners” substitute “or are proposed to be exercised for the express benefit or accommodation of owners”
In Schedule 12 (documents to be certified) In Schedule 12 (documents to be certified) In Schedule 12 (documents to be certified)
Column (2) For “The detailed archaeological mitigation strategy contained in document reference 8.11 (6) – Final Detailed Archaeological Mitigation Strategy (DAMS)” substitute “The detailed archaeological mitigation strategy contained in document reference 8.11 (7) Detailed Archaeological Mitigation Strategy (DAMS) – Revised response to Department for Transport request for further information dated 4th May 2020”
Column (2) For “The outline environmental management plan contained in document reference 6.3 (7) Environmental Statement Appendix 2.2 Outline Environmental Management Plan (OEMP)” substitute “The outline environmental management plan contained in document reference 6.3 (8) Final Outline Environmental Management Plan – Revised response to Department for Transport request for further information, May 2020”

Signed

Signed by authority of the Secretary of State

Natasha Kopala — Head of the Transport and Works Act Orders Unit — Department for Transport — 30th March 2021

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

This Order corrects errors in the A303 (Amesbury to Berwick Down) Development Consent Order 2020 (S.I. 2020 No. 1297), a development consent order made under the Planning Act 2008 (c. 29), following a request under paragraph 1(5)(a) of Schedule 4 to that Act.

Footnotes

[^f00001]: S.I. 2020/1297.

[^f00002]: 2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraphs 1 and 70 of Schedule 13 and Part 20 of Schedule 25 to the Localism Act 2011 (c. 20). There are other amendments to paragraph 1 of Schedule 4 that are not relevant to this Order.

[^f00003]: The term “applicant” is defined in paragraph 4 of Schedule 4 to the Act.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.