The Thames Water Utilities Limited (Thames Tideway Tunnel) (Amendment) Order 2022

Type Statutory-Instrument
Publication 2022-11-23
State In force
Department King's Printer of Acts of Parliament
PDF Download
articles Not indexed
Reform history JSON API

Made: 23rd November 2022

Coming into force: 24th November 2022

In accordance with paragraph 2 of Schedule 6 to the 2008 Act, the Secretary of State has had regard to the effect of the change, together with the previous changes made under that paragraph, on the 2014 Order as originally made, and is satisfied that the change to the 2014 Order is not material.

Citation and Commencement

1

Amendment of the 2014 Order

2

Schedule 1, Schedule 2, Schedule 3 and Schedule 5 to the 2014 Order are amended as set out in the tables in Schedules 1, 2, 3 and 4 to this Order, where—

Certification of substituted plans, etc.

3

to the Secretary of State for certification in accordance with paragraph (2).

SCHEDULE 1 — Amendments to Schedule 1 to the 2014 Order

Provision to be amended Current text Text to be substituted for the current text
Schedule 1, Part 1 (“Authorised Development”) Work No. 16c (xi) “(xi) removal of existing mooring for the Tattershall Castle attached to listed wall (and associated access ramps), construction and use of a new temporary and permanent mooring (over listed wall) for a vessel to the south of Work No. 16c(ii), and means of access for both attached to the listed wall including access brows, gangways, guide piles, mooring chains and anchors fixed to the river bed, construction dredging and associated sheet piling to accommodate the relocated vessel in both the permanent and temporary locations for the vessel;” “(xi) removal of existing mooring for the Tattershall Castle attached to listed wall (and associated access ramps), construction and use of a new mooring (over listed wall) for a vessel to the south of Work No. 16c(ii), and means of access attached to the listed wall including access brows, gangways, guide piles, mooring chains and anchors fixed to the river bed, construction dredging and associated sheet piling to accommodate the relocated vessel;”
Schedule 1, Part 1 (“Authorised Development”) Work No. 16c (xii) “(xii) temporary removal and then reinstatement of the service mooring / service pontoon to the east of the junction of Victoria Embankment and Horse Guards Avenue including guide piles;” “(xii) permanent removal of the service mooring / service pontoon to the east of the junction of Victoria Embankment and Horse Guards Avenue including guide piles;”

SCHEDULE 2 — Amendments to Schedule 2 to the 2014 Order

Provision to be amended Current text Text to be substituted for the current text
Schedule 2, Part 4 (“Approved Plans”) Table 1, column 3 “DCO-PP-16X-VCTEF-180007 - rev 2” “DCO-PP-16X-VCTEF-180007 – rev 3”
Schedule 2, Part 4 (“Approved Plans”) Table 1, column 3 “DCO-PP-16X-VCTEF-180008- rev 4” “DCO-PP-16X- VCTEF-180008- rev 5”
Schedule 2, Part 4 (“Approved Plans”) Table 1, column 3 “DCO-PP-16X-VCTEF-180013- rev 1” “DCO-PP-16X- VCTEF-180013- rev 2”
Schedule 2, Part 4 (“Approved Plans”) Table 2, column 3 “DCO-PP-16X- VCTEF-180027- rev 1” “DCO-PP-16X-VCTEF-180027- rev 2”
Schedule 2, Part 4 (“Approved Plans”) Table 2, column 3 “DCO-PP-16X-VCTEF-180047- rev 1” “DCO-PP-16X-VCTEF-180047- rev 2”

