The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022
- (5) Any archaeological investigations implemented and measures taken to protect record or preserve any identified significant archaeological features that may be found must be carried out—
- (a) in accordance with the approved scheme; and
- (b) by a suitably qualified person or organisation approved by the relevant planning authority.
Construction environmental management plan
17
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction environmental management plan for that part has been submitted to and, after consultation with Natural England and the Environment Agency, approved by the relevant planning authority.
- (2) The plan submitted and approved for that part must be in accordance with the framework construction environment management plan and incorporate—
- (a) a code of construction practice, specifying measures designed to minimise the impacts of construction works;
- (b) a scheme for the control of any emissions to air;
- (c) a soil management plan;
- (d) a site waste management plan;
- (e) a sediment control plan;
- (f) a scheme for environmental monitoring and reporting during the construction of the authorised development, including measures for undertaking any corrective actions;
- (g) a scheme for the notification of any significant construction impacts on local residents and for handling any complaints received from local residents relating to such impacts during the construction of the authorised development;
- (h) the contaminated land scheme for that part containing the matters under Requirement 15; and
- (i) a fish management plan.
- (3) All construction works associated with the authorised development must be carried out in accordance with the approved construction environmental management plan unless otherwise agreed with the relevant planning authority.
Protection of highway surfaces
18
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until details for undertaking condition surveys of the relevant highways which are maintainable at the public expense and which are to be used during construction have been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
- (2) The condition surveys must be undertaken in accordance with the approved details and a schedule of repairs, including a programme for undertaking any such repairs and their inspection, must, following the completion of the post-construction condition surveys, be submitted to, and after consultation with the highway authority, approved by the relevant planning authority.
- (3) The schedule of repairs must be carried out as approved unless otherwise agreed with the relevant planning authority.
Temporary haul road (traffic management and protection)
19
- (1) The authorised development comprised in Work No. 10A shall be retained and maintained in accordance with the haul road plans.
- (2) No part of the authorised development comprised in Work No. 10A shall be brought into use for the purposes of transporting abnormal loads until:
- (a) appropriate traffic management measures have been put in place to allow vehicles to safely access the existing jetty comprised in Work No. 10B and cross Trent Side; and
- (b) appropriate protection measures have been put in place to the Trent Side access points adjacent to the road crossing.
- (3) The traffic management and protection measures in (2) shall be in place at times when loads are utilising the haul road, unless otherwise agreed with the relevant planning authority.
Temporary haul road (biodiversity protection)
20
- (1) The authorised development comprised in Work No. 10A shall be carried out in accordance with the biodiversity measures contained in appendices C and D of the framework construction environmental management plan, unless otherwise agreed with the relevant planning authority.
- (2) Prior to the completion of the authorised development comprised in Work No. 10A, a report must be submitted to the relevant planning authority by a suitably qualified ecologist confirming conformity with (1).
Temporary haul road (removal and restoration)
21
- (1) No later than 28 days following the completion of commissioning the authorised development comprised in Work No. 10A shall be excavated, dismantled and removed.
- (2) No later than three months following the completion of the works authorised in (1) the site shall be restored in accordance with the restoration scheme approved under Requirement 22.
Temporary haul road (prior approval of restoration scheme)
22
- (1) No later than 36 months following commencement of the construction of Work No. 1, a scheme for the removal of the temporary haul road, road bridges and associated infrastructure and restoration of Work No. 10A including the incorporation of biodiversity enhancements and a timetable for implementation, shall be submitted to and approved in writing by the relevant planning authority.
- (2) The scheme authorised under (1) must be implemented in full unless otherwise agreed with the relevant planning authority.
Pilfrey laydown (design)
23
The authorised development comprised in Work No. 9A and located within the area described in the Pilfrey laydown plans shall be retained and maintained in accordance with the Pilfrey laydown plans unless otherwise agreed with the relevant planning authority.
Pilfrey laydown (removal and restoration)
24
- (1) The authorised development comprised in Work No. 9A and located within the area described in the Pilfrey laydown plans shall be removed and the land restored to its former condition no later than 3 months following the completion of commissioning in accordance with a scheme of work submitted to and approved by the relevant planning authority.
- (2) The scheme authorised under (1) must be implemented in full unless otherwise agreed with the relevant planning authority.
Construction traffic management plan
25
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction traffic management plan has been submitted to and, after consultation with National Highways, the highway authority (and in relation to paragraph (3)(c) below the Canal and River Trust), approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with the framework construction traffic management plan.
- (3) The plan submitted and approved must include—
- (a) details of the routes to be used for the delivery of construction materials and any temporary signage to identify routes and promote their safe use, including details of the access points to the construction site to be used by light goods vehicles and heavy goods vehicles;
- (b) details of the routing strategy and procedures for the notification and conveyance of abnormal indivisible loads, including measures to be taken to use water transport where feasible, agreed routes, and anticipated numbers of abnormal loads to be delivered on each route;
- (c) a wharf management plan. This shall include processes for agreeing in advance the general principles around scheduling of abnormal load deliveries that would temporarily obstruct the entrance to Keadby Lock and notifying the Canal and River Trust as to the timing of such deliveries, and measures that seek to avoid such deliveries occurring outside of the notified timings;
- (d) the construction programme; and
- (e) any necessary measures for the temporary protection of carriageway surfaces, the protection of statutory undertakers’ plant and equipment, and any temporary removal of street furniture.
- (4) Notices must be erected and maintained throughout the period of construction at every entrance to and exit from the construction site, indicating to drivers the approved routes for traffic entering and leaving the construction site.
- (5) The approved plan must be implemented within 3 months of commencement of the authorised development and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
Construction worker travel plan
26
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction workers travel plan has been submitted to and, after consultation with the highway authority, approved by the relevant planning authority.
- (2) The plan submitted and approved must be in accordance with the framework construction workers travel plan.
- (3) The plan submitted and approved must include—
- (a) measures to promote the use of sustainable transport modes to and from the authorised development by construction staff;
- (b) provision as to the responsibility for, and timescales of, the implementation of those measures;
- (c) details of parking for construction personnel within the construction sites; and
- (d) a monitoring and review regime.
