The Energy Bill Relief Scheme and Energy Price Guarantee Pass-through Requirement and Miscellaneous Amendments Regulations 2022

Type Statutory-Instrument
Publication 2022-11-03
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: at 12.17 p.m. on 3rd November 2022

Laid before Parliament: at 2.00 p.m. on 4th November 2022

Coming into force: 5th November 2022

The Secretary of State makes the following Regulations in exercise of the powers conferred by sections 9(1) to (4), 11(1) to (4), 19 and 26(2)(a) and (b) of, and paragraphs 2 and 4 of Schedule 1 and paragraphs 2 and 4 of Schedule 2 to, the Energy Prices Act 2022[^f00001].

PART 1 — Introductory

Citation, commencement and extent

1

Interpretation

2

In these Regulations—

PART 2 — Pass-through requirement – Northern Ireland

Pass-through requirement

3

Calculation of pass-through amount

4

a pass-through amount is just and reasonable for the purposes of regulation 3(2), if the relevant intermediary applies the same approach, as the case may be, to calculate the pass-through amount for each end user on this basis.

Provision of information to end users

5

Effecting the pass-through

6

or a combination of the methods set out in this paragraph, as appropriate.

Enforcement

7

PART 3 — Amendments to NI EBRS Regulations

Amendments to the NI EBRS Regulations

8

The NI EBRS Regulations are amended as follows—

PART 4 — Amendments to the 2022 Regulations – England and Wales and Scotland

Amendment to the Energy Bill Relief Scheme Regulations 2022

9

In regulation 44(2)(b) of the Energy Bill Relief Scheme Regulations 2022[^f00016] after “electricity” insert “or gas”.

Amendments to the Energy Bills Support Scheme and Energy Price Guarantee Pass-through Requirement (England and Wales and Scotland) Regulations 2022

10

Signed

Graham Stuart — Minister of State for Climate — Department for Business, Energy and Industrial Strategy — At 12.17 p.m. on 3rd November 2022

Explanatory note

(This note is not part of the Regulations)

EXPLANATORY NOTE

These Regulations make provision for pass-through requirements in relation to the Energy Bill Relief Scheme in Northern Ireland (NI EBRS) and the Energy Price Guarantee in Northern Ireland (NI EPG). Pass-through requirements are imposed on a “relevant intermediary” (as defined in regulation 2) and establish that they must pass-through the benefits of NI EBRS or NI EPG (as appropriate) to an “end user” to whom energy has been made available (defined in section 19(3) of the Energy Prices Act 2022 (c. 44) but excluding any person to whom a relevant intermediary supplies or makes available energy outside Northern Ireland). These Regulations apply in respect of relevant intermediaries, other than a) those constituting an “intermediary” as defined in regulation 2(1) of the Energy Bill Relief Scheme Pass-through Requirement (Heat Suppliers) (Northern Ireland) Regulations 2022 (S.I. 2022/1124) and b) those providing certain types of hospitality accommodation (defined as an “excluded intermediary” under these Regulations).

Regulation 3 establishes the requirement for relevant intermediaries to pass-through a just and reasonable amount of the benefit provided to them to each of their end users.

Regulation 4 provides for the calculation of the pass-through amount and sets out the way in which relevant intermediaries are to determine what is a just and reasonable amount for the purposes of regulation 3.

Regulation 5 sets out the information which relevant intermediaries are required to provide to each of their end users about the scheme benefit provided to them, the amount or proportion they intend to provide to the end user together with supporting details about how they have calculated that this is a just and reasonable amount.

Regulation 6 makes provision about the way in which the pass-through is to be given effect including that it must be provided to the end user as soon as reasonably practicable after the scheme benefit has been provided to the relevant intermediary.

Regulation 7 provides for unpaid pass-through amounts to be recoverable from the relevant intermediary by the end user as a civil debt.

Regulation 8 makes amendments to the Energy Bill Relief Scheme (Northern Ireland) Regulations 2022 (S.I. 2022/1106).

Regulation 9 makes an amendment to regulation 44(2)(b) of the Energy Bill Relief Scheme Regulations 2022 (S.I. 2022/1100).

Regulation 10 makes minor amendments to regulation 2, regulation 3 and regulation 6 of the Energy Bills Support Scheme and Energy Price Guarantee Pass-through Requirement (England and Wales and Scotland) Regulations 2022 (S.I. 2022/1102).

Impact assessments of the effect the NI EBRS, NI EPG schemes and the Energy Bill Relief Scheme Regulations 2022, including the related pass-through requirements, will have on the costs of business and the voluntary sector are available from the Department for Business, Energy and Industrial Strategy, 1 Victoria Street, London, SW1H 0ET.

Footnotes

[^f00001]: 2022 c. 44.

[^f00002]: Defined in section 28 of the Energy Prices Act 2022 (“the Act”).

[^f00003]: 2000 c. 17. Schedule 6 has been extensively amended, but the amendments are not relevant for the purposes of identifying the levy, and paragraphs 1 to 3 of the Schedule, which contain the core definition of the levy, have not been amended.

[^f00004]: 1992, No. 231 (N.I. 1), Schedule 6, paragraph 3. Schedule 6 was substituted by the Electricity Regulations (Northern Ireland) 2007 (S.R. 2007/321), regulations 1(2) and 5(2), and Schedule 1, but the core definition regarding “deemed contracts” remains unchanged.

[^f00005]: 2011 c. 6 (N.I.), Part 1, Section 12.

[^f00006]: Defined in Schedule 2, paragraph 1 to the Act.

[^f00007]: 2011 c. 12 (N.I.).

[^f00008]: S.I. 2022/1106.

[^f00009]: A hard copy of the scheme documents can be obtained from the Department for Business, Energy and Industrial Strategy, 1 Victoria Street, London, SW1H 0ET

[^f00010]: S.I. 2022/1105, regulation 3.

[^f00011]: S.I. 2022/1124.

[^f00012]: Published by the Office of the National Statistics. For information on how to obtain a hard copy, contact the Office for National Statistics, Classifications and Harmonisation Unit, Government Buildings, Cardiff Road, Newport, South Wales, NP108 XG. For an electronic copy, see https://www.ons.gov.uk/methodology/classificationsandstandards/ukstandardindustrialclassificationofeconomicactivities/uksic2007.

[^f00013]: Defined in section 12(2) and (3) of the Act.

[^f00014]: Defined in section 12(5) and (6) of the Act.

[^f00015]: 1998 c. 11.

[^f00016]: S.I. 2022/1100.

[^f00017]: S.I. 2022/1102.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.