SCHEDULE 3 — Amendments to Schedule 3 to the 2014 Order

Provision to be amended Current text Text to be substituted for the current text
Schedule 3, paragraph 16 Table, Requirement VCTEF3, column 1 “Location of moorings (temporary and permanent)” “Location of moorings”
Schedule 3, paragraph 16 Table, Requirement VCTEF11, column 1 “Use of replacement mooring (temporary and permanent)” “Use of replacement mooring”
Schedule 3, paragraph 16 Table, Requirement VCTEF3, column 3 “The replacement moorings shall be constructed as shown on the Proposed site features plan (Drawing No. DCO-PP-16X-VCTEF-180011 – rev 1) and the Proposed landscape plan (Drawing No. DCO-PP-16X-VCTEF-180013 – rev 1), unless otherwise approved by the relevant planning authority in consultation with the Port of London Authority, HBMCE, Transport for London and the Environment Agency.” “The replacement moorings shall be constructed as shown on the Proposed site features plan (Drawing No. DCO-PP-16X-VCTEF-180011 – rev 2) and the Proposed landscape plan (Drawing No. DCO-PP-16X-VCTEF-180013 – rev 2), unless otherwise approved by the relevant planning authority in consultation with the Port of London Authority, HBMCE, Transport for London and the Environment Agency.”
Schedule 3, paragraph 16 Table, Requirement VCTEF4, column 3, paragraph 3 “(3) The proposed amenity kiosks shown on the Proposed landscape plans (Drawing No. DCO-PP-16X-VCTEF-180012 – rev 2) shall not be brought into use until planning permission is granted for their use by the relevant planning authority and details of refuse storage and servicing are approved.” “(3) The proposed amenity kiosks shown on the Proposed landscape plans (Drawing No. DCO-PP-16X-VCTEF-180012 – rev 3) shall not be brought into use until planning permission is granted for their use by the relevant planning authority and details of refuse storage and servicing are approved.”
Schedule 3, paragraph 16 Table, Requirement VCTEF7, column 3, paragraph 1 “(1) Works to the listed embankment wall shall not commence until details of those works, which shall accord with the Proposed landscape plan (Drawing No. DCO-PP-16X-VCTEF-180013 – rev 1), Proposed listed structure interface – foreshore structure (Drawing No. DCO-PP-16X-VCTEF-180025), As existing and proposed listed structure interface weir structure (Drawing No. DCO-PP-16X-VCTEF-180026 – rev 1), the indicative features on the Proposed mooring access details (Drawing No. DCO-PP-16X-VCTEF-180027 – rev 1) and the design principles for this site, and the maximum temporary and permanent extent of loss of listed buildings/structures are submitted to and approved by the relevant planning authority in consultation with the HBMCE.” “(1) Works to the listed embankment wall shall not commence until details of those works, which shall accord with the Proposed landscape plan (Drawing No. DCO-PP-16X-VCTEF-180013 – rev 2), Proposed listed structure interface – foreshore structure (Drawing No. DCO-PP-16X-VCTEF-180025), As existing and proposed listed structure interface weir structure (Drawing No. DCO-PP-16X-VCTEF-180026 – rev 1), the indicative features on the Proposed mooring access details (Drawing No. DCO-PP-16X-VCTEF-180027 – rev 2) and the design principles for this site, and the maximum temporary and permanent extent of loss of listed buildings/structures are submitted to and approved by the relevant planning authority in consultation with the HBMCE.”
Schedule 3, paragraph 16 Table, Requirement VCTEF10, column 3, paragraph 1 “(1) Construction of the permanent replacement mooring shall not commence until details of the design (including external appearance and materials), which shall accord with the design principles for this site, the Proposed site features plan (Drawing No. DCO-PP-16X-VCTEF-180011 – rev 1), the Proposed landscape plan (Drawing No. DCO-PP-16X-VCTEF-180013 – rev 1), the indicative features of the Proposed mooring access details (Drawing No. DCO-PP-16X-VCTEF-180027 – rev 1) and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE and the Port of London Authority.” “(1) Construction of the permanent replacement mooring shall not commence until details of the design (including external appearance and materials), which shall accord with the design principles for this site, the Proposed site features plan (Drawing No. DCO-PP-16X-VCTEF-180011 – rev 2), the Proposed landscape plan (Drawing No. DCO-PP-16X-VCTEF-180013 – rev 2), the indicative features of the Proposed mooring access details (Drawing No. DCO-PP-16X-VCTEF-180027 – rev 2) and the Site works parameter plan, are submitted to and approved by the relevant planning authority in consultation with the HBMCE and the Port of London Authority.”
Schedule 3, paragraph 16 Table, Requirement VCTEF15, column 3, paragraph 1 “(1) Construction of the permanent above-ground structures shall not commence until details of the landscaping works, which shall accord with the Proposed site features plan (Drawing No. DCO-PP-16X-VCTEF-180011 – rev 1), Proposed landscape plans (Drawing Nos. DCO-PP-16X-VCTEF-180012 – rev 2 and DCO-PP-16X-VCTEF-180013 – rev 1), Kiosk design intent (Drawing No. DCO-PP-16X-VCTEF-180021) and the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the HBMCE and TfL (in respect of street trees).” “(1) Construction of the permanent above-ground structures shall not commence until details of the landscaping works, which shall accord with the Proposed site features plan (Drawing No. DCO-PP-16X-VCTEF-180011 – rev 2), Proposed landscape plans (Drawing Nos. DCO-PP-16X-VCTEF-180012 – rev 3 and DCO-PP-16X-VCTEF-180013 – rev 2), Kiosk design intent (Drawing No. DCO-PP-16X-VCTEF-180021) and the design principles for this site, are submitted to and approved by the relevant planning authority in consultation with the HBMCE and TfL (in respect of street trees).”