- (4) The approved plan must be implemented within three months of commencement of the authorised development and must be maintained throughout the construction of the authorised development unless otherwise agreed with the relevant planning authority.
Construction hours
27
- (1) Construction work relating to the authorised development must not take place on bank holidays nor otherwise outside the hours of—
- (a) 0700 to 1900 hours on Monday to Friday; and
- (b) 0800 to 1300 hours on a Saturday.
- (2) Delivery or removal of materials, plant and machinery must not take place on bank holidays nor otherwise outside the hours of—
- (a) 0800 to 1800 hours on Monday to Friday; and
- (b) 0800 to 1300 hours on a Saturday.
- (3) The restrictions in sub-paragraphs (1) and (2) do not apply to construction work or the delivery or removal of materials, plant and machinery, where these—
- (a) do not exceed a noise limit measured at the Order limits and which must be first agreed with the relevant planning authority in accordance with Requirement 28(1);
- (b) are carried out with the prior approval of the relevant planning authority; or
- (c) are associated with an emergency.
- (4) The restrictions in sub-paragraph (2) do not apply to the delivery of abnormal indivisible loads, where this is—
- (a) associated with an emergency; or
- (b) carried out with the prior approval of the relevant planning authority.
- (5) Sub-paragraph (1) does not preclude—
- (a) a start-up period from 0630 to 0700 and a shut-down period from 1900 to 1930 Monday to Friday and a start-up period from 0630 to 0700 and a shut-down period from 1300 to 1330 on a Saturday; or
- (b) maintenance at any time of plant and machinery engaged in the construction of the authorised development.
- (6) In this Requirement “emergency” means a situation where, if the relevant action is not taken, there will be adverse health, safety, security or environmental consequences that in the reasonable opinion of the undertaker would outweigh the adverse effects to the public (whether individuals, classes or generally as the case may be) of taking that action.
Control of noise and vibration - construction
28
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a scheme for the monitoring and control of noise and vibration during the construction of that part of the authorised development has been submitted to and approved by the relevant planning authority.
- (2) The scheme submitted and approved must specify—
- (a) each location from which noise is to be monitored;
- (b) the method of noise measurement;
- (c) the maximum permitted levels of noise at each monitoring location to be determined with reference to the ABC Assessment Method for the different working time periods, as set out in BS 5228-1:2009+A1:2014, unless otherwise agreed in writing with the relevant planning authority for specific construction activities;
- (d) provision as to the circumstances in which construction activities must cease as a result of a failure to comply with a maximum permitted level of noise; and
- (e) the noise control measures to be employed.
- (3) The scheme must be implemented and maintained during the construction of that part of the authorise development as approved unless otherwise agreed with the relevant planning authority.
Control of noise - operation
29
- (1) No part of the authorised development may be brought into commercial use until a scheme for management and monitoring of noise during operation of the authorised development has been submitted to and approved by the relevant planning authority.
- (2) The scheme submitted pursuant to sub-paragraph (1) must include the results of daytime and night time baseline noise monitoring that has been carried out by the undertaker for the purposes of this requirement as agreed with the relevant planning authority.
- (3) Noise (in terms of the BS4142:2014+A1:2019 rating level) from the operation of the authorised development must be no greater than +3dB higher than the defined representative background sound level during each of the daytime and the night time adjacent to the nearest residential properties at such locations as agreed with the relevant planning authority.
- (4) The scheme must be implemented and maintained as approved unless in an emergency or otherwise agreed with the relevant planning authority.
- (5) Any complaint to the undertaker in relation to operational noise must include contact details for the complainant and the date, time and nature of the noise and must then be:
- (a) acknowledged by the undertaker within 3 working days of receipt of complaint;
- (b) investigated within 7 working days of the date of acknowledgement referred to in sub-paragraph (a); and
- (c) a response provided within 7 working days of the date of completion of period for the investigations referred to in sub-paragraph (b) by reference to the threshold in paragraph (3) above.
- (6) In this Requirement—
- (a) “daytime” means the period from 0700 to 2300 and “night time” means the period from 2300 to 0700; and
- (b) “defined representative background sound level” means the sound level measured during the monitoring secured by sub-paragraph (2).
Piling and penetrative foundation design
30
- (1) No part of the authorised development comprised within Works Nos. 1, 2, 4A, 4B, 7, 8B or 9B may commence, save for the permitted preliminary works, until a written piling and penetrative foundation design method statement, informed by a risk assessment, for that part, has been submitted to and, after consultation with the Environment Agency, approved by the relevant planning authority.
- (2) All piling and penetrative foundation works must be carried out in accordance with the approved method statement unless otherwise agreed with the relevant planning authority.
Restoration of land used temporarily for construction
31
- (1) The authorised development must not be brought into commercial use until a scheme for the restoration of any land within the Order limits which has been used temporarily for construction has been submitted to and approved by the relevant planning authority.
- (2) The land must be restored within three years of the authorised development being brought into commercial use (or such other period as the relevant planning authority may approve), in accordance with—
- (a) the restoration scheme approved in accordance with sub-paragraph (1); and
- (b) the landscaping and biodiversity management and enhancement plan approved in accordance with Requirement 6(1).
Combined heat and power
32
- (1) The authorised development must not be brought into commercial use until the relevant planning authority has given notice that it is satisfied that the undertaker has allowed for space and routes within the design of the authorised development for the later provision of heat pass-outs for off-site users of process or space heating and its later connection to such systems, should they be identified and commercially viable.
- (2) The undertaker must maintain such space and routes during the operation of the authorised development unless otherwise agreed with the relevant planning authority.
- (3) On the date that is 12 months after the authorised development is first brought into commercial use, the undertaker must submit to the relevant planning authority for its approval a report (‘the CHP review’) updating the CHP assessment.
- (4) The CHP review submitted and approved must—
- (a) consider the opportunities that reasonably exist for the export of heat from the authorised development at the time of submission; and
- (b) include a list of actions (if any) that the undertaker is reasonably able to take to increase the potential for the export of heat from the authorised development.
- (5) The undertaker must take such actions as are included, within the timescales specified, in the approved CHP review unless otherwise agreed with the relevant planning authority.
- (6) On each date during the operation of the authorised development that is five years after the date on which it last submitted the CHP review or a revised CHP review to the relevant planning authority, the undertaker must submit to the relevant planning authority for its approval a revised CHP review.
- (7) Sub-paragraphs (4) and (5) apply in relation to a revised CHP review submitted under sub- paragraph (6) in the same way as they apply in relation to the CHP review submitted under sub- paragraph (3).
Carbon capture and compression plant
33
- (1) No part of the authorised development may commence, save for the permitted preliminary works and Work No.9B and Work No.9C, until details of the following have been submitted to and approved by the relevant planning authority—
- (a) evidence that Development Consent is in place for the construction of the National Grid Carbon Gathering Network;
- (b) evidence that a Carbon Dioxide Storage Licence for the intended storage site for the National Grid Carbon Gathering Network is in place;
- (c) evidence that an Environmental Permit is in place for Work No. 1; and
- (d) evidence of any pipeline works authorisation required by section 14 of the Petroleum Act 1998 for offshore pipeline works.
- (2) Prior to the start of commissioning of the authorised development, the undertaker must not without the consent of the Secretary of State—
- (a) dispose of any interest in the land required for Work No. 1C or Work No. 7; or
- (b) do anything, or allow anything to be done or to occur, which may reasonably be expected to diminish the undertaker’s ability, within two years of such action or occurrence, to prepare Work No. 1C and Work No. 7 for construction.
- (3) Work No. 1A may not be brought into commercial use without Work No. 1C and Work No. 7A also being brought into commercial use.
Aviation warning lighting
34
- (1) No part of the authorised development comprised within Work No. 1 or Work No. 10B may commence, save for the permitted preliminary works, until details of the timetable for construction and retention of tall structures or the placement and retention of mobile cranes and the specification and installation timetable for aviation warning lighting for that part during construction and operation have been submitted to and, after consultation with the Civil Aviation Authority and Ministry of Defence Safeguarding, approved by the relevant planning authority.
- (2) The aviation warning lighting approved pursuant to paragraph (1) must be installed, maintained and operated in accordance with the approved details.
Air safety
35
- (1) No part of the authorised development comprised within Work No. 1 or Work No. 10B may commence, save for the permitted preliminary works, until details of the heights of structures and temporary cranes and other information that is required by Civil Aviation Authority Airspace Regulation and the Defence Geographic Centre of the Ministry of Defence to chart the site for aviation purposes for that part have been submitted to and approved by the relevant planning authority.
- (2) The details approved pursuant to paragraph (1) must thereafter be implemented, operated and maintained in accordance with the approved details.
Local liaison committee
36
- (1) No part of the authorised development may commence, save for the permitted preliminary works and Works Nos. 9B and 9C, until the undertaker has established a committee to liaise with local residents and organisations to keep them informed on matters relating to the construction and commissioning of the authorised development (a ‘local liaison committee’).
- (2) The undertaker must invite the relevant planning authority, all parish councils within close proximity to the authorised development, and other relevant interest groups, as may be agreed with the relevant planning authority, to nominate representatives to join the local liaison committee.
- (3) The undertaker must provide a full secretariat service and supply an appropriate venue (which may include online conferencing with telephone dial in) for the local liaison committee meetings to take place.
- (4) The local liaison committee must—
- (a) include representatives of the undertaker;
- (b) meet every other month, starting in the month prior to commencement of the authorised development, until the completion of construction, testing and commissioning works unless otherwise agreed by the majority of the members of the local liaison committee; and
- (c) during the operation of the authorised development meet once a year unless otherwise agreed by the majority of the members of the local liaison committee.
Employment, skills and training plan
37
- (1) No part of the authorised development may commence, save for the permitted preliminary works, until a plan detailing arrangements to promote and monitor employment, skills and training development opportunities for residents of the borough of North Lincolnshire during construction and employment opportunities during operation of the authorised development has been submitted to and approved by the relevant planning authority.
- (2) The approved plan must be implemented and maintained during the construction and operation of the authorised development unless otherwise agreed by the relevant planning authority.
Decommissioning
38
- (1) Within 12 months of the date that the undertaker decides to decommission the authorised development, the undertaker must submit to the relevant planning authority for its approval a decommissioning environmental management plan.
- (2) No decommissioning works must be carried out until the relevant planning authority has approved the plan.
- (3) The plan submitted and approved must include measures to address any significant environmental effects.
- (4) The plan submitted and approved must include details of—
- (a) the buildings to be demolished;
- (b) the means of removal of the materials resulting from the decommissioning works;
- (c) the phasing of the demolition and removal works;
- (d) any restoration works to restore the land to a condition agreed with the relevant planning authority;
- (e) the phasing of any restoration works; and
- (f) a timetable for the implementation of the plan.
- (5) The plan must be implemented and maintained for the duration of the decommissioning of the authorised development as approved unless otherwise agreed with the relevant planning authority.
Requirement for written approval
39
Where under any of the above Requirements the approval or agreement of the relevant planning authority or another person is required, that approval or agreement must be provided in writing.
Approved details and amendments to them
40
- (1) All details submitted for the approval of the relevant planning authority under these Requirements must be in accordance with the parameters of the environmental statement and reflect the principles set out in the documents certified under article 41 (certification of plans etc.).
- (2) With respect to any Requirement which requires the authorised development to be carried out in accordance with the details approved by the relevant planning authority, the approved details are to be taken to include any amendments that may subsequently be approved by the relevant planning authority.
Amendments agreed by the relevant planning authority
41
- (1) Where the words “unless otherwise agreed by the relevant planning authority” appear in the above Requirements, any such approval or agreement may only be given in relation to non- material amendments and where it has been demonstrated to the satisfaction of that authority that the subject matter of the approval or agreement sought will not give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.
- (2) In cases where the Requirement or the relevant sub-paragraph requires consultation with specified persons, any such approval or agreement must not be given without the relevant planning authority having first consulted with those persons.