SCHEDULE 4 — Amendments to Schedule 5 to the 2014 Order

Provision to be amended Current text Text to be substituted for the current text
Schedule 5, column 3 (City of Westminster, Victoria Embankment, Victoria Embankment Foreshore) “Works to facilitate the temporary and permanent provision of access to boat moorings” “Works to facilitate the provision of access to boat moorings”

Signed

For and on behalf of the Secretary of State

Amira Amzour — Deputy Director, Water Quality — Department for Food, Environment and Rural Affairs — 23 November 2022

For and on behalf of the Secretary of State

Joanna Averley — Chief Planner — Department for Levelling Up, Housing and Communities — 23 November 2022

Explanatory note

(This note is not part of the Order)

EXPLANATORY NOTE

The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I 2014/2384) (“the 2014 Order”) granted development consent within the meaning of the Planning Act 2008 (c. 29).

Following an application made under paragraph 2 of Schedule 6 to the Planning Act 2008, this Order makes the following non-material changes to the 2014 Order—

A copy of the substituted plans mentioned in this Order and certified in accordance with article 3 of this Order (certification of plans, etc.) may be inspected free of charge during working hours at the offices of Westminster City Council, 64 Victoria Street, London, SW1E 6QP.

A full impact assessment has not been produced for this instrument as no, or no significant, impact on the private, voluntary or public sector is foreseen.

Footnotes

[^f00001]: 2008 c. 29; paragraph 2 of Schedule 6 was amended by paragraph 4(6)(a) of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23), by paragraph 72(3) to (7) of Schedule 13, and by section 28(2) of the Infrastructure Act 2015 (c. 7).

[^f00002]: S.I. 2018/378 makes provision for, and in connection with, the transfer of functions from the Secretary of State for Communities and Local Government to the Secretary of State for Housing, Communities and Local Government and S.I. 2021/1265 makes provision for, and in connection with, the transfer of functions from the Secretary of State for Housing, Communities and Local Government to the Secretary of State for Levelling Up, Housing and Communities.

[^f00003]: Article 62 of the Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (“the 2014 Order”) provides insofar as relevant to this Order that “the Secretary of State shall mean the Secretary of State for Communities and Local Government and the Secretary of State for Environment, Food and Rural Affairs”.

[^f00004]: S.I. 2011/2055; relevant amending instruments are S.I. 2012/635, 2015/760 and 2020/1534.

[^f00005]: S.I. 2014/2384, amended by S.I. 2015/723, 2017/659, 2018/1262, 2020/268 and 2020/862.

Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.

This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence. legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.