SCHEDULE 3 — STREETS SUBJECT TO STREET WORKS
| (1) Area | (2) Streets subject to street works | (3) Description of the street works |
|---|---|---|
| In the Borough of North Lincolnshire | A18 | Widening and improvement works to two accesses on the A18 marked at reference points A and C on the access and rights of way plan and re-grading and re-surfacing of carriageway between the points marked E and F on sheet 1 on the access and rights of way plan |
| Chapel Lane | Works for installation and maintenance of Works No. 3B, 4A, 4B and 5 in those areas marked G, H, I, J, K, L and M on sheet 3 of the access and rights of way plans | |
SCHEDULE 4 — STREETS SUBJECT TO PERMANENT ALTERATIONS OF LAYOUT
| (1) Area | (2) Streets subject to alternation of layout | (3) Description of alteration |
|---|---|---|
| A18 | Widening and improvement works to two accesses on the A18 marked at reference points A and C on the access and rights of way plan and re-grading, re-surfacing and layout alterations of carriageway between the points marked E and F on sheet 1 on the access and rights of way plan | |
SCHEDULE 5 — ACCESS - THOSE PARTS OF THE ACCESS TO BE MAINTAINED AT THE PUBLIC EXPENSE
| (1) Area | (2) Street | (3) Description of relevant part of access |
|---|---|---|
| In the Borough of North Lincolnshire | A18 | That part of each of the two accesses hatched blue and referenced at points marked A and C on sheet 1 of the access and rights of way plan |
SCHEDULE 6 — NEW RIGHTS
Interpretation
1
In this Schedule—
- “Work Nos. 3A and 3B infrastructure” means any work or development comprised within Work Nos. 3A and 3B in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work Nos. 3A and 3B on the works plans.
- “Work Nos. 4A and 4B infrastructure” means any work or development comprised within Work Nos. 4A and 4B in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work Nos. 4A and 4B on the works plans.
- “Work No. 5 infrastructure” means any work or development comprised within Work No. 5 in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 5 on the works plans.
- “Work No. 6 infrastructure” means any work or development comprised within Work No. 6 in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 6 on the works plans.
- “Work No. 8C infrastructure” means any work or development comprised within Work No. 8C in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 8C on the works plans.
- “Work Nos. 8A and 8B infrastructure” means any work or development comprised within Work No. 8A and 8B in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work Nos. 8A and 8B on the works plans.
- “Work No. 9B infrastructure” means any work or development comprised within Work No. 9B in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 9B on the works plans.
- “Work No. 11A infrastructure planting” means any work or development comprised within Work No. 11A in Schedule 1, ancillary apparatus and including any other necessary works or development permitted within the area delineated as Work No. 11A on the works plans. Table 4 (1) Number of plot shown on the land plans (2) Rights etc. which may be acquired 34a, 35, 40a, 41, 42, 43, 44, 45, 55a, 55b, 56, 56a, 59, 60, 64, 65, 66, 69, 70, 73, 86, 88, 94, 106, 107, 108, 109, 110, 166, 167, 168For and in connection with the Work Nos. 3A and 3B infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work Nos. 3A and 3B infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work Nos. 3A and 3B infrastructure, or interfere with or obstruct access from and to the Work Nos. 3A and 3B infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land.16, 34a, 35, 36, 52, 69, 70, 71, 72, 73, 74, 75, 76, 77, 79, 80, 81, 82, 83, 84, 85, 89, 90, 91, 92, 93, 95, 96, 97, 98, 99, 100, 101, 103, 105, 113, 114, 115, 116, 117, 118, 122, 123, 126, 137, 138, 139, 148, 150, 151, 159, 160, 164, 165, 166, 168, 169For and in connection with the Work Nos. 4A and 4B infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work Nos. 4A and 4B infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work Nos. 4A and 4B infrastructure, or interfere with or obstruct access from and to the Work Nos. 4A and 4B infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land.34a, 35, 69, 70, 73, 82, 83, 84, 85, 87, 89, 90, 99, 102, 103, 105, 111, 112, 113, 114, 115, 120, 121, 122, 123, 124, 125, 127, 128, 129, 130, 132, 133, 134, 140, 141, 142, 143, 147, 152, 153, 158, 161, 162, 163, 166, 168, 169, 171For and in connection with the Work No. 5 infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work No. 5 infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work Nos. 5 infrastructure, or interfere with or obstruct access from and to the Work No. 5 infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land.34a, 35, 36, 64, 69, 70, 73, 74, 82, 99, 102, 103, 105, 113, 166, 168, 169, 171For and in connection with the Work No. 6 infrastructure the right for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work No. 6 infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 6 infrastructure, or interfere with or obstruct access from and to the Work No. 6 infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land.40, 40a, 41, 44, 45, 55a, 55b, 56, 56a, 57, 60For and in connection with the Work No. 8C infrastructure the right to improve access roads and for the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work No. 8C infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 8C infrastructure, or interfere with or obstruct access from and to the Work No. 8C infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land.3, 12, 18, 19, 20, 22, 24, 27, 28, 29, 30, 33, 37, 38, 39 For and in connection with the Work Nos. 8A and 8B the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work Nos. 8A and 8B infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work Nos. 8A and 8B infrastructure, or interfere with or obstruct access from and to the Work Nos.8A and 8B infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land. For and in connection with Work No. 8B planting, a right for the undertaker and all persons authorised on its behalf to enter, pass, and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with and improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 8B planting together with the right to protect, retain, maintain, inspect and replant Work No. 8B, along with the right to prevent any works on or uses of the land which may interfere with or obstruct access from and to the Work No. 8B planting or existing planting. 3, 19For and in connection with the Work No 9B infrastructure the undertaker and all persons authorised on its behalf to enter, pass and re-pass, on foot, with or without vehicles, plant and machinery for all purposes in connection with and the laying, installation, use and maintenance of Work No. 9B infrastructure, and a right of support for it and the right to the free flow of water, along with the right to prevent any works on or uses of the land which may interfere with or damage the Work No. 9B infrastructure, or interfere with or obstruct access from and to the Work No. 9B infrastructure, including the right to prevent or remove the whole of any fixed or movable structure, tree, shrub, plant or other things and the right to prevent or remove any works or uses which alter the surface level, ground cover, or composition of the land.18, 20, 21For and in connection with Work No. 11A infrastructure planting, a right for the undertaker and all persons authorised on its behalf to enter, pass, and repass, on foot, with or without vehicles, plant and machinery, for all purposes in connection with and improvement, reinstatement, installation, implementation, retention, removal, relocation and maintenance of the Work No. 11A infrastructure planting together with the right to protect, retain, maintain, inspect and replant Work No. 11A along with the right to prevent any works on or uses of the land which may interfere with or obstruct access from and to the Work No. 11A infrastructure planting or existing planting.
SCHEDULE 7 — MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
Compensation enactments
1
The enactments for the time being in force with respect to compensation for the compulsory purchase of land are to apply, with the necessary modifications as respects compensation, in the case of a compulsory acquisition under this Order of a right by the creation of a new right as they apply as respects compensation on the compulsory purchase of land and interests in land.
2
- (1) Without limitation on the scope of paragraph 1, the Land Compensation Act 197334 has effect subject to the modifications set out in sub-paragraph (2).
- (2) In section 44(1) (compensation for injurious affection), as it applies to compensation for injurious affection under section 7 (measure of compensation in case of severance) of the 1965 Act as substituted by paragraph 5—
- (a) for “land is acquired or taken from” substitute “a right or restrictive covenant over land is purchased from or imposed on”; and
- (b) for “acquired or taken from him” substitute “over which the right is exercisable or the restrictive covenant enforceable”.
3
- (1) Without limitation on the scope of paragraph 1, the 1961 Act has effect subject to the modification set out in sub-paragraph (2).
- (2) In section 5A(5A) (relevant valuation date), omit the words after “if—” and substitute—
(a) the acquiring authority enters on land for the purpose of exercising a right in pursuance of a notice of entry under section 11(1) of the 1965 Act (as modified by paragraph 5(5) of Schedule 7 to the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022; (b) the acquiring authority is subsequently required by a determination under paragraph 12 of Schedule 2A to the 1965 Act (as substituted by paragraph 5(8) of Schedule 7 to the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022) to acquire an interest in the land; and (c) the acquiring authority enters on and takes possession of that land, the authority is deemed for the purposes of subsection (3)(a) to have entered on that land where it entered on that land for the purpose of exercising that right.
Application of Part 1 of the 1965 Act
4
Part 1 (compulsory purchase under Acquisition of Land Act 1946) of the 1965 Act, as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act to the acquisition of land under article 18 (compulsory acquisition of land) and as modified by article 23 (modification of Part 1 of the 1965 Act), applies to the compulsory acquisition of a right by the creation of a new right under article 21 (compulsory acquisition of rights)—
- (a) with the modifications specified in paragraph 5; and
- (b) with such other modifications as may be necessary.
5
- (1) The modifications referred to in paragraph 4(a) are as follows—
- (2) References in the 1965 Act to land are, in the appropriate contexts, to be read (according to the requirements of the particular context) as referring to, or as including references to—
- (a) the right acquired or to be acquired, or the restriction imposed or to be imposed; or
- (b) the land over which the right is or is to be exercisable, or the restriction is to be enforceable.
- (3) For section 7 of the 1965 Act (measure of compensation in case of severance) substitute—
(7) In assessing the compensation to be paid by the acquiring authority under this Act, regard must be had not only to the extent (if any) to which the value of the land over which the right is to be acquired or the restrictive covenant is to be imposed is depreciated by the acquisition of the right or the imposition of the covenant but also to the damage (if any) to be sustained by the owner of the land by reason of its severance from other land of the owner, or injuriously affecting that other land by the exercise of the powers conferred by this or the special Act.
- (4) The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
- (a) section 9(4) (failure by owners to convey);
- (b) paragraph 10(3) of Schedule 1 (owners under incapacity);
- (c) paragraph 2(3) of Schedule 2 (absent and untraced owners); and
- (d) paragraphs 2(3) and 7(2) of Schedule 4 (common land),
are modified to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired or the restrictive covenant which is to be imposed is vested absolutely in the acquiring authority.
- (5) Section 11 of the 1965 Act (powers of entry) is modified to secure that, where the acquiring authority has served notice to treat in respect of any right or restriction, as well as the notice of entry required by subsection (1) of that section (as it applied to compulsory acquisition under article 8), it has power, exercisable in equivalent circumstances and subject to equivalent conditions, to enter for the purpose of exercising that right or enforcing that restrictive covenant; and sections 11A35 (powers of entry: further notices of entry), 11B36 (counter-notice requiring possession to be taken on specified date), 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act are modified correspondingly.
- (6) Section 20 of the 1965 Act (protection for interests of tenants at will, etc.) applies with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right or the enforcement of the restrictive covenant in question.
- (7) Section 22 of the 1965 Act (interests omitted from purchase) as modified by article 23(3) is also modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, or enforce the restriction imposed, subject to compliance with that section as respects compensation.
- (8) For Schedule 2A to the 1965 Act substitute—
SCHEDULE2A (1) (1) This Schedule applies where an acquiring authority serve a notice to treat in respect of a right over, or restrictive covenant affecting, the whole or part of a house, building or factory and have not executed a general vesting declaration under section 4 of the 1981 Act as applied by article 23 (application of the Compulsory Purchase (Vesting Declarations) Act 1981) of the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022. (2) But see article 24 (acquisition of subsoil or airspace only) of the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 which excludes the acquisition of subsoil or airspace only from this Schedule. (2) In this Schedule, “house” includes any park or garden belonging to a house. (3) A person who is able to sell the house, building or factory (“the owner”) may serve a counter-notice requiring the authority to purchase the owner’s interest in the house, building or factory. (4) A counter-notice under paragraph 3 must be served within the period of twenty-eight days beginning with the day on which the notice to treat was served. (5) On receiving a counter-notice, the acquiring authority must decide whether to— (a) withdraw the notice to treat; (b) accept the counter-notice; or (c) refer the counter-notice to the Upper Tribunal. (6) The authority must serve notice of their decision on the owner within the period of 3 months beginning with the day on which the counter-notice is served (“the decision period”). (7) If the authority decide to refer the counter-notice to the Upper Tribunal they must do so within the decision period. (8) If the authority do not serve notice of a decision within the decision period they are to be treated as if they had served notice of a decision to withdraw the notice to treat at the end of that period. (9) If the authority serve notice of a decision to accept the counter-notice, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in the house, building or factory. (10) On a referral under paragraph 7, the Upper Tribunal must determine whether the acquisition of the right or the imposition of the restrictive covenant would— (a) in the case of a house, building or factory, cause material detriment to the house, building or factory; or (b) in the case of a park or garden, seriously affect the amenity or convenience of the house to which the park or garden belongs. (11) In making its determination, the Upper Tribunal must take into account- (a) the effect of the acquisition of the right or the imposition of the covenant; (b) the use to be made of the right or covenant proposed to be acquired or imposed; and (c) if the right or covenant is proposed to be acquired or imposed for works or other purposes extending to other land, the effect of the whole of the works and the use of the other land. (12) If the Upper Tribunal determines that the acquisition of the right or the imposition of the covenant would have either of the consequences described in paragraph 10, it must determine how much of the house, building or factory the authority ought to be required to take. (13) If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the compulsory purchase order and the notice to treat are to have effect as if they included the owner’s interest in that land. (14) (1) If the Upper Tribunal determines that the authority ought to be required to take some or all of the house, building or factory, the authority may at any time within the period of 6 weeks beginning with the day on which the Upper Tribunal makes its determination withdraw the notice to treat in relation to that land. (2) If the acquiring authority withdraws the notice to treat under this paragraph they must pay the person on whom the notice was served compensation for any loss or expense caused by the giving and withdrawal of the notice. (3) Any dispute as to the compensation is to be determined by the Upper Tribunal.
SCHEDULE 8 — LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
| (1) Number of plots shown on the land plans | (2) Purpose for which temporary possession may be take | (3) Relevant part of the authorised development |
|---|---|---|
| 47 | Access and construction worksite | Work No. 2A |
| 40b, 43, 56, 58, 59 | Access and construction worksite. | Work No. 3B |
| 32a | Access and construction worksite | Work No. 6 |
| 1, 2, 4, 5, 6, 7, 8, 9, 10, 26 | Access and construction worksite. | Work No. 8A |
| 40b, 55, 56, 58, 59, 67 | Access and construction worksite. | Work No. 8C |
| 1, 2, 3, 4, 10, 11, 12, 16a, 17, 17a, 18, 19, 20, 21, 22, 23, 25, 26, 27, 28, 29, 30, 32, 32a, 33, 34, 37, 38, 39, 49, 50a, 50, 51, 61, 62, 63, 72a | Access and construction worksite, use of the land for temporary laydown areas including any ancillary works necessary to facilitate the use of that land, storage, placing of temporary cranes and works associated with the re-instatement of the land. Works compound and welfare facilities, storage, laydown areas, and re-instatement of laydown areas. | Work Nos. 9A, 9B and 9C |
| 13, 14, 16, 16a, 17a, 17b, 31, 32a, 46, 47, 48, 49a, 50, 50a, 51, 53, 54, 62, 63, 72, 72a, 73, 74, 78, 79, 93, 95, 101, 119, 131, 135, 136, 144, 145, 165, 165a 170 | Access and construction worksite, including temporary haul road and any ancillary works necessary to facilitate the use of that land as a temporary haul road and re-instatement of the land. | Work No. 10A |
| 136, 146, 149, 155 | Access, inspection and repair, construction worksite and placing of temporary cranes. | Work No. 10B |
| 68 | Access and construction worksite. | Work No. 11A |
SCHEDULE 9 — PROCEDURE FOR DISCHARGE OF REQUIREMENTS
1
In this Schedule—
- “business day” means a day other than a Saturday or Sunday which is not Christmas Day, Good Friday or a bank holiday under section 1 (bank holidays) of the Banking and Financial Dealings Act 197137;
- “requirement consultee” means any body named in a Requirement as a body to be consulted by the relevant planning authority in discharging that Requirement; and
- “start date” means the date of the notification given by the Secretary of State under paragraph 5(2)(b).
Applications made under Requirements
2
- (1) Where an application has been made to the relevant planning authority for any consent, agreement or approval required by a Requirement the relevant planning authority must give notice to the undertaker of its decision on the application within a period of eight weeks beginning with the later of—
- (a) the day immediately following that on which the application is received by the authority; or
- (b) the day immediately following that on which further information has been supplied by the undertaker under paragraph 3,
or such longer period as may be agreed in writing by the undertaker and the relevant planning authority.
- (2) Subject to paragraph 5 and the exception set out in sub-paragraph 4 below, in the event that the relevant planning authority does not determine an application within the period set out in sub-paragraph (1), the relevant planning authority is to be taken to have granted all parts of the application (without any condition or qualification) at the end of that period.
- (3) Any application made to the relevant planning authority pursuant to sub-paragraph (1) must include a statement to confirm whether it is likely that the subject matter of the application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement and if it will then it must be accompanied by information setting out what those effects are.
- (4) Where an application has been made to the relevant planning authority for any consent, agreement or approval required by a Requirement included in this Order and the relevant planning authority does not determine the application within the period set out in sub-paragraph (1)—
- (a) An application is accompanied by a report pursuant to sub-paragraph (3) which states that the subject matter of such application is likely to give rise to any materially new or materially different environmental effects compared to those in the environmental statement; or
- (b) The relevant planning authority considers that the subject matter of such application will give rise to any materially new or materially different environmental effects compared to those in the environmental statement and has notified the undertaker of this in writing within 21 business days from receipt of such report,
then the application is deemed to have been refused by the relevant planning authority at the end of that period.
Further information and consultation
3
- (1) In relation to any application to which this Schedule applies, the relevant planning authority may request such reasonable further information from the undertaker as is necessary to enable it to consider the application.
- (2) In the event that the relevant planning authority considers such further information to be necessary and the provision governing or requiring the application does not specify that consultation with a requirement consultee is required, the relevant planning authority must, within 21 business days of receipt of the application, notify the undertaker in writing specifying the further information required.
- (3) If the provision governing or requiring the application specifies that consultation with a requirement consultee is required, the relevant planning authority must issue the consultation to the requirement consultee within ten business days of receipt of the application, and must notify the undertaker in writing specifying any further information requested by the requirement consultee within five business days of receipt of such a request and in any event within 21 days of receipt of the application (or such other period as is agreed in writing between the undertaker and the relevant planning authority).
- (4) In the event that the relevant planning authority does not give notification as specified in sub-paragraph (2) or (3) it is deemed to have sufficient information to consider the application and is not thereafter entitled to request further information without the prior agreement of the undertaker.
Fees
4
- (1) Where an application is made to the relevant planning authority for written consent, agreement or approval in respect of a requirement, the fee prescribed under regulation 16(1)(b) of the Town and Country Planning (Fees for Applications, Deemed Applications, Requests and Site Visits) (England) Regulations 201238 (as may be amended or replaced from time to time) is to apply and must be paid to the relevant planning authority for each application.
- (2) Any fee paid under this Schedule must be refunded to the undertaker within four weeks of—
- (a) the application being rejected as invalidly made; or
- (b) the relevant planning authority failing to determine the application within nine weeks from the relevant date in paragraph 1 unless—
- (i) within that period the undertaker agrees, in writing, that the fee is to be retained by the relevant planning authority and credited in respect of a future application; or
- (ii) a longer period of time for determining the application has been agreed pursuant to paragraph 2 of this Schedule.
Appeals
5
- (1) The undertaker may appeal in the event that—
- (a) the relevant planning authority refuses an application for any consent, agreement or approval required by a requirement included in this Order or grants it subject to conditions;
- (b) the relevant planning authority is deemed to have refused an application pursuant to paragraph 2(4);
- (c) on receipt of a request for further information pursuant to paragraph 3 the undertaker considers that either the whole or part of the specified information requested by the relevant planning authority is not necessary for consideration of the application; or
- (d) on receipt of any further information requested, the relevant planning authority notifies the undertaker that the information provided is inadequate and requests additional information which the undertaker considers is not necessary for consideration of the application.
- (2) The steps to be followed in the appeal process are as follows—
- (a) the undertaker must submit the appeal documentation to the Secretary of State and must on the same day provide copies of the appeal documentation to the relevant planning authority and the requirement consultee;
- (b) the Secretary of State must appoint a person to determine the appeal as soon as reasonably practicable after receiving the appeal documentation and must forthwith notify the appeal parties of the identity of the appointed person and the address to which all correspondence for the appointed person’s attention should be sent;
- (c) the relevant planning authority and the requirement consultee (if applicable) must submit written representations to the appointed person in respect of the appeal within ten business days of the start date and must ensure that copies of their written representations are sent to each other and to the undertaker on the day on which they are submitted to the appointed person;
- (d) the appeal parties must make any counter-submissions to the appointed person within ten business days of receipt of written representations pursuant to paragraph (c);
- (e) the appointed person must make his decision and notify it to the appeal parties, with reasons, as soon as reasonably practicable and in any event within 30 business days of the deadline for the receipt of counter-submissions pursuant to sub-paragraph (d); and
- (f) the appointment of the person pursuant to paragraph (b) may be undertaken by a person appointed by the Secretary of State for this purpose instead of by the Secretary of State.
- (3) In the event that the appointed person considers that further information is necessary to enable the appointed person to consider the appeal the appointed person must, within five business days of the appointed person’s appointment, notify the appeal parties in writing specifying the further information required.
- (4) Any further information required pursuant to sub-paragraph (3) must be provided by the undertaker to the appointed person, the relevant planning authority and the requirement consultee on the date specified by the appointed person (the “specified date”), and the appointed person must notify the appeal parties of the revised timetable for the appeal on or before that day. The revised timetable for the appeal must require submission of written representations to the appointed person within ten business days of the specified date, but otherwise the process and time limits set out in paragraphs (c) to (e) of sub-paragraph (2) apply.
- (5) The appointed person may—
- (a) allow or dismiss the appeal; or
- (b) reverse or vary any part of the decision of the relevant planning authority (whether the appeal relates to that part of it or not),
and may deal with the application as if it had been made to him in the first instance.
- (6) The appointed person may proceed to a decision on an appeal taking into account only such written representations as have been sent within the relevant time limits.
- (7) The appointed person may proceed to a decision even though no written representations have been made within the relevant time limits, if it appears that there is sufficient material to enable a decision to be made on the merits of the case.
- (8) The decision of the appointed person on an appeal is to be final and binding on the parties, unless proceedings are brought by a claim for judicial review.
- (9) If an approval is given by the appointed person pursuant to this Schedule, it is deemed to be an approval for the purpose of Schedule 2 (requirements) as if it had been given by the relevant planning authority. The relevant planning authority may confirm any determination given by the appointed person in identical form in writing but a failure to give such confirmation (or a failure to give it in identical form) does not affect or invalidate the effect of the appointed person’s determination.
- (10) Save where a direction is given pursuant to sub-paragraph (11) requiring the costs of the appointed person to be paid by the relevant planning authority, the reasonable costs of the appointed person must be met by the undertaker.
- (11) On application by the relevant planning authority or the undertaker, the appointed person may give directions as to the costs of the appeal parties and as to the parties by whom the costs of the appeal are to be paid. In considering whether to make any such direction and the terms on which it is to be made, the appointed person must have regard to the advice on planning appeals and award costs published on 20 December 2016 by what was then the Department for Communities and Local Government or any circular or guidance which may from time to time replace it.
SCHEDULE 10 — PROTECTIVE PROVISIONS
PART 1 — FOR THE PROTECTION OF NATIONAL GRID AS ELECTRICITY AND GAS UNDERTAKER
Application
1
- (1) For the protection of National Grid as referred to in this Part of this Schedule the following provisions have effect, unless otherwise agreed in writing between the undertaker and National Grid.
- (2) Subject to sub-paragraph (3) or to the extent otherwise agreed in writing between the undertaker and National Grid, where the benefit of this Order is transferred or granted to another person under article 7 (consent to transfer benefit of the Order)—
- (a) any agreement of the type mentioned in subparagraph (1) has effect as if it had been made between National Grid and the transferee or grantee (as the case may be); and
- (b) written notice of the transfer or grant must be given to National Grid on or before the date of that transfer or grant.
- (3) Sub-paragraph (2) does not apply where the benefit of the Order is transferred or granted to National Grid.
Interpretation
2
In this Part of this Schedule—
- “1991 Act” means the New Roads and Street Works Act 199139;
- “acceptable credit provider” means a bank or financial institution with a credit rating that is not lower than: (i) “A-” if the rating is assigned by Standard & Poor’s Ratings Group or Fitch Ratings; and “A3” if the rating is assigned by Moody’s Investors Services Inc.;
- “acceptable insurance” means a third party liability insurance effected and maintained by the undertaker with a limit of indemnity of not less than £100,000,000 (one hundred million pounds) per occurrence or series of occurrences arising out of one event. Such insurance shall be maintained for the construction period of the authorised works which constitute specified works and arranged with an internationally recognised insurer of repute operating in the London and worldwide insurance market underwriters whose security/credit rating meets the same requirements as an “acceptable credit provider”, such policy shall include (but without limitation):National Grid Electricity Transmission Plc and National Grid Gas Plc as a Co-Insured;a cross liabilities clause; andcontractors’ pollution liability for third party property damage and third party bodily damage arising from a pollution/contamination event with cover of £10,000,000.00 (ten million pounds) per event or £20,000,000.00 (twenty million pounds) in aggregate;
- “acceptable security” means either:a parent company guarantee from a parent company in favour of National Grid Electricity Transmission Plc and National Grid Gas Plc to cover the undertaker’s liability to National Grid Electricity Transmission Plc and National Grid Gas Plc to a total liability cap of £100,000,000.00 one hundred million pounds) (in a form reasonably satisfactory to National Grid and where required by National Grid, accompanied with a legal opinion confirming the due capacity and authorisation of the parent company to enter into and be bound by the terms of such guarantee); ora bank bond or letter of credit from an acceptable credit provider in favour of National Grid Electricity Transmission Plc and National Grid Gas Plc to cover the undertaker’s liability to National Grid Electricity Transmission Plc and National Grid Gas Plc for an amount of not less than £10,000,000.00 (ten million pounds) per asset per event up to a total liability cap of £100,000,000.00 (one hundred million pounds) (in a form reasonably satisfactory to the National Grid);
- “alternative apparatus” means appropriate alternative apparatus to the satisfaction of National Grid to enable National Grid to fulfil its statutory functions in a manner no less efficient than previously;
- “apparatus” means:any electric lines or electrical plant as defined in the Electricity Act 1989, belonging to or maintained by National Grid;any mains, pipes or other apparatus belonging to or maintained by National Grid for the purposes of gas supply;together with any replacement apparatus and such other apparatus constructed pursuant to this Order that becomes operational apparatus of National Grid for the purposes of transmission, distribution and/or supply and includes any structure in which apparatus is or will be lodged or which gives or will give access to apparatus;
- “authorised works” has the same meaning as is given to the term “authorised development” in article 2(1) of this Order and includes any associated development authorised by this Order and for the purposes of this Part of this Schedule includes the use and maintenance of the authorised works and construction of any works authorised by this Schedule;
- “commence” and “commencement” in this Part of this Schedule shall include any below ground surveys, monitoring, ground work operations or the receipt and erection of construction plant and equipment;
- “deed of consent” means a deed of consent, crossing agreement, deed of variation or new deed of grant agreed between the parties acting reasonably in order to vary or replace existing easements, agreements, enactments and other such interests so as to secure land rights and interests as are necessary to carry out, maintain, operate and use the apparatus in a manner consistent with the terms of this Part of this Schedule;
- “functions” includes powers and duties;
- “ground mitigation scheme” means a scheme approved by National Grid (such approval not to be unreasonably withheld or delayed) setting out the necessary measures (if any) for a ground subsidence event;
- “ground monitoring scheme” means a scheme for monitoring ground subsidence which sets out the apparatus which is to be subject to such monitoring, the extent of land to be monitored, the manner in which ground levels are to be monitored, the timescales of any monitoring activities and the extent of ground subsidence which, if exceeded, shall require the undertaker to submit for National Grid’s approval a ground mitigation scheme;
- “ground subsidence event” means any ground subsidence identified by the monitoring activities set out in the ground monitoring scheme that has exceeded the level described in the ground monitoring scheme as requiring a ground mitigation scheme;
- “in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon such land;
- “maintain” and “maintenance” shall include the ability and right to do any of the following in relation to any apparatus or alternative apparatus of National Grid including construct, use, repair, alter, inspect, renew or remove the apparatus;
- “National Grid” means:National Grid Electricity Transmission Plc (Company Number 2366977) whose registered office is at 1-3 Strand, London, WC2N 5EH or any successor as a licence holder within the meaning of Part 1 of the Electricity Act 1989; andNational Grid Gas plc (Company Number 02006000) whose registered office is at 1-3 Strand, London, WC2N 5EH or any successor as a gas transporter within the meaning of Part 1 of the Gas Act 1986;
- “parent company” means a parent company of the undertaker acceptable to and which shall have been approved by National Grid acting reasonably;
- “undertaker” means the undertaker as defined in article 2(1) of this Order;
Reading this document does not replace reading the official text published on legislation.gov.uk. Contains public sector information licensed under the Open Government Licence v3.0. We assume no responsibility for any inaccuracies arising from the conversion of the original CLML XML to this format.
This text is published under legislation.gov.uk's own terms of reuse, not a Legalize or public-domain licence.
legislation.gov.uk
Open Government Licence v3.0 (attribution required)
© Crown and database right. Derived from content available under the Open Government Licence v3.0 from legislation.gov.uk.